Cable structure optimization design method and device and computer equipment

Through the combination of simulation and experiment, the hollow core position in the cable is identified and the core is filled to replace the current-free transmission part, which solves the problems of high cable production costs and waste of wire resources, and achieves the extension of wire life and improvement of conductivity.

CN119416286APending Publication Date: 2025-02-11特变电工山东鲁能泰山电缆有限公司
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202411467946.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-21
Publication Date
2025-02-11

AI Technical Summary

Technical Problem

The cable production cost is high and the wire resources are wasted due to the skin effect, and traditional hollow wires are prone to deformation and damage, affecting the conductive performance.

Method used

By acquiring cable structure data, building a cable structure model, simulating the current transmission process, identifying the hollow core position, adjusting the structural model to fill the core instead of the current-free transmission part, and screening the target cable structure data in combination with simulation and experiments.

Benefits of technology

Reduces waste of wire resources, extends wire life, improves conductive performance, and reduces material costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119416286A_ABST
    Figure CN119416286A_ABST
Patent Text Reader

Abstract

The invention relates to a cable structure optimization design method and device and computer equipment. The method comprises the following steps: acquiring cable structure data of a cable, and core structure information and physical performance information of each filling core, constructing a cable structure model of the cable based on the cable structure data to simulate a current transmission process so as to obtain simulation structure data of the cable, and constructing a cable structure model of the cable based on the simulation structure data of the cable, the position information of each hollow core of the cable is identified, so that the cable structure model is adjusted, a cable core structure model of each filling core is obtained, and target cable structure data of the cable is identified based on core structure simulation data of each cable core structure model and core structure experiment data of each cable core structure model. By adopting the method, the resource optimization effect of designing the cable conductor structure can be improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of cable structure optimization, and in particular to a cable structure optimization design method, device and computer equipment. Background Art

[0002] In order to reduce production costs, cable manufacturers need to continuously optimize production processes and improve production efficiency. However, although cable manufacturers can reduce production costs in a variety of ways, facing the growing market demand and fluctuations in raw material prices, cable production costs are still under great pressure. For cable operation, the skin effect is common. The skin effect is also known as the skin effect, which exists in alternating current or alternating electromagnetic fields. The skin effect causes the current density to be concentrated on the surface of the wire, resulting in no current passing through the center of the wire, resulting in the problem of waste of the center wire. Therefore, how to reduce the waste of wire resources caused by the skin effect is the current research focus.

[0003] The traditional method of optimizing conductor structure is to reduce the resource cost of the cable by designing hollow conductors. However, hollow conductors are prone to deformation and damage, which reduces the life of the conductors and affects the electrical conductivity of the cable. This results in a large loss of resources in designing the cable conductor structure while ensuring the electrical conductivity. Summary of the invention

[0004] Based on this, it is necessary to provide a cable structure optimization design method, device, computer equipment, computer readable storage medium and computer program product to address the above technical problems.

[0005] In a first aspect, the present application provides a cable structure optimization design method, comprising:

[0006] Acquire cable structure data of the cable, core structure information of each filling core, and physical property information of each filling core, and construct a cable structure model of the cable based on the cable structure data;

[0007] By using a preset electric field simulation strategy, in the cable structure model, the current transmission process is simulated to obtain the simulation structure data of the cable, and based on the simulation structure data of the cable, the position information of each hollow core of the cable is identified;

[0008] Based on the core structure information of each of the filling cores, the physical property information of each of the filling cores, and the position information of each of the hollow cores of the cable, the cable structure model is adjusted to obtain a cable core structure model of each of the filling cores, and the current transmission process of each of the cable core structure models is simulated to obtain core structure simulation data of each of the cable core structure models;

[0009] The core structure experimental data of the sample cable structure corresponding to each of the cable core structure models are collected, and based on the core structure simulation data of each of the cable core structure models and the core structure experimental data of each of the cable core structure models, the target cable structure data of the cable is identified.

[0010] Optionally, constructing a cable structure model of the cable based on the cable structure data includes:

[0011] Splitting the cable structure data into substructure data of each cable structure, and collecting relative position information of each cable structure in a cable database;

[0012] Based on the substructure data of each cable structure, a substructure model of each cable structure is constructed, and based on the relative position information of each cable structure, the substructure models of each cable structure are spliced ​​to obtain a cable structure model of the cable.

[0013] Optionally, simulating the current transmission process in the cable structure model through a preset electric field simulation strategy to obtain the simulated structure data of the cable includes:

[0014] By means of a preset electric field simulation strategy, in the cable structure model, the current transmission process is simulated to obtain the current transmission cross-sectional information in the cable structure model, and based on the current transmission cross-sectional information, the current transmission area in the conductor of the cable and the non-current transmission area in the conductor of the cable are identified;

[0015] Based on the current transmission area and the non-current transmission area, simulation structure data of the conductor is generated, and the simulation structure data of the conductor is used as simulation structure data of the cable.

[0016] Optionally, the identifying the position information of each hollow core of the cable based on the simulated structural data of the cable includes:

[0017] Based on the simulation structure data of the cable, identifying each non-current cross-sectional range of each non-current transmission area in the conductor of the cable in the cross-section of the conductor, and position information of each non-current cross-sectional range;

[0018] Each non-current cross-sectional range is smoothed by a range edge smoothing strategy to obtain a core range of each hollow core, and the position information of each non-current cross-sectional range is used as a core position point of each hollow core;

[0019] The core range of each of the hollow cores and the core position point of each of the hollow cores are used as the position information of each of the hollow cores of the cable.

[0020] Optionally, adjusting the cable structure model based on the core structure information of each of the filling cores, the physical property information of each of the filling cores, and the position information of each hollow core of the cable to obtain the cable core structure model of each of the filling cores includes:

[0021] Based on the core structure information of each of the filling cores and the physical property information of each of the filling cores, identifying the structural parameters of each of the filling cores and the simulation operation parameters of each of the filling cores;

[0022] For each filling core, based on the core range of each hollow core of the cable structure model, a filling core model of each hollow core is constructed through the structural parameters of the filling core and the simulation operation parameters of the filling core, and each filling core model is filled to the core position point of each hollow core to obtain the cable core structure model of the filling core.

[0023] Optionally, the identifying target cable structure data of the cable based on the core structure simulation data of each of the cable core structure models and the core structure experimental data of each of the cable core structure models comprises:

[0024] For each cable core structure model, based on the core structure simulation data of the cable core structure model, the cable performance value of each cable performance type is identified, and based on the cable performance value of each cable performance type, the model score value of the cable core structure model is evaluated through a cable performance evaluation strategy;

[0025] Screening a cable core structure model with a score greater than a scoring threshold as an initial target cable structure model, and calculating a performance deviation value between each initial target cable structure model and the cable structure experimental data of the cable based on the core structure experimental data of each initial target cable structure model and the cable structure experimental data of the cable;

[0026] An initial target cable structure model corresponding to the minimum performance deviation value is selected as the target cable structure data of the cable.

[0027] In a second aspect, the present application also provides a cable structure optimization design device, comprising:

[0028] An acquisition module, used to acquire cable structure data of the cable, core structure information of each filling core, and physical property information of each filling core, and construct a cable structure model of the cable based on the cable structure data;

[0029] A simulation module, used to simulate the current transmission process in the cable structure model through a preset electric field simulation strategy, obtain the simulation structure data of the cable, and identify the position information of each hollow core of the cable based on the simulation structure data of the cable;

[0030] An adjustment module, configured to adjust the cable structure model based on the core structure information of each of the filling cores, the physical property information of each of the filling cores, and the position information of each of the hollow cores of the cable, obtain a cable core structure model of each of the filling cores, and simulate the current transmission process of each of the cable core structure models to obtain core structure simulation data of each of the cable core structure models;

[0031] An identification module is used to collect core structure experimental data of sample cable structures corresponding to each of the cable core structure models, and identify target cable structure data of the cable based on core structure simulation data of each of the cable core structure models and core structure experimental data of each of the cable core structure models.

[0032] Optionally, the acquisition module is specifically used to:

[0033] Splitting the cable structure data into substructure data of each cable structure, and collecting relative position information of each cable structure in a cable database;

[0034] Based on the substructure data of each cable structure, a substructure model of each cable structure is constructed, and based on the relative position information of each cable structure, the substructure models of each cable structure are spliced ​​to obtain a cable structure model of the cable.

[0035] Optionally, the simulation module is specifically used for:

[0036] By means of a preset electric field simulation strategy, in the cable structure model, the current transmission process is simulated to obtain the current transmission cross-sectional information in the cable structure model, and based on the current transmission cross-sectional information, the current transmission area in the conductor of the cable and the non-current transmission area in the conductor of the cable are identified;

[0037] Based on the current transmission area and the non-current transmission area, simulation structure data of the conductor is generated, and the simulation structure data of the conductor is used as simulation structure data of the cable.

[0038] Optionally, the simulation module is specifically used for:

[0039] Based on the simulation structure data of the cable, identifying each non-current cross-sectional range of each non-current transmission area in the conductor of the cable in the cross-section of the conductor, and position information of each non-current cross-sectional range;

[0040] Each non-current cross-sectional range is smoothed by a range edge smoothing strategy to obtain a core range of each hollow core, and the position information of each non-current cross-sectional range is used as a core position point of each hollow core;

[0041] The core range of each of the hollow cores and the core position point of each of the hollow cores are used as the position information of each of the hollow cores of the cable.

[0042] Optionally, the adjustment module is specifically used to:

[0043] Based on the core structure information of each of the filling cores and the physical property information of each of the filling cores, identifying the structural parameters of each of the filling cores and the simulation operation parameters of each of the filling cores;

[0044] For each filling core, based on the core range of each hollow core of the cable structure model, a filling core model of each hollow core is constructed through the structural parameters of the filling core and the simulation operation parameters of the filling core, and each filling core model is filled to the core position point of each hollow core to obtain the cable core structure model of the filling core.

[0045] Optionally, the identification module is specifically used to:

[0046] For each cable core structure model, based on the core structure simulation data of the cable core structure model, the cable performance value of each cable performance type is identified, and based on the cable performance value of each cable performance type, the model score value of the cable core structure model is evaluated through a cable performance evaluation strategy;

[0047] Screening a cable core structure model with a score greater than a scoring threshold as an initial target cable structure model, and calculating a performance deviation value between each initial target cable structure model and the cable structure experimental data of the cable based on the core structure experimental data of each initial target cable structure model and the cable structure experimental data of the cable;

[0048] An initial target cable structure model corresponding to the minimum performance deviation value is selected as the target cable structure data of the cable.

[0049] In a third aspect, the present application provides a computer device, wherein the computer device comprises a memory and a processor, wherein the memory stores a computer program, and when the processor executes the computer program, the steps of any one of the methods in the first aspect are implemented.

[0050] In a fourth aspect, the present application provides a computer-readable storage medium having a computer program stored thereon, wherein when the computer program is executed by a processor, the steps of any one of the methods in the first aspect are implemented.

[0051] In a fifth aspect, the present application provides a computer program product. The computer program product includes a computer program, and when the computer program is executed by a processor, the steps of any one of the methods in the first aspect are implemented.

[0052] The above-mentioned cable structure optimization design method, device and computer equipment obtain the cable structure data of the cable, the core structure information of each filling core, and the physical property information of each filling core, and construct a cable structure model of the cable based on the cable structure data; through a preset electric field simulation strategy, in the cable structure model, the current transmission process is simulated to obtain the simulation structure data of the cable, and based on the simulation structure data of the cable, the position information of each hollow core of the cable is identified; based on the core structure information of each filling core, the physical property information of each filling core, and the position information of each hollow core of the cable, the cable structure model is adjusted to obtain the cable core structure model of each filling core, and the current transmission process of each cable core structure model is simulated to obtain the core structure simulation data of each cable core structure model; the core structure experimental data of the sample cable structure corresponding to each cable core structure model is collected, and based on the core structure simulation data of each cable core structure model and the core structure experimental data of each cable core structure model, the target cable structure data of the cable is identified. This scheme replaces the structure of the cable conductor without current transmission part with a filling core, so as to ensure the support effect of the cable conductor and avoid the problem that the cable conductor is easily deformed and damaged, which reduces the life of the wire and affects the conductive performance of the cable. Secondly, the filling core replacement can greatly reduce the material cost, thereby reducing the waste of wire resources. Then this scheme simulates the current transmission process of the cable by simulation modeling, so as to locate the position information of the hollow core of the cable, and then builds a cable core structure model containing each filling core based on this to ensure the simulation accuracy of the cable containing the filling core. Finally, this scheme simulates the current transmission process of each cable core structure model, and combines the actual experimental data of the sample cable of the cable core structure model to screen the target cable structure data of the cable, so as to combine simulation with reality, avoid the non-realistic nature of a single simulation, and the problem of simulation data deviation, and improve the accuracy and practicality of the screened target cable structure data, thereby comprehensively improving the resource optimization effect of designing the cable conductor structure while ensuring the conductive performance. BRIEF DESCRIPTION OF THE DRAWINGS

[0053] In order to more clearly illustrate the technical solutions in the embodiments of the present application or the related technologies, the drawings required for use in the embodiments or the related technical descriptions are briefly introduced below. Obviously, the drawings described below are only some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0054] Figure 1 A process environment diagram of a cable structure optimization design method in one embodiment;

[0055] Figure 2 is a schematic structural diagram of each cable structure of a cable in an embodiment;

[0056] Figure 3 A schematic diagram of the effect of skin effect in a cable conductor in one embodiment;

[0057] Figure 4 A schematic diagram of a process flow of a cable structure optimization design example in one embodiment;

[0058] Figure 5 A structural block diagram of a cable structure optimization design device in one embodiment;

[0059] Figure 6 FIG. 4 is a diagram showing the internal structure of a computer device in one embodiment. DETAILED DESCRIPTION

[0060] In order to make the purpose, technical solution and advantages of the present application more clearly understood, the present application is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present application and are not used to limit the present application.

[0061] The cable structure optimization design method provided in the embodiment of the present application can be applied to the application environment of the cable structure equipment. Among them, the method can be applied to the terminal, can also be applied to the server, can also be applied to the system including the terminal and the server, and is realized through the interaction between the terminal and the server. Among them, the terminal can be but not limited to various personal computers, laptops, etc. Among them, the terminal replaces the structure of the cable conductor without the current transmission part with a filling core, so as to ensure the support effect of the cable conductor, avoid the problem that the cable conductor is easily deformed and damaged, so that the life of the wire is reduced and the conductive performance of the cable is affected. Secondly, the material cost can be greatly reduced by replacing the filling core, thereby reducing the waste of wire resources. Then this scheme simulates the current transmission process of the cable by simulation modeling, so as to locate the position information of the hollow core of the cable, and then constructs a cable core structure model containing each filling core based on this to ensure the simulation accuracy of the cable containing the filling core. Finally, this scheme simulates the current transmission process of each cable core structure model and combines the actual experimental data of the sample cable of the cable core structure model to screen the target cable structure data of the cable, thereby combining simulation with practice, avoiding the impracticality of a single simulation and the problem of simulation data deviation, and improving the accuracy and practicality of the screened target cable structure data, thereby comprehensively improving the resource optimization effect of designing the cable conductor structure while ensuring the conductive performance.

[0062] In an exemplary embodiment, Figure 1As shown, a cable structure optimization design method is provided, which is described by taking the method applied to a terminal as an example, and includes the following steps S101 to S104. Among them:

[0063] Step S101, obtaining cable structure data of the cable, core structure information of each filling core, and physical property information of each filling core, and constructing a cable structure model of the cable based on the cable structure data.

[0064] In this embodiment, the terminal responds to the user's data upload operation to obtain the cable structure data of the target cable that needs cable structure design, the core structure data of each filling core used to fill the hollow core of the cable, and the physical performance information of each filling core. The cable structure data includes the substructure data of each cable structure of the cable, such as Figure 2 As shown, it is the substructure data of the cable structure, wherein each substructure is connected by enclosing covering in a specific order to obtain the cable. Wherein, each cable structure includes but is not limited to an outer sheath layer, a metal shielding layer, a semi-conductive non-woven fabric belt, an insulating shielding layer, an XLPE insulating layer, a conductor shielding layer, a copper conductor, and a filling core. The substructure data of each cable structure includes but is not limited to three-dimensional structure data and structural physical performance data. The physical performance data is the same as the physical performance types included in the physical performance information of the filling core, but the performance data of each physical performance type is different. Wherein, the physical performance types include resistivity, current carrying capacity, conductivity, mechanical strength, thermal conductivity and corrosion resistance, etc. Wherein, the material of each filling core is, for example, hollow aluminum, copper-clad aluminum or polyethylene. Then, the terminal constructs a cable structure model of the cable based on the cable structure data. Wherein, the way to construct the cable structure model of the cable can be modeled by COMSOL Multiphysics software. The specific modeling process will be described in detail later.

[0065] Step S102, simulating the current transmission process in the cable structure model through a preset electric field simulation strategy to obtain the simulated structure data of the cable, and identifying the position information of each hollow core of the cable based on the simulated structure data of the cable.

[0066] In this embodiment, the terminal simulates the current transmission process in the cable structure model through a preset electric field simulation strategy to obtain the simulation structure data of the cable. Among them, the preset power plant simulation strategy is a simulation strategy for electromagnetic and thermal field simulation using COMSOL Multiphysics software. The simulation structure data of the cable is the current transmission of each cable structure in the cable cross section during the simulation of the cable, and the distribution data corresponding to the electromagnetic range. Finally, based on the simulation structure data of the cable, the terminal identifies the position information of each hollow core of the cable. Among them, the hollow core can be the core range at the center of the cable, or the irregular ranges of the cable close to the center. That is, the number of the hollow cores can be one or more. As Figure 3 As shown in the figure, when the ferromagnetic material after the cable is energized contacts the ferromagnetic material without power, the surface of the ferromagnetic material without power will also generate a magnetic field, and the two directions are opposite. At this time, the current appears like a vortex and passes through the magnetic lines of force. In this case, the skin effect is produced. As the frequency increases, the current intensity will also increase, and the current density will be unevenly distributed. As the surface of the conductor goes deeper into the conductor, it is found that the current density distribution gradually decreases; the smaller the frequency, the less obvious the skin effect. In high-voltage and high-frequency wires, people tend to weaken the current density and concentrate it on the surface of the wire. Because when current is supplied to high-voltage wires, the electromotive force on the current surface of the wire is opposite to the electromotive force inside the wire, which will cause the magnetic flux inside the wire to increase as it reaches the center.

[0067] Step S103, based on the core structure information of each filled core, the physical property information of each filled core, and the position information of each hollow core of the cable, adjust the cable structure model to obtain the cable core structure model of each filled core, and simulate the current transmission process of each cable core structure model to obtain the core structure simulation data of each cable core structure model.

[0068] In this embodiment, the terminal adjusts the cable structure model based on the core structure information of each filling core, the physical property information of each filling core, and the position information of each hollow core of the cable, obtains the cable core structure model of each filling core, and simulates the current transmission process of each cable core structure model to obtain the core structure simulation data of each cable core structure model. Among them, the cable core structure model of each filling core is a cable structure model obtained by replacing the conductor at each hollow core position of the cable structure model with each filling core.

[0069] Step S104, collecting core structure experimental data of sample cable structures corresponding to each cable core structure model, and identifying target cable structure data of the cable based on the core structure simulation data of each cable core structure model and the core structure experimental data of each cable core structure model.

[0070] In this embodiment, the terminal collects the core structure experimental data of the sample cable structure corresponding to each cable core structure model, and identifies the target cable structure data of the cable based on the core structure simulation data of each cable core structure model and the core structure experimental data of each cable core structure model. Among them, the terminal obtains the target cable structure data of the cable through two screenings in this step. The first screening is to screen the cable core structure model with better simulation effect through the core structure simulation data. Then, the terminal constructs the sample cable structure based on the core cable structure model, and then instructs the staff to perform the actual current transmission delay to obtain the core structure experimental data of each sample cable structure, and then screens the cable core structure model corresponding to the sample cable structure with a smaller deviation from the cable data of the cable, so as to ensure the target cable structure data after replacing the core, and also ensure the cable transmission performance with the original cable. Thereby, the resource loss of designing the cable conductor structure is reduced while ensuring the conductive performance.

[0071] Based on the above scheme, the structure of the cable conductor without current transmission part is replaced by the filling core, so as to ensure the support effect of the cable conductor, avoid the problem that the cable conductor is easily deformed and damaged, which reduces the life of the wire and affects the conductive performance of the cable. Secondly, the filling core replacement can greatly reduce the material cost, thereby reducing the waste of wire resources. Then this scheme simulates the current transmission process of the cable by simulation modeling, so as to locate the position information of the hollow core of the cable, and then builds a cable core structure model containing each filling core based on this to ensure the simulation accuracy of the cable containing the filling core. Finally, this scheme simulates the current transmission process of each cable core structure model, and combines the actual experimental data of the sample cable of the cable core structure model to screen the target cable structure data of the cable, so as to combine simulation with reality, avoid the non-realistic nature of a single simulation, and the problem of simulation data deviation, and improve the accuracy and practicality of the screened target cable structure data, thereby comprehensively improving the resource optimization effect of designing the cable conductor structure while ensuring the conductive performance.

[0072] Optionally, a cable structure model of the cable is constructed based on the cable structure data, including: splitting the cable structure data into substructure data of each cable structure, and collecting relative position information of each cable structure in a cable database; constructing a substructure model of each cable structure based on the substructure data of each cable structure, and splicing the substructure models of each cable structure based on the relative position information of each cable structure to obtain the cable structure model of the cable.

[0073] In this embodiment, the terminal splits the cable structure data into substructure data of each cable structure, and collects the relative position information of each cable structure in the cable database. The relative position information is the mutual wrapping information of the two cable structures, as well as the wrapping connection information. Then, the terminal constructs a substructure model of each cable structure based on the substructure data of each cable structure, and then, the terminal converts the physical performance information in the substructure data of each cable structure into the model operation parameters of each substructure model through COMSOL Multiphysics software, and adds the model operation parameters of each substructure model to each substructure model.

[0074] Then, the terminal splices the substructure models of each cable structure based on the relative position information of each cable structure to obtain the cable structure model of the cable.

[0075] Based on the above scheme, by splitting the substructure data of each cable structure and constructing the substructure model of each cable structure respectively, the cable structure model of the cable is obtained by structural splicing, thereby improving the accuracy and comprehensiveness of constructing the cable structure model.

[0076] Optionally, through a preset electric field simulation strategy, the process of current transmission is simulated in the cable structure model to obtain simulation structural data of the cable, including: through a preset electric field simulation strategy, the process of current transmission is simulated in the cable structure model to obtain current transmission cross-sectional information in the cable structure model, and based on the current transmission cross-sectional information, the current transmission area in the conductor of the cable and the non-current transmission area in the conductor of the cable are identified; based on the current transmission area and the non-current transmission area, the simulation structural data of the conductor is generated, and the simulation structural data of the conductor is used as the simulation structural data of the cable.

[0077] In this embodiment, the terminal simulates the current transmission process in the cable structure model through a preset electric field simulation strategy, obtains the current transmission cross-sectional information in the cable structure model, and identifies the current transmission area in the conductor of the cable and the non-current transmission area in the conductor of the cable based on the current transmission cross-sectional information. Among them, the current transmission area is the conductor cross-sectional area where current transmission exists and can be actually used for current transmission, and the non-current transmission area is the conductor cross-sectional area where current transmission does not exist and is not actually used for current transmission. That is, the area without current transmission corresponding to the skin effect. Afterwards, the terminal generates the simulation structure data of the conductor based on the current transmission area and the non-current transmission area, and uses the simulation structure data of the conductor as the simulation structure data of the cable.

[0078] Based on the above scheme, by analyzing the current transmission area in the cable conductor and the non-current transmission area in the conductor of the cable, the simulation structure data of the cable is determined, thereby improving the accuracy of identifying the hollow area.

[0079] Optionally, based on the simulation structure data of the cable, the position information of each hollow core of the cable is identified, including: based on the simulation structure data of the cable, identifying each non-current cross-sectional range of each non-current transmission area in the conductor of the cable in the cross-section of the conductor, and the position information of each non-current cross-sectional range; smoothing each non-current cross-sectional range through a range edge smoothing strategy to obtain the core range of each hollow core, and using the position information of each non-current cross-sectional range as the core position point of each hollow core; using the core range of each hollow core and the core position point of each hollow core as the position information of each hollow core of the cable.

[0080] In this embodiment, the terminal identifies the non-current cross-sectional ranges of each non-current transmission area in the conductor of the cable in the cross section of the conductor and the position information of each non-current cross-sectional range based on the simulation structure data of the cable. Then, the terminal smoothes each non-current cross-sectional range through the range edge smoothing strategy to obtain the core range of each hollow core, and uses the position information of each non-current cross-sectional range as the core position point of each hollow core. Among them, the range edge smoothing strategy is a processing method for image edge smoothing, which can be a spatial domain processing method including low-pass filtering, median filtering, and a method of smoothing using low-pass filters such as low-pass trapezoidal filters, low-pass Gaussian filters, low-pass exponential filters, Butterworth low-pass filters, etc. in the frequency domain. Among them, smoothing the edge of the range can reduce data deviation and data abnormality, and improve the accuracy of the identified hollow core range. Finally, the terminal uses the core range of each hollow core and the core position point of each hollow core as the position information of each hollow core of the cable.

[0081] Based on the above scheme, the position information of each hollow core is obtained by identifying the hollow core range corresponding to the non-current cross-sectional range and the position points of the hollow core range, thereby improving the accuracy of the obtained position information of each hollow core.

[0082] Optionally, based on the core structure information of each filling core, the physical property information of each filling core, and the position information of each hollow core of the cable, the cable structure model is adjusted to obtain the cable core structure model of each filling core, including: identifying the structural parameters of each filling core and the simulation operation parameters of each filling core based on the core structure information of each filling core and the physical property information of each filling core; for each filling core, based on the core range of each hollow core of the cable structure model, constructing the filling core model of each hollow core through the structural parameters of the filling core and the simulation operation parameters of the filling core, and filling each filling core model to the core position point of each hollow core to obtain the cable core structure model of the filling core.

[0083] In this embodiment, the terminal identifies the structural parameters of each filling core and the simulation operation parameters of each filling core based on the core structural information of each filling core and the physical performance information of each filling core. The conversion method of each structural parameter and each simulation operation parameter is preset in the COMSOL Multiphysics software. The terminal directly inputs the core structural information of each filling core and the physical performance information of each filling core into the COMSOL Multiphysics software to obtain the structural parameters of each filling core and the simulation operation parameters of each filling core.

[0084] Then, for each filled core, the terminal constructs a filled core model of each hollow core based on the core range of each hollow core in the cable structure model, through the structural parameters of the filled core and the simulation operation parameters of the filled core, and fills each filled core model to the core position point of each hollow core to obtain the cable core structure model of the filled core.

[0085] Based on the above scheme, the efficiency of constructing the cable core structure model of each filling core is improved by converting the structural parameters of each filling core and the simulation operation parameters.

[0086] Optionally, based on the core structure simulation data of each cable core structure model and the core structure experimental data of each cable core structure model, the target cable structure data of the cable is identified, including: for each cable core structure model, based on the core structure simulation data of the cable core structure model, the cable performance value of each cable performance type is identified, and based on the cable performance value of each cable performance type, through a cable performance evaluation strategy, the model score value of the cable core structure model is evaluated; the cable core structure model with a score greater than a threshold is selected as the initial target cable structure model, and based on the core structure experimental data of each initial target cable structure model and the cable structure experimental data of the cable, the performance deviation value between each initial target cable structure model and the cable; the initial target cable structure model corresponding to the minimum performance deviation value is selected as the target cable structure data of the cable.

[0087] In this embodiment, the terminal identifies the cable performance value of each cable performance type based on the core structure simulation data of the cable core structure model for each cable core structure model, and evaluates the model score value of the cable core structure model based on the cable performance value of each cable performance type through the cable performance evaluation strategy. Among them, the cable performance type includes but is not limited to electrical performance (such as resistance, capacitance, insulation withstand voltage, etc.) type, thermal performance (such as thermal conductivity, heat resistance, etc.) type and mechanical performance (such as tensile strength, bending performance, etc.) type, and resource cost saving type, etc., and then, the terminal presets the model score value corresponding to each performance value range of each cable performance type, thereby automatically generating the model score value of each cable core structure model. Improve the efficiency of scoring.

[0088] Then, the terminal screens the cable core structure models with a score greater than the scoring threshold as the initial target cable structure models, and calculates the performance deviation value between each initial target cable structure model and the cable based on the core structure experimental data of each initial target cable structure model and the cable structure experimental data of the cable.

[0089] Finally, the terminal selects the initial target cable structure model corresponding to the minimum performance deviation value as the target cable structure data of the cable.

[0090] Based on the above scheme, by simulating the current transmission process of each cable core structure model and combining the actual experimental data of the sample cable of the cable core structure model, the target cable structure data of the cable is screened, thereby combining simulation with practice, avoiding the unrealistic nature of a single simulation and the problem of simulation data deviation, and improving the accuracy and practicality of the screened target cable structure data.

[0091] This application also provides an example of cable structure optimization design, such as Figure 4 As shown, the specific processing process includes the following steps:

[0092] Step S401, obtaining cable structure data of the cable, core structure information of each filling core, and physical property information of each filling core.

[0093] Step S402: split the cable structure data into substructure data of each cable structure, and collect relative position information of each cable structure in the cable database.

[0094] Step S403, constructing a substructure model of each cable structure based on the substructure data of each cable structure, and splicing the substructure models of each cable structure based on the relative position information of each cable structure to obtain a cable structure model of the cable.

[0095] Step S404, through a preset electric field simulation strategy, simulate the current transmission process in the cable structure model, obtain the current transmission cross-sectional information in the cable structure model, and based on the current transmission cross-sectional information, identify the current transmission area in the conductor of the cable and the non-current transmission area in the conductor of the cable.

[0096] Step S405: Generate simulation structure data of the conductor based on the current transmission area and the non-current transmission area, and use the simulation structure data of the conductor as simulation structure data of the cable.

[0097] Step S406, based on the simulation structure data of the cable, identifying each non-current cross-sectional range of each non-current transmission area in the conductor of the cable in the cross section of the conductor and the position information of each non-current cross-sectional range.

[0098] Step S407, smoothing each non-current cross-sectional range through a range edge smoothing strategy to obtain a core range of each hollow core, and using the position information of each non-current cross-sectional range as a core position point of each hollow core.

[0099] Step S408: Using the core range of each hollow core and the core position point of each hollow core as the position information of each hollow core of the cable.

[0100] Step S409 , based on the core structure information of each filling core and the physical property information of each filling core, identifying the structural parameters of each filling core and the simulation operation parameters of each filling core.

[0101] Step S410, for each filled core, based on the core range of each hollow core of the cable structure model, through the structural parameters of the filled core, and the simulation operation parameters of the filled core, construct a filled core model of each hollow core, and fill each filled core model to the core position point of each hollow core to obtain the cable core structure model of the filled core.

[0102] Step S411, collecting core structure experimental data of sample cable structures corresponding to each cable core structure model.

[0103] Step S412, for each cable core structure model, based on the core structure simulation data of the cable core structure model, the cable performance value of each cable performance type is identified, and based on the cable performance value of each cable performance type, the model score value of the cable core structure model is evaluated through a cable performance evaluation strategy.

[0104] Step S413, screening cable core structure models with a score greater than a scoring threshold as initial target cable structure models, and calculating the performance deviation value between each initial target cable structure model and the cable based on the core structure experimental data of each initial target cable structure model and the cable structure experimental data of the cable.

[0105] Step S414, selecting the initial target cable structure model corresponding to the minimum performance deviation value as the target cable structure data of the cable.

[0106] It should be understood that, although the various steps in the flowcharts involved in the above-mentioned embodiments are displayed in sequence according to the indication of the arrows, these steps are not necessarily executed in sequence according to the order indicated by the arrows. Unless there is a clear explanation in this article, the execution of these steps does not have a strict order restriction, and these steps can be executed in other orders. Moreover, at least a part of the steps in the flowcharts involved in the above-mentioned embodiments can include multiple steps or multiple stages, and these steps or stages are not necessarily executed at the same time, but can be executed at different times, and the execution order of these steps or stages is not necessarily to be carried out in sequence, but can be executed in turn or alternately with other steps or at least a part of the steps or stages in other steps.

[0107] Based on the same inventive concept, the embodiment of the present application also provides a cable structure optimization design device for implementing the cable structure optimization design method involved above. The implementation scheme for solving the problem provided by the device is similar to the implementation scheme recorded in the above method, so the specific limitations in one or more cable structure optimization design device embodiments provided below can refer to the limitations of the cable structure optimization design method above, and will not be repeated here.

[0108] In an exemplary embodiment, Figure 5 As shown, a cable structure optimization design device is provided, including: an acquisition module 510, a simulation module 520, an adjustment module 530 and an identification module 540, wherein:

[0109] An acquisition module 510, for acquiring cable structure data of the cable, core structure information of each filling core, and physical property information of each filling core, and constructing a cable structure model of the cable based on the cable structure data;

[0110] The simulation module 520 is used to simulate the current transmission process in the cable structure model through a preset electric field simulation strategy to obtain the simulation structure data of the cable, and identify the position information of each hollow core of the cable based on the simulation structure data of the cable;

[0111] An adjustment module 530 is used to adjust the cable structure model based on the core structure information of each of the filling cores, the physical property information of each of the filling cores, and the position information of each of the hollow cores of the cable to obtain a cable core structure model of each of the filling cores, and simulate the current transmission process of each of the cable core structure models to obtain core structure simulation data of each of the cable core structure models;

[0112] The identification module 540 is used to collect the core structure experimental data of the sample cable structure corresponding to each of the cable core structure models, and identify the target cable structure data of the cable based on the core structure simulation data of each of the cable core structure models and the core structure experimental data of each of the cable core structure models.

[0113] Optionally, the acquisition module 510 is specifically configured to:

[0114] Splitting the cable structure data into substructure data of each cable structure, and collecting relative position information of each cable structure in a cable database;

[0115] Based on the substructure data of each cable structure, a substructure model of each cable structure is constructed, and based on the relative position information of each cable structure, the substructure models of each cable structure are spliced ​​to obtain a cable structure model of the cable.

[0116] Optionally, the simulation module 520 is specifically used for:

[0117] By means of a preset electric field simulation strategy, in the cable structure model, the current transmission process is simulated to obtain the current transmission cross-sectional information in the cable structure model, and based on the current transmission cross-sectional information, the current transmission area in the conductor of the cable and the non-current transmission area in the conductor of the cable are identified;

[0118] Based on the current transmission area and the non-current transmission area, simulation structure data of the conductor is generated, and the simulation structure data of the conductor is used as simulation structure data of the cable.

[0119] Optionally, the simulation module 520 is specifically used for:

[0120] Based on the simulation structure data of the cable, identifying each non-current cross-sectional range of each non-current transmission area in the conductor of the cable in the cross-section of the conductor, and position information of each non-current cross-sectional range;

[0121] Each non-current cross-sectional range is smoothed by a range edge smoothing strategy to obtain a core range of each hollow core, and the position information of each non-current cross-sectional range is used as a core position point of each hollow core;

[0122] The core range of each of the hollow cores and the core position point of each of the hollow cores are used as the position information of each of the hollow cores of the cable.

[0123] Optionally, the adjustment module 530 is specifically configured to:

[0124] Based on the core structure information of each of the filling cores and the physical property information of each of the filling cores, identifying the structural parameters of each of the filling cores and the simulation operation parameters of each of the filling cores;

[0125] For each filling core, based on the core range of each hollow core of the cable structure model, a filling core model of each hollow core is constructed through the structural parameters of the filling core and the simulation operation parameters of the filling core, and each filling core model is filled to the core position point of each hollow core to obtain the cable core structure model of the filling core.

[0126] Optionally, the identification module 540 is specifically configured to:

[0127] For each cable core structure model, based on the core structure simulation data of the cable core structure model, the cable performance value of each cable performance type is identified, and based on the cable performance value of each cable performance type, the model score value of the cable core structure model is evaluated through a cable performance evaluation strategy;

[0128] Screening a cable core structure model with a score greater than a scoring threshold as an initial target cable structure model, and calculating a performance deviation value between each initial target cable structure model and the cable structure experimental data of the cable based on the core structure experimental data of each initial target cable structure model and the cable structure experimental data of the cable;

[0129] An initial target cable structure model corresponding to the minimum performance deviation value is selected as the target cable structure data of the cable.

[0130] Each module in the above cable structure optimization design device can be implemented in whole or in part by software, hardware and their combination. Each module can be embedded in or independent of the processor in the computer device in the form of hardware, or can be stored in the memory of the computer device in the form of software, so that the processor can call and execute the corresponding operations of each module.

[0131] In an exemplary embodiment, a computer device is provided. The computer device may be a terminal, and its internal structure diagram may be as shown in FIG. Figure 6As shown. The computer device includes a processor, a memory, an input / output interface, a communication interface, a display unit and an input device. Among them, the processor, the memory and the input / output interface are connected through a system bus, and the communication interface, the display unit and the input device are connected to the system bus through the input / output interface. Among them, the processor of the computer device is used to provide computing and control capabilities. The memory of the computer device includes a non-volatile storage medium and an internal memory. The non-volatile storage medium stores an operating system and a computer program. The internal memory provides an environment for the operation of the operating system and the computer program in the non-volatile storage medium. The input / output interface of the computer device is used to exchange information between the processor and the external device. The communication interface of the computer device is used to communicate with an external terminal in a wired or wireless manner, and the wireless manner can be implemented through WIFI, a mobile cellular network, NFC (near field communication) or other technologies. When the computer program is executed by the processor, a cable structure optimization design method is implemented. The display unit of the computer device is used to form a visually visible picture, which can be a display screen, a projection device or a virtual reality imaging device. The display screen can be a liquid crystal display screen or an electronic ink display screen, and the input device of the computer device can be a touch layer covering the display screen, or a button, trackball or touchpad set on the computer device shell, or an external keyboard, touchpad or mouse.

[0132] Those skilled in the art will understand that Figure 6 The structure shown in the figure is only a block diagram of a part of the structure related to the solution of the present application, and does not constitute a limitation on the computer device to which the solution of the present application is applied. The specific computer device may include more or fewer components than those shown in the figure, or combine certain components, or have a different arrangement of components.

[0133] In an exemplary embodiment, a computer device is provided, including a memory and a processor, wherein a computer program is stored in the memory, and when the processor executes the computer program, the steps of any one of the methods in the first aspect are implemented.

[0134] In one embodiment, a computer-readable storage medium is provided, on which a computer program is stored. When the computer program is executed by a processor, the steps of any one of the methods in the first aspect are implemented.

[0135] In one embodiment, a computer program product is provided, comprising a computer program, which, when executed by a processor, implements the steps of any one of the methods in the first aspect.

[0136] It should be noted that the user information (including but not limited to user device information, user personal information, etc.) and data (including but not limited to data used for analysis, stored data, displayed data, etc.) involved in this application are all information and data authorized by the user or fully authorized by all parties, and the collection, use and processing of relevant data must comply with relevant regulations.

[0137] Those skilled in the art can understand that all or part of the processes in the above-mentioned embodiment methods can be completed by instructing the relevant hardware through a computer program, and the computer program can be stored in a non-volatile computer-readable storage medium. When the computer program is executed, it can include the processes of the embodiments of the above-mentioned methods. Among them, any reference to the memory, database or other medium used in the embodiments provided in the present application can include at least one of non-volatile and volatile memory. Non-volatile memory can include read-only memory (ROM), magnetic tape, floppy disk, flash memory, optical memory, high-density embedded non-volatile memory, resistive random access memory (ReRAM), magnetoresistive random access memory (MRAM), ferroelectric random access memory (FRAM), phase change memory (PCM), graphene memory, etc. Volatile memory can include random access memory (RAM) or external cache memory, etc. As an illustration and not limitation, RAM can be in various forms, such as static random access memory (SRAM) or dynamic random access memory (DRAM). The database involved in each embodiment provided in this application may include at least one of a relational database and a non-relational database. Non-relational databases may include distributed databases based on blockchains, etc., but are not limited to this. The processor involved in each embodiment provided in this application may be a general-purpose processor, a central processing unit, a graphics processor, a digital signal processor, a programmable logic device, a data processing logic device based on quantum computing, etc., but are not limited to this.

[0138] The technical features of the above embodiments may be combined arbitrarily. To make the description concise, not all possible combinations of the technical features in the above embodiments are described. However, as long as there is no contradiction in the combination of these technical features, they should be considered to be within the scope of this specification.

[0139] The above-described embodiments only express several implementation methods of the present application, and the descriptions thereof are relatively specific and detailed, but they cannot be understood as limiting the scope of the present application. It should be pointed out that, for a person of ordinary skill in the art, several variations and improvements can be made without departing from the concept of the present application, and these all belong to the protection scope of the present application. Therefore, the protection scope of the present application shall be subject to the attached claims.

Claims

1. A cable structure optimization design method, characterized in that: The method comprises: Acquire cable structure data of the cable, core structure information of each filling core, and physical property information of each filling core, and construct a cable structure model of the cable based on the cable structure data; By using a preset electric field simulation strategy, in the cable structure model, the current transmission process is simulated to obtain the simulation structure data of the cable, and based on the simulation structure data of the cable, the position information of each hollow core of the cable is identified; Based on the core structure information of each of the filling cores, the physical property information of each of the filling cores, and the position information of each of the hollow cores of the cable, the cable structure model is adjusted to obtain a cable core structure model of each of the filling cores, and the current transmission process of each of the cable core structure models is simulated to obtain core structure simulation data of each of the cable core structure models; The core structure experimental data of the sample cable structure corresponding to each of the cable core structure models are collected, and based on the core structure simulation data of each of the cable core structure models and the core structure experimental data of each of the cable core structure models, the target cable structure data of the cable is identified.

2. The method according to claim 1, characterized in that The step of constructing a cable structure model of the cable based on the cable structure data comprises: Splitting the cable structure data into substructure data of each cable structure, and collecting relative position information of each cable structure in a cable database; Based on the substructure data of each cable structure, a substructure model of each cable structure is constructed, and based on the relative position information of each cable structure, the substructure models of each cable structure are spliced ​​to obtain a cable structure model of the cable.

3. The method according to claim 2, characterized in that The process of simulating current transmission in the cable structure model by using a preset electric field simulation strategy to obtain simulation structure data of the cable includes: By means of a preset electric field simulation strategy, in the cable structure model, the current transmission process is simulated to obtain the current transmission cross-sectional information in the cable structure model, and based on the current transmission cross-sectional information, the current transmission area in the conductor of the cable and the non-current transmission area in the conductor of the cable are identified; Based on the current transmission area and the non-current transmission area, simulation structure data of the conductor is generated, and the simulation structure data of the conductor is used as simulation structure data of the cable.

4. The method according to claim 3, characterized in that The identifying the position information of each hollow core of the cable based on the simulated structural data of the cable comprises: Based on the simulation structure data of the cable, identifying each non-current cross-sectional range of each non-current transmission area in the conductor of the cable in the cross-section of the conductor, and position information of each non-current cross-sectional range; Each non-current cross-sectional range is smoothed by a range edge smoothing strategy to obtain a core range of each hollow core, and the position information of each non-current cross-sectional range is used as a core position point of each hollow core; The core range of each of the hollow cores and the core position point of each of the hollow cores are used as the position information of each of the hollow cores of the cable.

5. The method according to claim 4, characterized in that The adjusting the cable structure model based on the core structure information of each of the filling cores, the physical property information of each of the filling cores, and the position information of each of the hollow cores of the cable to obtain the cable core structure model of each of the filling cores includes: Based on the core structure information of each of the filling cores and the physical property information of each of the filling cores, identifying the structural parameters of each of the filling cores and the simulation operation parameters of each of the filling cores; For each filling core, based on the core range of each hollow core of the cable structure model, a filling core model of each hollow core is constructed through the structural parameters of the filling core and the simulation operation parameters of the filling core, and each filling core model is filled to the core position point of each hollow core to obtain the cable core structure model of the filling core.

6. The method according to claim 1, characterized in that The identifying target cable structure data of the cable based on the core structure simulation data of each of the cable core structure models and the core structure experimental data of each of the cable core structure models comprises: For each cable core structure model, based on the core structure simulation data of the cable core structure model, the cable performance value of each cable performance type is identified, and based on the cable performance value of each cable performance type, the model score value of the cable core structure model is evaluated through a cable performance evaluation strategy; Screening a cable core structure model with a score greater than a scoring threshold as an initial target cable structure model, and calculating a performance deviation value between each initial target cable structure model and the cable structure experimental data of the cable based on the core structure experimental data of each initial target cable structure model and the cable structure experimental data of the cable; An initial target cable structure model corresponding to the minimum performance deviation value is selected as the target cable structure data of the cable.

7. A cable structure optimization design device, characterized in that: The device comprises: An acquisition module, used to acquire cable structure data of the cable, core structure information of each filling core, and physical property information of each filling core, and construct a cable structure model of the cable based on the cable structure data; A simulation module, used to simulate the current transmission process in the cable structure model through a preset electric field simulation strategy, obtain the simulation structure data of the cable, and identify the position information of each hollow core of the cable based on the simulation structure data of the cable; An adjustment module, configured to adjust the cable structure model based on the core structure information of each of the filling cores, the physical property information of each of the filling cores, and the position information of each of the hollow cores of the cable, obtain a cable core structure model of each of the filling cores, and simulate the current transmission process of each of the cable core structure models to obtain core structure simulation data of each of the cable core structure models; An identification module is used to collect core structure experimental data of sample cable structures corresponding to each of the cable core structure models, and identify target cable structure data of the cable based on core structure simulation data of each of the cable core structure models and core structure experimental data of each of the cable core structure models.

8. A computer device comprising a memory and a processor, wherein the memory stores a computer program, wherein: When the processor executes the computer program, the steps of the method according to any one of claims 1 to 6 are implemented.

9. A computer-readable storage medium having a computer program stored thereon, characterized in that: When the computer program is executed by a processor, the steps of the method according to any one of claims 1 to 6 are implemented.

10. A computer program product, comprising a computer program, characterized in that When the computer program is executed by a processor, the steps of the method according to any one of claims 1 to 6 are implemented.

Citation Information

Cited By

  • A constrained cable structure simulation optimization method

    CN122712876A