technical field
[0001] The invention relates to a construction method for deep mixing cement land connecting walls, belonging to the technical field of building construction. Background technique
[0002] In recent years, my country's urbanization has developed rapidly, and high-rise buildings in various cities have sprung up like mushrooms. In the construction of the soil layer containing or mixed with egg (crushed) stones with a particle size not greater than 10cm, there are still problems such as poor continuity, insufficient integrity and poor anti-permeability of the constructed diaphragm wall. Contents of the invention
[0003] The purpose of the present invention is to solve the problems existing in the construction of the land continuous wall in the current building construction, and provide a construction method of the deep mixing cement land continuous wall to solve the above-mentioned problems.
[0004] In order to achieve the above object, the technical scheme ...
Examples
Embodiment Construction
[0022] See attached figure 1 ,
[0023] 1. Clear the site, prepare materials, level and compact the construction site, remove ground and underground obstacles, and the working surface should not be less than 7m. When the ground surface is too soft, measures should be taken to prevent mechanical instability. Prepare enough cement and admixtures.
[0024] 2. Surveying and setting out The axis of the wall construction shall be determined according to the design requirements, and an elevation control pile shall be arranged every 50m, and a clear mark shall be made.
[0025] 3. Installation and commissioning to support the mobile machine and the main engine in place; erect pile frames; install pulping, grouting and gas-making equipment; connect water, electric and gas circuits; run and test run.
[0026] 4. Ditching and decking The excavation cross-section is a storage ditch with a depth of 1m and a width of 1.2m to solve the residual slurry storage and slurry return supply durin...