Abstract
Description
technical field
[0001] The invention relates to the field of well workover, in particular to a method for evaluating construction effects of measure operations in downhole workover operations. Background technique
[0002] Downhole operation is a general term for all kinds of construction procedures such as the commissioning of oil and water wells, production maintenance, troubleshooting in wells, increasing and stabilizing production, etc. It is an important guarantee for the long-term and efficient operation of oil, gas and water wells. After years of exploitation and development, the oil production of most oilfields is currently showing a downward trend. The problems faced by various oil production plants are high water content in liquid production, complex well conditions of oil and water wells, difficult construction of some oil wells, and long time for oil well operations , resulting in an increase in lost time, which greatly affects the crude oil production process in...
Examples
Embodiment 1
[0048] A method for evaluating the construction effect of measure operations in downhole workover operations, comprising the following steps:
[0049] (a) Determine the evaluation index set U of the measure operation, U={oil increment u 1 , validity period u 2 , effective u 3 , construction period u 4 , Injection amount u 5 , water injection pressure u 6};
[0050] (b) Determine the evaluation set V of the job effect, V={good v 1 , better v 2 , generally v 3 , poorer v 4 , difference v 5};
[0051] (c) Determine the weight W of each evaluation index;
[0052] (d) Given the evaluation matrix R=(R 1 , R 2 , R 3 , R 4 , R 5 , R 6 ) T , R i =(r i1 ,r i2 ,r i3 ,r i4 ,r i5 ), where the element R i =U i ×W i , i=1,2,…,6, where U i For each evaluation index in the index set U, W i is the weight corresponding to the evaluation index, element r ij is the possibility degree of the j-th evaluation of the i-th evaluation index;
[0053] (e) Establish a fuzzy ...
Embodiment 2
[0056] A method for evaluating the construction effect of measure operations in downhole workover operations, characterized in that it comprises the following steps:
[0057] (a) Determine the evaluation index set U of the measure operation, U={oil increment u 1 , validity period u 2 , effective u 3 , construction period u 4 , Injection amount u 5 , water injection pressure u 6}; Standardize the data of each index in the index set U by the range normalization method:
[0058] (1) There are s evaluation blocks, based on 6 evaluation indicators, an index data matrix Y=(y ij ) s×6 ;
[0059] (2) When the jth index is a very large index, that is, the index value y ij When the bigger the better, the conversion formula is:
[0060]
[0061] When the jth index is a very small index, that is, the index value y ij When the smaller the better, the conversion formula is:
[0062]
[0063] (3) By the two conversion formulas, the index data matrix Y is converted into a dec...