Construction structure of transverse wind-resistant support of extra-large bridge and installation method of construction structure

By adopting a construction structure with reserved bolt holes and leveling space on the lateral wind-resistant support of the suspension bridge, the problem of low angle accuracy in the prior art is solved, and a higher connection strength and service life are achieved.

CN119531243APending Publication Date: 2025-02-28CHINA RAILWAY GUANGZHOU ENG GRP CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411744477.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-11-30
Publication Date
2025-02-28

AI Technical Summary

Technical Problem

The lateral wind-resistant support pre-embedded method of existing suspension bridges leads to low angular accuracy and affects service life.

Method used

The construction structure of the super-large bridge transverse wind-resistant support is adopted, including the stone pads that reserve bolt holes and the first connecting steel plate with leveling space. The leveling layer is formed by pouring concrete to ensure the precise connection between the bolts and the stone pads.

Benefits of technology

It improves the angular accuracy and connection strength of the transverse wind-resistant support, and extends the service life.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119531243A_ABST
    Figure CN119531243A_ABST
Patent Text Reader

Abstract

The invention discloses an extra-large bridge transverse wind-resistant support construction structure and an installation method thereof. The extra-large bridge transverse wind-resistant support construction structure comprises a padstone, and reserved bolt holes are formed in the padstone; a leveling space is reserved between the first connecting steel plate and the padstone, and the leveling space is used for pouring concrete to form a leveling layer; and the support bolt is in threaded connection with the first connecting steel plate, penetrates into the reserved bolt hole and is connected with the padstone. When the padstone is poured, the reserved bolt holes are reserved firstly, connection with the first connecting steel plate is facilitated, meanwhile, the leveling space is formed between the first connecting steel plate and the padstone, after angle adjustment of the first connecting steel plate is completed, a leveling layer is formed through pouring, and the connection strength of the first connecting steel plate and the padstone is guaranteed under the condition that the precision of the first connecting steel plate is guaranteed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of suspension bridge construction, and in particular to a transverse wind-resistant bearing construction structure for a super-large bridge and an installation method thereof. Background Art

[0002] A suspension bridge, also known as a suspension bridge, refers to a bridge with cables suspended from towers and anchored on both sides as the main load-bearing components of the upper structure. The geometric shape of the cables is determined by the balance of forces and is generally close to a parabola. Many hangers are hung from the cables to suspend the bridge deck. Stiffening beams are often set between the bridge deck and the hangers to form a combined system with the cables to reduce the deflection caused by the load.

[0003] The deck of a suspension bridge is generally supported by the transverse braces of the cable towers, that is, the steel frame of the bridge deck is directly located on the transverse braces of the cable towers. In order to prevent the steel frame from shifting along the lateral transition, transverse wind-resistant bearings are generally used to limit the steel frame. The part where the existing transverse wind-resistant bearings are connected to the cable towers is generally pre-buried directly on the pad stones of the cable towers. However, the pre-buried method easily causes the angle accuracy of the transverse wind-resistant bearings to be low, affecting the service life of the transverse wind-resistant bearings. Summary of the invention

[0004] The purpose of this application is to provide a construction structure for a transverse wind-resistant support of a super-large bridge and an installation method thereof, so as to improve the problem that the conventional jacking method cannot be applied due to interference between the steel frame under the bridge deck and the cable tower cross brace.

[0005] The present application provides a construction structure of a transverse wind-resistant support for a super-large bridge, which adopts the following technical solution: A transverse wind-resistant bearing construction structure for a super-large bridge includes a pad stone, on which a reserved bolt hole is provided; a first connecting steel plate, a leveling space is reserved between the first connecting steel plate and the pad stone, and the leveling space is used for pouring concrete to form a leveling layer; and a bearing bolt, which is threadedly connected to the first connecting steel plate and penetrates into the reserved bolt hole to be connected to the pad stone.

[0006] By adopting the above technical solution, when pouring the pad stone, reserved bolt holes are first reserved to facilitate connection with the first connecting steel plate. At the same time, a leveling space is set between the first connecting steel plate and the pad stone. After the angle adjustment of the first connecting steel plate is completed, a leveling layer is poured to form. While ensuring the accuracy of the first connecting steel plate, the connection strength between the first connecting steel plate and the pad stone is guaranteed.

[0007] Optionally, it also includes a second connecting steel plate, which is fixedly connected to the steel frame, and a shock absorbing assembly is connected between the first connecting steel plate and the second connecting steel plate.

[0008] Optionally, the thickness of the leveling layer is 3 cm.

[0009] By adopting the above technical solution, the 3 cm leveling layer can provide the first connecting steel plate with sufficient space to adjust the angle, while ensuring the connection strength between the first connecting steel plate and the pad stone.

[0010] Optionally, a concrete column is formed in the reserved bolt hole to fix the support bolt and the cushion stone relative to each other.

[0011] By adopting the above technical solution, the connection strength between the support bolts and the cushion stone is improved through casting.

[0012] An installation method, based on the above-mentioned super-large bridge transverse wind-resistant bearing construction structure, comprises the following steps: S1. Casting pad stone, with reserved bolt holes during casting; S2. Fix the first connecting steel plate by auxiliary tooling, and reserve a leveling space between the first connecting steel plate and the cushion stone; S3. Install the support bolts on the first connecting steel plate, and extend the heads of the support bolts into the reserved bolt holes; S4. Pour concrete into the leveling space to form the leveling layer and fix the support bolts and the pad stone relatively.

[0013] By adopting the above technical solution, when pouring the pad stone, reserved bolt holes are first reserved to facilitate connection with the first connecting steel plate. At the same time, a leveling space is set between the first connecting steel plate and the pad stone. After the angle adjustment of the first connecting steel plate is completed, a leveling layer is poured to form. While ensuring the accuracy of the first connecting steel plate, the connection strength between the first connecting steel plate and the pad stone is guaranteed.

[0014] Optionally, the auxiliary tooling includes a frame and a steel plate positioning assembly and a template assembly arranged on the frame, wherein the steel plate positioning assembly is used to connect with the first connecting steel plate to limit the position of the first connecting steel plate; the template assembly is used to abut against the pad stone and the first connecting steel plate to close the bottom and sides of the leveling space.

[0015] By adopting the above technical solution, the first connecting steel plate is positioned by the steel plate positioning assembly, and the pouring and leveling space is facilitated by the template assembly. The steel plate positioning assembly and the template assembly are arranged on the same frame, which can ensure the pouring accuracy.

[0016] Optionally, the steel plate positioning assembly includes a connecting frame and a positioning plate, the connecting frame is connected to the frame, the positioning plate is connected to the connecting frame, the positioning plate abuts against an end of the first connecting steel plate away from the pad stone, the positioning plate is provided with a positioning bolt, and the positioning bolt passes through the positioning plate and is threadedly connected to the first connecting steel plate.

[0017] By adopting the above technical solution, the first connecting steel plate is locked through the cooperation of the positioning bolts and the positioning plate to ensure stability when pouring the leveling layer.

[0018] Optionally, a gasket is provided between the positioning plate and the first connecting steel plate, and the angle of the first connecting steel plate is controlled by adjusting the number of the gaskets.

[0019] By adopting the above technical solution, the angle of the first connecting plate is adjusted by the gasket, which is more reliable and can be maintained for a longer time.

[0020] Optionally, the formwork assembly includes a bottom form and two side forms, the bottom form is connected to the frame via a vertical moving assembly, and the side forms are connected to the frame via a transverse moving assembly, both the bottom form and the side forms are abutted against the side of the pad stone facing the first connecting steel plate, the bottom form is abutted against the bottom surface of the first connecting steel plate, and the two side forms are respectively abutted against two side surfaces of the first connecting steel plate; the vertical moving assembly is used to drive the bottom form to move in the vertical direction, and the transverse moving assembly is used to drive the side forms to move in the transverse direction.

[0021] Optionally, the auxiliary tooling further includes a vibration assembly, which includes a vibration frame and a vibration motor, and the vibration motor is in contact with a side of the first connecting steel plate away from the pad stone.

[0022] Through the above technical solution, the first connecting steel plate is vibrated by the vibration motor, thereby ensuring the vibration effect, ensuring the uniformity of the leveling layer, and thus ensuring the compressive resistance.

[0023] In summary, the present application includes at least one of the following beneficial technical effects: 1. When pouring the pad stone, reserve bolt holes first to facilitate connection with the first connecting steel plate. At the same time, set a leveling space between the first connecting steel plate and the pad stone. After the angle adjustment of the first connecting steel plate is completed, pour to form a leveling layer. Under the condition of ensuring the accuracy of the first connecting steel plate, the connection strength between the first connecting steel plate and the pad stone is guaranteed; 2. The first connecting steel plate is positioned by the steel plate positioning assembly, and the pouring and leveling space is facilitated by the template assembly. The steel plate positioning assembly and the template assembly are arranged on the same frame, which can ensure the pouring accuracy; 3. The first connecting steel plate is vibrated by a vibration motor to ensure the vibration effect, ensure the uniformity of the leveling layer, and thus ensure the compressive resistance. BRIEF DESCRIPTION OF THE DRAWINGS

[0024] Figure 1 It is a schematic diagram of a transverse wind-resistant bearing construction structure of a super-large bridge in the present invention.

[0025] Figure 2 It is a schematic diagram of the auxiliary tooling in the present invention.

[0026] Figure 3 It is a schematic diagram of the vibration component and the template component in the present invention.

[0027] Figure 4 It is a schematic diagram of a gasket embodied in the present invention.

[0028] In the figure, 1, cushion stone; 11, reserved bolt hole; 12, concrete column; 2, first connecting steel plate; 21, support bolt; 3, second connecting steel plate; 4, shock-absorbing assembly; 5, leveling layer; 6, frame; 61, steel plate positioning assembly; 611, connecting frame; 612, positioning plate; 613, positioning bolt; 62, formwork assembly; 621, side form; 622, bottom form; 6221, vertical plate; 623, vertical moving assembly; 6231, screw; 6232, guide rod; 6233, handle; 624, lateral moving assembly; 63, vibration assembly; 631, vibration frame; 632, vibration motor. DETAILED DESCRIPTION

[0029] The present invention will now be described in further detail with reference to the accompanying drawings. These drawings are simplified schematic diagrams, which only illustrate the basic structure of the present invention in a schematic manner, and therefore only show the components related to the present invention.

[0030] In the description of the present invention, it should be understood that the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", "clockwise", "counterclockwise", "axial", "radial", "circumferential" and the like indicate positions or positional relationships based on the positions or positional relationships shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention. In addition, the features defined as "first" and "second" may explicitly or implicitly include one or more of the features. In the description of the present invention, unless otherwise specified, "multiple" means two or more. In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected" and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be a connection between the two elements. For those skilled in the art, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0031] Embodiment 1 A construction structure of a transverse wind-resistant support for a super-large bridge, referring to Figures 1 to 4, including a cushion stone 1, a first connecting steel plate 2, a second connecting steel plate 3 and a support bolt 21, and a reserved bolt hole 11 is provided on the cushion stone 1. A leveling space is reserved between the first connecting steel plate 2 and the cushion stone 1, and the leveling space is used to pour concrete to form a leveling layer 5. The support bolt 21 is threadedly connected to the first connecting steel plate 2, and is inserted into the reserved bolt hole 11 to be connected to the cushion stone 1. The second connecting steel plate 3 is fixedly connected to the steel frame, and a shock absorbing component 4 is connected between the first connecting steel plate 2 and the second connecting steel plate 3, and the shock absorbing component 4 can be a rubber pad. When pouring the cushion stone 1, the reserved bolt hole 11 is first reserved to facilitate the connection with the first connecting steel plate 2, and a leveling space is set between the first connecting steel plate 2 and the cushion stone 1. After the angle adjustment of the first connecting steel plate 2 is completed, the leveling layer 5 is poured to form. While ensuring the accuracy of the first connecting steel plate 2, the connection strength between the first connecting steel plate 2 and the cushion stone 1 is guaranteed.

[0032] Specifically, the thickness of the leveling layer 5 may be 3 cm. The 3 cm leveling layer 5 can provide the first connecting steel plate 2 with enough space to adjust the angle, while ensuring the connection strength between the first connecting steel plate 2 and the cushion stone 1 .

[0033] In addition, a concrete column 12 is formed in the reserved bolt hole 11 to relatively fix the support bolt 21 and the cushion stone 1, and the connection strength between the support bolt 21 and the cushion stone 1 is improved by casting.

[0034] An installation method, based on the above-mentioned super-large bridge transverse wind-resistant bearing construction structure, comprises the following steps: S1, pouring pad stone 1, with reserved bolt holes 11 reserved during pouring.

[0035] S2. Fix the first connecting steel plate 2 by auxiliary tooling, and reserve a leveling space between the first connecting steel plate 2 and the cushion stone 1.

[0036] S3. Install the support bolt 21 on the first connecting steel plate 2 and allow the head of the support bolt 21 to extend into the reserved bolt hole 11.

[0037] S4. Pour concrete into the leveling space to form the leveling layer 5 and fix the support bolts 21 and the cushion stone 1 relatively.

[0038] When pouring the pad stone 1, a reserved bolt hole 11 is first reserved to facilitate connection with the first connecting steel plate 2. At the same time, a leveling space is set between the first connecting steel plate 2 and the pad stone 1. After the angle adjustment of the first connecting steel plate 2 is completed, a leveling layer 5 is poured to form. While ensuring the accuracy of the first connecting steel plate 2, the connection strength between the first connecting steel plate 2 and the pad stone 1 is guaranteed.

[0039] The auxiliary tooling includes a frame 6, a steel plate positioning assembly 61, a template assembly 62 and a vibration assembly 63. The steel plate positioning assembly 61 and the template assembly 62 are both arranged on the frame 6. The steel plate positioning assembly 61 is used to connect with the first connecting steel plate 2 to limit the position of the first connecting steel plate 2; the template assembly 62 is used to abut against the pad stone 1 and the first connecting steel plate 2 to close the bottom and side surfaces of the leveling space. The first connecting steel plate 2 is positioned by the steel plate positioning assembly 61, and the leveling space is conveniently poured by the template assembly 62. The steel plate positioning assembly 61 and the template assembly 62 are arranged on the same frame 6, which can ensure the pouring accuracy. At the same time, the concrete in the leveling space is vibrated by the vibration assembly 63 to ensure the uniformity of the leveling layer 5, thereby ensuring the pressure-bearing performance of the leveling layer 5.

[0040] Specifically, the steel plate positioning assembly 61 includes a connecting frame 611 and a positioning plate 612. The connecting frame 611 is fixedly connected to the frame 6. The positioning plate 612 is fixedly connected to the connecting frame 611. There are four positioning plates 612. The four positioning plates 612 are all in contact with one end of the first connecting steel plate 2 away from the pad stone 1. Each positioning plate 612 is provided with a positioning bolt 613. The positioning bolt 613 passes through the positioning plate 612 and is threadedly connected to the first connecting steel plate 2. The first connecting steel plate 2 is provided with a threaded hole for connecting with the shock absorbing assembly 4, which can be used to connect with the positioning bolt 613. Through the cooperation of the positioning bolt 613 and the positioning plate 612, the first connecting steel plate 2 is locked to ensure the stability when pouring the leveling layer 5. A gasket is provided between the positioning plate 612 and the first connecting steel plate 2. The number of gaskets can be adjusted to control the angle of the first connecting steel plate 2 to achieve the leveling of the first connecting steel plate 2. The angle of the first connecting plate is adjusted by controlling the number of gaskets, which is more reliable and can be maintained for a long time.

[0041] The template assembly 62 includes a bottom mold 622 and two side molds 621. The bottom mold 622 is connected to the frame 6 via a vertical moving assembly 623, and the side mold 621 is connected to the frame 6 via a horizontal moving assembly 624. The bottom mold 622 and the side molds 621 are both in contact with the side of the pad stone 1 facing the first connecting steel plate 2. The bottom mold 622 is in contact with the bottom surface of the first connecting steel plate 2, and the two side molds 621 are respectively in contact with the two side surfaces of the first connecting steel plate 2. The vertical moving assembly 623 is used to drive the bottom mold 622 to move in the vertical direction, and the horizontal moving assembly 624 is used to drive the side mold 621 to move in the horizontal direction. The vertical moving component 623 has the same structure as the horizontal moving component 624, so the vertical moving component 623 is taken as an example for explanation here. The vertical moving component 623 includes a screw 6231, a guide rod 6232 and a handle 6233. The screw 6231 is rotatably connected to the connecting frame 611, and the screw 6231 is threadedly connected to the bottom mold 622. The guide rod 6232 is fixedly connected to the connecting frame 611, and the guide rod 6232 passes through the bottom mold 622. The handle 6233 is coaxially fixed with the screw 6231, and the handle 6233 can be rotated to adjust the position of the bottom mold 622.

[0042] It should be noted that the bottom of the bottom mold 622 is fixedly connected with a vertical plate 6221 , and the vertical plate 6221 is fixedly connected to the cushion stone 1 through expansion bolts, thereby ensuring the stability of the bottom mold 622 .

[0043] The vibration assembly 63 includes a vibration frame 631 and a vibration motor 632. The vibration motor 632 is attached to the side of the first connecting steel plate 2 away from the pad stone 1, and the vibration frame 631 does not contact the frame 6, thereby reducing the influence of the vibration motor 632 on the side mold 621 and the bottom mold 622. The first connecting steel plate 2 is vibrated by the vibration motor 632, thereby ensuring the vibration effect, ensuring the uniformity of the leveling layer 5, and then ensuring the compressive strength. Because the lateral wind-resistant support mainly bears pressure and has a relatively small requirement for tensile resistance, it is sufficient to mainly ensure the strength of the leveling layer 5, and the requirement for the concrete column 12 is relatively low.

[0044] The embodiments of this specific implementation are all preferred embodiments of the present application, and are not intended to limit the protection scope of the present application. The same components are represented by the same figure marks. Therefore, any equivalent changes made based on the structure, shape, and principle of the present application should be included in the protection scope of the present application.

Claims

1. A construction structure of a transverse wind-resistant support for a super-large bridge, characterized in that: include A cushion stone (1), wherein the cushion stone (1) is provided with a reserved bolt hole (11); A first connecting steel plate (2), wherein a leveling space is reserved between the first connecting steel plate (2) and the cushion stone (1), and the leveling space is used for pouring concrete to form a leveling layer (5); A support bolt (21), wherein the support bolt (21) is threadedly connected to the first connecting steel plate (2), and is inserted into a reserved bolt hole (11) to be connected to the cushion stone (1).

2. The transverse wind-resistant support construction structure of a super-large bridge according to claim 1 is characterized by: It also comprises a second connecting steel plate (3), wherein the second connecting steel plate (3) is fixedly connected to the steel frame, and a shock absorbing assembly (4) is connected between the first connecting steel plate (2) and the second connecting steel plate (3).

3. The construction structure of a super-large bridge transverse wind-resistant support and the installation method thereof according to claim 1 are characterized by: The thickness of the leveling layer (5) is 3 cm.

4. The transverse wind-resistant support construction structure for a super-large bridge according to claim 1 is characterized by: A concrete column (12) is formed in the reserved bolt hole (11) so that the support bolt (21) and the cushion stone (1) are relatively fixed.

5. An installation method, based on the construction structure of the super-large bridge transverse wind-resistant support according to any one of claims 1 to 4, characterized in that: The steps include: S1, pouring the pad stone (1), with reserved bolt holes (11) reserved during pouring; S2. Fixing the first connecting steel plate (2) by means of auxiliary tooling, and leaving a leveling space between the first connecting steel plate (2) and the cushion stone (1); S3, installing the support bolt (21) on the first connecting steel plate (2), and allowing the head of the support bolt (21) to extend into the reserved bolt hole (11); S4, pouring concrete into the leveling space to form the leveling layer (5) and to fix the support bolts (21) and the cushion stone (1) relative to each other.

6. The installation method according to claim 5, characterized in that: The auxiliary tooling comprises a frame (6) and a steel plate positioning assembly (61) and a template assembly (62) arranged on the frame (6); the steel plate positioning assembly (61) is used to connect with the first connecting steel plate (2) to define the position of the first connecting steel plate (2); the template assembly (62) is used to abut against the cushion stone (1) and the first connecting steel plate (2) to close the bottom and side surfaces of the leveling space.

7. The installation method according to claim 6, characterized in that: The steel plate positioning assembly (61) comprises a connecting frame (611) and a positioning plate (612), wherein the connecting frame (611) is connected to the frame (6), and the positioning plate (612) is connected to the connecting frame (611), and the positioning plate (612) abuts against an end of the first connecting steel plate (2) away from the pad stone (1), and a positioning bolt (613) is provided on the positioning plate (612), and the positioning bolt (613) passes through the positioning plate (612) and is threadedly connected to the first connecting steel plate (2).

8. The installation method according to claim 7, characterized in that: Gaskets are provided between the positioning plate (612) and the first connecting steel plate (2), and the angle of the first connecting steel plate (2) is controlled by adjusting the number of gaskets.

9. The installation method according to claim 6, characterized in that: The template assembly (62) comprises a bottom template (622) and two side templates (621); the bottom template (622) is connected to the frame (6) via a vertical moving assembly (623); the side template (621) is connected to the frame (6) via a horizontal moving assembly (624); the bottom template (622) and the side template (621) are both in contact with a side of the cushion stone (1) facing the first connecting steel plate (2); the bottom template (622) is in contact with the bottom surface of the first connecting steel plate (2); and the two side templates (621) are respectively in contact with two side surfaces of the first connecting steel plate (2); The vertical moving assembly (623) is used to drive the bottom mold (622) to move in the vertical direction, and the lateral moving assembly (624) is used to drive the side mold (621) to move in the lateral direction.

10. The installation method according to claim 6, characterized in that: The auxiliary tooling also includes a vibration component (63), and the vibration component (63) includes a vibration frame (631) and a vibration motor (632), and the vibration motor (632) is in contact with a side of the first connecting steel plate (2) away from the cushion stone (1).