A formwork for lifting elevator and construction method thereof

By designing a mold frame for ultra-high-rise jump elevators, self-climbing construction equipment and winches can be used to achieve self-climbing of elevators, the problems of insufficient tower crane capacity occupation and safety are solved, and the safety of elevator lifting and operation are improved , and provide additional protection through protective sheds and isolation sheds.

CN109436985BActive Publication Date: 2024-11-08SHANGHAI CONSTRUCTION FIRST CONSTRUCTION (GROUP) CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN201811363144.8
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2018-11-15
Publication Date
2024-11-08
Estimated Expiration
2038-11-15

AI Technical Summary

Technical Problem

During the lifting of super-high-rise elevators, construction machinery such as tower cranes need to be borrowed, which affects the tower crane's transportation capacity and is insufficient in safety, and lacks effective mold frame equipment to achieve self-climbing and protection.

Method used

Design a mold frame, including the first lifting ring, hoist, fixed beam and lifting beam at the bottom of the self-climbing construction equipment, and realize the self-lifting of the elevator room and the bridge cabin through the winch driving wire rope, and connect the telescopic horns to the shaft structure to achieve the The elevators are climbed by themselves and improve safety through protective sheds and isolation sheds.

Benefits of technology

Without occupying the tower crane, the elevator is self-climbed, saving tower crane transport capacity, improving the safety of elevator lift and operation, and effectively protecting the elevator through protective sheds and isolation sheds.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN109436985B_ABST
    Figure CN109436985B_ABST
Patent Text Reader

Abstract

The present invention provides a formwork frame for lifting an elevator and a construction method thereof. The formwork frame comprises a first lifting ring, a hoisting machine, a fixed beam and a lifting beam arranged at the bottom of a self-climbing construction device. Under normal construction conditions, the elevator is fixed to a shaft structure by the fixed beam, and the elevator works normally. Before lifting, the elevator stops being used, and the elevator still bears its own structural weight through the fixed beam. At this time, the connection between the lifting beam and the shaft structure is disconnected, and the lifting beam is lifted to an upper floor by using the self-climbing construction device and the hoisting machine. After the lifting beam is in place, the lifting beam is fixed to the shaft structure. The connection between the fixed beam and the shaft structure is disconnected, and the elevator machine room and the elevator bridge car are lifted into place in reverse with the lifting beam as a fulcrum by using the fixed lifting beam and the hoisting machine. After reaching a predetermined position, the fixed beam is fixed to the shaft structure, thereby realizing the climbing of the elevator without occupying a tower crane, saving the tower crane's transportation capacity, and improving the safety of the elevator during lifting and operation.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the field of building construction and is used for lifting a super-high-rise leap-floor elevator. Background Art

[0002] With the continuous advancement of construction technology, super-high-rise buildings have become an increasingly widely used building form, and the forms of super-high-rise elevators have become more and more diverse, and split-level elevators have come into being. Split-level elevators are to temporarily close part of the completed shaft, and temporarily fix a mobile machine room on the top of the shaft, install the elevator power device, bridge and other elevator components, and after installation, they can run in the closed shaft to carry out vertical transportation of construction materials, equipment and personnel, and also be used as construction elevators; when the upper shaft structure completes a certain floor, the temporary closed partition is lifted, and it is installed and debugged again, and so on, until the structure is capped, the equipment in the mobile machine room is lifted into the permanent machine room, and the elevator is installed and debugged again, that is, it is converted into a permanent elevator for the building. Split-level elevators have been widely used for their superior performance.

[0003] However, the lifting of the leap-level elevator often requires the use of construction machinery such as tower cranes, which affects the crane's transportation capacity and is often not safe enough. Therefore, it is urgent to develop a formwork equipment that accompanies the lifting of the leap-level elevator. Summary of the invention

[0004] The purpose of the present invention is to provide a formwork for lifting an elevator and a construction method thereof, which can realize the self-climbing of the leap-layer elevator, save the transportation energy of the tower crane, and effectively protect the leap-layer elevator, thereby greatly improving the safety of the leap-layer elevator during lifting and operation.

[0005] In order to solve the above technical problems, the present invention provides the following technical solutions:

[0006] A formwork for lifting an elevator is arranged in a shaft structure, the elevator comprising an elevator room and an elevator bridge, the elevator room is provided with an elevator motor, the elevator motor drives the elevator bridge to move up and down, the formwork comprising: a first lifting ring arranged at the bottom of a self-climbing construction equipment, a winch, a fixed beam and a lifting beam, the fixed beam is fixedly connected to the elevator room, the elevator bridge, the elevator room, the lifting beam and the self-climbing construction equipment are arranged in sequence from bottom to top, telescopic brackets are respectively provided at both ends of the fixed beam and the lifting beam, the telescopic brackets can be extended into the corresponding support opening of the shaft structure and separated from the corresponding support opening of the shaft structure, the winch is fixedly arranged in the elevator room, the winch comprises a winch motor and two drums driven by the winch motor, a first steel wire rope and a second steel wire rope are respectively provided on the two drums, the free end of the first steel wire rope is fixedly connected to the lifting beam, and the free end of the second steel wire rope is fixedly connected to the lifting beam after passing through the first lifting ring.

[0007] Preferably, the above-mentioned formwork for lifting the elevator also includes a horizontally arranged isolation shed, which is located between the elevator room and the lifting beam, and is supported on the top of the elevator room by a second vertical supporting member, and the isolation shed covers the top of the elevator room.

[0008] Preferably, the above-mentioned formwork for lifting elevators also includes a horizontally arranged protective shed, wherein the protective shed is located between the self-climbing construction equipment and the lifting beam, and the protective shed is supported on the lifting beam through a first vertical supporting member, and both sides of the protective shed are respectively provided with wall guide wheels in contact with the inner wall of the shaft structure.

[0009] Preferably, in the above-mentioned formwork for lifting elevators, the fixed beam is transversely fixed on the elevator machine room to separate the elevator machine room into a control machine room and a traction machine room, and the traction machine room is located below the control machine room. There are two winches, which are symmetrically arranged in the traction machine room.

[0010] Preferably, in the above-mentioned formwork for lifting elevators, the upper part of the lifting beam is provided with a lower lifting ring for connecting to the free end of the first steel wire rope, and the upper part of the lifting beam is provided with an upper lifting ring for connecting to the free end of the second steel wire rope.

[0011] The present invention also discloses a construction method for the formwork for lifting an elevator as described above, comprising the following steps:

[0012] Under normal construction conditions, the elevator is fixed to the hoistway structure by a fixed beam, and the elevator bridge works normally under the power of the elevator motor;

[0013] Before lifting, the elevator stops using and still bears its own structural weight through the fixed beam. At this time, the connection between the lifting beam and the shaft structure is disconnected, and the lifting beam is lifted to the upper floor using the self-climbing construction equipment and winch;

[0014] After the lifting beam is in place, fix the lifting beam to the hoistway structure;

[0015] Disconnect the connection between the fixed beam and the hoistway structure, and use the fixed lifting beam and winch to lift the elevator machine room and the elevator bridge car in reverse with the lifting beam as the fulcrum;

[0016] After reaching the predetermined position, the fixed beam is fixed to the support hole corresponding to the upper floor on the hoistway structure, thereby completing the elevator lifting.

[0017] Preferably, in the above-mentioned construction method of the formwork for lifting the elevator, the lifting beam is lifted to the upper floor by using self-climbing construction equipment and a winch, and the self-climbing construction equipment climbs upward, and the first steel wire rope of the winch is synchronously paid out with the second steel wire rope.

[0018] Preferably, in the above-mentioned construction method of the formwork for lifting the elevator, the fixed lifting beam and winch are used to lift the elevator machine room and the elevator bridge car into place in reverse with the lifting beam as a fulcrum, and this is achieved by synchronously winding up the first steel wire rope and the second steel wire rope of the winch to shorten the distance between the lifting beam and the winch.

[0019] Preferably, in the above-mentioned construction method of the formwork for lifting the elevator, the fixed connection between the fixed beam or the lifting beam and the shaft structure is achieved by extending the telescopic corbel into the corresponding support hole on the shaft structure; and the connection between the fixed beam or the lifting beam and the shaft structure is disconnected by retracting the telescopic corbel.

[0020] Preferably, in the above-mentioned construction method of the formwork for lifting the elevator, all the above-mentioned steps are repeated until the construction is completed and the elevator machine room reaches the highest permanent position, and then the winch is removed.

[0021] It can be seen from the technical solutions disclosed above that, compared with the prior art, the beneficial effects of the present invention are as follows:

[0022] The formwork for lifting the elevator and the construction method thereof provided in the present embodiment are provided with a first lifting ring, a winch, a fixed beam and a lifting beam arranged at the bottom of the self-climbing construction equipment. Under normal construction conditions, the fixed beam fixes the entire elevator to the shaft structure, and the elevator bridge works normally under the power of the elevator motor. Before lifting, the elevator stops using, and the elevator still bears its own structural weight through the fixed beam. At this time, the connection between the lifting beam and the shaft structure is disconnected, and the lifting beam is lifted to the upper floor by using the self-climbing construction equipment and the winch. After the lifting beam is in place, the lifting beam is fixed to the shaft structure. The connection between the fixed beam and the shaft structure is disconnected, and the elevator machine room and the elevator bridge are lifted into place in the reverse direction with the lifting beam as the fulcrum by using the fixed lifting beam and the winch. After reaching the predetermined position, the fixed beam is fixed to the supporting opening of the shaft structure corresponding to the upper floor, thereby realizing the climbing of the elevator without occupying the tower crane, saving the tower crane's transportation capacity, and improving the safety of the elevator during lifting and operation.

[0023] The formwork for lifting an elevator and the construction method thereof provided in this embodiment are provided by setting a protective shed, which is supported on the lifting beam by a first vertical support member, and the two sides of the protective shed are respectively provided with wall-attached guide wheels in contact with the inner wall of the shaft structure. The isolation shed almost covers the entire shaft space, and the protective shed can isolate various debris falling from the upper part and concrete splashed and falling during the pouring process. It has the characteristics of high strength, good sealing, and easy cleaning, which can effectively protect the elevator and improve the safety of the elevator during lifting and operation. The two sides of the protective shed are respectively provided with wall-attached guide wheels in contact with the inner wall of the shaft structure, which can reduce the friction between the protective shed and the shaft structure and help to ensure the stability of the overall structure.

[0024] The formwork for lifting an elevator and the construction method thereof provided in this embodiment are provided with an isolation shed, the isolation shed being located between the elevator machine room and the lifting beam, the isolation shed being supported on the top of the elevator machine room by a second vertical support member, and the isolation shed covering the top of the elevator machine room. The isolation shed does not need to cover the entire shaft space, but only the area where the elevator is located, and is mainly used to isolate small sundries to ensure that the upper part of the elevator is clean and tidy, and can also be used to protect maintenance personnel who climb to the top of the control room. BRIEF DESCRIPTION OF THE DRAWINGS

[0025] Figure 1 It is a structural schematic diagram of a formwork for lifting an elevator according to an embodiment of the present invention;

[0026] Figure 2 This is a structural schematic diagram of a lifting beam when it is lifted into place according to an embodiment of the present invention;

[0027] Figure 3 This is a schematic diagram of the structure of a fixed beam when it is lifted according to an embodiment of the present invention;

[0028] Figure 4 This is a schematic diagram of the structure when the fixed beam is lifted into place according to an embodiment of the present invention;

[0029] In the figure: 1- shaft structure, 2- elevator room, 21- control room, 22- traction room, 3- elevator bridge, 4- elevator motor, 5- self-climbing construction equipment, 6- first lifting ring, 7- winch, 71- first steel wire rope, 72- second steel wire rope, 8- fixed beam, 9- lifting beam, 81 / 91- telescopic bracket, 10- support opening, 11- protection shed, 12- first vertical support member, 13- wall roller, 14- isolation shed, 15- second vertical support member, 16- lower lifting ring, 17- upper lifting ring. DETAILED DESCRIPTION

[0030] The present invention is further described in detail below in conjunction with the accompanying drawings and specific embodiments. The technical content and features of the present invention will be described in detail below by combining the enumerated embodiments with the accompanying drawings. It should be noted that the accompanying drawings are all in a very simplified form and are not in precise proportions, and are only used to conveniently and clearly assist in explaining the purpose of the embodiments of the present invention. For the convenience of description, the "upper" and "lower" described below are consistent with the upper and lower directions of the accompanying drawings, but this cannot be a limitation of the technical solution of the present invention.

[0031] See also Figures 1 to 4 This embodiment discloses a formwork for lifting an elevator, which is arranged in a shaft structure 1. The elevator is a leap-level elevator. The elevator includes an elevator machine room 2 and an elevator bridge car 3. The elevator machine room 2 is provided with an elevator motor 4, and the elevator motor 4 drives the elevator bridge car 3 to move up and down. The formwork for lifting the elevator includes: a first lifting ring 6, a hoist 7, a fixed beam 8 and a lifting beam 9 arranged at the bottom of the self-climbing construction equipment 5, the fixed beam 8 is fixedly connected to the elevator machine room 2, the elevator bridge 3, the elevator machine room 2, the lifting beam 9 and the self-climbing construction equipment 5 are arranged in sequence from bottom to top, and telescopic brackets are respectively provided at both ends of the fixed beam 8 and the lifting beam 9, and the telescopic brackets can extend into the corresponding support openings 10 of the shaft structure 1 and detach from the corresponding support openings 10 of the shaft structure 1, and the shaft structure 1 is provided with support openings 10 corresponding to each layer of the structure, and the hoist 7 is fixedly arranged in the elevator machine room 2, the hoist 7 includes a hoist 7 motor and two drums driven by the hoist 7 motor, and the two drums are respectively provided with a first steel wire rope 71 and a second steel wire rope 72, the free end of the first steel wire rope 71 is fixedly connected to the lifting beam 9, and the free end of the second steel wire rope 72 is fixedly connected to the lifting beam 9 after passing through the first lifting ring 6.

[0032] The formwork for lifting the elevator provided in the present embodiment connects the fixed beam 8 with the shaft structure 1, that is, extends the telescopic bracket 81 of the fixed beam 8 into the corresponding support hole 10 of the shaft structure 1, disconnects the connection between the lifting beam 9 and the shaft structure 1, that is, separates the telescopic bracket 91 of the lifting beam 9 from the corresponding support hole 10 of the shaft structure 1, and the self-climbing construction equipment climbs upward, and at the same time, the winch 7 simultaneously pays out the first steel wire rope 71 and the second steel wire rope 72, so that the lifting beam 9 is lifted upward relative to the fixed beam 8, and after lifting to the specified position, the lifting beam 9 is connected to the shaft structure 1; disconnects the connection between the fixed beam 8 and the shaft structure 1, and the winch 7 simultaneously reels in the first steel wire rope 71 and the second steel wire rope, so that the fixed beam 8 is lifted upward relative to the lifting beam 9, and after the fixed beam 8 reaches the specified position, the fixed beam 8 is connected to the shaft structure 1, thereby realizing the climbing of the elevator, without occupying the tower crane, saving the tower crane's transportation capacity, and effectively protecting the elevator, greatly improving the safety of the elevator during lifting and operation.

[0033] In this embodiment, the telescopic corbel 91 is a commonly used technical means in the field, and its specific structure is not described in detail. Its structure mainly includes a corbel block, one end of which is installed in a slide groove at the end of a fixed beam or a lifting beam through a pin shaft, and the corbel block can move left and right relative to the fixed beam or the lifting beam.

[0034] Preferably, in the above-mentioned formwork for lifting the elevator, a horizontally arranged protective shed 11 is also included. The protective shed 11 is located between the self-climbing construction equipment 5 and the lifting beam 9. The protective shed 11 is supported on the lifting beam 9 through a first vertical support member 12. Both sides of the protective shed 11 are provided with wall-attached guide wheels in contact with the inner wall of the shaft structure 1. The protective shed 11 includes primary and secondary beams of the steel structure and smooth surface layers such as wooden boards or steel plates laid on the primary and secondary beams of the steel structure. The protective shed 11 is mainly used to isolate various debris dropped from the upper part and concrete splashed and dropped during the pouring process, and has the characteristics of high strength, good sealing, and easy cleaning.

[0035] Preferably, in the above-mentioned formwork for lifting the elevator, a horizontally arranged isolation shed 14 is also included, the isolation shed 14 is located between the elevator room 2 and the lifting beam 9, the isolation shed 14 is supported on the top of the elevator room 2 by the second vertical support member 15, and the isolation shed 14 covers the top of the elevator room 2. The isolation shed 14 includes a primary and secondary steel structure beam and a smooth surface layer such as a wooden board or steel plate laid on the primary and secondary steel structure beams. The isolation shed 14 does not need to cover the entire shaft, but only covers the area where the elevator is located, and is mainly used to isolate small sundries to ensure that the upper part of the elevator is clean and tidy, and can also be used to protect maintenance personnel who climb to the top of the control room 21.

[0036] Preferably, in the above-mentioned formwork for lifting the elevator, the upper part of the lifting beam 9 is provided with a lower lifting ring 16 for connecting to the free end of the first steel wire rope 71, and the upper part of the lifting beam 9 is provided with an upper lifting ring 17 for connecting to the free end of the second steel wire rope 72.

[0037] Preferably, in the above-mentioned formwork for lifting elevators, the fixed beam 8 is transversely fixedly arranged on the elevator room 2, dividing the elevator room 2 into a control room 21 and a traction room 22, the traction room 22 is located below the control room 21, and the number of the hoist 7 is two, which are symmetrically arranged in the traction room 22. Correspondingly, there are two first lifting ears, which are symmetrically arranged at the bottom of the self-climbing construction equipment 5, two upper lifting ears, which are symmetrically arranged at the upper part of the lifting beam 9, and two lower lifting ears, which are symmetrically arranged at the lower part of the lifting beam 9, so as to achieve steady lifting of the lifting beam 9 and the fixed beam 8, and improve the safety of construction.

[0038] Please continue reading Figures 1 to 4This embodiment also discloses a construction method for a formwork for lifting an elevator as described above, comprising the following steps:

[0039] Under normal construction conditions, Figure 1 As shown, the elevator as a whole is fixed to the shaft structure 1 by a fixed beam 8, and the elevator bridge 3 works normally under the power of the elevator motor 4;

[0040] Before lifting, the elevator stops using, and the elevator still bears its own structural weight through the fixed beam 8. At this time, the connection between the lifting beam 9 and the shaft structure 1 is disconnected, and the lifting beam 9 is lifted to the upper floor by using the self-climbing construction equipment 5 and the winch 7, that is, the lifting beam 9 is lifted from the current floor, that is, the Nth floor, to the upper floor, that is, the N+1th floor;

[0041] After the lifting beam 9 is in place, the lifting beam 9 is fixed to the hoistway structure 1. Figure 2 As shown;

[0042] like Figure 3 As shown, disconnect the fixed beam 8 from the shaft structure 1, and use the fixed lifting beam 9 and the hoist 7 to lift the elevator room 2 and the elevator bridge 3 into place in the reverse direction with the lifting beam 9 as the fulcrum;

[0043] like Figure 4 As shown, after reaching the predetermined position, the fixed beam 8 is fixed in the support opening 10 corresponding to the upper floor of the hoistway structure 1, thereby completing the elevator lifting.

[0044] The construction method of the formwork for lifting the elevator provided in this embodiment is that under normal construction conditions, the elevator is fixed to the shaft structure 1 by the fixed beam 8, and the elevator bridge 3 works normally under the power of the elevator motor 4; before lifting, the elevator is stopped, and the elevator still bears its own structural weight through the fixed beam 8. At this time, the connection between the lifting beam 9 and the shaft structure 1 is disconnected, and the lifting beam 9 is lifted to the upper floor by using the self-climbing construction equipment 5 and the hoist 7; after the lifting beam 9 is in place, the lifting beam 9 is fixed to the shaft structure 1; the connection between the fixed beam 8 and the shaft structure 1 is disconnected, and the elevator room 2 and the elevator bridge 3 are lifted into place in the reverse direction with the lifting beam 9 as the fulcrum by using the fixed lifting beam 9 and the hoist 7; after reaching the predetermined position, the fixed beam 8 is fixed to the support opening 10 on the shaft structure 1 corresponding to the upper floor, so that the elevator can be climbed without occupying the tower crane, saving the tower crane's transportation capacity while effectively protecting the elevator, greatly improving the safety of the elevator during lifting and operation.

[0045] Preferably, in the above-mentioned construction method of the formwork for lifting the elevator, the self-climbing construction equipment 5 and the winch 7 are used to lift the lifting beam 9 to the upper floor, and this is achieved by the self-climbing construction equipment 5 climbing upward and the first steel wire rope 71 and the second steel wire rope 72 of the winch 7 being released synchronously.

[0046] Preferably, in the above-mentioned construction method of the formwork for lifting the elevator, the fixed lifting beam 9 and the winch 7 are used to lift the elevator machine room 2 and the elevator bridge car 3 into place in reverse with the lifting beam 9 as a fulcrum, and the first steel wire rope 71 and the second steel wire rope 72 of the winch 7 are synchronously wound up to shorten the distance between the lifting beam 9 and the winch 7 to achieve this.

[0047] Preferably, in the above-mentioned construction method of the formwork for lifting the elevator, the fixed connection between the fixed beam 8 or the lifting beam 9 and the shaft structure 1 is achieved by extending the telescopic corbel into the corresponding support opening 10 on the shaft structure 1; and the connection between the fixed beam 8 or the lifting beam 9 and the shaft structure 1 is disconnected by retracting the telescopic corbel.

[0048] Preferably, in the above-mentioned construction method of the formwork for lifting the elevator, all the above-mentioned steps are repeated until the construction is completed and the elevator room 2 reaches the highest permanent position, and then the winch 7 is removed.

[0049] The above description is only a description of the preferred embodiments of the present invention, and is not intended to limit the scope of the present invention. Any changes or modifications made by a person skilled in the art in the field of the present invention based on the above disclosure shall fall within the scope of protection of the claims.

Claims

1. A construction method for a formwork for lifting an elevator, characterized in that: The formwork for lifting the elevator is arranged in a shaft structure, the elevator includes an elevator room and an elevator bridge, the elevator room is provided with an elevator motor, the elevator motor drives the elevator bridge to move up and down, and is characterized in that the formwork includes: a first lifting ring, a winch, a fixed beam and a lifting beam arranged at the bottom of the self-climbing construction equipment, the fixed beam is fixedly connected to the elevator room, the elevator bridge, the elevator room, the lifting beam and the self-climbing construction equipment are arranged in sequence from bottom to top, and telescopic brackets are respectively provided at both ends of the fixed beam and the lifting beam, and the telescopic brackets can be extended into the corresponding support openings of the shaft structure and detached from the corresponding support openings of the shaft structure. The hoist is fixedly arranged in the elevator room, and the hoist includes a hoist motor and two drums driven by the hoist motor. The two drums are respectively provided with a first steel wire rope and a second steel wire rope, and the free end of the first steel wire rope is fixedly connected to the lifting beam, and the free end of the second steel wire rope is fixedly connected to the lifting beam after passing through the first lifting ring. The formwork for lifting the elevator also includes a horizontally arranged protective shed, and the protective shed is located between the self-climbing construction equipment and the lifting beam. The protective shed is supported on the lifting beam through a first vertical supporting member, and both sides of the protective shed are respectively provided with wall guide wheels in contact with the inner wall of the hoistway structure. The construction method includes the following steps: Under normal construction conditions, the elevator is fixed to the hoistway structure by a fixed beam, and the elevator bridge works normally under the power of the elevator motor; Before lifting, the elevator stops using, and the elevator still bears its own structural weight through the fixed beam. At this time, the connection between the lifting beam and the shaft structure is disconnected, and the lifting beam is lifted to the upper floor by using the self-climbing construction equipment and the hoisting machine. The lifting beam is lifted to the upper floor by using the self-climbing construction equipment and the hoisting machine, which is achieved by synchronously paying out the first steel wire rope and the second steel wire rope of the hoisting machine during the upward climbing of the self-climbing construction equipment; After the lifting beam is in place, fix the lifting beam to the hoistway structure; Disconnect the connection between the fixed beam and the hoistway structure, and use the fixed lifting beam and winch to lift the elevator machine room and the elevator bridge car in reverse with the lifting beam as the fulcrum; After reaching the predetermined position, the fixed beam is fixed to the support hole corresponding to the upper floor on the hoistway structure, thereby completing the elevator lifting.

2. The construction method of the formwork for lifting an elevator according to claim 1, characterized in that: The method of utilizing the fixed lifting beam and hoisting machine to lift the elevator machine room and the elevator bridge car into place in the reverse direction with the lifting beam as the fulcrum is achieved by synchronously winding up the first steel wire rope and the second steel wire rope of the hoisting machine and shortening the distance between the lifting beam and the hoisting machine.

3. The construction method of the formwork for lifting an elevator according to claim 1, characterized in that: The fixed connection between the fixed beam or the lifting beam and the shaft structure is achieved by extending the telescopic bracket into the corresponding support hole on the shaft structure; the connection between the fixed beam or the lifting beam and the shaft structure is disconnected by retracting the telescopic bracket.

4. The construction method of the formwork for lifting an elevator according to claim 1, characterized in that: Repeat all the above steps until the construction is completed and the elevator room reaches the highest permanent position, then remove the winch.

5. The construction method of the formwork for lifting an elevator according to claim 1, characterized in that: It also includes a horizontally arranged isolation shed, which is located between the elevator machine room and the lifting beam, and the isolation shed is supported on the top of the elevator machine room through a second vertical supporting member, and the isolation shed covers the top of the elevator machine room.

6. The construction method of the formwork for lifting an elevator according to claim 1, characterized in that: The fixed beam is transversely fixed on the elevator machine room to separate the elevator machine room into a control machine room and a traction machine room. The traction machine room is located below the control machine room. There are two winches, which are symmetrically arranged in the traction machine room.

7. The construction method of the formwork for lifting an elevator according to claim 1, characterized in that: The upper part of the lifting beam is provided with a lower lifting ring for connecting with the free end of the first steel wire rope, and the upper part of the lifting beam is provided with an upper lifting ring for connecting with the free end of the second steel wire rope.