One-stage prestressed concrete pipe
A concrete pipe and prestressing technology, applied in the direction of pipes, rigid pipes, pipes/pipe joints/pipe fittings, etc., can solve problems such as water leakage, rubber ring slippage at the pipe socket, and poor adaptability, so as to ensure the overall quality and reduce Construction cost, easy counterpart effect
Patent Information
- Authority / Receiving Office
- CN · China
- Current Assignee / Owner
- Publication Date
- 2011-03-30
- Estimated Expiration
- Not applicable · inactive patent
Smart Images

Figure 1 
Figure 2
Abstract
Description
technical field
[0001] The invention relates to a prestressed concrete pipe, in particular to a one-stage prestressed concrete pipe. Background technique
[0002] One-stage prestressed concrete pipe (YYG) is a non-metallic pipe successfully trial-produced in the mid-1960s in my country. Because of its simple processing technology and low cost (only 60% of steel pipe), it is widely used in urban water supply and drainage, long-distance water delivery, farmland irrigation and various water conservancy projects. According to the national standard "Prestressed Concrete Pipe (GB5696-2006)" of the People's Republic of China, the first-stage prestressed concrete pipe (YYG) adopts a socket-type interface with a circular rubber seal ring, and the pipes of different pressure levels from DN400 to 1600 The length and size of the socket and the socket are exactly the same, only the diameter of the ring and the diameter of the apron used are different. The pipes with different pressure g...
Examples
Embodiment Construction
[0011] As shown in the figure: the one-stage prestressed concrete pipe (YYG) is a prefabricated prefabricated concrete pipe with two-way prestressed in the concrete pipe wall, which is prepared by vibratory extrusion process of concrete 1, circumferential prestressed steel bar 2 and longitudinal prestressed steel bar 3 Concrete pipe body 4. Its socket 5 is arranged on the left side of concrete pipe body 4, and socket 6 is arranged on the right side of concrete pipe body 4, and pipe socket and socket joint are sealed with a circular solid rubber sealing ring 7 during installation.
[0012] Shorten the length a of the outer slope of the socket by 20mm, that is, 30mm for DN400~1600, 40mm for DN1800~2000, and grind to a smooth level; shorten the length b of the socket face of the first-stage prestressed concrete pipe (YYG) Increase the value to more than 100mm, and grind it to the level of smoothness; increase the total depth c value of the first-stage prestressed concrete pipe (Y...