Wall body structure with underground diaphragm wall serving as core tube shear wall
In the construction of cover excavation reverse operation, the underground continuous walls set up at multiple intervals and the rear pouring belts form shear walls, combined with the setting of I-shaped steel and steel cages, the problem of increasing costs and extending the construction cycle of underground continuous walls is solved. , achieving higher support strength and shorter construction cycle.
Patent Information
- Application Number
- CN202420368152.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-02-27
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2034-02-27
AI Technical Summary
During the construction of cover excavation counter-work, the underground continuous wall needs to be demolished as a temporary enclosure structure, which increases construction costs and extends the construction cycle.
The underground continuous wall with multiple intervals is used to form a shear wall with the rear casting belt, replacing traditional support piles and columns, forming a support structure with higher strength and stability, and after the construction is completed, I-shaped steel and steel cages are used. Concrete is poured inside to form a reinforced concrete structure and connected into a whole, eliminating the later step of demolishing the underground continuous wall.
The demolition cost is reduced, the construction cycle is shortened, the support effect is improved to the upper structure, and the vertical and horizontal load bearing capacity is better. The quality and construction efficiency of the steel cage are improved by setting the positioning cylinder and adjusting rod.
Smart Images

Figure CN222065427U_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of underground continuous wall construction, and in particular to a wall structure in which an underground continuous wall also serves as a core tube shear wall. Background Art
[0002] The top-down synchronous method of cover-and-cut construction is to first build piles, columns and underground continuous walls for underground projects, and then use them as supporting components, and then excavate the earth layer by layer and cast the floor structures of each layer until the bottom of the bottom slab is sealed. At the same time, the floor structure of the ground layer is used as a construction platform to construct the above-ground structure layer by layer. In the cover-and-cut construction, generally, the underground continuous wall is constructed along the outer wall of the building's basement or other temporary retaining walls are constructed along the circumference of the foundation pit, and then the underground core tube and the columns and piles used to support the upper structure are cast at the relevant positions inside the building. These supporting piles and columns serve as vertical supports to bear the deadweight and construction loads of the upper structure during the construction period until the bottom of the bottom slab is sealed.
[0003] As a temporary retaining structure, the underground continuous wall needs to be demolished later, which increases the construction cost and prolongs the construction period. Utility Model Content
[0004] In order to improve the problem of increasing construction costs and extending construction period due to demolition of underground continuous walls, the present application provides a wall structure in which an underground continuous wall also serves as a core tube shear wall.
[0005] The wall structure of an underground continuous wall also serving as a core tube shear wall provided in this application adopts the following technical solution:
[0006] A wall structure in which an underground continuous wall also serves as a core tube shear wall comprises a plurality of underground continuous walls arranged at intervals, a post-cast strip is arranged between two adjacent underground continuous walls, and the plurality of underground continuous walls and the post-cast strip together enclose a shear wall with a supporting function.
[0007] By adopting the above technical solution, multiple underground continuous walls and post-cast strips are set together, so that the two can be enclosed into a shear wall with a supporting function. The shear wall can replace the supporting piles and columns to support the upper structure, and there is no need to carry out subsequent demolition operations on the underground continuous walls, thereby reducing the demolition cost and shortening the construction period; and compared with supporting the upper structure through supporting piles and columns, the shear wall structure composed of multiple underground continuous walls and post-cast strips is more stable, can form a better supporting effect on the upper structure, and has a better vertical and lateral load bearing capacity.
[0008] Optionally, the post-cast strip includes an I-beam and a steel cage, the I-beam is respectively fixed at the ends of two adjacent underground continuous walls that are close to each other, the steel cage is arranged between two adjacent I-beams, and concrete is poured in the steel cage.
[0009] By adopting the above technical scheme, after the construction of the underground continuous wall is completed, I-beams are arranged at both ends of the underground continuous wall, and then a steel cage is arranged between the I-beams at one end of two adjacent underground continuous walls close to each other, and then concrete is poured into the steel cage to form a reinforced concrete structure with high strength. The reinforced concrete structure has high strength and can form a good supporting effect on the upper structure; the reinforced concrete structure is connected to the underground continuous wall as a whole, with a simple structure and convenient construction.
[0010] Optionally, the steel cage includes horizontal bars and vertical bars, the horizontal bars are welded and fixed to two adjacent I-beams in the transverse direction, and the vertical bars are tied and fixed to the horizontal bars in the vertical direction.
[0011] By adopting the above technical scheme, the horizontal reinforcement is welded and fixed to the I-beam at one end of two adjacent underground continuous walls close to each other, so that the two adjacent underground continuous walls are connected into a whole; the vertical reinforcement connects and fixes multiple horizontal reinforcements in the height direction, and the steel cage structure is simple and easy to manufacture; and the horizontal reinforcement, vertical reinforcement and I-beam are coordinated to connect all the underground continuous walls into a whole, thereby improving the overall consistency and stability of the shear wall.
[0012] Optionally, a plurality of positioning tubes are vertically spaced apart along the upper edge of the I-beam, and the inner diameter of the positioning tubes is adapted to the diameter of the horizontal ribs.
[0013] By adopting the above technical solution, the setting of the positioning tube makes it possible for the horizontal reinforcement to be welded by simply inserting the horizontal reinforcement into the positioning tube first, and then welding the positioning tube and the horizontal reinforcement to fix them. The positioning tube helps to quickly position the positioning reinforcement during welding, shortens the positioning time during welding of the horizontal reinforcement, and reduces the construction period; and prevents the welding position deviation of the positioning reinforcement from affecting the quality of the steel cage, thereby improving the quality of the post-casting strip.
[0014] Optionally, a plurality of adjusting rods are vertically spaced apart on the I-beam, and the positioning cylinder is threadedly connected to the adjusting rods.
[0015] By adopting the above technical solution, the positioning cylinder is threadedly connected to the adjusting rod, and the positioning cylinder is rotated to adjust the length of the threaded connection between the positioning cylinder and the adjusting rod, so that the positioning cylinder can be moved axially along the adjusting rod, so that the positioning cylinder can be gradually sleeved on the horizontal rib by rotating the positioning cylinder, thereby reducing the difficulty of inserting the horizontal rib into the positioning cylinder and shortening the construction period.
[0016] Optionally, anti-slip grooves are provided on the outer peripheral wall of the positioning tube.
[0017] By adopting the above technical solution, the provision of the anti-skid pattern makes the rotation of the positioning tube more convenient and avoids slipping.
[0018] Optionally, a chamfer is provided on an inner wall port of the positioning cylinder away from one end of the I-beam.
[0019] By adopting the above technical solution, the chamfering can reduce the difficulty of inserting the horizontal rib into the positioning tube, and the horizontal rib is easy to insert.
[0020] Optionally, a connecting screw is reserved on the underground continuous wall, a through hole corresponding to the connecting screw is opened on the I-beam, the connecting screw is inserted into the through hole, and a fastening nut is threadedly connected to the connecting screw.
[0021] By adopting the above technical solution, when installing the I-beam, it is only necessary to put the I-beam on the connecting screw through the through hole, then thread the fastening nut on the connecting screw, and tighten the fastening nut to fix the I-beam tightly on the underground continuous wall. The structure is simple and the fixing of the I-beam is convenient and stable.
[0022] In summary, the present application includes at least one of the following beneficial technical effects:
[0023] 1. The joint setting of underground continuous wall and post-cast strip enables the two to enclose an integral shear wall. As a supporting structure, the shear wall has higher strength and more stable and reliable support than the traditional supporting structure of one pile and one column. In addition, since the underground continuous wall also serves as the core tube shear wall, the trouble of dismantling the underground continuous wall in the later stage is saved, the cost of dismantling is reduced, and the construction period is shortened;
[0024] 2. The setting of I-beams and steel cages enables the post-cast belt to form a reinforced concrete structure with high strength. The reinforced concrete structure is connected to the underground continuous wall, so that the overall strength is high and a good support effect can be formed for the upper structure;
[0025] 3. The setting of the positioning tube can make the welding position more accurate when the horizontal is welded and fixed, thereby ensuring the quality of the steel cage, and then improving the quality of the post-casting belt and the strength of the post-casting belt. BRIEF DESCRIPTION OF THE DRAWINGS
[0026] In order to more clearly illustrate the technical solutions in the embodiments of the present application, the drawings required for use in the description of the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.
[0027] Figure 1 It is a schematic diagram of the overall structure of an embodiment of the present application;
[0028] Figure 2 yes Figure 1 A partial enlarged schematic diagram for showing the positioning tube;
[0029] Figure 3 is along Figure 1 Schematic diagram of the cross-sectional structure.
[0030] Figure numerals: 1. underground continuous wall; 2. post-cast strip; 21. I-beam; 211. side plate; 212. connecting plate; 2121. through hole; 22. steel cage; 221. horizontal ribs; 222. vertical ribs; 23. connecting screw; 24. fastening nut; 3. positioning cylinder; 31. anti-slip pattern; 4. adjusting rod; 41. external thread. DETAILED DESCRIPTION
[0031] The following is combined with Figure 1-3 This application is described in further detail.
[0032] The present application embodiment discloses a wall structure in which an underground continuous wall also serves as a core tube shear wall. Figure 1 The wall structure of the underground continuous wall that also serves as the core tube shear wall includes an underground continuous wall 1 and a post-cast strip 2. Exemplarily, the underground continuous wall 1 is an L-shaped wall, four underground continuous walls 1 are arranged at intervals, and the post-cast strip 2 is arranged between two adjacent underground continuous walls 1. All the underground continuous walls 1 and the post-cast strips 2 together enclose a shear wall with a supporting function, and the shear wall is rectangular as a whole.
[0033] As a whole, the underground continuous wall 1 and the post-cast strip 2 have a higher shear wall strength and a more stable structure than the traditional one-pile-one-column support structure, and a better support effect on the upper structure. In addition, since the underground continuous wall 1 also serves as the core tube shear wall, the process of dismantling the underground continuous wall 1 in the later stage is omitted, which reduces the dismantling cost and shortens the construction period.
[0034] Reference Figure 1-2 The post-cast strip 2 includes an I-beam 21 and a steel cage 22. The I-beam 21 is fixedly connected to the end of the underground continuous wall 1 through a connecting assembly. The ends of two adjacent underground continuous walls 1 close to each other are both provided with an I-beam 21. The steel cage 22 is fixedly connected to the two I-beams 21 at the ends of two adjacent underground continuous walls 1 close to each other. Concrete is poured in the steel cage 22. The vibrated concrete, the steel cage 22 and the I-beam 21 form a reinforced concrete structure with high strength.
[0035] The I-beam 21 includes two mutually parallel side plates 211 and a connecting plate 212 vertically connected to the middle of the two side plates 211. The spacing between the two side plates 211 is the same as the thickness of the underground continuous wall 1. The side plates 211 and the connecting plate 212 form two installation cavities separated by the connecting plate 212. When installing the I-beam 21, the end of the underground continuous wall 1 is clamped in one of the installation cavities of the I-beam 21, and the two side walls of the underground continuous wall 1 in the thickness direction are respectively abutted against the two side plates 211 of the I-beam 21, and then the I-beam 21 is fixedly connected to the underground continuous wall 1 through the connecting assembly.
[0036] Reference Figure 2-3 The connection assembly includes a connection screw 23 and a fastening nut 24. The connection screw 23 is pre-placed in the underground continuous wall 1 in the horizontal direction, and the connection screw 23 protrudes from the outer surface of the end of the underground continuous wall 1. A plurality of connection screws 23 are arranged at intervals in the vertical direction. A through hole 2121 is provided on the connection plate 212 corresponding to each connection screw 23. When the I-beam 21 is installed at the end of the underground continuous wall 1, the connection screw 23 passes through the through hole 2121 on the connection plate 212, and the fastening nut 24 is threadedly connected to one end of the connection screw 23 passing through the through hole 2121. The connection plate 212 can be fixed to the underground continuous wall 1 by tightening the fastening nut 24, thereby fixing the I-beam 21 to the underground continuous wall 1. The structure is simple, and the fixing of the I-beam 21 is convenient and quick.
[0037] The steel cage 22 includes horizontal ribs 221 and vertical ribs 222. A positioning assembly is provided on the I-beam 21. The horizontal ribs 221 are horizontally connected to the two I-beams 21 at one end of the two adjacent underground continuous walls 1 that are close to each other through the positioning assembly. The vertical ribs 222 are vertically fixed to the horizontal ribs 221 by iron wire binding, and the iron wire is not shown in the figure. The positioning assembly includes a positioning cylinder 3 and an adjusting rod 4. The adjusting rod 4 is horizontally welded and fixed to the connecting plate 212. A plurality of adjusting rods 4 are arranged at intervals along the vertical direction, and multiple rows of adjusting rods 4 are arranged at intervals along the thickness direction of the underground continuous wall 1. An external thread 41 is provided on the outer peripheral wall of the adjusting rod 4. The inner peripheral wall of the positioning cylinder 3 is threadedly connected to the adjusting rod 4. The minimum diameter of the inner peripheral wall of the positioning cylinder 3 is the same as the diameter of the horizontal rib 221.
[0038] When installing and fixing the horizontal rib 221, one end of the horizontal rib 221 is inserted into the positioning tube 3 on one of the I-beams 21 in the horizontal direction, and then the positioning tube 3 at the same height on the adjacent I-beam 21 is rotated and adjusted to be away from the horizontal rib 221. After the horizontal rib 221 is roughly adjusted to a horizontal state and coaxially aligned with the positioning tube 3, the positioning tube 3 is rotated and adjusted again so that the positioning tube 3 moves toward the horizontal rib 221 until it is sleeved on the outer peripheral wall of the horizontal rib 221, and finally the horizontal rib 221 and the positioning tubes 3 at both ends are welded and fixed. The setting of the positioning tube 3 enables the welding position of the horizontal rib 221 to be accurately positioned, thereby increasing the quality of the steel cage 22, and further improving the quality of the post-casting strip 2. The matching setting of the positioning tube 3 and the adjusting rod 4 enables the horizontal rib 221 to be more conveniently inserted into the positioning tube 3. After the steel cage 22 is manufactured, the positioning tube 3 and the adjusting rod 4 are cast and formed in reinforced concrete, which reduces the interference of the positioning tube 3 and the adjusting rod 4 with other components.
[0039] In other embodiments, the positioning assembly may not be provided, and the two ends of the horizontal rib 221 may be directly welded and fixed to the I-beam 21 at one end of the adjacent underground continuous wall 1 that is close to each other.
[0040] In addition, in order to facilitate the rotation of the positioning tube 3, the outer peripheral wall of the positioning tube 3 is provided with anti-slip grooves 31. In order to further reduce the difficulty of inserting the horizontal rib 221 into the positioning tube 3, the inner wall port of the positioning tube 3 away from the I-beam 21 is provided with a chamfer.
[0041] The implementation principle of the wall structure of the underground continuous wall that also serves as the core tube shear wall in the embodiment of the present application is as follows: after the construction of the underground continuous wall 1 is completed, the through hole 2121 on the connecting plate 212 of the I-beam 21 is sleeved on the corresponding connecting screw 23, and then the fastening nut 24 is tightened to fix the I-beam 21 tightly on the underground continuous wall 1; then one end of the horizontal reinforcement 221 is inserted into the positioning tube 3 on the I-beam 21, and the other end of the horizontal reinforcement 221 is inserted into the corresponding positioning tube 3 on the adjacent I-beam 21, and then both ends of the horizontal reinforcement 221 are welded and fixed to the corresponding positioning tube 3, and finally the vertical reinforcement 222 is tied and fixed to the horizontal reinforcement 221 along the vertical direction, so that the production of the steel cage 22 can be completed, and then concrete is poured into the steel cage 22 to complete the production of the backcast strip 2. The entire underground continuous wall 1 and the post-cast strip 2 enclose an integral shear wall. Compared with the traditional one-pile-one-column support structure, the overall shear wall has higher strength, can form a more stable support for the upper structure, and has better vertical and lateral load bearing capacity; and because the underground continuous wall 1 also serves as a shear wall, the trouble of later demolition of the underground continuous wall 1 is eliminated, the demolition cost is saved, and the construction period is shortened.
[0042] The above are all optional embodiments of the present application, and are not intended to limit the protection scope of the present application. Therefore, any equivalent changes made based on the structure, shape, and principle of the present application should be included in the protection scope of the present application.
Claims
1. A wall structure in which an underground continuous wall also serves as a core tube shear wall. Features: The invention comprises a plurality of underground continuous walls (1) arranged at intervals, a post-cast strip (2) being arranged between two adjacent underground continuous walls (1), and the plurality of underground continuous walls (1) and the post-cast strip (2) together enclose a shear wall having a supporting function; the post-cast strip (2) comprises an I-beam (21) and a steel cage (22), the I-beam (21) being respectively fixed at the ends of the two adjacent underground continuous walls (1) close to each other, the steel cage (22) being arranged between the two adjacent I-beams (21), and concrete being poured in the steel cage (22); the steel cage (22) comprising horizontal bars (221) and vertical bars (222), the horizontal bars (221) being welded and fixed to the two adjacent I-beams (21) in the transverse direction, and the vertical bars (222) being tied and fixed to the horizontal bars (221) in the vertical direction; A plurality of positioning cylinders (3) are arranged at intervals along the upper edge of the I-beam (21), and the inner diameter of the positioning cylinders (3) matches the diameter of the horizontal rib (221); a plurality of adjusting rods (4) are arranged at intervals along the upper edge of the I-beam (21), and the positioning cylinders (3) are connected to the adjusting rods (4) via threads.
2. The wall structure of the underground continuous wall also serving as the core tube shear wall according to claim 1, Features: The outer peripheral wall of the positioning cylinder (3) is provided with anti-slip grooves (31).
3. The wall structure of the underground continuous wall also serving as the core tube shear wall according to claim 1, Features: The inner wall port of the positioning cylinder (3) at one end away from the I-beam (21) is provided with a chamfer.
4. The wall structure of the underground continuous wall also serving as the core tube shear wall according to claim 1, Features: A connecting screw (23) is reserved on the underground continuous wall (1), a through hole (2121) is opened on the I-beam (21) corresponding to the connecting screw (23), the connecting screw (23) is inserted into the through hole (2121), and a fastening nut (24) is threadedly connected to the connecting screw (23).