A special material lifting equipment for construction
The integration of a safety rope and elastic guide wheel with a dust removal system addresses the maintenance shutdowns due to wire rope breakage, ensuring continuous operation and extended rope life in construction lifting equipment.
Patent Information
- Application Number
- CN201910499672.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2019-06-11
- Publication Date
- 2025-01-03
- Estimated Expiration
- 2039-06-11
AI Technical Summary
Traditional lifting equipment in construction requires shutdown for maintenance due to wire rope breakage, affecting construction progress.
Incorporation of a safety rope and movable elastic guide wheel to ensure continuous operation after main load-bearing rope failure, along with a dust removal system using a brush ring and fan blades to prevent corrosion from dust particles.
Ensures safe and continuous operation of lifting buckets by preventing falls and extends rope life by cleaning the ropes, thereby minimizing construction delays and maintaining equipment functionality.
Smart Images

Figure CN110182709B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of building material lifting equipment, in particular to special material lifting equipment for building construction. Background Art
[0002] Material lifting frame (well frame) is referred to as hoist. It is a simple and convenient lifting equipment commonly used in construction to solve vertical transportation. It is generally composed of chassis, derrick body (standard section), sky beam, frame rail, hanging basket, pulley block, rocker arm and electric winch, wire rope, cable wind rope (with wall frame), ground anchor and various safety protection devices. It is an amorphous semi-mechanized product. The material hoist has the characteristics of simple structure, reliable technical performance, high safety factor, easy disassembly and assembly, and ready to use. Especially in the wire rope break test, the self-locking device plays an excellent insurance performance. It is widely used in exhibition layout, warehousing, warehouse, and building without external wall up and down cargo transportation, saving a lot of labor.
[0003] Traditional lifting equipment uses an anti-fall self-locking device to ensure safety by using a hook to stop the lifting bucket urgently when the rope breaks. Then the equipment needs to be repaired, including replacing the wire rope, which requires shutdown for maintenance and affects the progress of construction. Summary of the invention
[0004] The object of the present invention is to provide a special material lifting equipment for construction to solve the problems raised in the above background technology.
[0005] To achieve the above object, the present invention provides the following technical solutions:
[0006] A material lifting equipment specially used in construction, comprising a lifting bucket and a winding mechanism; the winding mechanism comprises a main load-bearing rope and a safety rope respectively fixedly connected to the lifting bucket; a safety winding wheel is wound around the upper end of the safety rope, the safety winding wheel is fixedly sleeved with a winding shaft, an elastic guide wheel is arranged below the safety winding wheel, the elastic guide wheel abuts against the safety rope, the elastic guide wheel is rotatably connected with a movable plate, the movable plate is sleeved with a spring sleeve rod, the spring sleeve rod is fixedly connected with a fixed plate fixedly connected to an anti-slip cover.
[0007] As a further solution of the present invention: a dust removal cylinder is passed through the protective cover, and a group of brush rings are arranged in the dust removal cylinder, and the brush rings are respectively sleeved on the main load-bearing rope and the safety rope; the brush ring is fixedly connected with a lifting frame, and the lifting frame is T-shaped, the lifting frame extends to the top of the dust removal cylinder and is fixedly connected with a sliding clamp, the sliding clamp is clamped with an eccentric groove disk, and the end surfaces of both sides of the eccentric groove disk are provided with eccentric circular grooves, and the upper end of the sliding clamp is nested in the eccentric circular groove; the eccentric groove disk is sleeved and fixed with the winding shaft.
[0008] As a further solution of the present invention: sliding blocks are fixedly connected to both sides of the lifting bucket, and the sliding blocks are nested on the guide rail frame.
[0009] As a further solution of the present invention: a main winding wheel is wound around the upper end of the main load-bearing rope, the main winding wheel is fixedly connected to a winding shaft, the winding shaft is rotatably connected to an anti-slip cover through a bearing and extends to the outside of the anti-slip cover, and the winding shaft is connected to a winding motor through a reducer.
[0010] As a further solution of the present invention: the main load-bearing rope and the safety rope pass through the dust removal cylinder, and limiting guide wheels are provided at the upper and lower parts of the dust removal cylinder.
[0011] As a further solution of the present invention: the brush ring is an annular brush with bristles arranged on the inner wall.
[0012] As a further solution of the present invention: fan blades are provided in the dust collection barrel, the fan blades are fixedly connected to a rotating shaft, a dustproof net is nested and fixed at the end of the dust collection barrel, the rotating shaft passes through the dustproof net and extends to the outside of the dust collection barrel, and the rotating shaft is connected to the output shaft of the winding motor through a transmission belt; a dust collecting hood is provided at a position opposite to the fan blades, the dust collecting hood is nested in the dust collection barrel, and the dust collecting hood is connected to a dust collecting bag.
[0013] Compared with the prior art, the beneficial effects of the present invention are as follows: by providing a safety rope and a movable elastic guide wheel, the present invention can carry the lifting bucket after the main load-bearing rope breaks, thereby ensuring the safe and continuous operation of the lifting bucket and avoiding delays in the construction period; by providing a dust removal cylinder, a brush ring that reciprocates up and down, fan blades and a dust collecting bag, the rope is cleaned to avoid dust particles from accelerating corrosion of the rope and extend the service life of the rope. BRIEF DESCRIPTION OF THE DRAWINGS
[0014] Figure 1 This is an overall perspective view of a material lifting device specifically designed for construction;
[0015] Figure 2 This is a schematic diagram of the structure of the winding mechanism in the material lifting equipment used for construction;
[0016] Figure 3 This is a schematic diagram of the connection structure of the elastic guide wheel in the material lifting equipment specially used for construction;
[0017] Figure 4 for Figure 2 The enlarged view of point A in the middle;
[0018] Figure 5 A three-dimensional image of an eccentric trough plate used in material lifting equipment for construction.
[0019] In the figure: 1-base; 2-lifting bucket; 3-guide rail frame; 4-slider; 5-winding mechanism; 6-main load-bearing rope; 7-main winding wheel; 8-winding shaft; 9-protective cover; 10-speed reducer; 11-winding motor; 12-safety rope; 13-elastic guide wheel; 14-movable plate; 15-fixed plate; 16-spring sleeve rod; 17-safety winding wheel; 18-dust removal cylinder; 19-limiting guide wheel; 20-brush ring; 21-lifting frame; 22-sliding clamping piece; 23-eccentric groove disk; 2301-eccentric circular groove; 24-fan blade; 25-rotating shaft; 26-driving belt; 27-dust hood; 28-dust bag; 29-dustproof net. DETAILED DESCRIPTION
[0020] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0021] Example 1
[0022] See also Figure 1-3 In an embodiment of the present invention, a material lifting equipment specially used for construction includes a base 1, a lifting bucket 2, a guide rail frame 3, a slider 4 and a winding mechanism 5; the lifting bucket 2 is fixedly connected with sliders 4 on both sides, and the sliders 4 are nested on the guide rail frame 3, so that the lifting bucket 2 can move up and down along the guide rail frame 3.
[0023] See also Figure 2 The winding mechanism 5 includes a main load-bearing rope 6 and a safety rope 12. A main winding wheel 7 is wound around the upper end of the main load-bearing rope 6. The main winding wheel 7 is fixedly connected to a winding shaft 8. The winding shaft 8 is rotatably connected to an anti-slip cover 9 through a bearing and extends to the outside of the anti-slip cover 9. The winding shaft 8 is connected to a winding motor 11 through a reducer 10. The winding motor 11 drives the winding shaft 8 to rotate through the reducer 10, thereby driving the main winding wheel 7 to wind the main load-bearing rope 6, thereby driving the lifting bucket 2 to move up and down.
[0024] The safety rope 12 is fixedly connected to the lifting bucket 2, and a safety winding wheel 17 is wound around the upper end of the safety rope 12, and the safety winding wheel 17 is sleeved and fixed with the winding shaft 8, and an elastic guide wheel 13 is arranged below the safety winding wheel 17, and the elastic guide wheel 13 abuts against the safety rope 12, and the elastic guide wheel 13 is rotatably connected with a movable plate 14, and the movable plate 14 is sleeved with a spring sleeve rod 16, and the spring sleeve rod 16 is fixedly connected with a fixed plate 15, and the fixed plate 15 is fixedly connected with the anti-slip cover 9; the elastic guide wheel 13 allows the safety rope 12 to be normally in the main load-bearing rope 6 It does not bear the weight of the lifting bucket 2 during operation. Specifically, when the main load-bearing rope 6 breaks, the safety rope 12 begins to be stressed, the spring guide wheel 13 moves under the force, and the spring on the spring sleeve rod 16 is compressed, so that the safety rope 12 straightens and begins to bear the weight of the lifting bucket 2. After the main load-bearing rope breaks, the lifting bucket 2 can still be lifted and lowered normally and continue to work to prevent the lifting bucket 2 from falling, so that the material transportation before the break is not affected. The main load-bearing rope can be replaced during construction breaks or construction stoppages to avoid affecting the construction period.
[0025] Example 2
[0026] The difference between this embodiment and embodiment 1 is: Figure 2 , Figure 4 and Figure 5 A dust removal cylinder 18 is passed through the protective cover 9, the main load-bearing rope 6 and the safety rope 12 pass through the dust removal cylinder 18, and a limiting guide wheel 19 is provided above and below the dust removal cylinder 18. The limiting guide wheel 19 allows the main load-bearing rope 6 and the safety rope 12 to vertically pass through the dust removal cylinder 18; a group of brush rings 20 are provided in the dust removal cylinder 18, and the brush rings 20 are respectively sleeved on the main load-bearing rope 6 and the safety rope 12. The brush ring 20 is an annular brush with bristles on the inner wall; the brush ring 20 is fixedly connected to a lifting frame 21, and the lifting frame 21 is T-shaped. The lifting frame 21 extends to the top of the dust removal cylinder 18 and is fixedly connected to a sliding card The connecting piece 22, the sliding clamping piece 22 is clamped with an eccentric groove disk 23, and the end surfaces on both sides of the eccentric groove disk 23 are provided with eccentric circular grooves 2301, and the upper end of the sliding clamping piece 22 is nested in the eccentric circular groove 2301; the eccentric groove disk 23 is sleeved and fixed with the winding shaft 8, and the winding shaft 8 drives the eccentric groove disk 23 to rotate, and the sliding clamping piece 22 slides in the eccentric circular groove 2301, and the sliding clamping piece 22 drives the brush ring 20 to move up and down through the lifting frame 21, and the brush ring 20 brushes and cleans the surface of the main load-bearing rope 6 and the safety rope 12 to prevent dust or other construction waste from affecting the rope winding and reducing the service life of the rope.
[0027] The dust collecting cylinder 18 is provided with fan blades 24, and the fan blades 24 are fixedly connected with a rotating shaft 25. A dustproof net 29 is nested and fixed at the end of the dust collecting cylinder 18. The rotating shaft 25 penetrates the dustproof net 29 and extends to the outside of the dust collecting cylinder 18. The rotating shaft 25 is connected to the output shaft of the winding motor 11 through a transmission belt 26; a dust collecting cover 27 is provided at a position opposite to the fan blades 24, and the dust collecting cover 27 is nested in the dust collecting cylinder 18. The dust collecting cover 27 is connected with a dust collecting bag 28, so as to efficiently and centrally collect the fallen dust.
[0028] It should be noted that: the main load-bearing rope, lifting bucket, slide rail frame, winding motor, and winding shaft in this application are existing technologies, and the elastic guide wheel, safety rope, dust removal cylinder, brush ring, lifting frame, sliding clamp, and eccentric groove plate are the innovations of this application; by providing a safety rope and a movable elastic guide wheel, the lifting bucket can be loaded after the main load-bearing rope breaks, thereby ensuring the safe and continuous operation of the lifting bucket and avoiding delays in the construction period; by providing a dust removal cylinder, a brush ring that reciprocates up and down, fan blades, and a dust bag, the rope is cleaned to prevent dust particles from accelerating corrosion of the rope and extending the service life of the rope.
[0029] It will be apparent to those skilled in the art that the invention is not limited to the details of the exemplary embodiments described above and that the invention can be implemented in other specific forms without departing from the spirit or essential features of the invention. Therefore, the embodiments should be considered exemplary and non-limiting in all respects, and the scope of the invention is defined by the appended claims rather than the foregoing description, and it is intended that all variations falling within the meaning and scope of the equivalent elements of the claims be included in the invention. Any reference numeral in a claim should not be considered as limiting the claim to which it relates.
[0030] In addition, it should be understood that although the present specification is described according to implementation modes, not every implementation mode contains only one independent technical solution. This description of the specification is only for the sake of clarity. Those skilled in the art should regard the specification as a whole. The technical solutions in each embodiment may also be appropriately combined to form other implementation modes that can be understood by those skilled in the art.
Claims
1. A material lifting device for construction, comprising a lifting bucket (2) and a winding mechanism (5); characterized in that: The winding mechanism (5) comprises a main load-bearing rope (6) and a safety rope (12) respectively fixedly connected to the lifting bucket (2); a safety winding wheel (17) is wound around the upper end of the safety rope (12); the safety winding wheel (17) is sleeved and fixedly connected to the winding shaft (8); an elastic guide wheel (13) is provided below the safety winding wheel (17); the elastic guide wheel (13) abuts against the safety rope (12); the elastic guide wheel (13) is rotatably connected to a movable plate (14); the movable plate (14) is sleeved with a spring sleeve rod (16); the spring sleeve rod (16) is fixedly connected to a fixed plate (15) fixedly connected to the protective cover (9); The protective cover (9) is penetrated by a dust removal cylinder (18), and a group of brush rings (20) are arranged in the dust removal cylinder (18), and the brush rings (20) are respectively sleeved on the main load-bearing rope (6) and the safety rope (12); the brush rings (20) are fixedly connected to a lifting frame (21), and the lifting frame (21) is T-shaped. The lifting frame (21) extends above the dust removal cylinder (18) and is fixedly connected to a sliding clamping member (22), and the sliding clamping member (22) is clamped with an eccentric groove disk (23), and the end surfaces of both sides of the eccentric groove disk (23) are provided with eccentric circular grooves (2301), and the upper end of the sliding clamping member (22) is nested in the eccentric circular groove (2301); the eccentric groove disk (23) is sleeved and fixed to the winding shaft (8); The dust collecting cylinder (18) is provided with a fan blade (24), the fan blade (24) is fixedly connected to a rotating shaft (25), a dust-proof net (29) is nested and fixed at the end of the dust collecting cylinder (18), the rotating shaft (25) passes through the dust-proof net (29) and extends to the outside of the dust collecting cylinder (18), and the rotating shaft (25) is connected to the output shaft of the winding motor (11) via a transmission belt (26); a dust collecting cover (27) is provided at a position opposite to the fan blade (24), the dust collecting cover (27) is nested in the dust collecting cylinder (18), and the dust collecting cover (27) is connected to a dust collecting bag (28); Slide blocks (4) are fixedly connected to both sides of the lifting bucket (2), and the slide blocks (4) are nested on the guide rail frame (3).
2. A material lifting equipment for construction according to claim 1, characterized in that: A main winding wheel (7) is wound around the upper end of the main bearing rope (6), the main winding wheel (7) is fixedly connected to a winding shaft (8), the winding shaft (8) is rotatably connected to a protective cover (9) via a bearing and extends to the outside of the protective cover (9), and the winding shaft (8) is connected to a winding motor (11) via a reducer (10).
3. A material lifting equipment for construction according to claim 1, characterized in that: The main load-bearing rope (6) and the safety rope (12) pass through the dust removal cylinder (18), and limiting guide wheels (19) are provided at the upper and lower parts of the dust removal cylinder (18).
4. The material lifting equipment for construction according to claim 1, characterized in that: The brush ring (20) is an annular brush with bristles provided on the inner wall.