Cooperative operation transaction management method and system between two levels of buildings and parks
Through artificial intelligence, predict the power and carbon emissions of renewable energy, build an objective function to maximize returns, optimize energy transaction management, solve the resource coordination and carbon emission problems between the buildings and parks, and improve energy utilization efficiency and market efficiency .
Patent Information
- Application Number
- CN202411068402.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-06
- Publication Date
- 2024-12-03
AI Technical Summary
There are difficulties in the coordinated operation transaction management between the two levels of the building and the park, such as resource coordination, large carbon emissions and low user participation. Traditional load management methods rely on experience scheduling and static planning, making it difficult to adapt to the complex and changing power market and energy supply. environment.
Using an artificial intelligence-based method, we predict the power generation power and carbon emissions of renewable energy through historical operating data, build an income function and a return maximization objective function, combine the K-means clustering algorithm and Stackelberg game model to optimize energy transaction management. Determine the optimal electricity price and distribute profits to improve system coupling and user participation.
It improves energy utilization efficiency, reduces carbon emissions, enhances market efficiency, improves user participation and the effect of power demand response adjustment mechanism, and makes the coordinated operation transaction management between the building and the park more efficient and economical.
Smart Images

Figure BDA0004980053460000021 
Figure BDA0004980053460000023 
Figure BDA0004980053460000024
Abstract
Description
Technical Field
[0001] The present invention belongs to the technical field of electric power engineering and relates to a collaborative operation transaction management method and system. Background Art
[0002] With the acceleration of urbanization and the continuous development of the economy, the energy management efficiency of the park, as an important part of urban energy consumption, directly affects the energy utilization efficiency and carbon emission level of the entire society.
[0003] Traditional load management methods mainly rely on empirical scheduling and static planning, often ignoring the energy interaction and collaborative optimization potential between buildings and parks, resulting in low energy efficiency, relatively high energy costs, lack of flexibility and real-time response capabilities, and difficulty in adapting to the complex and changing electricity market and energy supply environment. By utilizing artificial intelligence technology, a large amount of complex energy data can be analyzed and processed to achieve more accurate and dynamic load forecasting, optimization of scheduling strategies, and energy trading management; especially in micro-energy systems such as buildings and parks, buildings are part of the park. Through artificial intelligence technology, more detailed and personalized energy management can be achieved between the two levels of buildings and parks, further improving energy efficiency and economic benefits; however, the collaborative operation and trading management between buildings and parks has the following problems: (1) Difficulty in resource coordination: Although the park can integrate a variety of distributed energy resources, how to achieve stable output of renewable energy? Under such circumstances, it is still a technical difficulty to efficiently coordinate the operation of these energy resources and ensure the stability of the power system. Ignoring the coordination of energy resources may lead to disorderly competition between electricity buyers and sellers, thereby reducing market efficiency; (2) High carbon emissions: While improving energy utilization efficiency and pursuing economic benefits, the park often fails to consider the impact of energy resources on the environment, resulting in high carbon emissions; (3) Low user participation: In the current park model, due to the disorderly competition between electricity buyers and sellers, especially in commercial and residential areas such as buildings, the user participation is low, which greatly reduces the effectiveness of the power demand response regulation mechanism and greatly affects the successful implementation of the park. Summary of the invention
[0004] In order to solve the problems of difficult resource coordination, high carbon emissions and low user participation in the collaborative operation transaction management between buildings and parks as described in the background technology, the present invention proposes a collaborative operation transaction management method and system between buildings and parks.
[0005] The method of the present invention comprises:
[0006] Based on the historical operation data of renewable energy between the building and the park in various scenarios, the power generation of renewable energy in various scenarios in the future is predicted according to the distribution density function, and the probability of occurrence of various scenarios of renewable energy in the future is calculated by the K-means clustering algorithm. Based on the power generation of renewable energy in various scenarios in the future and the probability of occurrence of various scenarios of renewable energy in the future, the income function of renewable energy is constructed;
[0007] The power generation of the gas turbine at the future time is obtained based on the historical operation data of the gas turbine between the building and the park. The carbon emission rights trading cost is calculated based on the historical carbon emission data between the building and the park. The income function of gas turbine power generation is constructed based on the power generation of the gas turbine at the future time and the carbon emission rights trading cost.
[0008] Based on the revenue function of renewable energy and the revenue function of gas turbine power generation, the objective function of maximizing the revenue of energy aggregators is constructed;
[0009] According to the load curve after the power demand response between the building and the park, the load criterion with only shape characteristics is calculated, and the response performance of the adjustable load is evaluated through the load criterion. According to the evaluation results of the response performance of the adjustable load, the objective function of maximizing the profit of the load aggregator is constructed;
[0010] According to the objective function of maximizing the profit of energy aggregators, the corresponding power supply under the condition of maximizing the profit of energy aggregators is determined. According to the objective function of maximizing the profit of load aggregators, the corresponding power demand under the condition of maximizing the profit of load aggregators is determined. The optimal electricity price is calculated based on the power supply and power demand, profits are distributed to power generation participants, and coordinated operation and transaction management are carried out between the two levels of buildings and parks.
[0011] Furthermore, the renewable energy includes wind power generation energy and photovoltaic power generation energy;
[0012] The calculation method of the power generation of the wind power generation energy in various scenarios at future moments is as follows:
[0013] Using the Rayleigh distribution density function as the correct expression model for wind speed behavior, the expression is:
[0014]
[0015] In the formula, is the shape parameter, σ is the scale parameter, and v is the wind speed parameter;
[0016] The probability of a wind speed state is calculated by:
[0017]
[0018] Taking the average value of each interval as the input wind speed, the wind power calculation formula at the future time t is as follows:
[0019]
[0020] Where P t wt is the wind power generation at time t in the future; v t is the actual speed of the wind turbine at time t in the future; v in is the cut-in wind speed of the wind turbine; v out is the cut-out wind speed of the wind turbine; v rated is the rated wind speed of the wind turbine; P R is the rated output power of the wind turbine generator set;
[0021] The calculation method of the power generation of the photovoltaic power generation energy in various scenarios at future moments is as follows:
[0022] The solar irradiance is described by Beta distribution, and the calculation formula is as follows:
[0023]
[0024] Where f(θ) represents the probability density function of solar radiation intensity, θ is the solar radiation intensity, α and β are the parameters of the Beta distribution function, u is the average value of solar radiation intensity, and σ is the standard deviation of solar irradiance;
[0025] The calculation formula of photovoltaic power generation at time t in the future is as follows:
[0026] P PV,t =η PV ×S PV ×θ t ,
[0027] Where P PV,t is the photovoltaic power output power at time t in the future; S PV is the total area of solar photovoltaic panels; η PV is the energy conversion efficiency of the solar photovoltaic panel; θ t is the solar radiation intensity at time t in the future.
[0028] Furthermore, the revenue function of renewable energy includes a wind power generation revenue function and a photovoltaic power generation revenue function;
[0029] The wind power generation income function I wt The expression is:
[0030]
[0031] Among them, π(γ) represents the probability of future power generation of wind power; Γ represents all scenarios of future power generation of wind power; is the electricity price at time t in the future, Y t wt To convert the operating cost to the dispatch interval; To convert the scrap income into dispatch interval; is the wind deviation cost;
[0032] Wind Deviation Cost The expression is:
[0033]
[0034] In the formula, C o The cost factor for overestimating wind power generation; is the available wind power at time t in the future; C u is the cost factor for underestimating wind power generation, C o ≥C u ;
[0035] The photovoltaic power generation income function I pv The expression is:
[0036]
[0037] Among them, π(γ) represents the probability of the scene, Γ Represents the total scene, P t pv is the power generation of photovoltaic power generation at time t, is the electricity price at time t, Y t pv is the operating cost converted to the dispatch interval, and They represent the scrap income and PV deviation cost converted into the dispatch interval respectively.
[0038] Furthermore, the income function I of the gas turbine power generation is gt The expression is:
[0039]
[0040] Where P t gt is the power generated by the gas turbine at time t in the future, is the electricity price of the gas turbine at the future time t, C c is the fuel cost, g c The cost of carbon emission rights trading;
[0041] The power generation power P of the gas turbine at the future time tt gt The constraints are expressed as:
[0042]
[0043] In the formula, The upper limit of the power generation capacity of the gas turbine; It is the lower limit of gas turbine power generation; is the upper limit of the gas turbine ramp rate; is the lower limit of the gas turbine ramp rate;
[0044] The carbon emission rights trading cost g c It is expressed as:
[0045]
[0046] In the formula, g c is the carbon emission rights trading cost, λ c is the carbon emission rights trading price, μ is the handling fee ratio, e t is the carbon emission at time t in the future, and R is the carbon emission quota;
[0047] The carbon emissions at time t in the future are e t And the carbon emission quota R satisfies:
[0048]
[0049] In the formula, e t is the carbon emission at time t in the future, R is the carbon emission quota, r buy is the carbon emission quota purchased; sell is the carbon emission quota sold, k represents the specific type of greenhouse gas, and p k and q k represents the emission factor associated with the kth greenhouse gas, P t gt is the power generated by the gas turbine at time t in the future.
[0050] Furthermore, the energy aggregator's profit maximization objective function expression is as follows:
[0051]
[0052] In the formula, gas turbine power generation, wind power generation and photovoltaic power generation form a cooperative game alliance, that is, N1 = {GT}, N2 = {WT}, N3 = {PV}, the grand alliance is recorded as N1 = {GT, WT, PV}, and the strategy set is the output of power generation equipment, recorded as ψ c = {P t gt ,P t wt,P t pv}; is the total profit of alliance N; i represents the i-th power generation participant; C c For fuel costs; is the electricity selling price of the i-th power generation participant; is the government subsidy price for the i-th power generation participant; is the power generation of the ith power generation participant.
[0053] Furthermore, the load aggregator profit maximization objective function is constructed as follows:
[0054] First, the load curve after demand response is calculated using the demand price elasticity matrix to obtain the load criterion with only shape characteristics. The demand price elasticity matrix M is expressed as:
[0055]
[0056] In the formula, ε i,j is the price elasticity coefficient of demand in the i-th time period relative to the j-th time period, i and j are two different time nodes in the scheduling phase; ΔP i The amount of load transferred or reduced; P i 0 is the total load, Δλ j is the electricity price change after DR, is the initial electricity price; when i=j, it is called self-elasticity, that is, the load cannot be shifted and will only appear when the demand is reduced; when i≠j, it is called cross-elasticity, that is, some loads can be shifted from peak period to non-peak period or valley period;
[0057] The load curve after demand response is expressed as:
[0058]
[0059] In the formula, is the total load at time t after the implementation of demand response; P t is the original load, Δλ t is the change in electricity price, λ t is the original electricity price;
[0060] The load curve after demand response is normalized to obtain a load line with only shape characteristics, which is expressed as:
[0061]
[0062] In the formula, is the optimal load at time t after normalization;
[0063] The expression for evaluating the response performance of the adjustable load is:
[0064]
[0065] Where ω is the line similarity; e represents the base of the natural logarithm; d is the Euclidean distance between the actual load shape of the adjustable load and the load line with only shape features; γ is a constant set by the load aggregator; ω0 is the similarity threshold; is the actual load at time t;
[0066] The load aggregator's profit maximization objective function is expressed as:
[0067]
[0068] In the formula, is the price of electricity sold by the load aggregator to the user at time t; is the price of electricity purchased by the load aggregator from the dispatching control center at time t; m is the subsidy price for users to participate in the response performance.
[0069] Furthermore, the optimal electricity price is calculated as follows:
[0070] A Stackelberg game model is constructed. The power generation participants in the Stackelberg game model are the park dispatching and control center, load aggregators and energy aggregators, denoted as N2 = {DCC, LA, EA}, where the park dispatching and control center is the leader, and the load aggregators and energy aggregators are followers. The power demand corresponding to the load aggregator's profit maximization and the power supply corresponding to the energy aggregator's profit maximization are transmitted to the park dispatching and control center. The purchase and sale prices of the park dispatching and control center are denoted as and The amount of electricity purchased from the large power grid is recorded as P t grid , the policy set is represented as The objective function is expressed as follows:
[0071]
[0072] Among them, F DCC For the benefits of the dispatching control center, represents the revenue from the dispatching control center selling electricity to load aggregators, represents the expenditure of the dispatching control center on purchasing electricity from energy aggregators, The expenditure of the dispatching and control center for purchasing electricity from the large power grid is calculated as follows:
[0073]
[0074] in, represents the electricity price sold by the dispatching control center to the load aggregator, λ t wt and λ t pv are the electricity sales prices of gas turbine, wind power and photovoltaic power generation, and They represent the electricity selling and purchasing prices from the dispatching control center to the large power grid at time t, P t DR represents the total load at time t after the implementation of demand response, P t EA is the total electricity sales of the energy aggregator EA at time t, which is equal to the sum of the power generation of gas turbines, wind power, and photovoltaics;
[0075] The relevant constraints are as follows:
[0076]
[0077] In the formula, Indicates the price of electricity purchased by the large power grid from the power generation unit; It represents the price of electricity sold by energy aggregators to the large grid; They are the electricity purchase prices that energy aggregators pay to gas turbine generators, wind power and photovoltaic generators;
[0078] The method of profit distribution among the power generation participants is as follows:
[0079] The Shapley method is used to distribute profits according to the contribution values of power generation participants including gas turbine power generation, wind power generation and photovoltaic power generation. The expression is as follows:
[0080]
[0081] in, represents the Shapley value of power generation participant i, ν(S) is the characteristic function of the cooperative game, and S is the number of power generation participants. The characteristic function here is a concept in cooperative game, which describes a function of the benefits that each possible cooperative alliance can obtain, that is, the total benefits that each alliance can obtain.
[0082] Furthermore, the process of solving the optimal electricity price and profit distribution of power generation participants is as follows:
[0083] 1) Input the original data and parameters to initialize the data required to establish the Stackelberg game model, including load data, electricity prices and parameters required to calculate the profits of power generation participants;
[0084] 2) Set the initial value for the equilibrium point and select the initial value for the policy space of each decision variable. The initial value is randomly selected in the policy space;
[0085] 3) Optimize the strategies of energy aggregators and load aggregators respectively, and determine the optimal strategy combination of energy aggregators and load aggregators based on NSGA-II and GA;
[0086] 4) Determine whether the Nash equilibrium of the cooperative game is reached by checking whether the obtained result satisfies the following formula:
[0087]
[0088] in, They represent the power generation of gas turbine, wind power and photovoltaic power at time t when iterating to the jth step. The equation shows that the output of gas turbine, wind power and photovoltaic power is the same at the jth step and j-1 step, and Nash equilibrium is reached at this time. The results are recorded as
[0089] 5) According to the optimization process of step 3) and step 4), the result of Stackelberg game is output: the optimal electricity price and the profit distribution result of power generation participants;
[0090] 6) Evaluate whether the Stackelberg-Nash equilibrium is satisfied and ensure that the result meets the following criteria:
[0091]
[0092] u E =(P t gt ,P t wt ,P t pv ),
[0093]
[0094] Among them, u D ,u E ,u L The strategies of the park dispatching control center, energy aggregator and load aggregator are respectively, j represents the number of iteration steps, and the equation of the first formula shows that the strategies of the park dispatching control center, energy aggregator and load aggregator are the same at the j-1 step, and the Nash equilibrium is reached at this time. The results are recorded as
[0095] If satisfied, output the result; if not satisfied, return to step 4) and iterate again.
[0096] The present invention also proposes a collaborative operation transaction management system between the building and park levels, including a revenue function construction module for renewable energy, a revenue function construction module for gas turbine power generation, a target function construction module for energy aggregator profit maximization, a target function construction module for load aggregator profit maximization, and an optimal electricity price calculation and profit distribution module.
[0097] The module for constructing the income function of renewable energy is used to predict the power generation of renewable energy in various scenarios at future moments according to the distribution density function based on the historical operation data of renewable energy between the building and the park in various scenarios, and calculate the probability of occurrence of various scenarios of renewable energy at future moments through the K-means clustering algorithm, and construct the income function of renewable energy according to the power generation of renewable energy in various scenarios at future moments and the probability of occurrence of various scenarios of renewable energy at future moments. The module for constructing the income function of gas turbine power generation is used to obtain the power generation of gas turbine at future moments according to the historical operation data of gas turbine between the building and the park, calculate the carbon emission rights trading cost according to the historical carbon emission data between the building and the park, and construct the income function of gas turbine power generation according to the power generation of gas turbine at future moments and the carbon emission rights trading cost. The module for constructing the objective function for maximizing the income of energy aggregators is used to construct the objective function for maximizing the income of energy aggregators according to the income function of renewable energy and the income function of gas turbine power generation. The load aggregator profit maximization objective function construction module is used to calculate the load criterion with only shape characteristics according to the load curve after the power demand response between the building and the park, evaluate the response performance of the adjustable load through the load criterion, and construct the load aggregator profit maximization objective function according to the evaluation result of the adjustable load response performance. The optimal electricity price calculation and profit distribution module is used to determine the corresponding power supply under the condition of maximizing the energy aggregator profit according to the energy aggregator profit maximization objective function, determine the corresponding power demand under the condition of maximizing the load aggregator profit according to the load aggregator profit maximization objective function, calculate the optimal electricity price based on the power supply and power demand, distribute profits to power generation participants, and conduct collaborative operation transaction management between the building and the park.
[0098] The present invention also proposes an electronic device, comprising: a memory and a processor, wherein the memory and the processor are communicatively connected to each other, the memory stores computer instructions, and the processor implements the above-mentioned collaborative operation transaction management method between the building and the park by executing the computer instructions.
[0099] The present invention also proposes a computer-readable storage medium, which stores a computer program. When the computer program is executed by a processor, it implements the above-mentioned collaborative operation transaction management method between the building and the park.
[0100] Compared with the prior art, the present invention constructs an objective function for maximizing the revenue of energy aggregators based on the revenue function of renewable energy and the revenue function of gas turbine power generation for the micro energy system between the building and the park; constructs an objective function for maximizing the revenue of load aggregators based on the response performance evaluation result of adjustable loads; and combines the power supply corresponding to the case of maximizing the revenue of energy aggregators and the power demand corresponding to the case of maximizing the revenue of load aggregators according to the objective function to obtain the optimal electricity price, distribute profits to power generation participants, and conduct collaborative operation and transaction management between the building and the park. The present invention takes into account the interaction between the entities in the park, coordinates distributed resources and power demand through the park, enhances system coupling under the condition of stable output of renewable energy, efficiently coordinates the operation of these energy resources, ensures the stability of the power system, and effectively reduces carbon emissions while improving energy utilization efficiency, avoiding disorderly competition between power buyers and sellers, greatly improving market efficiency, improving user participation, and improving the effect of the power demand response adjustment mechanism, so that it can be successfully implemented between the building and the park. The present invention realizes the optimal dispatch of power resources in the park through price signals, so that all power generation participants can make profits and optimize energy consumption, thereby improving market efficiency and increasing economic benefits. The present invention improves the energy utilization efficiency of the park, optimizes the energy consumption structure, promotes the green and low-carbon development of the power grid, and provides important economic and technical guidance for the operation and management of the park system. BRIEF DESCRIPTION OF THE DRAWINGS
[0101] Figure 1 It is a flow chart of the present invention.
[0102] Figure 2 This is a schematic diagram of the park aggregate scheduling structure of the present invention.
[0103] Figure 3 Schematic diagram of wind power generation and photovoltaic power generation output in different scenarios of the present invention.
[0104] Figure 4 It is a schematic diagram of the original load in the present invention and the load curve after participating in demand response, that is, the DR load.
[0105] Figure 5 A schematic diagram of a solution framework for collaborative transaction management according to the present invention.
[0106] Figure 6 It is a schematic diagram of the output of each power generation unit in the present invention.
[0107] Figure 7 This is a schematic diagram comparing the biological benefits of each participant in the present invention.
[0108] Figure 8 It is a structural schematic diagram of the present invention. DETAILED DESCRIPTION
[0109] The implementation of the present invention is described in detail below in conjunction with the accompanying drawings, but they do not constitute a limitation of the present invention, but are only examples. At the same time, through the description, the advantages of the present invention will be more clearly understood. All variations that can be directly derived or associated with the content disclosed by ordinary technicians in the field should be considered as the protection scope of the present invention. Other parts not described in detail in the embodiments are all prior art.
[0110] The micro energy system between the building and the park of the present invention includes: gas turbine power generation, wind power generation equipment and photovoltaic power generation equipment, power-consuming buildings and a dispatching control center. The park aggregate dispatching structure is as follows: Figure 2 As shown in the figure, collaborative operation transactions include two levels: the lower level is the optimal allocation of resources for buildings and power generation equipment; the upper level focuses on the price setting of the park dispatching and control center and the interaction with the power grid.
[0111] The main responsibilities of each party are summarized as follows:
[0112] 1) The main responsibility of the load aggregator (LA) is to collect the electricity consumption data of building users and determine the hourly load capacity; calculate the 24-hour electricity demand curve based on the demand price elasticity coefficient and feed it back to the dispatch control center. At the same time, the load curve is normalized to obtain a load criterion with only shape characteristics, which is released to demand-side electricity users and corresponding subsidies are provided based on the criterion similarity.
[0113] 2) The Energy Aggregator (EA) centrally manages the power generation strategies of gas turbine power generation, wind power generation and photovoltaic power generation units. Based on the initial quotation provided by the dispatching and control center, the cooperative game method is used to optimize the power generation plan of distributed energy resources, and the optimized 24-hour power supply curve is transmitted to the dispatching and control center.
[0114] 3) The Dispatch Control Center (DCC) receives 24-hour power supply and demand information transmitted by energy aggregators and load aggregators to ensure coordination between the power grid, energy aggregators and load aggregators. If there is an imbalance between supply and demand, the Dispatch Control Center needs to calculate the amount of electricity to be purchased from or sold to the power grid.
[0115] Example 1
[0116] The present invention proposes a collaborative operation transaction management method between buildings and parks, the process is as follows Figure 1 As shown, the specific steps are described as follows.
[0117] Based on the historical operation data of renewable energy between the building and the park levels under various scenarios, the power generation of renewable energy in various scenarios in the future is predicted according to the distribution density function, and the probability of occurrence of various scenarios of renewable energy in the future is calculated through the K-means clustering algorithm. According to the power generation of renewable energy in various scenarios in the future and the probability of occurrence of various scenarios of renewable energy in the future, the income function of renewable energy is constructed.
[0118] Specifically, renewable energy consists of wind power generation energy and photovoltaic power generation energy.
[0119] The calculation method of wind power generation power under various scenarios at future times is as follows:
[0120] Using the Rayleigh distribution density function as the correct expression model for wind speed behavior, the expression is:
[0121]
[0122] In the formula, is the shape parameter, σ is the scale parameter, and v is the wind speed parameter;
[0123] The probability of a wind speed state is calculated by:
[0124]
[0125] Taking the average value of each interval as the input wind speed, the wind power calculation formula at the future time t is as follows:
[0126]
[0127] Where P t wt is the wind power generation at time t in the future; v t is the actual speed of the wind turbine at time t in the future; v in is the cut-in wind speed of the wind turbine; v out is the cut-out wind speed of the wind turbine; v rated is the rated wind speed of the wind turbine; P R is the rated output power of the wind turbine.
[0128] The calculation method of photovoltaic power generation power under various scenarios at future times is:
[0129] The solar irradiance is described by Beta distribution, and the calculation formula is as follows:
[0130]
[0131]
[0132] Where f(θ) represents the probability density function of solar radiation intensity, θ is the solar radiation intensity, α and β are the parameters of the Beta distribution function, u is the average value of solar radiation intensity, and σ is the standard deviation of solar irradiance;
[0133] The calculation formula of photovoltaic power generation at time t in the future is as follows:
[0134] P PV,t =η PV ×S PV ×θ t ,
[0135] Where P PV,t is the photovoltaic power output power at time t in the future; S PV is the total area of solar photovoltaic panels; η PV is the energy conversion efficiency of the solar photovoltaic panel; θ t is the solar radiation intensity at time t in the future.
[0136] The specific method of calculating the probability of various scenarios of wind power generation at the future moment and the probability of power generation of various scenarios of photovoltaic power generation at the future moment by using the K-means clustering algorithm includes:
[0137] The generated wind power and light intensity data are used to generate multiple scenarios through probability density functions. In this embodiment, there are 1000 scenarios. The K-means algorithm is used to reduce the multiple scenarios to several selected scenarios. In this embodiment, there are 10 selected scenarios. The corresponding probability of each scenario is obtained. These scenarios fully represent the uncertainty of wind power generation and photovoltaic power generation scenarios. The results are as follows: Figure 3 As shown, Figure 3 A in represents the photovoltaic power generation curve. Figure 3 B in the figure represents the wind power generation curve. Figure 3 The wind power and photovoltaic curves under different scenarios can be obtained to represent the uncertainty of wind power and photovoltaic output, which is convenient for studying the impact of uncertain scenarios on the results.
[0138] The income function of renewable energy consists of wind power generation income function and photovoltaic power generation income function.
[0139] Wind power generation income function I wt The expression is:
[0140]
[0141] Among them, π(γ) represents the probability of future power generation of wind power; Γ represents all scenarios of future power generation of wind power; is the electricity price at time t in the future, Y t wt To convert the operating cost to the dispatch interval; To convert the scrap income into dispatch interval; is the wind deviation cost;
[0142] Wind Deviation Cost The expression is:
[0143]
[0144] In the formula, C o The cost factor for overestimating wind power generation; is the available wind power at time t in the future; C u is the cost factor for underestimating wind power generation, C o ≥C u .
[0145] Photovoltaic power generation income function I pv The expression is:
[0146]
[0147] Among them, π(γ) represents the probability of the scene, Γ Represents the total scene, P t pv is the power generation of photovoltaic power generation at time t, is the electricity price at time t, Y t pv is the operating cost converted to the dispatch interval, and They represent the scrap income and PV deviation cost converted into the dispatch interval respectively.
[0148] The power generation capacity of the gas turbine in the future is obtained based on the historical operation data of the gas turbine between the building and the park. The carbon emission rights trading cost is calculated based on the historical carbon emission data between the building and the park. The income function of gas turbine power generation is constructed based on the power generation capacity of the gas turbine in the future and the carbon emission rights trading cost.
[0149] In this embodiment, the power generation demand is met by a small gas turbine, photovoltaic power, and wind power. The power generation of each power generation is determined by a cooperative game model. The small gas turbine is set to generate electricity to make up for the shortfall when wind power and photovoltaic power cannot meet the power demand. Therefore, the income function of gas turbine power generation is gt The expression is:
[0150]
[0151] Where Pt gt is the power generated by the gas turbine at time t in the future, is the electricity price of the gas turbine at the future time t, C c is the fuel cost, g c The cost of carbon emission rights trading;
[0152] The power generation power P of the gas turbine at the future time t t gt The constraints are expressed as:
[0153]
[0154] In the formula, The upper limit of the power generation capacity of the gas turbine; It is the lower limit of gas turbine power generation; is the upper limit of the gas turbine ramp rate; is the lower limit of the gas turbine ramp rate;
[0155] Carbon emission rights trading costg c It is expressed as:
[0156]
[0157] In the formula, g c is the carbon emission rights trading cost, λ c is the carbon emission rights trading price, μ is the handling fee ratio, e t is the carbon emission at time t in the future, and R is the carbon emission quota;
[0158] The purpose of considering the transaction cost of carbon emission rights is to reduce carbon emissions and transfer power generation rights to renewable energy. When the carbon emissions caused by the power generation party in one day exceed its carbon emission quota, it should purchase the corresponding difference. Conversely, the power generation party sells the remaining certified emission reductions in the market. The carbon emissions at time t in the future e t And the carbon emission quota R satisfies:
[0159]
[0160]
[0161] In the formula, e t is the carbon emission at time t in the future, R is the carbon emission quota, r buy is the carbon emission quota purchased; sell is the carbon emission quota sold, k represents the specific type of greenhouse gas, and p k and q k represents the emission factor associated with the kth greenhouse gas, P t gtis the power generated by the gas turbine at time t in the future.
[0162] Then, based on the revenue function of renewable energy and the revenue function of gas turbine power generation, the objective function of maximizing the revenue of the energy aggregator is constructed.
[0163] Based on the income function of photovoltaic power generation, wind power generation and thermal power generation, and taking into account the uncertainty penalty of wind and photovoltaic power generation, carbon emission trading costs and wind deviation costs, the objective function expression of maximizing the revenue of energy aggregators is obtained as follows:
[0164]
[0165] In the formula, gas turbine power generation, wind power generation and photovoltaic power generation form a cooperative game alliance, that is, N1 = {GT}, N2 = {WT}, N3 = {PV}, the grand alliance is recorded as N1 = {GT, WT, PV}, and the strategy set is the output of power generation equipment, recorded as ψ c = {P t gt ,P t wt ,P t pv}; is the total profit of alliance N; i represents the i-th power generation participant; C c For fuel costs; is the electricity selling price of the i-th power generation participant; is the government subsidy price for the i-th power generation participant; is the power generation of the ith power generation participant.
[0166] Next, based on the load curve after the power demand response between the building and the park, the load criterion with only shape characteristics is calculated. The response performance of the adjustable load is evaluated through the load criterion, and the objective function of maximizing the load aggregator's profit is constructed according to the evaluation results of the response performance of the adjustable load.
[0167] In this embodiment, by collecting the building load data of a certain park, the peak load periods are 9:00-12:00 and 15:00-18:00, the flat load periods are 12:00-15:00 and 18:00-20:00, and the valley load periods are 00:00-09:00 and 20:00-24:00. The user's willingness to respond to demand varies with time. The relevant demand price elasticity coefficient is given in Table 1. Therefore, the demand price elasticity matrix can be obtained through the demand price elasticity coefficient in Table 1.
[0168] Table 1 Price elasticity coefficient of demand in different periods
[0169]
[0170] The load curve after demand response is calculated using the demand price elasticity matrix, and the load line with only shape characteristics is obtained. The demand price elasticity matrix M is expressed as:
[0171]
[0172] In the formula, ε i,j is the price elasticity coefficient of demand in the i-th time period relative to the j-th time period, i and j are two different time nodes in the scheduling phase; ΔP i The amount of load transferred or reduced; P i 0 is the total load, Δλ j is the electricity price change after DR, is the initial electricity price. When i=j, it is called self-elasticity, that is, the load cannot be transferred and it will only appear when the demand is reduced. When i≠j, it is called cross-elasticity, that is, some loads can be transferred from peak period to non-peak period or valley period.
[0173] The load curve after demand response is expressed as:
[0174]
[0175] In the formula, is the total load at time t after the implementation of demand response; P t is the original load, Δλ t is the change in electricity price, λ t The original electricity price.
[0176] The normal load of users who do not participate in demand response is the original load curve obtained based on historical data, and the load curve after participating in demand response is DR load. Figure 4 As shown, from Figure 4 It can be seen that the peak load of the load implementing demand response has been reduced relative to the original load, and the peak and valley loads have been supplemented, achieving the effect of peak shaving and valley filling.
[0177] The load curve after demand response is normalized to obtain a load line with only shape characteristics, which is convenient for the subsequent accurate quantification of demand response performance, expressed as:
[0178]
[0179] In the formula, is the optimal load at time t after normalization;
[0180] The expression for evaluating the response performance of the adjustable load is:
[0181]
[0182] In the formula, ω is the line similarity; e represents the base of the natural logarithm; d is the Euclidean distance between the actual load shape of the adjustable load and the load line with only shape characteristics; γ is a constant set by the load aggregator; ω0 is the similarity threshold. If it is lower than this value, the adjustable load is considered to have no contribution to the demand response and no incentive compensation will be given; the purpose of incentive compensation is to encourage users to participate in demand response, that is, the closer the user is to the published load line, the more compensation he will get, and the better the effect of demand response will be; is the actual load at time t;
[0183] After obtaining the response performance of the adjustable load, the load aggregator pays according to the actual response performance of the load. The purpose of payment is to encourage users to participate in demand response to achieve better peak shaving and valley filling effects. Based on this, the load aggregator's profit maximization objective function is expressed as:
[0184]
[0185] In the formula, is the price of electricity sold by the load aggregator to the user at time t; is the price of electricity purchased by the load aggregator from the dispatching control center at time t; m is the subsidy price for users to participate in the response performance.
[0186] Finally, the corresponding power supply under the condition of maximizing the energy aggregator's profit is determined according to the objective function of maximizing the energy aggregator's profit. The corresponding power demand under the condition of maximizing the load aggregator's profit is determined according to the objective function of maximizing the load aggregator's profit. The optimal electricity price is calculated based on the power supply and power demand, profits are distributed to power generation participants, and coordinated operation and transaction management are carried out between the buildings and the park levels.
[0187] The best electricity price is calculated as follows:
[0188] A Stackelberg game model is constructed. The power generation participants are the park dispatching and control center, load aggregators, and energy aggregators, denoted as N2 = {DCC, LA, EA}, where the park dispatching and control center is the leader, and the load aggregators and energy aggregators are followers. The power demand corresponding to the maximization of the load aggregator's profit and the power supply corresponding to the maximization of the energy aggregator's profit are transmitted to the park dispatching and control center. The purchase and sale prices of the park dispatching and control center are denoted as λ t EA and Lambda t LA, the amount of electricity purchased from the large power grid is recorded as P t grid , the strategy set is represented by ψ d ={λ tEA ,λ t LA ,P t grid}, the objective function is expressed as follows:
[0189]
[0190] Among them, F DCC For the benefits of the dispatching control center, represents the revenue from the dispatching control center selling electricity to load aggregators, represents the expenditure of the dispatching control center on purchasing electricity from energy aggregators, The expenditure of the dispatching and control center for purchasing electricity from the large power grid is calculated as follows:
[0191]
[0192] Among them, λ t LA represents the electricity price sold by the dispatching control center to the load aggregator, λ t wt and λ t pv are the electricity sales prices of gas turbine, wind power and photovoltaic power generation, and They represent the electricity selling and purchasing prices from the dispatching control center to the large power grid at time t, P t DR represents the total load at time t after the implementation of demand response, P t EA It is the total electricity sales of energy aggregator EA at time t, which is equal to the sum of power generation of gas turbines, wind power and photovoltaic power.
[0193] The relevant constraints are as follows:
[0194]
[0195] In the formula, Indicates the price of electricity purchased by the large power grid from the power generation unit; It represents the price of electricity sold by energy aggregators to the large grid; They are the electricity purchase prices that energy aggregators pay to gas turbine generators, wind power and photovoltaic generators;
[0196] The method of profit distribution among power generation participants is as follows:
[0197] The Shapley method is used to distribute profits according to the contribution values of power generation participants including gas turbine power generation, wind power generation and photovoltaic power generation. The expression is as follows:
[0198]
[0199] in, represents the Shapley value of power generation participant i, ν(S) is the characteristic function of the cooperative game, and S is the number of power generation participants. The characteristic function here is a concept in cooperative game, which describes a function of the benefits that each possible cooperative alliance can obtain, that is, the total benefits that each alliance can obtain.
[0200] like Figure 5 As shown in Figure 2, the optimal electricity price and profit distribution of power generation participants are solved as follows:
[0201] 1) Input the original data and parameters to initialize the data required to establish the Stackelberg game model, including load data, electricity prices and parameters required to calculate the profits of power generation participants;
[0202] 2) Set the initial value for the equilibrium point and select the initial value for the policy space of each decision variable. The initial value is randomly selected in the policy space;
[0203] 3) Optimize the strategies of energy aggregators and load aggregators respectively, and determine the optimal strategy combination of energy aggregators and load aggregators based on NSGA-II and GA;
[0204] 4) Determine whether the Nash equilibrium of the cooperative game is reached by checking whether the obtained result satisfies the following formula:
[0205]
[0206] in, They represent the power generation of gas turbine, wind power and photovoltaic power at time t when iterating to the jth step. The equation shows that the output of gas turbine, wind power and photovoltaic power is the same at the jth step and j-1 step, and Nash equilibrium is reached at this time. The results are recorded as
[0207] 5) According to the optimization process of step 3) and step 4), the result of Stackelberg game is output: the optimal electricity price and the profit distribution result of power generation participants;
[0208] 6) Evaluate whether the Stackelberg-Nash equilibrium is satisfied and ensure that the result meets the following criteria:
[0209]
[0210] u E =(P t gt ,P t wt ,P t pv),
[0211]
[0212] Among them, u D ,u E ,u L The strategies of the park dispatching control center, energy aggregator and load aggregator are respectively, j represents the number of iteration steps, and the equation of the first formula shows that the strategies of the park dispatching control center, energy aggregator and load aggregator are the same at the j-1 step, and the Nash equilibrium is reached at this time. The results are recorded as
[0213] If satisfied, output the result; if not satisfied, return to step 4) and iterate again.
[0214] In a specific case, when the Stackelberg-Nash equilibrium is reached, the output of each power generation unit is as follows: Figure 6 As shown, Figure 6 Grid in the middle represents the large power grid. Figure 6 Indicates that the internal power supply and demand are unbalanced, and it is necessary to purchase or sell power from the large power grid; the revenue comparison between the dispatching control center, load aggregator and energy aggregator is as follows: Figure 7 As shown, it can be seen that after adopting the present invention, the income of each entity is improved relative to the original income.
[0215] Example 2
[0216] The present invention proposes a collaborative operation transaction management system between buildings and parks, and its architecture diagram is as follows: Figure 8 As shown, it consists of a revenue function building module for renewable energy, a revenue function building module for gas turbine power generation, a target function building module for energy aggregator revenue maximization, a target function building module for load aggregator revenue maximization, and an optimal electricity price calculation and profit distribution module.
[0217] The module for constructing the income function of renewable energy is used to predict the power generation of renewable energy in various scenarios in the future according to the distribution density function based on the historical operation data of renewable energy between the building and park levels in various scenarios, and calculate the probability of occurrence of various scenarios of renewable energy in the future through the K-means clustering algorithm. The income function of renewable energy is constructed based on the power generation of renewable energy in various scenarios in the future and the probability of occurrence of various scenarios of renewable energy in the future.
[0218] In the revenue function building block of renewable energy, renewable energy consists of wind power generation energy and photovoltaic power generation energy.
[0219] The calculation method of wind power generation power under various scenarios at future times is as follows:
[0220] Using the Rayleigh distribution density function as the correct expression model for wind speed behavior, the expression is:
[0221]
[0222] In the formula, is the shape parameter, σ is the scale parameter, and v is the wind speed parameter;
[0223] The probability of a wind speed state is calculated by:
[0224]
[0225] Taking the average value of each interval as the input wind speed, the wind power calculation formula at the future time t is as follows:
[0226]
[0227] Where P t wt is the wind power generation at time t in the future; v t is the actual speed of the wind turbine at time t in the future; v in is the cut-in wind speed of the wind turbine; v out is the cut-out wind speed of the wind turbine; v rated is the rated wind speed of the wind turbine; P R is the rated output power of the wind turbine.
[0228] The calculation method of photovoltaic power generation power under various scenarios at future times is:
[0229] The solar irradiance is described by Beta distribution, and the calculation formula is as follows:
[0230]
[0231] Where f(θ) represents the probability density function of solar radiation intensity, θ is the solar radiation intensity, α and β are the parameters of the Beta distribution function, u is the average value of solar radiation intensity, and σ is the standard deviation of solar irradiance;
[0232] The calculation formula of photovoltaic power generation at time t in the future is as follows:
[0233] P PV,t =η PV ×S PV ×θ t ,
[0234] Where P PV,t is the photovoltaic power output power at time t in the future; S PV is the total area of solar photovoltaic panels; ηPV is the energy conversion efficiency of the solar photovoltaic panel; θ t is the solar radiation intensity at time t in the future.
[0235] The specific method of calculating the probability of various scenarios of wind power generation at the future moment and the probability of power generation of various scenarios of photovoltaic power generation at the future moment by using the K-means clustering algorithm includes:
[0236] The generated wind power and light intensity data are used to generate multiple scenarios through probability density functions. In this embodiment, there are 1000 scenarios. The K-means algorithm is used to reduce the multiple scenarios to several selected scenarios. In this embodiment, there are 10 selected scenarios. The corresponding probability of each scenario is obtained. These scenarios fully represent the uncertainty of wind power generation and photovoltaic power generation scenarios. The results are as follows: Figure 3 As shown, Figure 3 A in represents the photovoltaic power generation curve. Figure 3 B in the figure represents the wind power generation curve. Figure 3 The wind power and photovoltaic curves under different scenarios can be obtained to represent the uncertainty of wind power and photovoltaic output, which is convenient for studying the impact of uncertain scenarios on the results.
[0237] The income function of renewable energy consists of wind power generation income function and photovoltaic power generation income function.
[0238] Wind power generation income function I wt The expression is:
[0239]
[0240] Among them, π(γ) represents the probability of future power generation of wind power; Γ represents all scenarios of future power generation of wind power; is the electricity price at time t in the future, Y t wt To convert the operating cost to the dispatch interval; To convert the scrap income into dispatch interval; is the wind deviation cost;
[0241] Wind Deviation Cost The expression is:
[0242]
[0243] In the formula, C o The cost factor for overestimating wind power generation; is the available wind power at time t in the future; C u is the cost factor for underestimating wind power generation, C o ≥C u .
[0244] Photovoltaic power generation income function I pv The expression is:
[0245]
[0246] Among them, π(γ) represents the probability of the scene, Γ represents the total scene, P t pv is the power generation of photovoltaic power generation at time t, λ t pv is the electricity price at time t, Y t pv is the operating cost converted to the dispatch interval, and They represent the scrap income and PV deviation cost converted into the dispatch interval respectively.
[0247] The revenue function construction module of gas turbine power generation is used to obtain the power generation of the gas turbine at a future time based on the historical operation data of the gas turbine between the building and the park level, calculate the carbon emission rights trading cost based on the historical carbon emission data between the building and the park level, and construct the revenue function of gas turbine power generation based on the power generation of the gas turbine at a future time and the carbon emission rights trading cost.
[0248] In this embodiment, the power generation demand is met by a small gas turbine, photovoltaic power, and wind power. The power generation of each power generation is determined by a cooperative game model. The small gas turbine is set to generate electricity to make up for the shortfall when wind power and photovoltaic power cannot meet the power demand. Therefore, the income function of gas turbine power generation is gt The expression is:
[0249]
[0250] In the formula, is the power generated by the gas turbine at time t in the future, is the electricity price of the gas turbine at the future time t, C c is the fuel cost, g c The cost of carbon emission rights trading;
[0251] The power generated by the gas turbine at the future time t The constraints are expressed as:
[0252]
[0253] In the formula, The upper limit of the power generation capacity of the gas turbine; It is the lower limit of gas turbine power generation; is the upper limit of the gas turbine ramp rate; is the lower limit of the gas turbine ramp rate;
[0254] Carbon emission rights trading costg c It is expressed as:
[0255]
[0256] In the formula, g c is the carbon emission rights trading cost, λ c is the carbon emission rights trading price, μ is the handling fee ratio, e t is the carbon emission at time t in the future, and R is the carbon emission quota.
[0257] The purpose of considering the transaction cost of carbon emission rights is to reduce carbon emissions and transfer power generation rights to renewable energy. When the carbon emissions caused by the power generation party in one day exceed its carbon emission quota, it should purchase the corresponding difference. Conversely, the power generation party sells the remaining certified emission reductions in the market. The carbon emissions at time t in the future e t And the carbon emission quota R satisfies:
[0258]
[0259] In the formula, e t is the carbon emission at time t in the future, R is the carbon emission quota, r buy is the carbon emission quota purchased; sell is the carbon emission quota sold, k represents the specific type of greenhouse gas, and p k and q k represents the emission factor associated with the kth greenhouse gas, P t gt is the power generated by the gas turbine at time t in the future.
[0260] The energy aggregator's revenue maximization objective function construction module is used to construct the energy aggregator's revenue maximization objective function based on the revenue function of renewable energy and the revenue function of gas turbine power generation.
[0261] Based on the income function of photovoltaic power generation, wind power generation and thermal power generation, and taking into account the uncertainty penalty of wind and photovoltaic power generation, carbon emission trading costs and wind deviation costs, the objective function expression of maximizing the revenue of energy aggregators is obtained as follows:
[0262]
[0263] In the formula, gas turbine power generation, wind power generation and photovoltaic power generation form a cooperative game alliance, that is, N1 = {GT}, N2 = {WT}, N3 = {PV}, the grand alliance is recorded as N1 = {GT, WT, PV}, and the strategy set is the output of power generation equipment, recorded as ψ c = {Pt gt ,P t wt ,P t pv}; is the total profit of alliance N; i represents the i-th power generation participant; C c For fuel costs; is the electricity selling price of the i-th power generation participant; is the government subsidy price for the i-th power generation participant; is the power generation of the ith power generation participant.
[0264] The load aggregator profit maximization objective function construction module is used to calculate the load criterion with only shape characteristics according to the load curve after the power demand response between the building and the park, evaluate the response performance of the adjustable load through the load criterion, and construct the load aggregator profit maximization objective function according to the evaluation result of the adjustable load response performance.
[0265] In this embodiment, by collecting the building load data of a certain park, the peak load periods are 9:00-12:00 and 15:00-18:00, the flat load periods are 12:00-15:00 and 18:00-20:00, and the valley load periods are 00:00-09:00 and 20:00-24:00. The user's willingness to respond to demand varies with time. The relevant demand price elasticity coefficient is given in Table 1. Therefore, the demand price elasticity matrix can be obtained through the demand price elasticity coefficient in Table 1.
[0266] Table 1 Price elasticity coefficient of demand in different periods
[0267]
[0268] The load curve after demand response is calculated using the demand price elasticity matrix, and the load line with only shape characteristics is obtained. The demand price elasticity matrix M is expressed as:
[0269]
[0270] In the formula, ε i,j is the price elasticity coefficient of demand in the i-th time period relative to the j-th time period, i and j are two different time nodes in the scheduling phase; ΔP i The amount of load transferred or reduced; P i 0 is the total load, Δλ j is the electricity price change after DR, is the initial electricity price. When i=j, it is called self-elasticity, that is, the load cannot be transferred and it will only appear when the demand is reduced. When i≠j, it is called cross-elasticity, that is, some loads can be transferred from peak period to non-peak period or valley period.
[0271] The load curve after demand response is expressed as:
[0272]
[0273] In the formula, is the total load at time t after the implementation of demand response; P t is the original load, Δλ t is the change in electricity price, λ t The original electricity price.
[0274] The normal load of users who do not participate in demand response is the original load curve obtained based on historical data, and the load curve after participating in demand response is DR load. Figure 4 As shown, from Figure 4 It can be seen that the peak load of the load implementing demand response has been reduced relative to the original load, and the peak and valley loads have been supplemented, achieving the effect of peak shaving and valley filling.
[0275] The load curve after demand response is normalized to obtain a load line with only shape characteristics, which is convenient for the subsequent accurate quantification of demand response performance, expressed as:
[0276]
[0277] In the formula, is the optimal load at time t after normalization;
[0278] The expression for evaluating the response performance of the adjustable load is:
[0279]
[0280] In the formula, ω is the line similarity; e represents the base of the natural logarithm; d is the Euclidean distance between the actual load shape of the adjustable load and the load line with only shape characteristics; γ is a constant set by the load aggregator; ω0 is the similarity threshold. If it is lower than this value, the adjustable load is considered to have no contribution to the demand response and no incentive compensation will be given; the purpose of incentive compensation is to encourage users to participate in demand response, that is, the closer the user is to the published load line, the more compensation he will get, and the better the effect of demand response will be; is the actual load at time t;
[0281] After obtaining the response performance of the adjustable load, the load aggregator pays according to the actual response performance of the load. The purpose of payment is to encourage users to participate in demand response to achieve better peak shaving and valley filling effects. Based on this, the load aggregator's profit maximization objective function is expressed as:
[0282]
[0283] In the formula, is the electricity price that the load aggregator sells to users at time t; t LA is the price of electricity purchased by the load aggregator from the dispatching control center at time t; m is the subsidy price for users to participate in the response performance.
[0284] The optimal electricity price calculation and profit distribution module is used to determine the corresponding power supply when the energy aggregator's profit is maximized according to the energy aggregator's profit maximization objective function, and determine the corresponding power demand when the load aggregator's profit is maximized according to the load aggregator's profit maximization objective function. The optimal electricity price is calculated based on the power supply and power demand situations, profits are distributed to power generation participants, and collaborative operation transaction management is carried out between the building and the park levels.
[0285] The best electricity price is calculated as follows:
[0286] A Stackelberg game model is constructed, in which the power generation participants are the park dispatching and control center, load aggregators and energy aggregators, denoted as N2 = {DCC, LA, EA}, where the park dispatching and control center is the leader, and the load aggregators and energy aggregators are followers. The power demand corresponding to the load aggregator's profit maximization and the power supply corresponding to the energy aggregator's profit maximization are transmitted to the park dispatching and control center. The purchase and sale prices of the park dispatching and control center are denoted as and The amount of electricity purchased from the large power grid is recorded as P t grid , the policy set is represented as The objective function is expressed as follows:
[0287]
[0288] Among them, F DCC For the benefits of the dispatching control center, represents the revenue from the dispatching control center selling electricity to load aggregators, represents the expenditure of the dispatching control center on purchasing electricity from energy aggregators, The expenditure of the dispatching and control center for purchasing electricity from the large power grid is calculated as follows:
[0289]
[0290] Among them, λt LA represents the electricity price sold by the dispatching control center to the load aggregator, λ t gt , t wt and λ t pv are the electricity sales prices of gas turbine, wind power and photovoltaic power generation, and They represent the electricity selling and purchasing prices from the dispatching control center to the large power grid at time t, P t DR represents the total load at time t after the implementation of demand response, P t EA It is the total electricity sales of energy aggregator EA at time t, which is equal to the sum of power generation of gas turbines, wind power and photovoltaic power.
[0291] The relevant constraints are as follows:
[0292]
[0293] In the formula, Indicates the price of electricity purchased by the large power grid from the power generation unit; It represents the price of electricity sold by energy aggregators to the large grid; λ t wt ,λ t pv They are the electricity purchase prices that energy aggregators pay to gas turbine generators, wind power and photovoltaic generators;
[0294] The method of profit distribution among power generation participants is as follows:
[0295] The Shapley method is used to distribute profits according to the contribution values of power generation participants including gas turbine power generation, wind power generation and photovoltaic power generation. The expression is as follows:
[0296]
[0297] in, represents the Shapley value of power generation participant i, ν(S) is the characteristic function of the cooperative game, and S is the number of power generation participants. The characteristic function here is a concept in cooperative game, which describes a function of the benefits that each possible cooperative alliance can obtain, that is, the total benefits that each alliance can obtain.
[0298] like Figure 5 As shown in Figure 2, the optimal electricity price and profit distribution of power generation participants are solved as follows:
[0299] 1) Input the original data and parameters to initialize the data required to establish the Stackelberg game model, including load data, electricity prices and parameters required to calculate the profits of power generation participants;
[0300] 2) Set the initial value for the equilibrium point and select the initial value for the policy space of each decision variable. The initial value is randomly selected in the policy space;
[0301] 3) Optimize the strategies of energy aggregators and load aggregators respectively, and determine the optimal strategy combination of energy aggregators and load aggregators based on NSGA-II and GA;
[0302] 4) Determine whether the Nash equilibrium of the cooperative game is reached by checking whether the obtained result satisfies the following formula:
[0303]
[0304] in, They represent the power generation of gas turbine, wind power and photovoltaic power at time t when iterating to the jth step. The equation shows that the output of gas turbine, wind power and photovoltaic power is the same at the jth step and j-1 step, and Nash equilibrium is reached at this time. The results are recorded as
[0305] 5) According to the optimization process of step 3) and step 4), the result of Stackelberg game is output: the optimal electricity price and the profit distribution result of power generation participants;
[0306] 6) Evaluate whether the Stackelberg-Nash equilibrium is satisfied and ensure that the result meets the following criteria:
[0307]
[0308] u E =(P t gt ,P t wt ,P t pv ),
[0309]
[0310] Among them, u D ,u E ,u L The strategies of the park dispatching control center, energy aggregator and load aggregator are respectively, j represents the number of iteration steps, and the equation of the first formula shows that the strategies of the park dispatching control center, energy aggregator and load aggregator are the same at the j-1 step, and the Nash equilibrium is reached at this time. The results are recorded as
[0311] If satisfied, output the result; if not satisfied, return to step 4) and iterate again.
[0312] In a specific case, when the Stackelberg-Nash equilibrium is reached, the output of each power generation unit is as follows: Figure 6 As shown, Figure 6 Grid in the middle represents the large power grid. Figure 6 Indicates that the internal power supply and demand are unbalanced, and it is necessary to purchase or sell power from the large power grid; the revenue comparison between the dispatching control center, load aggregator and energy aggregator is as follows: Figure 7 As shown, it can be seen that after adopting the present invention, the income of each entity is improved relative to the original income.
[0313] Example 3
[0314] An electronic device includes: a memory and a processor, the memory and the processor are communicatively connected to each other, the memory stores computer instructions, and the processor implements the collaborative operation transaction management method between the building and the park level described in Example 1 by executing the computer instructions.
[0315] Example 4
[0316] The present invention also proposes a computer-readable storage medium, which stores a computer program. When the computer program is executed by a processor, it implements the collaborative operation transaction management method between the building and the park level described in Example 1.
[0317] Those skilled in the art will appreciate that the embodiments of the present application can be provided as methods, systems, or computer program products. Therefore, the present application can adopt the form of complete hardware embodiments, complete software embodiments, or embodiments in combination with software and hardware. Moreover, the present application can adopt the form of a computer program product implemented on one or more computer-usable storage media (including but not limited to disk storage, CD-ROM, optical storage, etc.) that contain computer-usable program code. The scheme in the embodiments of the present application can be implemented in various computer languages, for example, object-oriented programming language Java and literal scripting language JavaScript, etc.
[0318] The present application is described with reference to the flowcharts and / or block diagrams of the methods, devices (systems), and computer program products according to the embodiments of the present application. It should be understood that each process and / or box in the flowchart and / or block diagram, as well as the combination of the processes and / or boxes in the flowchart and / or block diagram, can be implemented by computer program instructions. These computer program instructions can be provided to a processor of a general-purpose computer, a special-purpose computer, an embedded processor, or other programmable data processing device to generate a machine, so that the instructions executed by the processor of the computer or other programmable data processing device generate instructions for implementing the processes in the flowchart and / or block diagram. Figure 1 A process or multiple processes and / or boxes Figure 1 A device that provides the functions specified in a block or multiple blocks.
[0319] These computer program instructions may also be stored in a computer-readable memory capable of directing a computer or other programmable data processing device to operate in a specific manner, so that the instructions stored in the computer-readable memory produce an article of manufacture comprising an instruction device, which implements the process Figure 1 A process or multiple processes and / or boxes Figure 1 A function specified in one or more boxes.
[0320] These computer program instructions can also be loaded onto a computer or other programmable data processing device so that a series of operating steps are executed on the computer or other programmable device to produce a computer-implemented process, thereby providing instructions for implementing the process. Figure 1 A process or multiple processes and / or boxes Figure 1 The steps for the functions specified in one or more boxes.
[0321] Although the preferred embodiments of the present application have been described, those skilled in the art may make other changes and modifications to these embodiments once they have learned the basic creative concept. Therefore, the appended claims are intended to be interpreted as including the preferred embodiments and all changes and modifications falling within the scope of the present application.
[0322] Obviously, those skilled in the art can make various changes and modifications to the present application without departing from the spirit and scope of the present application. Thus, if these modifications and variations of the present application fall within the scope of the claims of the present application and their equivalents, the present application is also intended to include these modifications and variations.
Claims
1. A collaborative transaction management method between buildings and parks. It is characterized in that include: Based on the historical operation data of renewable energy between the building and the park in various scenarios, the power generation of renewable energy in various scenarios in the future is predicted according to the distribution density function, and the probability of occurrence of various scenarios of renewable energy in the future is calculated by the K-means clustering algorithm. Based on the power generation of renewable energy in various scenarios in the future and the probability of occurrence of various scenarios of renewable energy in the future, the income function of renewable energy is constructed; The power generation of the gas turbine at the future time is obtained based on the historical operation data of the gas turbine between the building and the park. The carbon emission rights trading cost is calculated based on the historical carbon emission data between the building and the park. The income function of gas turbine power generation is constructed based on the power generation of the gas turbine at the future time and the carbon emission rights trading cost. Based on the revenue function of renewable energy and the revenue function of gas turbine power generation, the objective function of maximizing the revenue of energy aggregators is constructed; According to the load curve after the power demand response between the building and the park, the load criterion with only shape characteristics is calculated, and the response performance of the adjustable load is evaluated through the load criterion. According to the evaluation results of the response performance of the adjustable load, the objective function of maximizing the profit of the load aggregator is constructed; According to the objective function of maximizing the profit of energy aggregators, the corresponding power supply under the condition of maximizing the profit of energy aggregators is determined. According to the objective function of maximizing the profit of load aggregators, the corresponding power demand under the condition of maximizing the profit of load aggregators is determined. The optimal electricity price is calculated based on the power supply and power demand, profits are distributed to power generation participants, and coordinated operation and transaction management are carried out between the two levels of buildings and parks.
2. According to the collaborative operation transaction management method between buildings and parks as described in claim 1, Features: The renewable energy includes wind power generation energy and photovoltaic power generation energy; The calculation method of the power generation of the wind power generation energy in various scenarios at future moments is as follows: Using the Rayleigh distribution density function as the correct expression model for wind speed behavior, the expression is: In the formula, is the shape parameter, σ is the scale parameter, and v is the wind speed parameter; The probability of a wind speed state is calculated by: Taking the average value of each interval as the input wind speed, the wind power calculation formula at the future time t is as follows: Where P t wt is the wind power generation at time t in the future; v t is the actual speed of the wind turbine at time t in the future; v in is the cut-in wind speed of the wind turbine; v out is the cut-out wind speed of the wind turbine; v rated is the rated wind speed of the wind turbine; P R is the rated output power of the wind turbine generator set; The calculation method of the power generation of the photovoltaic power generation energy in various scenarios at future moments is as follows: The solar irradiance is described by Beta distribution, and the calculation formula is as follows: Where f(θ) represents the probability density function of solar radiation intensity, θ is the solar radiation intensity, α and β are the parameters of the Beta distribution function, u is the average value of solar radiation intensity, and σ is the standard deviation of solar irradiance; The calculation formula of photovoltaic power generation at time t in the future is as follows: P PV,t =the PV ×S PV ×θ t , Where P PV,t is the photovoltaic power output power at time t in the future; S PV is the total area of solar photovoltaic panels; η PV is the energy conversion efficiency of the solar photovoltaic panel; θ t is the solar radiation intensity at time t in the future; The income function of the renewable energy includes a wind power generation income function and a photovoltaic power generation income function; The wind power generation income function I wt The expression is: Among them, π(γ) represents the probability of future power generation of wind power; Γ represents all scenarios of future power generation of wind power; is the electricity price at time t in the future, Y t wt To convert the operating cost to the dispatch interval; To convert the scrap income into dispatch interval; is the wind deviation cost; Wind Deviation Cost The expression is: In the formula, C o The cost factor for overestimating wind power generation; is the available wind power at time t in the future; C u is the cost factor for underestimating wind power generation, C o ≥C u ; The photovoltaic power generation income function I pv The expression is: Among them, π(γ) represents the probability of the scene, Γ Represents the total scene, P t pv is the power generation of photovoltaic power generation at time t, is the electricity price at time t, Y t pv is the operating cost converted to the dispatch interval, and They represent the scrap income and PV deviation cost converted into the dispatch interval respectively.
3. The collaborative operation transaction management method between buildings and parks according to claim 2, Features: The income function of gas turbine power generation I gt The expression is: Where P t gt is the power generated by the gas turbine at time t in the future, is the electricity price of the gas turbine at the future time t, C c is the fuel cost, g c The cost of carbon emission rights trading; The power generation power P of the gas turbine at the future time t t gt The constraints are expressed as: In the formula, The upper limit of the power generation capacity of the gas turbine; It is the lower limit of gas turbine power generation; is the upper limit of the gas turbine ramp rate; is the lower limit of the gas turbine ramp rate; The carbon emission rights trading cost g c It is expressed as: In the formula, g c is the carbon emission rights trading cost, λ c is the carbon emission rights trading price, μ is the handling fee ratio, e t is the carbon emission at time t in the future, and R is the carbon emission quota; The carbon emissions at time t in the future are e t And the carbon emission quota R satisfies: In the formula, e t is the carbon emission at time t in the future, R is the carbon emission quota, r buy is the carbon emission quota purchased; sell is the carbon emission quota sold, k represents the specific type of greenhouse gas, and p k and q k represents the emission factor associated with the kth greenhouse gas, P t gt is the power generated by the gas turbine at time t in the future.
4. The collaborative operation transaction management method between buildings and parks according to claim 3, Features: The energy aggregator's profit maximization objective function expression is as follows: In the formula, gas turbine power generation, wind power generation and photovoltaic power generation form a cooperative game alliance, that is, N 1 ={GT},N 2 ={WT},N 3 ={PV}, the grand coalition is denoted as N1 = {GT, WT, PV}, and the strategy set is the output of the power generation equipment, denoted as ψ c = {P t gt ,P t wt ,P t pv }; is the total profit of alliance N; i represents the i-th power generation participant; C c For fuel costs; is the electricity selling price of the i-th power generation participant; is the government subsidy price for the i-th power generation participant; is the power generation of the ith power generation participant.
5. The collaborative operation transaction management method between buildings and parks according to claim 4, Features: The method for constructing the load aggregator profit maximization objective function is as follows: First, the load curve after demand response is calculated using the demand price elasticity matrix to obtain the load criterion with only shape characteristics. The demand price elasticity matrix M is expressed as: In the formula, ε i,j is the price elasticity coefficient of demand in the i-th time period relative to the j-th time period, i and j are two different time nodes in the scheduling phase; ΔP i The amount of load transferred or reduced; P i 0 is the total load, Δλ j is the electricity price change after DR, is the initial electricity price; when i=j, it is called self-elasticity, that is, the load cannot be shifted and will only appear when the demand is reduced; when i≠j, it is called cross-elasticity, that is, some loads can be shifted from peak period to non-peak period or valley period; The load curve after demand response is expressed as: In the formula, is the total load at time t after the implementation of demand response; P t is the original load, Δλ t is the change in electricity price, λ t is the original electricity price; The load curve after demand response is normalized to obtain a load line with only shape characteristics, which is expressed as: In the formula, is the optimal load at time t after normalization; The expression for evaluating the response performance of the adjustable load is: Where ω is the line similarity; e represents the base of the natural logarithm; d is the Euclidean distance between the actual load shape of the adjustable load and the load line with only shape characteristics; γ is a constant set by the load aggregator; ω 0 is the similarity threshold; is the actual load at time t; The load aggregator's profit maximization objective function is expressed as: In the formula, is the price of electricity sold by the load aggregator to the user at time t; is the price of electricity purchased by the load aggregator from the dispatching control center at time t; m is the subsidy price for users to participate in the response performance.
6. The collaborative operation transaction management method between buildings and parks according to claim 5, Features: The calculation method of the optimal electricity price is as follows: construct a Stackelberg game model, in which the power generation participants are the park dispatching and control center, the load aggregator and the energy aggregator, denoted as N2={DCC, LA, EA}, wherein the park dispatching and control center is the leader, the load aggregator and the energy aggregator are followers, and the power demand corresponding to the load aggregator's profit maximization and the power supply corresponding to the energy aggregator's profit maximization are transmitted to the park dispatching and control center. The purchase and sale prices of the park dispatching and control center are respectively denoted as and The amount of electricity purchased from the large power grid is recorded as P t grid , the policy set is represented as The objective function is expressed as follows: Among them, F DCC For the benefits of the dispatching control center, represents the revenue from the dispatching control center selling electricity to load aggregators, represents the expenditure of the dispatching control center on purchasing electricity from energy aggregators, The expenditure of the dispatching and control center for purchasing electricity from the large power grid is calculated as follows: in, represents the electricity price sold by the dispatching control center to the load aggregator, λ t gt , t wt and λ t pv are the electricity sales prices of gas turbine, wind power and photovoltaic power generation, and They represent the electricity selling and purchasing prices from the dispatching control center to the large power grid at time t, P t DR represents the total load at time t after the implementation of demand response, P t EA is the total electricity sales of the energy aggregator EA at time t, which is equal to the sum of the power generation of gas turbines, wind power, and photovoltaics; The relevant constraints are as follows: In the formula, Indicates the price of electricity purchased by the large power grid from the power generation unit; It represents the price of electricity sold by energy aggregators to the large grid; λ t wt ,λ t pv They are the electricity purchase prices that energy aggregators pay to gas turbine generators, wind power and photovoltaic generators; The method for distributing profits among power generation participants is to use the Shapley method to distribute profits according to the contribution values of power generation participants including gas turbine power generation, wind power generation and photovoltaic power generation. The expression is as follows: in, represents the Shapley value of power generation participant i, ν(S) is the characteristic function of the cooperative game, and S is the number of power generation participants.
7. The collaborative operation transaction management method between buildings and parks according to claim 6, Features: The specific process of solving the optimal electricity price and profit distribution of power generation participants is as follows: 1) Input the original data and parameters to initialize the data required to establish the Stackelberg game model, including load data, electricity prices and parameters required to calculate the profits of power generation participants; 2) Set the initial value for the equilibrium point and select the initial value for the policy space of each decision variable. The initial value is randomly selected in the policy space; 3) Optimize the strategies of energy aggregators and load aggregators respectively, and determine the optimal strategy combination of energy aggregators and load aggregators based on NSGA-II and GA; 4) Determine whether the Nash equilibrium of the cooperative game is reached by checking whether the obtained result satisfies the following formula: in, They represent the power generation of gas turbine, wind power and photovoltaic power at time t when iterating to the jth step. The equation shows that the output of gas turbine, wind power and photovoltaic power is the same at the jth step and j-1 step, and Nash equilibrium is reached at this time. The results are recorded as 5) According to the optimization process of step 3) and step 4), the result of Stackelberg game is output: the optimal electricity price and the profit distribution result of power generation participants; 6) Evaluate whether the Stackelberg-Nash equilibrium is satisfied and ensure that the result meets the following criteria: u E =(P t gt ,P t wt ,P t pv ), Among them, u D ,u E ,u L The strategies of the park dispatching control center, energy aggregator and load aggregator are respectively, j represents the number of iteration steps, and the equation of the first formula shows that the strategies of the park dispatching control center, energy aggregator and load aggregator are the same at the j-1 step, and the Nash equilibrium is reached at this time. The results are recorded as If satisfied, output the result; if not satisfied, return to step 4) and iterate again.
8. A collaborative transaction management system between buildings and parks. Features: It includes a revenue function building module for renewable energy, a revenue function building module for gas turbine power generation, a target function building module for energy aggregator revenue maximization, a target function building module for load aggregator revenue maximization, and an optimal electricity price calculation and profit distribution module; The module for constructing the income function of renewable energy is used to predict the power generation of renewable energy in various scenarios at future moments according to the distribution density function based on the historical operation data of renewable energy between the building and the park in various scenarios, and calculate the probability of occurrence of various scenarios of renewable energy at future moments through the K-means clustering algorithm, and construct the income function of renewable energy according to the power generation of renewable energy in various scenarios at future moments and the probability of occurrence of various scenarios of renewable energy at future moments; The revenue function construction module of the gas turbine power generation is used to obtain the power generation of the gas turbine at a future time based on the historical operation data of the gas turbine between the building and the park, calculate the carbon emission rights trading cost based on the historical carbon emission data between the building and the park, and construct the revenue function of the gas turbine power generation based on the power generation of the gas turbine at a future time and the carbon emission rights trading cost; The energy aggregator revenue maximization objective function construction module is used to construct the energy aggregator revenue maximization objective function based on the revenue function of renewable energy and the revenue function of gas turbine power generation; The load aggregator profit maximization objective function construction module is used to calculate the load criterion with only shape characteristics according to the load curve after the power demand response between the building and the park, evaluate the response performance of the adjustable load through the load criterion, and construct the load aggregator profit maximization objective function according to the evaluation result of the response performance of the adjustable load; The optimal electricity price calculation and profit distribution module is used to determine the corresponding power supply when the energy aggregator's profit is maximized according to the energy aggregator's profit maximization objective function, determine the corresponding power demand when the load aggregator's profit is maximized according to the load aggregator's profit maximization objective function, calculate the optimal electricity price based on the power supply and power demand situations, distribute profits to power generation participants, and conduct collaborative operation transaction management between buildings and parks.
9. The collaborative operation transaction management system between buildings and parks according to claim 8, Features: In the renewable energy income function building module, renewable energy includes wind power generation energy and photovoltaic power generation energy; The calculation method of the power generation of the wind power generation energy in various scenarios at future moments is as follows: Using the Rayleigh distribution density function as the correct expression model for wind speed behavior, the expression is: In the formula, is the shape parameter, σ is the scale parameter, and v is the wind speed parameter; The probability of a wind speed state is calculated by: Taking the average value of each interval as the input wind speed, the wind power calculation formula at the future time t is as follows: Where P t wt is the wind power generation at time t in the future; v t is the actual speed of the wind turbine at time t in the future; v in is the cut-in wind speed of the wind turbine; v out is the cut-out wind speed of the wind turbine; v rated is the rated wind speed of the wind turbine; P R is the rated output power of the wind turbine generator set; The calculation method of the power generation of the photovoltaic power generation energy in various scenarios at future moments is as follows: The solar irradiance is described by Beta distribution, and the calculation formula is as follows: Where f(θ) represents the probability density function of solar radiation intensity, θ is the solar radiation intensity, α and β are the parameters of the Beta distribution function, u is the average value of solar radiation intensity, and σ is the standard deviation of solar irradiance; The calculation formula of photovoltaic power generation at time t in the future is as follows: P PV,t =the PV ×S PV ×θ t , Where P PV,t is the photovoltaic power output power at time t in the future; S PV is the total area of solar photovoltaic panels; η PV is the energy conversion efficiency of the solar photovoltaic panel; θ t is the solar radiation intensity at time t in the future; The income function of the renewable energy includes a wind power generation income function and a photovoltaic power generation income function; The wind power generation income function I wt The expression is: Among them, π(γ) represents the probability of future power generation of wind power; Γ represents all scenarios of future power generation of wind power; λ t wt is the electricity price at time t in the future, Y t wt To convert the operating cost to the dispatch interval; To convert the scrap income into dispatch interval; is the wind deviation cost; Wind Deviation Cost The expression is: In the formula, C o The cost factor for overestimating wind power generation; is the available wind power at time t in the future; C u is the cost factor for underestimating wind power generation, C o ≥C u ; The photovoltaic power generation income function I pv The expression is: Among them, π(γ) represents the probability of the scene, Γ Represents the total scene, P t pv is the power generation of photovoltaic power generation at time t, λ t pv is the electricity price at time t, Y t pv is the operating cost converted to the dispatch interval, and They represent the scrap income and PV deviation cost converted into the dispatch interval respectively.
10. The collaborative operation transaction management system between buildings and parks according to claim 9, Features: In the revenue function building module of the gas turbine power generation, the revenue function I of the gas turbine power generation gt The expression is: Where P t gt is the power generation of the gas turbine at the future time t, λ t gt is the electricity price of the gas turbine at the future time t, C c is the fuel cost, g c The cost of carbon emission rights trading; The power generation power P of the gas turbine at the future time t t gt The constraints are expressed as: In the formula, The upper limit of the power generation capacity of the gas turbine; It is the lower limit of gas turbine power generation; is the upper limit of the gas turbine ramp rate; is the lower limit of the gas turbine ramp rate; The carbon emission rights trading cost g c It is expressed as: In the formula, g c is the carbon emission rights trading cost, λ c is the carbon emission rights trading price, μ is the handling fee ratio, e t is the carbon emission at time t in the future, and R is the carbon emission quota; The carbon emissions at time t in the future are e t And the carbon emission quota R satisfies: In the formula, e t is the carbon emission at time t in the future, R is the carbon emission quota, r buy is the carbon emission quota purchased; sell is the carbon emission quota sold, k represents the specific type of greenhouse gas, and p k and q k represents the emission factor associated with the kth greenhouse gas, P t gt is the power generated by the gas turbine at time t in the future.
11. The collaborative operation transaction management system between buildings and parks according to claim 10, Features: In the energy aggregator profit maximization objective function construction module, the energy aggregator profit maximization objective function expression is as follows: In the formula, gas turbine power generation, wind power generation and photovoltaic power generation form a cooperative game alliance, that is, N 1 ={GT},N 2 ={WT},N 3 = {PV}, the grand alliance is denoted as N1 = {GT, WT, PV}, and the strategy set is the output of the power generation equipment, denoted as ψ c = {P t gt ,P t wt ,P t pv }; is the total profit of alliance N; i represents the i-th power generation participant; C c For fuel costs; is the electricity selling price of the i-th power generation participant; is the government subsidy price for the i-th power generation participant; is the power generation of the ith power generation participant.
12. The collaborative operation transaction management system between buildings and parks according to claim 11, Features: In the load aggregator profit maximization objective function construction module, the load aggregator profit maximization objective function construction method is: First, the load curve after demand response is calculated using the demand price elasticity matrix to obtain the load criterion with only shape characteristics. The demand price elasticity matrix M is expressed as: In the formula, ε i,j is the price elasticity coefficient of demand in the i-th time period relative to the j-th time period, i and j are two different time nodes in the scheduling phase; ΔP i The amount of load transferred or reduced; P i 0 is the total load, Δλ j is the electricity price change after DR, is the initial electricity price. When i=j, it is called self-elasticity, that is, the load cannot be shifted and will only appear when the demand is reduced. When i≠j, it is called cross-elasticity, that is, some loads can be shifted from peak period to non-peak period or valley period. The load curve after demand response is expressed as: In the formula, is the total load at time t after the implementation of demand response; P t is the original load, Δλ t is the change in electricity price, λ t is the original electricity price; The load curve after demand response is normalized to obtain a load line with only shape characteristics, which is expressed as: In the formula, is the optimal load at time t after normalization; The expression for evaluating the response performance of the adjustable load is: Where ω is the line similarity; e represents the base of the natural logarithm; d is the Euclidean distance between the actual load shape of the adjustable load and the load line with only shape characteristics; γ is a constant set by the load aggregator; ω 0 is the similarity threshold; is the actual load at time t; The load aggregator's profit maximization objective function is expressed as: In the formula, is the price of electricity sold by the load aggregator to the user at time t; is the price of electricity purchased by the load aggregator from the dispatching control center at time t; m is the subsidy price for users to participate in the response performance.
13. The collaborative operation transaction management system between buildings and parks according to claim 12, Features: In the optimal electricity price calculation and profit distribution module, the optimal electricity price is calculated by: constructing a Stackelberg game model, the power generation participants of the Stackelberg game model are the park dispatching and control center, the load aggregator and the energy aggregator, denoted as N2={DCC, LA, EA}, where the park dispatching and control center is the leader, the load aggregator and the energy aggregator are followers, and the power demand corresponding to the load aggregator's profit maximization and the power supply corresponding to the energy aggregator's profit maximization are transmitted to the park dispatching and control center. The purchase and sale prices of the park dispatching and control center are denoted as λ t EA and λ t LA , the amount of electricity purchased from the large power grid is recorded as P t grid , the policy set is represented as The objective function is expressed as follows: Among them, F DCC For the benefits of the dispatching control center, represents the revenue from the dispatching control center selling electricity to load aggregators, represents the expenditure of the dispatching control center on purchasing electricity from energy aggregators, The expenditure of the dispatching and control center for purchasing electricity from the large power grid is calculated as follows: in, represents the electricity price sold by the dispatching control center to the load aggregator, λ t gt , t wt and λ t pv are the electricity sales prices of gas turbine, wind power and photovoltaic power generation, and They represent the electricity selling and purchasing prices from the dispatching control center to the large power grid at time t, P t DR represents the total load at time t after the implementation of demand response, P t EA is the total electricity sales of the energy aggregator EA at time t, which is equal to the sum of the power generation of gas turbines, wind power, and photovoltaics; The relevant constraints are as follows: In the formula, Indicates the price of electricity purchased by the large power grid from the power generation unit; It represents the price of electricity sold by energy aggregators to the large grid; λ t wt ,λ t pv They are the electricity purchase prices that energy aggregators pay to gas turbine generators, wind power and photovoltaic generators; The method for distributing profits among power generation participants is to use the Shapley method to distribute profits according to the contribution values of power generation participants including gas turbine power generation, wind power generation and photovoltaic power generation. The expression is as follows: in, represents the Shapley value of power generation participant i, ν(S) is the characteristic function of the cooperative game, and S is the number of power generation participants.
14. The collaborative operation transaction management system between buildings and parks according to claim 13, Features: In the optimal electricity price calculation and profit distribution module, the optimal electricity price and the profit distribution of power generation participants are solved as follows: 1) Input the original data and parameters to initialize the data required to establish the Stackelberg game model, including load data, electricity prices and parameters required to calculate the profits of power generation participants; 2) Set the initial value for the equilibrium point and select the initial value for the policy space of each decision variable. The initial value is randomly selected in the policy space; 3) Optimize the strategies of energy aggregators and load aggregators respectively, and determine the optimal strategy combination of energy aggregators and load aggregators based on NSGA-II and GA; 4) Determine whether the Nash equilibrium of the cooperative game is reached by checking whether the obtained result satisfies the following formula: in, They represent the power generation of gas turbine, wind power and photovoltaic power at time t when iterating to the jth step. The equation shows that the output of gas turbine, wind power and photovoltaic power is the same at the jth step and j-1 step, and Nash equilibrium is reached at this time. The results are recorded as 5) According to the optimization process of step 3) and step 4), the result of Stackelberg game is output: the optimal electricity price and the profit distribution result of power generation participants; 6) Evaluate whether the Stackelberg-Nash equilibrium is satisfied and ensure that the result meets the following criteria: Among them, u D ,u E ,u L The strategies of the park dispatching control center, energy aggregator and load aggregator are respectively, j represents the number of iteration steps, and the equation of the first formula shows that the strategies of the park dispatching control center, energy aggregator and load aggregator are the same at the j-1 step, and the Nash equilibrium is reached at this time. The results are recorded as If satisfied, output the result; if not satisfied, return to step 4) and iterate again.
15. An electronic device, It is characterized in that include: A memory and a processor, wherein the memory and the processor are communicatively connected to each other, the memory stores computer instructions, and the processor implements the collaborative operation transaction management method between the building and the park level as described in any one of claims 1 to 7 by executing the computer instructions.
16. A computer-readable storage medium storing a computer program. Features: When the computer program is executed by a processor, the collaborative operation transaction management method between the building and the park level as described in any one of claims 1 to 7 is implemented.
Citation Information
Cited By
Virtual power plant optimal scheduling method and device considering demand and output uncertainty
CN122137022A