Assembly type elevator shaft hoisting structure

Through the design of pre-installed elevator shaft modules and flip-around connection platforms, the rapid and safe lifting of elevator shafts is achieved, solving the problem of long elevator installation time in old residential buildings, and improving the synchronization of installation efficiency and on-site assembly.

CN222184234UActive Publication Date: 2024-12-17HUNAN TIJING ELEVATOR ENG CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420601861.4
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-26
Publication Date
2024-12-17
Estimated Expiration
2034-03-26

AI Technical Summary

Technical Problem

During the elevator installation process in old residential buildings, how to quickly and safely complete the elevator shaft lifting and installation to reduce the impact on residents' lives and installation time.

Method used

Pre-installed elevator shaft modules are adopted, each module is a U-shaped frame, and a flip-fitting connection platform and lifting hole are set up. They are folded and folded during transportation, and are expanded as a connecting corridor after arriving at the site. They are lifted vertically by lifting equipment to ensure the shaft frame and corridor. Synchronous installation of the channel foundation.

Benefits of technology

It shortens the working cycle, ensures the consistency of on-site assembly and design, simplifies the transportation and lifting installation process, and improves the efficiency of elevator installation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222184234U_ABST
    Figure CN222184234U_ABST
Patent Text Reader

Abstract

The utility model discloses an assembly type elevator shaft hoisting structure. Comprising one to two sections of preassembled elevator shaft modules, each section of preassembled elevator shaft module is a U-shaped frame, a turnover connecting platform is arranged on the opening side of each U-shaped frame, a lifting hole is formed in the top of each elevator shaft module to serve as a lifting point, and if the number of the elevator shaft modules is two sections, a lifting hole is formed in one end, away from a foundation pit connecting end, of one section to serve as a lifting point. According to the structure, the steel structure elevator shaft and the connecting gallery foundation are installed at the same time, the work period is shortened, the consistency of field assembly and design of the shaft frame is guaranteed, and transportation, hoisting and installation are convenient.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of elevator installation, in particular to a hoisting structure for an assembled elevator shaft. Background Art

[0002] The installation of elevators in multi-story old residential buildings has become a development trend with the advancement of barrier-free urbanization. In projects such as installing elevators in old residential buildings, in order to minimize the impact of the project on the daily lives of residents, the elevators need to be installed in a very short time. In order to speed up the installation of elevators, the steel frames used to form the elevator shafts are modularized, and then the modules of the steel frames are stacked to form the elevator shafts, and then hoisted and installed. How to hoist the elevator shafts quickly and safely is also becoming the focus of attention in this technical field. Utility Model Content

[0003] The utility model provides a prefabricated elevator shaft hoisting structure, which is used for hoisting operations in the construction of prefabricated steel structure elevator shafts and effectively improves the efficiency of elevator installation.

[0004] In order to achieve the above-mentioned purpose, the technical solution adopted by the utility model is: an assembled elevator shaft hoisting structure, including one to two pre-installed elevator shaft modules, each pre-installed elevator shaft module is a U-shaped frame, and a flippable connecting platform is arranged on the opening side of the U-shaped frame. The connecting platform can be folded and stowed during transportation, and unfolded when the hoisting is complete to serve as a connecting corridor between the elevator shaft and the existing residential opening side. A lifting hole is arranged on the top of the elevator shaft module as a lifting point. If there are two elevator shaft modules, a lifting hole is arranged on the end of one of the sections away from the foundation pit connection end as a lifting point.

[0005] Preferably, the connecting platform is a steel beam structure, and the steel beam is hinged to the frame for flipping arrangement.

[0006] Preferably, reinforcing ribs are fixed to the lower portion of the steel beam on the opening side of the U-shaped frame.

[0007] Preferably, an embedded steel plate is provided on the opening side of the existing residence, a connecting plate is fixed on the embedded steel plate, the connecting plate is butt-jointed with the flipped steel beam to form the basis of the connecting corridor, and the production of the steel beam and the production of the connecting plate are matched and designed in advance.

[0008] Beneficial effects:

[0009] The utility model adopts the above technical solution, by setting up a pre-installed elevator shaft module, during transportation, the pre-installed elevator shaft module is horizontally placed on the transport vehicle, the steel beam is flipped and folded, and then hoisted to the corresponding, after the vehicle arrives at the destination, the horizontal pre-installed elevator shaft module is connected to the hoisting equipment, hoisted to a vertical state, the steel beam is unfolded, and the connection and installation with the existing residential opening are carried out. The utility model structure installs the steel structure elevator shaft and the connecting corridor foundation at the same time, shortens the working cycle, ensures the consistency of the on-site assembly and design of the shaft frame, and is convenient for transportation and hoisting installation. BRIEF DESCRIPTION OF THE DRAWINGS

[0010] In order to more clearly illustrate the implementation mode of the utility model and the beneficial effects of the utility model, the drawings required for use in the implementation mode or the prior art description will be briefly introduced below. Obviously, the drawings in the following description are only some implementation modes of the utility model. For ordinary technicians in this field, other structures can be obtained based on the structures shown in these drawings without paying creative work.

[0011] Figure 1 This is one of the structural schematic diagrams of an embodiment of the utility model.

[0012] Figure 2 for Figure 1 Enlarged view of part B in the middle.

[0013] Figure 3 for Figure 1 Enlarged view of part C in the middle.

[0014] Figure 4 Schematic diagram of the connection between steel beam and frame.

[0015] Figure 5 for Figure 4 Enlarged view of part A.

[0016] Figure 6 This is the schematic diagram of the hoisting of the first section.

[0017] Figure 7 This is the hoisting diagram of the second section.

[0018] Explanation of the accompanying figures: U-shaped frame-1, steel beam-2, lifting point-3, reinforcement rib-4, embedded steel plate-5, connecting plate-6, cross beam-7, hinge-8. DETAILED DESCRIPTION

[0019] Specific embodiments of the utility model:

[0020] See also Figure 1 , Figure 2 , Figure 3 , Figure 4 , Figure 5An assembled elevator shaft hoisting structure of the present embodiment includes two sections of pre-installed elevator shaft modules, each of which is a U-shaped frame 1. A reversible connecting platform is arranged on the opening side of the U-shaped frame. The connecting platform can be folded and stowed during transportation, and unfolded when the hoisting is complete to serve as a connecting corridor between the elevator shaft and the existing residential opening side. A lifting hole is arranged on the top of the elevator shaft module as a lifting point, and a lifting hole is arranged at one end of one section away from the foundation pit connection end as a lifting point 3.

[0021] Preferably, the connecting platform is a steel beam structure, the steel beam 2 is hinged to the frame for flipping arrangement, in the embodiment, the steel beam and the frame column are connected by hinges 8, and cross beams 7 are arranged between the steel beams.

[0022] Preferably, a reinforcing rib 4 is fixed to the lower portion of the steel beam on the opening side of the U-shaped frame.

[0023] Preferably, an embedded steel plate 5 is provided on the opening side of the existing residence, a connecting plate 6 is fixed on the embedded steel plate, and the connecting plate is butted with the turned-over steel beam to form the basis of the connecting corridor, and the production of the steel beam and the production of the connecting plate are matched and designed in advance.

[0024] The working process of the utility model is as follows:

[0025] See also Figure 6 , Figure 7 The aisle steel beam is fixed to the A side of the shaft module by a hinge. The steel beam is folded and put away during transportation. After being transported to the installation site, the section shaft is fixed and lifted by a crane with a lifting point. It is lifted vertically and slowly. The steel beam slowly unfolds due to gravity. After one end of the shaft rises to a certain height and forms an elevation angle, the steel beam is fully unfolded. The shaft and corridor foundation are hoisted to the designated installation position as a whole. The embedded steel plates and connecting plates are fixed at the existing residential openings. After completing the hoisting of one section of the shaft module, the second section of the shaft module can be hoisted into place in the same way.

[0026] The above are only preferred embodiments of the present invention, and are not intended to limit the patent scope of the present invention. Any equivalent structure or equivalent process transformation made using the contents of the specification and drawings of the present invention, or directly or indirectly applied in other related technical fields, are also included in the patent protection scope of the present invention.

Claims

1. An assembled elevator hoistway hoisting structure, characterized in that: It includes one or two pre-installed elevator shaft modules, each of which is a U-shaped frame. A reversible connecting platform is arranged on the opening side of the U-shaped frame. A lifting hole is arranged on the top of the elevator shaft module as a lifting point. If there are two elevator shaft modules, a lifting hole is arranged on the end of one of the modules away from the foundation pit connection end as a lifting point.

2. The assembled elevator hoistway hoisting structure according to claim 1, characterized in that: The connecting platform is a steel beam structure, and the steel beam is hinged to the frame for flipping arrangement.

3. The assembled elevator hoistway hoisting structure according to claim 1, characterized in that: A reinforcing rib is fixed on the lower part of the steel beam on the opening side of the U-shaped frame.

4. The assembled elevator hoistway hoisting structure according to claim 1, characterized in that: The existing residential opening side is provided with an embedded steel plate, and the connecting plate is fixed on the embedded steel plate.

5. The assembled elevator hoistway hoisting structure according to claim 4, characterized in that: The steel beam is connected to the frame column through a hinge.

6. The assembled elevator hoistway hoisting structure according to claim 5, characterized in that: Cross beams are arranged between the steel beams.