Nuclear power overhaul preparation plan management and control method and system

Through the preparation planning and control methods and systems of nuclear power overhaul preparation, the problem of low planning and tracking management and control efficiency in the preparation work of overhaul preparation is solved, and the effect of transparent task progress and convenient quality inspection is achieved, and the efficiency and quality of overhaul preparation management is improved.

CN119130430APending Publication Date: 2024-12-13CNNC NUCLEAR POWER OPERATION MANAGEMENT CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411133758.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-19
Publication Date
2024-12-13

AI Technical Summary

Technical Problem

Due to the long time span and the large number of participating departments and personnel preparations, the planning tracking and control efficiency is low, information transmission efficiency is low, execution progress tracking is difficult, and quality inspection is inconvenient.

Method used

提供一种核电大修准备计划管控方法和系统,包括编制大修准备计划内容,输入到管控系统中,分配任务,跟踪任务进展状态,控制延期和监测超期,通过数据存储、查询、匹配和互动模块实现任务管理。

Benefits of technology

The overall tracking and control of the overhaul preparation plan has been realized, the efficiency of the delivery of the plan content is improved, the task progress tracking is convenient, and the quality inspection is convenient, ensuring transparent task execution and storage of completion materials, and the quality inspection is conveniently completed.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119130430A_ABST
    Figure CN119130430A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of nuclear power overhaul, and provides a nuclear power overhaul preparation plan management and control method, which comprises the following steps of: compiling overhaul preparation plan contents according to overhaul preparation management requirements; inputting the compiled overhaul preparation plan content into a nuclear power overhaul preparation plan management and control system; specific task lines are distributed to corresponding responsible departments, preparation plan issuing is executed, and related task issuing notifications are sent to the corresponding responsible departments; tracking the task progress state, controlling the task delay and monitoring the task expiration. According to the invention, the overall tracking control of the overhaul preparation plan is realized, and the overhaul preparation work quality is improved through the preparation plan deviation identification.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of nuclear power overhaul, and in particular to a nuclear power overhaul preparation plan management and control method and system. Background Art

[0002] Doing a good job in overhaul preparation is the fundamental guarantee for nuclear power overhaul to create excellent performance. Implementing overhaul preparation work according to plan is an important measure for overhaul preparation. However, due to the long time span of overhaul preparation, many departments and personnel involved, and many tasks that need to be tracked and implemented, how to do a good job in tracking and controlling the overhaul plan is a difficulty that plagues nuclear power companies.

[0003] Normally, nuclear power companies manually track the overhaul preparation plan in EXCEL or PROJECT version. However, this method has low efficiency in information transmission, difficulty in tracking execution progress, and inconvenience in completing quality inspection. Summary of the invention

[0004] The purpose of the present invention is to provide a nuclear power overhaul preparation plan management and control method and system to improve the efficiency of overhaul preparation management and ensure the quality of preparation work.

[0005] In order to achieve the above object, the present invention provides the following technical solutions:

[0006] A nuclear power overhaul preparation plan management and control method, comprising:

[0007] Step 1: Prepare the contents of the overhaul preparation plan according to the overhaul preparation management requirements;

[0008] Step 2: Input the prepared overhaul preparation plan content into the nuclear power overhaul preparation plan management and control system;

[0009] Step 3: Allocate specific task lines to the corresponding responsible departments, issue the execution preparation plan, and send the relevant task issuance notification to the corresponding responsible departments;

[0010] Step 4: Track task progress status, control task extensions, and monitor task overdue.

[0011] In some embodiments, the overhaul preparation plan content includes task name, task category, responsible department, milestone number, milestone completion status, planned start time, planned completion time, task completion marker, and task weight in the preparation work.

[0012] In some embodiments, after receiving the task, each responsible department can choose to assign the task to a specific responsible person, or choose to return the task to the preparation planner to reallocate the responsible department.

[0013] In some embodiments, step 4 includes:

[0014] Step 4.1: The nuclear power overhaul preparation plan control system reads the milestone completion status data to determine the task progress;

[0015] Step 4.2: Propose a new planned completion time in the nuclear power overhaul preparation plan control system, and record the extension date after approval;

[0016] Step 4.3: Determine whether the task is completed beyond the deadline. When the task completion date exceeds the planned completion date, the nuclear power overhaul preparation plan management and control system will count the task as completed beyond the deadline and send the information to the person in charge of the task and the person in charge of the responsible department.

[0017] In some embodiments, the nuclear power overhaul preparation plan management and control method further includes:

[0018] Step 5: Confirm the completion status and close the task. The nuclear power overhaul preparation plan management and control system determines the task file submission status based on the feedback of the completion status. If the upload has been completed, the task will be closed.

[0019] On the other hand, the present invention also provides a nuclear power overhaul preparation plan management and control system, comprising:

[0020] A data storage module, used to store the contents of the overhaul preparation plan;

[0021] Data query module, used to filter query tasks;

[0022] Data matching module, used for tasks assigned by managers;

[0023] The data interaction module is used for task responsible persons and managers to interact with the nuclear power overhaul preparation plan management and control system.

[0024] In some embodiments, the data storage module is also used to record the task status of each task during execution; extension application and approval information during task execution; and when the task is completed, record the completion time, task closing instructions, and task closing attachment file data.

[0025] In some embodiments, during the data interaction process, the overhaul preparation plan content is imported into the nuclear power overhaul preparation plan management and control system through the data storage module using a standard template and stored in the storage module.

[0026] On the other hand, the present invention also provides a computer device, including a memory and a processor, wherein the memory stores computer-readable instructions, and when the processor executes the computer-readable instructions, the steps of the nuclear power overhaul preparation plan management and control method are implemented.

[0027] On the other hand, the present invention also provides a computer-readable storage medium, on which computer-readable instructions are stored, and when the computer-readable instructions are executed, the steps of the nuclear power overhaul preparation plan management and control method are implemented.

[0028] Compared with the prior art, the nuclear power overhaul preparation plan management and control method and system provided by the present invention have the following beneficial effects:

[0029] The present invention realizes the overall tracking and control of the overhaul preparation plan, and improves the quality of overhaul preparation work by identifying deviations from the preparation plan. The present invention realizes the online issuance, online tracking and promotion, and online inspection of the completion quality of the overhaul preparation plan, and realizes the transformation of overhaul preparation work from offline to online.

[0030] The present invention enables efficient content delivery of the overhaul preparation plan, convenient tracking of the progress of the preparation work, and convenient inspection of the quality of the preparation work.

[0031] Furthermore, by transmitting the overhaul preparation plan, the present invention enables each department to obtain the content of the preparation plan at the first time, and the query is convenient.

[0032] Furthermore, the present invention assigns tasks to task execution responsible persons in responsible departments, with clear division of labor, transparent task progress, and convenient tracking and statistics of preparatory work.

[0033] Furthermore, the present invention confirms the closing of the preparation task, and the task completion data is stored in the system, so that the quality inspection is completed conveniently. BRIEF DESCRIPTION OF THE DRAWINGS

[0034] In order to more clearly illustrate the technical solution of the present invention, the following briefly introduces the drawings required for the technical description.

[0035] Figure 1 A flow chart of the nuclear power overhaul preparation plan control method provided by the present invention;

[0036] Figure 2 A schematic diagram of the structure of the nuclear power overhaul preparation plan management and control system provided by the present invention. DETAILED DESCRIPTION

[0037] The following is further explained in detail through specific implementation methods.

[0038] like Figure 1 As shown, the present invention provides a nuclear power overhaul preparation plan management and control method, comprising the following steps:

[0039] Step 1: Prepare a preparation plan. According to the overhaul preparation management requirements, the management personnel prepare the corresponding overhaul preparation plan offline.

[0040] The overhaul preparation plan includes information such as task name, task category, responsible department, milestone number, milestone completion status, planned start time, planned completion time, task completion marker, and task weight in the preparation work.

[0041] Step 2: Input the prepared preparation plan into the nuclear power overhaul preparation plan management and control system. The management personnel upload the prepared overhaul preparation plan to the nuclear power overhaul preparation plan management and control system according to the template. The uploaded overhaul preparation plan can be viewed on the nuclear power overhaul preparation plan management and control system.

[0042] As an implementable method, the management personnel can add, delete, modify, etc. the content of the preparation plan. For example, when the start date of the overhaul is adjusted, the management personnel are required to make an overall adjustment to the completion time of each task in the preparation plan.

[0043] Step 3: Issue preparation plan.

[0044] After the preparation plan task is uploaded to the nuclear power overhaul preparation plan control system, it is selected and assigned to the corresponding responsible department according to the specific task line, and the preparation plan issuance operation is executed. Each responsible department will receive the relevant task issuance notification. After receiving the task, each responsible department can choose to issue the task to a specific responsible person, or choose to return the task to the preparation plan personnel to reassign the responsible department.

[0045] When the task is assigned to a specific person in charge, the nuclear power overhaul preparation plan management and control system records the name of the person in charge.

[0046] As an implementable method, the nuclear power overhaul preparation plan control system permits the adjustment of responsible persons by modifying their names.

[0047] Step 4: Track the progress of the preparation plan tasks.

[0048] Step 4 involves task progress status tracking, task extension control, and task overdue monitoring, as follows:

[0049] Step 4.1: Task progress judgment: The nuclear power overhaul preparation plan control system reads the milestone completion status data and judges the task progress.

[0050] Milestone completion status = Not started, the task has not been assigned to the responsible person, and execution has not started;

[0051] Milestone completion status = in progress, the task has been assigned to the responsible person and has started execution;

[0052] Milestone completion status = postponed, the task cannot be completed as planned and has been postponed;

[0053] Milestone Completion Status = Completed, the task has been completed and closed.

[0054] Step 4.2: Task extension operation.

[0055] The need for a new planned completion time is proposed in the nuclear power overhaul preparation plan control system. After approval, the nuclear power overhaul preparation plan control system records the approved extension date, and the person responsible for the task implements the extension task.

[0056] Step 4.3: Determine whether the task is completed beyond the deadline. When the task completion date exceeds the planned completion date, the nuclear power overhaul preparation plan management and control system will count the task as completed beyond the deadline and send the information to the person in charge of the task and the person in charge of the responsible department.

[0057] Step 5: Confirm the completion status and close the task. The Nuclear Power Overhaul Preparation Plan Management and Control System determines the task file submission status based on the feedback of the completion status. If the upload has been completed, the task will be closed.

[0058] The confirmation can also be implemented in the following ways: After the task responsible person completes the task, the task responsible person will feedback the completion status in the nuclear power overhaul preparation plan management and control system and upload the documents required to complete the task. After confirmation by the overhaul preparation plan management personnel, the task is closed. The time when the task responsible person applies for completion is recorded in the system as the task completion date. When the task completion date exceeds the planned completion date, the nuclear power overhaul preparation plan management and control system will count the task as overdue completion.

[0059] In addition, if Figure 2 As shown, the present invention also provides a nuclear power overhaul preparation plan management and control system, including a data storage module, a data query module, a data matching module, and a data interaction module.

[0060] The data storage module is used to store the contents of the overhaul preparation plan imported into the nuclear power overhaul preparation plan management and control system. The contents of the overhaul preparation plan include the task name, responsible department, responsible person, planned start time, planned completion time, milestone number, task completion marker, and task category.

[0061] The data storage module is also used to record the task status of each task during execution; the extension application and approval information during task execution; and when the task is completed, the completion time, task closing instructions, and task closing attachment file data are recorded.

[0062] As an implementable manner, the data storage module permits administrators to upload and delete data.

[0063] The data query module is used to filter and query tasks, query completed task information, and query task list export. During the execution of the overhaul preparation plan, managers can filter out the preparation plan tasks that need to be queried by task name, responsible department, planned start time, planned completion time, milestone number, milestone status, etc.

[0064] The data query module provides the function of querying information of completed tasks. If a single preparation plan task has been completed, the selected plan task can be queried through the data query module, and the attachment file attached when the task is closed for review can be clicked.

[0065] The data query module provides the task list export query function. Through the data query module, managers can export task lists, milestone status, completion time, etc.

[0066] The data matching module is used for tasks assigned by managers. The task assignment operation is that managers associate the milestone number of the preparation plan task with the name information of the responsible person for a specific task. After the nuclear power overhaul preparation plan management and control system obtains the data, it is placed in the storage module.

[0067] The data interaction module is used for task responsible persons and managers to interact with the nuclear power overhaul preparation plan management and control system.

[0068] After the task is issued, the task responsible person and the management personnel can interact through the nuclear power overhaul preparation plan management and control system, mainly including:

[0069] (1) Task upload: Import the overhaul preparation plan content into the system using a standard template through the data storage module and store it in the storage module;

[0070] (2) Task assignment: Fill the responsible person information into the responsible person field through the data matching module;

[0071] (3) Modify the task responsible person: fill the responsible person information into the new responsible person field through the data matching module;

[0072] (4) Task extension: Enter information in the extension application through the data interaction module and submit a new task completion date. Modify the task completion date according to actual needs through the data interaction module, and the system will record the milestone status as extension.

[0073] (5) Task completion: The data storage module records the task completion time, task completion description, and task completion marker file data, records the milestone status as completed, and stores the task closing marker data.

[0074] Therefore, the overhaul preparation plan control system of the present invention realizes high-efficiency information transmission of overhaul preparation plan management, no omissions in task execution, full control of task progress, monitorable completion quality, and queryable historical data.

[0075] In addition, the present invention also provides a computer device, including a memory and a processor, the memory storing computer-readable instructions, and the processor implementing the steps of the above-mentioned nuclear power overhaul preparation plan management and control method when executing the computer-readable instructions.

[0076] In addition, the present invention also provides a computer-readable storage medium, on which computer-readable instructions are stored, and when the computer-readable instructions are executed, the steps of the above-mentioned nuclear power overhaul preparation plan management and control method are implemented.

[0077] Computer readable media include permanent and non-permanent, removable and non-removable media that can be implemented by any method or technology to store information. Information can be computer readable instructions, data structures, program modules or other data. Examples of computer storage media include, but are not limited to, phase change memory (PRAM), static random access memory (SRAM), dynamic random access memory (DRAM), other types of random access memory (RAM), read-only memory (ROM), electrically erasable programmable read-only memory (EEPROM), flash memory or other memory technology, compact disk read-only memory (CD-ROM), digital versatile disk (DVD) or other optical storage, magnetic cassettes, magnetic tape magnetic disk storage or other magnetic storage devices or any other non-transmission media that can be used to store information that can be accessed by a computing device.

[0078] The above is only a specific embodiment of the present invention, but the protection scope of the present invention is not limited thereto. Any changes or substitutions that can be easily thought of by a person skilled in the art within the technical scope disclosed by the present invention should be included in the protection scope of the present invention. Therefore, the protection scope of the present invention should be based on the protection scope of the claims.

Claims

1. A method for controlling a nuclear power overhaul preparation plan, characterized in that: include: Step 1: Prepare the overhaul preparation plan content according to the overhaul preparation management requirements; Step 2: Input the prepared overhaul preparation plan content into the nuclear power overhaul preparation plan management and control system; Step 3: Assign specific tasks to the corresponding responsible departments, issue execution preparation plans, and send relevant task issuance notifications to the corresponding responsible departments; Step 4: Track task progress status, control task extensions, and monitor task overdue.

2. The method for controlling nuclear power overhaul preparation plan according to claim 1, characterized in that: The contents of the overhaul preparation plan include task name, task category, responsible department, milestone number, milestone completion status, planned start time, planned completion time, task completion marker, and task weight in the preparation work.

3. The method for controlling nuclear power overhaul preparation plan according to claim 1, characterized in that: In step 3, after receiving the task, each responsible department can choose to assign the task to a specific person in charge, or choose to return the task to the preparation planner to reallocate the responsible department.

4. The method for controlling nuclear power overhaul preparation plan according to claim 1, characterized in that: Step 4 includes: Step 4.1: The nuclear power overhaul preparation plan control system reads the milestone completion status data to determine the task progress; Step 4.2: Propose a new planned completion time in the nuclear power overhaul preparation plan control system, and record the extension date after approval; Step 4.3: Determine whether the task is completed beyond the deadline. When the task completion date exceeds the planned completion date, the nuclear power overhaul preparation plan management and control system will count the task as completed beyond the deadline and send the information to the person in charge of the task and the person in charge of the responsible department.

5. The method for controlling nuclear power overhaul preparation plan according to claim 1, characterized in that: The method further includes: Step 5: Confirm the completion status and close the task. The nuclear power overhaul preparation plan management and control system determines the task file submission status based on the feedback of the completion status. If the upload has been completed, the task will be closed.

6. A nuclear power overhaul preparation plan management and control system, characterized in that: include: A data storage module, used for storing the contents of the overhaul preparation plan; Data query module, used to filter query tasks; Data matching module, used for tasks assigned by managers; The data interaction module is used for task responsible persons and managers to interact with the nuclear power overhaul preparation plan management and control system.

7. The nuclear power overhaul preparation plan management and control system according to claim 6, characterized in that: The data storage module is also used to record the task status of each task during execution; the extension application and approval information during task execution; and when the task is completed, record the completion time, task closing instructions, and task closing attachment file data.

8. The nuclear power overhaul preparation plan management and control system according to claim 6, characterized in that: During the data interaction process, the overhaul preparation plan content is imported into the system through the data storage module using a standard template and stored in the storage module.

9. A computer device comprising a memory and a processor, wherein the memory stores computer-readable instructions, characterized in that: When the processor executes the computer-readable instructions, the steps of the nuclear power overhaul preparation plan management and control method described in any one of claims 1-5 are implemented.

10. A computer-readable storage medium having computer-readable instructions stored thereon, characterized in that: When the computer-readable instructions are executed, the steps of the nuclear power overhaul preparation plan management and control method described in any one of claims 1-5 are implemented.