A prefabricated rail top air duct assembly structure and construction method thereof

By using the prefabricated rail top air duct assembly structure and cast-in-situ concrete consolidation method in the rail top air duct structure, the existing problems of poor construction environment and difficult quality assurance are solved, and more efficient construction and better quality are achieved.

CN110359672BActive Publication Date: 2024-10-29CHINA RAILWAY SIYUAN SURVEY & DESIGN GRP CO LTD
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
CN201910628395.2
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2019-07-12
Publication Date
2024-10-29
Estimated Expiration
2039-07-12

AI Technical Summary

Technical Problem

The construction of the existing rail top air duct structure has problems such as poor environment, complex processes, slow speed, and difficult to guarantee quality. Especially in the later construction of the rail top air duct, scaffolding and formwork need to be re-erected, and steel bars are tied and concrete is poured in a small space. The difficulty is medium and high, which affects the construction quality.

Method used

The prefabricated rail top air duct assembly structure is adopted. Multiple assembly holes and corresponding assembly components are provided on the structural plate. The cast-in-place concrete consolidation is used to fix the assembly components and the prefabricated rail top air duct unit. This simplifies the construction process and reduces the need for scaffolding and Depend on formwork and achieve rapid rise and installation through hoisting equipment.

Benefits of technology

It improves the structural bearing capacity and durability of the prefabricated rail top air duct, simplifies the construction process, reduces construction time and cost, and ensures the stability of construction quality.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN110359672B_ABST
    Figure CN110359672B_ABST
Patent Text Reader

Abstract

The present invention relates to a prefabricated track top air duct assembly structure and a construction method thereof, wherein the assembly structure comprises a structural plate and a prefabricated track top air duct, wherein the prefabricated track top air duct comprises a plurality of prefabricated track top air duct units sequentially spliced ​​along the longitudinal direction of the air duct, wherein each prefabricated track top air duct unit is provided with an assembly component, wherein a plurality of assembly holes are provided on the structural plate, wherein the number of the assembly components is the same as that of the assembly holes and the assembly components are arranged one by one, wherein the assembly components extend into the corresponding assembly holes and are solidified by cast-in-place concrete poured into the assembly holes. The cast-in-place wet node structure formed by the cast-in-place concrete in the assembly holes can effectively improve the structural bearing capacity and durability of the assembled prefabricated track top air duct, and improve the quality of the track top air duct.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of rail transit engineering, and in particular relates to a prefabricated rail top air duct assembly structure and a construction method thereof. Background Art

[0002] At present, the rail top air duct structure is mostly constructed by cast-in-place reinforced concrete, which has a poor construction environment, complex procedures, slow speed, and the construction quality is affected by many factors and difficult to guarantee. At the same time, a lot of abandoned construction waste is generated during the construction process, which wastes resources and pollutes the environment.

[0003] Specifically, there are the following problems in the construction of cast-in-place rail top air duct:

[0004] (1) The top-of-track air duct is located below the middle plate of the subway station and above the track. It is a secondary structure of the station and needs to be constructed later due to factors such as shield construction. During the later construction of the top-of-track air duct, the scaffolding for erecting the middle plate has been removed, and the scaffolding and formwork need to be re-erected, which is time-consuming, labor-intensive and costly.

[0005] (2) The rail-top air duct is suspended below the middle plate using the reserved steel bars in the middle plate. The space of the rail-top air duct is small, and it is very difficult to tie the steel bars and pour the concrete. The construction quality is difficult to guarantee, which easily leaves quality risks.

[0006] (3) The on-site casting of the rail top air duct is time-consuming, labor-intensive and requires a large investment, so construction units have always been reluctant to do so. Summary of the invention

[0007] The embodiments of the present invention relate to a prefabricated rail-top air duct assembly structure and a construction method thereof, which can at least solve some of the defects of the prior art.

[0008] An embodiment of the present invention relates to a prefabricated rail top air duct assembly structure, comprising a structural plate and a prefabricated rail top air duct, the prefabricated rail top air duct comprising a plurality of prefabricated rail top air duct units sequentially spliced ​​along the longitudinal direction of the air duct, each of the prefabricated rail top air duct units being provided with an assembly component, a plurality of assembly holes being opened on the structural plate, the assembly components being the same in number as the assembly holes and being arranged in a one-to-one correspondence, the assembly components extending into the corresponding assembly holes and being solidified by cast-in-place concrete poured into the assembly holes.

[0009] As one of the embodiments, at least a portion of the hole wall of the assembly hole is an inclined wall that gradually inclines from top to bottom toward the inside of the hole.

[0010] As one of the embodiments, the assembly hole is a wedge-shaped assembly hole that is wider at the top and narrower at the bottom.

[0011] As one of the embodiments, the prefabricated rail top air duct unit includes a bottom plate and two side plates, and the assembly components are provided on both side plates.

[0012] As one of the embodiments, the assembly component is prefabricated on the corresponding side panel, including a base section extending into the concrete structure of the side panel and an assembly section connected to the top of the base section and exposed above the side panel, and the assembly section extends into the corresponding assembly hole.

[0013] As one of the embodiments, each of the assembly components is provided with vertical reinforcing steel bars and stirrups and combined and connected into a steel cage structure, wherein the vertical reinforcing steel bars and stirrups are partially fixed in the corresponding side plate concrete and the rest are fixed in the cast-in-place concrete of the corresponding assembly hole.

[0014] As one of the embodiments, a supporting portion is provided on the assembly component, a supporting component is provided on the top of the structural plate, and the supporting portion is supported by the supporting component.

[0015] As one of the embodiments, the top of the assembly component is an inverted U-shaped structure, the supporting part is a connecting rod with two ends respectively connected to two straight parts of the inverted U-shaped structure, the supporting component is a pin installed on the top of the structure, and the connecting rod is supported on the pin.

[0016] The embodiment of the present invention also relates to a construction method of the prefabricated rail top air duct assembly structure as described above, comprising the following steps:

[0017] Carry out prefabrication of each prefabricated rail top air duct unit;

[0018] The assembly construction of each prefabricated track top air duct unit is performed, wherein the assembly construction of each prefabricated track top air duct unit includes: raising the prefabricated track top air duct unit, and after the prefabricated track top air duct unit is raised to a position, pouring concrete into the assembly hole.

[0019] As one of the embodiments, the prefabricated rail top air duct unit is lifted up by a hoisting device on the structural plate or by a lifting device below the structural plate.

[0020] The embodiments of the present invention have at least the following beneficial effects:

[0021] The assembly components and the prefabricated rail top air duct unit are fixed by cast-in-place concrete in the assembly holes. This cast-in-place wet node structure can effectively improve the structural bearing capacity and durability of the assembled prefabricated rail top air duct and improve the quality of the rail top air duct. BRIEF DESCRIPTION OF THE DRAWINGS

[0022] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0023] Figure 1 A schematic structural diagram of a prefabricated rail top air duct unit (with vertical walls) provided in an embodiment of the present invention;

[0024] Figure 2 A schematic structural diagram of a prefabricated rail top air duct unit (without vertical walls) provided in an embodiment of the present invention;

[0025] Figure 3 A schematic diagram of the structure of a hoisting component provided by an embodiment of the present invention;

[0026] Figure 4 A schematic diagram of a steel cage structure formed by connecting a hoisting member, reinforcing steel bars and stirrups provided in an embodiment of the present invention;

[0027] Figure 5 for Figure 4 Sectional view of AA in the middle;

[0028] Figure 6 A schematic front view of a prefabricated rail top air duct assembly structure provided in an embodiment of the present invention;

[0029] Figure 7 A schematic side view of the assembly structure of a rail top air duct unit and a structural plate provided in an embodiment of the present invention. DETAILED DESCRIPTION

[0030] The technical solutions in the embodiments of the present invention are described clearly and completely below. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0031] Embodiment 1

[0032] like Figure 1-Figure 6 An embodiment of the present invention provides a prefabricated rail top air duct unit 1, comprising a bottom plate 11 and two side plates 12 connected to both ends of the bottom plate 11, the side plates 12 extending upward from the corresponding side ends of the bottom plate 11. Generally, after the prefabricated rail top air duct unit 1 is installed on the structural plate 2, the plate surface of the bottom plate 11 is parallel to the horizontal direction, and the plate surface of the side plates 12 is parallel to the vertical direction.

[0033] In one embodiment, the above-mentioned prefabricated rail top air duct unit 1 is an integral prefabricated unit, that is, the bottom plate 11 and the two side plates 12 are prefabricated as one, with a simple structure, easy to manufacture and install, few joints and not easy to leak air, and high structural strength; in another embodiment, the above-mentioned prefabricated rail top air duct unit 1 is a split prefabricated unit, that is, the bottom plate 11 and the side plates 12 are prefabricated separately, and then assembled after being delivered to the site, which is easy to manufacture, has high prefabrication efficiency, and is convenient for transportation and later maintenance. The prefabrication of the prefabricated rail top air duct unit 1 can be completed offline in the factory, which can ensure the standardization of the size of the prefabricated rail top air duct unit 1, which is conducive to industrialization.

[0034] The prefabrication method is a conventional technique in the art and will not be described in detail here.

[0035] Preferably, a hoisting member 131 for supporting is provided on the top of the two side panels 12, that is, the hoisting member 131 is used to cooperate with the hoisting equipment to hoist the prefabricated rail top air duct unit 1.

[0036] In this embodiment, by arranging a lifting component 131 on the prefabricated rail top air duct unit 1, the prefabricated rail top air duct unit 1 can be lifted by lifting equipment, and the prefabricated rail top air duct unit 1 can be installed on the structural plate 2 using ordinary lifting equipment, without the need to set up scaffolding, formwork, etc., the construction is convenient, the construction speed is fast, the efficiency is high, and the construction time and cost are effectively saved.

[0037] More preferably, if Figure 7 There are multiple hoisting components 131 arranged on the top of each side plate 12 and arranged at intervals along the longitudinal direction of the air duct, preferably at equal intervals. The multiple hoisting components 131 can ensure the stability of the hoisting operation of the prefabricated rail top air duct unit 1, and the increase in the number of connection points between the prefabricated rail top air duct unit 1 and the structural plate 2 is conducive to the stability and reliability of the installation structure of the prefabricated rail top air duct unit 1.

[0038] The above-mentioned hanging component 131 is further optimized as follows:

[0039] like Figure 1 , Figure 2 and Figure 6 The hoisting member 131 includes a base section 1311 extending into the concrete structure of the side panel 12 and a hoisting section 1312 connected to the top of the base section 1311 and exposed above the side panel 12, and a hook is provided at the bottom of the base section 1311. The hoisting member 131 partially extends into the concrete structure of the side panel 12 to ensure the reliability of its connection with the side panel 12, avoid the hoisting member 131 from being separated from the side panel 12 during the hoisting process, and can improve the reliability of the connection between the prefabricated rail top air duct unit 1 and the structural plate 2. The hoisting member 131 can be made of steel bars, and a hook is provided at the bottom of the base section 1311 to ensure the reliability of its connection with the concrete of the side panel 12.

[0040] Obviously, the lifting section 1312 is used to cooperate with the lifting equipment, and it is preferable to have a certain length. After the prefabricated rail-top air duct unit 1 is lifted into place, its top is preferably located above the structural plate 2 to facilitate the unhooking of the lifting hook of the lifting equipment.

[0041] The above-mentioned lifting section 1312 is preferably convenient for being hooked by the hook of the lifting equipment, for example, its top is set as a lifting ring structure. In this embodiment, preferably, as Figure 3 and Figure 7 The supporting section 1312 is in an inverted U-shape, that is, it includes two straight sections and a top arc-shaped section connecting the two straight sections, and the arc-shaped section can be hooked by the hook of the lifting equipment to facilitate lifting. Accordingly, the base section 1311 is preferably formed by the two straight sections of the supporting section 1312 extending downward, and the connection reliability between the lifting component 131 and the side plate 12 is further improved. Of course, the lifting component 131 can also be tied by a lifting rope / sling, which will not be described in detail here.

[0042] Furthermore, if Figure 3 , Figure 6 and Figure 7 A supporting portion 1313 is provided on the supporting section 1312 for cooperating with the supporting member 23 on the structural plate 2 after being hoisted into place, and the supporting portion 1313 is respectively connected to two straight portions of the supporting section 1312. After the prefabricated rail top air duct unit 1 is hoisted into place, the supporting portion 1313 cooperates with the supporting member 23 on the structural plate 2, that is, the supporting portion 1313 is supported by the supporting member 23, so that the prefabricated rail top air duct unit 1 can be supported and positioned, and at this time, the hoisting equipment can be unhooked. The supporting portion 1313 can be a connecting rod, and both ends of the connecting rod can be welded to the straight portion of the supporting section 1312. The supporting member 23 can be a bolt pin / bolt plate, etc., which can stably support the prefabricated rail top air duct unit 1.

[0043] More preferably, if Figure 1-Figure 6Each of the hanging components 131 is provided with vertical reinforcing steel bars 132 and stirrups 133 and they are combined and connected to form a steel cage structure 13, and the vertical reinforcing steel bars 132 and stirrups 133 are partially exposed above the side plate 12. For example, for the above-mentioned inverted U-shaped hanging section 1312 and the hanging component 131 structure extending downward to form the foundation section 1311, a vertical reinforcing steel bar 132 is respectively arranged on both sides thereof, and the two vertical reinforcing steel bars 132 and the two straight sections of the hanging component 131 are arranged in a ring form, and then connected by stirrups 133 to form the above-mentioned steel cage structure 13. Of course, the top of the hanging section 1312 is located above the top of the reinforcing steel bar 132 and the top of the stirrup 133, which is convenient for hanging; the bottom of the foundation section 1311 can be roughly flush with the bottom of the reinforcing steel bar 132 and the bottom of the stirrup 133, or it can be located below the bottom of the reinforcing steel bar 132 and the bottom of the stirrup 133. The specific length is determined according to the design calculation needs. Based on the above-mentioned steel cage structure 13, the structural stability and reliability of the concrete connection between the hanging member 131 and the side plate 12 can be effectively improved; the vertical reinforcing steel bars 132 and stirrups 133 are partially exposed above the side plate 12, that is, the steel cage body also partially extends into the hanging hole 21 of the structural plate 2. When the concrete 22 is cast in the hanging hole 21 of the structural plate 2, the cast-in-place concrete 22 can be consolidated with the steel cage body, thereby improving the structural stability and reliability of the connection between the hanging member 131 and the structural plate 2, that is, ensuring the reliability of the connection between the above-mentioned prefabricated rail top air duct unit 1 and the structural plate 2. Generally, a hook can also be set at the bottom of the above-mentioned vertical reinforcing steel bar 132 to improve the reliability of its concrete connection with the side plate 12.

[0044] In addition, if Figure 1 The above-mentioned prefabricated track top air duct unit 1 can adopt the structural shape of the lower hanging shield door area, that is, it has a vertical wall 121. In another embodiment, as Figure 2 , which can also be used in a structure without a vertical wall 121.

[0045] Embodiment 2

[0046] An embodiment of the present invention provides a prefabricated rail top air duct assembly structure, comprising a structural plate 2 and a prefabricated rail top air duct, the prefabricated rail top air duct comprising a plurality of prefabricated rail top air duct units 1 sequentially spliced ​​along the longitudinal direction of the air duct, each of the prefabricated rail top air duct units 1 being provided with an assembly component 131, a plurality of assembly holes 21 being opened on the structural plate 2, the assembly components 131 being the same in number as the assembly holes 21 and being arranged in one-to-one correspondence, the assembly components 131 extending into the corresponding assembly holes 21 and being solidified by cast-in-place concrete poured into the assembly holes 21.

[0047] Among them, the above-mentioned prefabricated rail top air duct unit 1 can adopt the prefabricated rail top air duct unit 1 provided by the above-mentioned embodiment 1. When hoisting the above-mentioned prefabricated rail top air duct unit 1, the assembly hole 21 is constituted as a hoisting hole 21, and the above-mentioned hoisting component 131 is the assembly component 131. The hoisting device located on the structural plate 2 cooperates with the hoisting component 131 on the prefabricated rail top air duct unit 1 through the assembly hole 21.

[0048] Of course, the prefabricated rail top air duct unit 1 may not be lifted by the lifting equipment, for example, the prefabricated rail top air duct unit 1 may be lifted by the lifting equipment under the structural plate 2. Then the above-mentioned assembly member 131 may be other members, such as bolts, ordinary columnar steel bars, etc., to achieve consolidation with the cast-in-place concrete in the assembly hole 21.

[0049] After the prefabricated track top air duct unit 1 rises into place, the assembly component 131 on the prefabricated track top air duct unit 1 extends into the assembly hole 21, and the cast-in-place concrete 22 in the assembly hole 21 can realize the consolidation of the assembly component 131, that is, the connection between the prefabricated track top air duct unit 1 and the structural plate 2 is realized.

[0050] Based on the above structure, the assembly component 131 and the prefabricated rail top air duct unit 1 are fixed by cast-in-place concrete 22 in the assembly hole 21. This cast-in-place wet node structure can effectively improve the structural bearing capacity and durability of the assembled prefabricated rail top air duct and improve the quality of the rail top air duct.

[0051] In addition, based on the structure in which the supporting portion 1313 on the prefabricated rail top air duct cooperates with the supporting member 23 on the structural plate 2, combined with the above-mentioned cast-in-place wet node structure, the structural bearing capacity and durability of the assembled prefabricated rail top air duct are better.

[0052] Further preferably, at least a portion of the hole wall of the assembly hole 21 is an inclined wall that gradually inclines from top to bottom toward the inside of the hole, and in the structure in which the assembly component 131 is inserted into the assembly hole 21, that is, the lower end of the inclined wall is closer to the assembly component 131 than the upper end thereof. Compared with the situation in which the wall of the assembly hole is a vertical surface and shear force is generated at the joint between the cast-in-place concrete 22 and the wall of the assembly hole, the design of the inclined wall can improve the bonding strength between the cast-in-place concrete 22 and the structural plate 2 (i.e., the wall of the assembly hole), and the wall of the assembly hole can effectively support the structure of the cast-in-place concrete 22, and the friction between the two is also significantly increased, further improving the structural bearing capacity and durability of the assembled prefabricated rail top air duct. As a preferred structure, Figure 6 and Figure 7 The above-mentioned assembly hole 21 is a wedge-shaped hole that is wide at the top and narrow at the bottom, which has a better effect.

[0053] For the protruding portion of the above-mentioned assembly component 131 protruding from the upper surface of the structural plate 2, if there is a laminated layer structure on the structural plate 2, the protruding portion is directly cast in the laminated layer structure; if there is no laminated layer structure on the structural plate 2, the protruding portion is buried in the decorative cushion layer of the structural plate 2.

[0054] In addition, the connection between the air duct unit 1 and the lower plate surface of the structural plate 2 is preferably provided with a caulking grouting pipe to further improve the sealing performance of the rail top air duct.

[0055] Embodiment 3

[0056] The embodiment of the present invention provides a method for installing and constructing a rail top air duct, which can be used for the construction of the prefabricated rail top air duct assembly structure provided in the above-mentioned embodiment 2, comprising:

[0057] Prefabricate each prefabricated rail top air duct unit 1;

[0058] The assembly construction of each prefabricated track top air duct unit 1 is performed, wherein the assembly construction of each prefabricated track top air duct unit 1 includes: raising the prefabricated track top air duct unit 1, and after raising it to a position, pouring concrete 22 into the assembly hole 21.

[0059] The lifting of the prefabricated rail top air duct unit 1 can be achieved by a hoisting device on the structural plate 2 or by a lifting device below the structural plate 2 .

[0060] Generally, the size and reinforcement of the bottom plate 11 and the side plate 12 of the prefabricated rail top air duct unit 1, as well as the corresponding parameters of the hanging components 131, the reinforcing steel bars 132, the reinforcing stirrups 133, etc., can be determined according to the structural design calculation, so as to realize the prefabrication of the prefabricated rail top air duct in the factory.

[0061] The above-mentioned lifting equipment can adopt conventional lifting equipment such as hoist crane.

[0062] Further preferably, after the prefabricated rail-top air duct unit 1 is hoisted into place, the corresponding hoisting component 131 is supported and positioned by the supporting component 23 , and then the cast-in-place concrete 22 is poured in the hoisting hole 21 .

[0063] Further preferably, after the prefabricated track top air duct unit 1 is hoisted in place, a grouting pipe 14 is used to perform grouting and caulking treatment at the connection between the prefabricated track top air duct unit 1 and the lower plate surface of the structural plate 2.

[0064] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims

1. A prefabricated track top air duct assembly structure, comprising a structural plate and a prefabricated track top air duct, wherein the prefabricated track top air duct comprises a plurality of prefabricated track top air duct units sequentially spliced ​​along the longitudinal direction of the air duct, characterized in that: Each of the prefabricated rail top air duct units is provided with an assembly component, a plurality of assembly holes are opened on the structural plate, the number of the assembly components is the same as the number of the assembly holes and they are arranged one-to-one, the assembly components extend into the corresponding assembly holes and are solidified by cast-in-place concrete poured into the assembly holes; The assembly hole is a wedge-shaped assembly hole that is wide at the top and narrow at the bottom; The assembly component is a lifting component, which is used to cooperate with the lifting equipment on the structural plate to lift the prefabricated rail top air duct unit; the lifting component includes a base section extending into the concrete structure of the side plate and a hanging section connected to the top of the base section and exposed above the side plate, and the hanging section is used to cooperate with the lifting equipment and extend into the corresponding assembly hole; Each of the assembly components is provided with vertical reinforcing steel bars and stirrups and is combined and connected to form a steel cage structure, wherein the vertical reinforcing steel bars and stirrups are partially fixed in the corresponding side plate concrete and the rest are fixed in the cast-in-place concrete of the corresponding assembly hole; A supporting portion is provided on the assembly component, a supporting component is provided on the top of the structural plate, and the supporting portion is supported by the supporting component.

2. The prefabricated rail top air duct assembly structure according to claim 1, characterized in that: The prefabricated rail top air duct unit comprises a bottom plate and two side plates, and the assembly components are arranged on both side plates.

3. The prefabricated rail top air duct assembly structure according to claim 1, characterized in that: The top of the assembly component is an inverted U-shaped structure, the supporting part is a connecting rod with two ends respectively connected to two straight parts of the inverted U-shaped structure, the supporting component is a bolt installed on the top of the structural plate, and the connecting rod is supported on the bolt.

4. The construction method of the prefabricated rail top air duct assembly structure according to any one of claims 1 to 3, characterized in that: The steps include: Carry out prefabrication of each prefabricated rail top air duct unit; The assembly construction of each prefabricated rail top air duct unit is performed, wherein the assembly construction of each prefabricated rail top air duct unit includes: raising the prefabricated rail top air duct unit, and after the prefabricated rail top air duct unit is raised to a position, pouring concrete into the assembly hole; The lifting of the prefabricated rail top air duct unit is achieved by the hoisting equipment on the structural plate.

Citation Information

Patent Citations

  • Wind channel board

    CN205330100U

  • Portable hoist and mount formula concrete model wall

    CN208105574U

  • Prefabricated rail top air duct assembly structure

    CN210685282U

  • Prefabricated rail top air duct structure unit

    CN211143121U