By designing the auxiliary construction device in the well, including the base, support mechanism and tensioning mechanism, an adjustable construction platform is provided, which solves the problem of insufficient safety guarantee for construction personnel and improves the safety and efficiency of construction personnel.
Patent Information
- Application Number
- CN202420408148.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-01
- Publication Date
- 2024-11-22
- Estimated Expiration
- 2034-03-01
AI Technical Summary
During the construction of the side wall of the pipe well, the safety guarantee of construction personnel is insufficient, and the existing technology is difficult to effectively ensure the safety of construction personnel.
An auxiliary construction device in the well is designed, including a base, a support mechanism and a tensioning mechanism. Through a combination of the support mechanism and a tensioning mechanism, an adjustable and safe construction platform is provided, which includes angle steel, iron chain or wire rope, Brackets, shafts and ratchet pawl assemblies allow construction workers to carry out construction at different heights and reduce labor intensity.
It improves the safety and convenience of construction personnel, has a wide range of application, reduces labor intensity, and the device structure is simple and light in use, improving construction efficiency.
Smart Images

Figure CN222042598U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to an auxiliary construction device in a well, belonging to an auxiliary construction device in a well. Background Art
[0002] Pipe wells are facilities placed vertically underground for underground pipeline inspection and construction, etc. They include power pipe wells, gas pipe wells, heating pipe wells, communication pipe wells, underground pipe gallery pipe wells, etc.
[0003] Currently, when working on the side wall of a pipe well, workers need to lie on the wellhead or use ladders to work at a suitable position, and the safety of the workers cannot be effectively guaranteed. Utility Model Content
[0004] Technical purpose: In order to overcome the deficiencies in the prior art, the utility model provides an auxiliary construction device in a well.
[0005] An auxiliary construction device in a well comprises a base, a supporting mechanism and a tensioning mechanism, wherein the upper end of the tensioning mechanism is connected to the supporting mechanism, and the lower end is connected to the base; the supporting mechanism comprises a first angle steel and a second angle steel, each of the first angle steel and the second angle steel is provided with two connecting holes connected to the tensioning mechanism, and the tensioning mechanism comprises four first iron chains and four second iron chains, an open accommodating space is formed between the four first iron chains, the four second iron chains and the base, the four first iron chains do not cross each other, and two adjacent first iron chains are tightened by the second iron chain.
[0006] Preferably, the upper ends of two of the first iron chains are detachably connected to the connection holes on the first angle steel, and the lower ends are connected to the corresponding connection holes on the base; the upper ends of the other two first iron chains are detachably connected to the connection holes on the second angle steel, and the lower ends are connected to the corresponding connection holes on the base;
[0007] Preferably, the supporting mechanism comprises a bracket, a supporting seat, a rotating shaft and a ratchet and pawl assembly, wherein supporting seats are provided at the four corners of the top of the bracket, and a ratchet and pawl assembly is provided on the supporting seat, wherein two adjacent ratchet and pawl assemblies are rotationally connected via a rotating shaft, and another two adjacent ratchet and pawl assemblies are also rotationally connected via a rotating shaft.
[0008] Preferably, the tensioning mechanism includes four first steel wire ropes and four second steel wire ropes, an open accommodating space is formed between the four first steel wire ropes, the four second steel wire ropes and the base, the four first steel wire ropes do not cross each other, and two adjacent first steel wire ropes are tensioned by the second steel wire rope.
[0009] Preferably, the base is in a circular or square shape.
[0010] Preferably, the base is a hollow structure.
[0011] Preferably, the base is made of stainless steel or carbon steel.
[0012] Preferably, the supporting mechanism further comprises a hand wheel.
[0013] Beneficial effects of the utility model:
[0014] 1. The utility model assists construction workers in construction by providing a base, a supporting mechanism and a tensioning mechanism. The utility model has a simple structure and is easy to use, which provides great convenience and safety to construction workers and also improves construction efficiency.
[0015] 2. The utility model has a wide range of applications. By arranging a bracket, a support seat, a rotating shaft and a ratchet pawl assembly, construction workers can adjust the length of the first iron chain before entering the well to achieve the lifting and lowering of the tensioning mechanism, which is convenient for construction workers to carry out construction at different heights.
[0016] 3. The utility model replaces the first iron chain with the first steel wire rope and the second iron chain with the second steel wire rope, which can reduce the weight of the tensioning mechanism, make adjustment more labor-saving, and reduce the labor intensity of workers.
[0017] 4. The base of the utility model is a hollow structure, which can reduce the weight of the base, making it lighter to use and easier to carry, saving time and effort, and the soles are not easily sticky with mud, and there is almost no need to clean the base later. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] Figure 1 This is a schematic diagram of the structure of the first embodiment of the utility model;
[0019] Figure 2 This is a schematic diagram of the structure of the second embodiment of the present utility model.
[0020] In the figure, 1. base; 21. first angle steel; 22. second angle steel; 23. bracket; 24. support seat; 25. rotating shaft; 26. ratchet pawl assembly; 27. handwheel; 3. tensioning mechanism; 31. first iron chain; 32. second iron chain; 4. accommodating space. DETAILED DESCRIPTION
[0021] The following is combined with Figure 1 To Attachment Figure 2 The principles and features of the present invention are described, and the examples given are only used to explain the present invention, and are not used to limit the scope of the present invention.
[0022] Embodiment 1
[0023] An auxiliary construction device in a well comprises a base 1, a supporting mechanism and a tensioning mechanism 3, wherein the upper end of the tensioning mechanism 3 is connected to the supporting mechanism, and the lower end is connected to the base 1; the supporting mechanism comprises a first angle steel 21 and a second angle steel 22, each of which is provided with two connecting holes connected to the tensioning mechanism 3; the tensioning mechanism 3 comprises four first iron chains 31 and four second iron chains 32, an open accommodating space 4 is formed between the four first iron chains 31, the four second iron chains 32 and the base 1, the four first iron chains 31 do not cross each other, and two adjacent first iron chains 31 are tightened by the second iron chains 32.
[0024] The upper ends of two of the first iron chains 31 are detachably connected to the connection holes on the first angle steel 21, and the lower ends are connected to the corresponding connection holes on the base 1; the upper ends of the other two of the first iron chains 31 are detachably connected to the connection holes on the second angle steel 22, and the lower ends are connected to the corresponding connection holes on the base 1;
[0025] The base 1 is in a circular or square shape.
[0026] The base 1 is a hollow structure, which can reduce the weight of the base 1, making it lighter to use and easier to carry, saving time and effort, and the soles are not easily sticky with mud, so there is almost no need to clean the base 1 later.
[0027] The base 1 is made of stainless steel or carbon steel.
[0028] The working principle of this embodiment:
[0029] When construction is required in the pipe shaft, the base 1 and the tensioning mechanism 3 are passed through the wellhead into the shaft. At this time, the first angle steel 21 and the second angle steel 22 are placed in parallel outside the wellhead, and the first angle steel 21 and the second angle steel 22 are separated by a certain distance. At this time, the first iron chain 31 is in a drooping state, and the construction personnel enter the shaft through the space between the first angle steel 21 and the second angle steel 22 and step on the base 1. At this time, the first iron chain 31 is in a tensioned state, and the construction personnel start construction.
[0030] Embodiment 2
[0031] The difference between this embodiment and the first embodiment is that the support mechanism of this embodiment can realize the lifting function, and the length of the first iron chain 31 can be adjusted according to the construction height in the well. The support mechanism includes a bracket 23, a support seat 24, a rotating shaft 25 and a ratchet pawl assembly 26. Support seats 24 are provided at the four corners of the top of the bracket 23, and a ratchet pawl assembly 26 is provided on the support seat 24. Two adjacent ratchet pawl assemblies 26 are rotatably connected by a rotating shaft 25, and another two adjacent ratchet pawl assemblies 26 are also rotatably connected by the rotating shaft 25.
[0032] The supporting mechanism further comprises a hand wheel 27 .
[0033] When construction is required in the pipe well, the bracket 23 is first erected outside the wellhead, and then the base 1 and the tensioning mechanism 3 are passed through the wellhead into the well. At this time, the first iron chain 31 is in a drooping state, and the construction personnel enter the well through the side entrance of the bracket 23 and step on the base 1. At this time, the first iron chain 31 is in a tensioned state, and the construction personnel begin construction. Before entering the well, the construction personnel can adjust the length of the first iron chain 31 through the hand wheel 27 to facilitate construction at different heights in the well.
[0034] Embodiment 3
[0035] The difference between this embodiment and the first embodiment is that the first iron chain 31 is replaced with a first steel wire rope, and the second iron chain 32 is replaced with a second steel wire rope, which can reduce the weight of the tensioning mechanism 3, make adjustment more labor-saving, and reduce the labor intensity of workers; the tensioning mechanism 3 includes four first steel wire ropes and four second steel wire ropes, and an open accommodating space 4 is formed between the four first steel wire ropes, the four second steel wire ropes and the base 1. The four first steel wire ropes do not cross each other, and two adjacent first steel wire ropes are tightened by the second steel wire rope.
[0036] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.
Claims
1. An auxiliary construction device in a well, characterized in that: The invention comprises a base (1), a supporting mechanism and a tensioning mechanism (3), wherein the upper end of the tensioning mechanism (3) is connected to the supporting mechanism, and the lower end is connected to the base (1); the supporting mechanism comprises a first angle steel (21) and a second angle steel (22), and the first angle steel (21) and the second angle steel (22) are each provided with two connection holes connected to the tensioning mechanism (3); the tensioning mechanism (3) comprises four first iron chains (31) and four second iron chains (32), and an open accommodation space (4) is formed between the four first iron chains (31), the four second iron chains (32) and the base (1); the four first iron chains (31) do not cross each other, and two adjacent first iron chains (31) are tensioned by the second iron chains (32).
2. The auxiliary construction device in the well according to claim 1, characterized in that: The upper ends of two of the first iron chains (31) are detachably connected to the connection holes on the first angle steel (21), and the lower ends are connected to the corresponding connection holes on the base (1); the upper ends of the other two of the first iron chains (31) are detachably connected to the connection holes on the second angle steel (22), and the lower ends are connected to the corresponding connection holes on the base (1).
3. The auxiliary construction device in the well according to claim 1, characterized in that: The support mechanism comprises a bracket (23), a support seat (24), a rotating shaft (25) and a ratchet pawl assembly (26); the support seats (24) are provided at the four corners of the top of the bracket (23); the ratchet pawl assembly (26) is provided on the support seat (24); two adjacent ratchet pawl assemblies (26) are rotatably connected via the rotating shaft (25); and another two adjacent ratchet pawl assemblies (26) are also rotatably connected via the rotating shaft (25).
4. The auxiliary construction device in the well according to claim 1, characterized in that: The tensioning mechanism (3) comprises four first steel wire ropes and four second steel wire ropes. An open accommodation space (4) is formed between the four first steel wire ropes, the four second steel wire ropes and the base (1). The four first steel wire ropes do not cross each other, and two adjacent first steel wire ropes are tensioned by the second steel wire ropes.
5. The auxiliary construction device in the well according to claim 1, characterized in that: The base (1) is in a shape of a circle or a square.
6. The auxiliary construction device in the well according to claim 1, characterized in that: The base (1) is a hollow structure.
7. The auxiliary construction device in a well according to claim 1, characterized in that: The base (1) is made of stainless steel or carbon steel.