DP-MPSO algorithm based weekly repair plan compiling and optimizing method for power dispatching
A DP-MPSO and power grid dispatching technology, applied in computing, instrumentation, data processing applications, etc., can solve problems such as sub-problems are not independent of each other, can not get the correct results, maintenance model is cumbersome, etc., to achieve easy implementation, processing Good, the effect of rapid algorithm convergence process
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Publication Date
- 2016-08-31
- Estimated Expiration
- Not applicable · inactive patent
Smart Images
Figure 1 Figure 2 Figure 3
Abstract
Description
technical field
[0001] The invention relates to the technical field of power system dispatching automation, in particular to a method for preparing and optimizing a power grid dispatching weekly maintenance plan based on a DP-MPSO algorithm. Background technique
[0002] With the rapid development of the economy, social electricity consumption has increased rapidly year-on-year, the scale of the power grid has expanded rapidly, and the structure of the power grid has become increasingly complex; the number of power equipment such as buses, transformers, and switches has increased rapidly, which in turn has brought about the safety of power grid equipment and economical operation. security issues.
[0003] After the implementation of the strong and smart grid plan, the development of many emerging technologies has put forward new requirements for the maintenance of the power grid, including the power market, distributed power technology and condition-based maintenance, among ...
Examples
Embodiment 1
[0043] In step 1 of the method of the present invention, the equivalent unit is constructed, and the load L of the system during the normal operation of the whole network equipment is obtained from the system f , and when the equipment to be repaired in the maintenance ticket is disconnected, the loadable load L of the system d , define the installed capacity C of the equivalent unit e ,details as follows:
[0044] C e =L f -L d
[0045] Model preprocessing, read into the compilation cycle T, load forecast L within T pAs well as the installed capacity W of the entire network, discretize T from 0 on a daily basis, and refine the daily load forecast L pi , get all maintenance tickets M in T j Scheduled start and end times t js , t je , if t js p on, make sure the t of the remaining maintenance ticket js ≥0.
[0046] In step 2, maintenance constraint processing, for mutually exclusive constraints, it is necessary to establish split sets according to mutually exclusive...