A pump system teaching and training equipment

By designing the pump system teaching and training equipment, the problem that the existing water treatment training equipment cannot simulate complex environments is solved, automated control and switching of multiple pumps is realized, students' hands-on ability and teaching effect are improved, and students have high diagnostic ability is equipped with high diagnostic ability and safe, inexpensive.

CN110570717BActive Publication Date: 2024-11-29SHANGHAI YUHANG INFORMATION TECHNOLOGY CO LTD
View PDF 6 Cites 0 Cited by

Patent Information

Application Number
CN201911019450.4
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2019-10-24
Publication Date
2024-11-29
Estimated Expiration
2039-10-24

AI Technical Summary

Technical Problem

The existing water treatment training equipment cannot effectively simulate the complex water treatment environment, and it is difficult to improve students' practical ability and inspect the teaching results of trainees.

Method used

A pump system teaching and training equipment was designed, including a water pool, main pipeline, auxiliary pipeline and water treatment device of a simulated water plant. Water circulation and treatment are realized through automatic control system, and electromagnetic air pumps, metering pumps are installed in the equipment. Screw pumps, pneumatic valves, solenoid proportional valves, etc., combined with PLC controllers and touch screens, realize automated control and monitoring.

Benefits of technology

The equipment can simulate a complex water treatment environment, improve students' hands-on ability and teaching effect, has high diagnostic ability, strong safety, low cost, simple maintenance, and can switch and assess various pumps, and is safe and pollution-free. The price is only one-tenth of the same type of system abroad.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN110570717B_ABST
    Figure CN110570717B_ABST
Patent Text Reader

Abstract

The present invention discloses a pump system teaching and training equipment, including a pool for simulating water storage in a water plant, a main pipeline constituting a circulating water circuit is arranged below the pool, an auxiliary pipeline is connected to the main pipeline, a water treatment device simulating water treatment is arranged on one side of the pool, and the main pipeline, the auxiliary pipeline and the water treatment device are all controlled and operated by an automatic control system. The present invention is ingenious in conception, reasonable in structure, and has a wide range of application scenarios. There are 4 types of pumps in the system, which can be switched at will by selecting a program without disassembly, which is simple and convenient. Students can be tested on the cold start-up of a screw pump, the cold start-up of a jet pump, aeration calculation, and dosing dosage calculation, and the test content is wide; and the overall pipeline connection strength is large, the corrosion resistance is strong, the service life is long, the disassembly is convenient, the cost is low, and the safety protection level is high.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to a teaching training device, in particular to a pump system teaching training device which can improve students' hands-on motivation and test teaching results, and belongs to the field of educational technology. Background Art

[0002] With the improvement of social and economic development, a large amount of sewage is generated in life and production, which also means that complex technologies and equipment are applied to sewage treatment in water plants. Therefore, a large number of water treatment skilled personnel need to be trained to participate in the maintenance of equipment and troubleshooting of pump systems and pipeline equipment during the operation of water plants.

[0003] However, the existing water treatment training equipment is only built with a small number of pipes and pumps, which makes it difficult to simulate complex water treatment environments, and cannot effectively improve students' practical ability and test the teaching results of trainers. Summary of the invention

[0004] The main technical problems to be solved by the present invention are

[0005] In order to solve the above technical problems, the present invention provides the following technical solutions:

[0006] A pump system teaching and training equipment comprises a water pool for simulating water storage in a water plant, a main pipeline constituting a circulating water circuit is arranged below the water pool, an auxiliary pipeline is connected to the main pipeline, a water treatment device simulating water treatment is arranged on one side of the water pool, and the main pipeline, the auxiliary pipeline and the water treatment device are all controlled and operated by an automatic control system.

[0007] The following is a further optimization of the above technical solution by the present invention:

[0008] The water treatment device comprises an electromagnetic air pump installed outside the water pool, the output end of the electromagnetic air pump is connected with an air supply pipe, and the other end of the air supply pipe extends below the liquid surface in the water pool.

[0009] Further optimization: a water tank is arranged outside the water pool, a metering pump is fixedly installed on the water tank, a water inlet end of the metering pump is connected with the water tank, and a water outlet end of the metering pump is connected to the water tank through a water pipe.

[0010] Further optimization: the main pipeline includes a main pipe, the water inlet end of the main pipe is installed at the bottom of the pool and connected to the pool, and the water outlet end of the main pipe is forked into two water outlet branches, one of which is installed at the bottom of the pool and connected to the pool, and the other water outlet branch is installed above the pool and connected to the pool.

[0011] Further optimization: The main pipe is provided with a first butterfly valve, a Y-type filter, a screw pump, a second ball valve, a second butterfly valve, a flow meter, a pneumatic valve, and an electromagnetic proportional valve in series in the direction of water flow.

[0012] Further optimization: the pneumatic valve is arranged in series on the main pipe and located on the water outlet side of the flow meter, and the electromagnetic proportional valve is arranged in series on the main pipe and located on the water outlet branch at the bottom of the pool.

[0013] Further optimization: the main pipe is also connected to a shunt pressure relief circuit, which includes a safety valve and a first ball valve. The water inlet and outlet ends of the safety valve are respectively connected to the main pipes at the water inlet and outlet ends of the screw pump through connecting pipes.

[0014] Further optimization: The main pipeline and the shunt pressure relief circuit are respectively provided with a first pressure sensor and a second pressure sensor for monitoring the water pressure in the pipeline.

[0015] Further optimization: the auxiliary pipeline includes an auxiliary pipeline, on which a third ball valve, a first solenoid valve, a jet pump, a second solenoid valve, and a fourth ball valve are arranged in series on one side according to the direction of water flow, the water inlet end of the auxiliary pipeline is connected to the side of the main pipeline close to the water outlet end of the Y-type filter, and the water outlet end of the auxiliary pipeline is connected to the side of the main pipeline close to the water inlet end of the second butterfly valve.

[0016] Further optimization: the automatic control system includes a PLC controller, the signal output end of the PLC controller is electrically connected to the electromagnetic air pump, metering pump, screw pump, pneumatic valve; electromagnetic proportional valve; the control end of the first solenoid valve, injection pump, and second solenoid valve, and the control input end of the PLC controller is connected to a touch screen.

[0017] The present invention adopts the above-mentioned pump system teaching and training equipment to carry out a teaching method, which specifically includes the following steps:

[0018] 1) Turn on the power, all actions are in the off state, turn on the main switch first (must be met), then turn on S1, P1, contactor Q2, and start the PLC controller;

[0019] 2) After the system is started, press the air pump start button, and the contactor Q8 is closed to control the electromagnetic air pump to start. Press the air pump off button to stop the electromagnetic air pump.

[0020] 3) After the system is started, press the metering pump start button, and the contactor Q10 is energized to control the metering pump to start; press the metering pump stop button, and the metering pump stops;

[0021] 4) After the system is started, press the pneumatic valve start button, and the contactor Q3 is closed to control the start of the pneumatic valve; press the pneumatic valve close button, and the pneumatic valve stops;

[0022] 5) After the system is started, press the forward button of the electromagnetic proportional valve, and the contactor Q4 is closed to control the forward start of the electromagnetic proportional valve; press the close button to stop the electromagnetic proportional valve; press the reverse button of the electromagnetic proportional valve, and the contactor Q5 is closed to start the reverse rotation of the electromagnetic proportional valve; press the close button to stop the electromagnetic proportional valve;

[0023] 6) After the system is started, press the water inlet solenoid valve button, and the contactor Q6 is closed to control the start of the first solenoid valve M2; press the close button to stop the first solenoid valve;

[0024] 7) After the system is started, open the first butterfly valve, open the second ball valve, open the second butterfly valve, open the pneumatic valve, close the fourth ball valve, close the first ball valve, press the forward button of the screw pump, the screw pump starts forward, press the close button, and the screw pump stops running;

[0025] 8) After the system is started, open the first butterfly valve, close the first ball valve, open the second ball valve, open the second butterfly valve, close the fourth ball valve, open the pneumatic valve, and open the electromagnetic proportional valve; press the reverse button of the screw pump, the screw pump will start in reverse, press the close button, and the screw pump will stop running;

[0026] 9) After the system is started, open the first butterfly valve, open the third ball valve, open the first solenoid valve, open the fourth ball valve, close the second ball valve, open the second butterfly valve, and open the pneumatic valve; press the jet pump start button, the jet pump starts, and the second solenoid valve opens after a delay; press the jet pump close button to close the jet pump.

[0027] The present invention adopts the above technical solution, which has ingenious conception, reasonable structure, faster overall processing speed, stronger networking capability, high diagnostic capability and security, which can not only save costs and improve production efficiency, but also be safe and reliable, simple and convenient to maintain, powerful configuration programming function, and users can program freely;

[0028] The application scenarios are wide. There are 4 types of pumps in the system. You can switch them at will by simply selecting the program. There is no need to disassemble them. It is simple and convenient. Students can be tested on the cold start-up of screw pumps, cold start-up of jet pumps, aeration calculations, and dosing calculations. The test content is very wide.

[0029] In addition, the overall pipeline connection is strong, corrosion-resistant, has a long service life, is easy to disassemble, has low cost, a high degree of safety protection, is harmless to players and students, has no pollution, and has low noise. Compared with similar foreign systems, the price is only one-tenth of that.

[0030] The present invention is further described below in conjunction with the accompanying drawings and embodiments. BRIEF DESCRIPTION OF THE DRAWINGS

[0031] Figure 1 It is a structural schematic diagram of an embodiment of the present invention;

[0032] Figure 2 is a schematic diagram of a control circuit in an embodiment of the present invention;

[0033] Figure 3 This is a PLC control principle diagram in an embodiment of the present invention;

[0034] Figure 4 This is a PLC control principle diagram in an embodiment of the present invention;

[0035] Figure 5 This is a PLC control principle diagram in an embodiment of the present invention;

[0036] Figure 6 This is a PLC control principle diagram in an embodiment of the present invention.

[0037] In the figure: 1-water tank; 2-liquid level meter; 3-touch screen; MA3-electromagnetic air pump; MA5-metering pump; 6-water tank; LV1-first butterfly valve; 8-Y-type filter; 9-drainage and exhaust port, 10-first pressure sensor; 11-safety valve; LV2-first ball valve; 13-second pressure sensor; MA1-screw pump; OV1-second ball valve; OV2-second butterfly valve; 17-flow meter; OV3-pneumatic valve; OV4-electromagnetic proportional valve; LV3-third ball valve; M2-first solenoid valve; MA4-jet pump; 23-pressure gauge; M3-second solenoid valve; OV5-fourth ball valve; 26-main pipeline; 27-auxiliary pipeline. DETAILED DESCRIPTION

[0038] Example: Figure 1-2 A pump system teaching and training equipment comprises a water pool 1 for simulating water storage in a water plant, a main pipeline constituting a circulating water circuit is arranged below the water pool 1, an auxiliary pipeline is connected to the main pipeline, a water treatment device simulating water treatment is arranged on one side of the water pool 1, and the main pipeline, the auxiliary pipeline and the water treatment device are all controlled and operated by an automatic control system.

[0039] A liquid level meter 2 for displaying the water level in the water pool 1 in real time is vertically fixedly installed on the upper part of the water pool 1 .

[0040] The water treatment device includes an electromagnetic air pump MA3 installed outside the water pool 1, and the output end of the electromagnetic air pump MA3 is connected to an air supply pipe, and one end of the air supply pipe away from the electromagnetic air pump MA3 extends below the liquid surface in the water pool 1.

[0041] With this design, the electromagnetic air pump MA3 can be used to continuously deliver external air into the water pool 1, thereby aerating the water in the water pool 1, increasing the contact area between water and air, and obtaining sufficient dissolved oxygen in the water body.

[0042] A water tank 6 is provided outside the pool 1 , and a metering pump MA5 is fixedly installed on the water tank 6 . The water inlet of the metering pump MA5 is connected to the liquid medicine stored in the water tank 6 , and the water outlet of the metering pump MA5 is connected to the water tank 6 through a water pipe.

[0043] With this design, the water tank 6 can be used to store flocculants and other liquid chemicals used to treat wastewater, and the metering pump MA5 can accurately transport the liquid chemicals in the water tank 6 to the water pool 1, thereby accurately adding water treatment liquid chemicals to ensure a good water treatment effect.

[0044] The main pipeline includes a main pipe 26, the water inlet end of the main pipe 26 is installed at the bottom of the pool 1 and is connected to the pool 1, and the water outlet end of the main pipe 26 is forked into two water outlet branches, one of which is installed at the bottom of the pool 1 and is connected to the pool 1, and the other water outlet branch is installed above the pool 1 and is connected to the pool 1.

[0045] The main pipeline 26 is provided with a first butterfly valve LV1, a Y-type filter 8, a screw pump MA1, a second ball valve OV1, a second butterfly valve OV2, a flow meter 17, a pneumatic valve OV3, and an electromagnetic proportional valve OV4 in series in the direction of water flow.

[0046] The first butterfly valve LV1 is arranged in series on the main pipeline 26 and close to the water inlet end of the main pipeline 26 . The first butterfly valve LV1 is used to directly control the on-off of the main pipeline 26 .

[0047] The Y-type filter 8 is arranged in series on the main pipe 26 and is located behind the water outlet end of the first butterfly valve LV1. The Y-type filter 8 is used to preliminarily remove impurities in the water entering the main pipe 26 from the pool 1 to protect the normal use of various valves and equipment.

[0048] The water inlet and the water outlet of the screw pump MA1 are respectively arranged in series on the main pipeline 26 , and the output power of the screw pump MA1 is used to drive the pressurized flow of water in the main pipeline 26 .

[0049] The second ball valve OV1 is arranged in series on the main pipe 26 and is located at the water outlet side of the screw pump MA1 . The second ball valve OV1 is manually rotated to cut off or open the main pipe 26 .

[0050] The second butterfly valve OV2 is disposed on the main pipe 26 and located at the water outlet side of the second ball valve OV1 . The second butterfly valve OV2 is manually rotated to cut off or open whether the water in the main pipe 26 flows back into the pool 1 .

[0051] The flow meter 17 is arranged in series on the main pipe 26 and is located at the water outlet side of the second butterfly valve OV2. The flow meter 17 is a tubular flow meter for constantly monitoring the flow of water in the main pipe 26.

[0052] The pneumatic valve OV3 is arranged in series on the main pipe 26 and is located on the water outlet side of the flow meter 17. The pneumatic actuator of the pneumatic valve OV3 is connected to an external air compressor. The pneumatic valve OV3 is used to automatically control whether the water in the main pipe 26 flows back to the pool 1.

[0053] The electromagnetic proportional valve OV4 is arranged in series on the main line 26 and is located on the water outlet branch at the bottom of the pool 1. The electromagnetic actuator MA2 of the electromagnetic proportional valve OV4 can open any opening as needed, thereby controlling the size of the flow rate, and then controlling the flow rate of the water outlet branch of the main line 26 located at the bottom of the pool 1, so that the water in the main line 26 enters the bottom of the pool 1.

[0054] A first pressure sensor 10 for constantly monitoring the water pressure in the main pipe 26 is provided on one side of the main pipe 26 close to the outlet of the Y-type filter 8 .

[0055] With this design, the first pressure sensor 10 can be used to constantly monitor the water pressure in the main line 26 , and thus determine whether there is a blockage in the main line 26 , or whether the water pressure in the main line 26 fluctuates abnormally due to the presence of gas.

[0056] A drainage and exhaust port 9 is provided on one side of the main pipe 26 close to the outlet of the Y-type filter 8 , and a control ball valve is provided on the drainage and exhaust port 9 .

[0057] With this design, the ball valve can be controlled to open or close the drain and exhaust port 9, which can be used to discharge gas in the pipeline during operation to prevent the pipeline from being pressurized, and can be used to sample water in the main pipeline 26.

[0058] The water outlet end of the Y-type filter is connected to an auxiliary pipeline and a drainage and exhaust port 9 arranged on the main pipeline for discharging gas in the pipeline during operation to prevent the pipeline from causing pressure build-up.

[0059] With this design, it is possible to determine whether there is a blockage in the pipeline or a pressure abnormality caused by the presence of gas by detecting the pressure of the first pressure sensor 10 in the pipeline, so as to facilitate timely discharge of gas through the drainage exhaust port 9 or timely cleaning of blockages in the pipeline.

[0060] The main line 26 is also connected to a shunt pressure relief circuit, which includes a safety valve 11 and a first ball valve LV2. The water inlet and outlet of the safety valve 11 are respectively connected to the main line 26 at the water inlet and outlet of the screw pump MA1 through connecting pipes.

[0061] The first ball valve LV2 is arranged in parallel with the safety valve 11 , and the water inlet and outlet of the first ball valve LV2 are connected to the main pipe 26 at the water inlet and outlet of the screw pump MA1 through connecting pipes respectively.

[0062] With this design, the safety valve 11 and the first ball valve LV2 can be connected in parallel to the main pipe 26 at the water inlet and outlet ends of the screw pump MA1. When the water pressure in the main pipe 26 entering the water inlet end of the screw pump MA1 is too high, the safety valve 11 or the first ball valve LV2 can be opened, or the safety valve 11 and the first ball valve LV2 can be opened at the same time to reduce the water pressure at the water inlet end of the screw pump MA1 and avoid damage to the equipment.

[0063] A second pressure sensor 13 is provided on the connecting pipe where the water outlet of the first ball valve LV2 is connected to the main line 26 . The second pressure sensor 13 is used to constantly monitor the water pressure when the water outlets of the first ball valve LV2 and the safety valve 11 enter the main line 26 .

[0064] The auxiliary pipeline includes an auxiliary pipeline 27, on which a third ball valve LV3, a first electromagnetic valve M2, a jet pump MA4, a second electromagnetic valve M3, and a fourth ball valve OV5 are arranged in series on one side according to the direction of water flow.

[0065] The water inlet end of the auxiliary pipeline 27 is connected to the main pipeline 26 near the water outlet end of the Y-type filter 8, and the water outlet end of the auxiliary pipeline 27 is connected to the main pipeline 26 near the water inlet end of the second butterfly valve OV2.

[0066] A pressure gauge 23 for constantly monitoring the outlet pressure of the jet pump 22 is provided on the auxiliary pipeline 27 and near the outlet of the jet pump 22 .

[0067] With this design, the pressure gauge 23 can be used to constantly monitor the water pressure at the outlet of the jet pump 22 , and the working state of the jet pump 22 and the blockage state of the pipeline can also be determined by the reading range value of the pressure gauge 23 .

[0068] like Figure 2 As shown, the power connection end of the screw pump MA1 is connected to the output end of the frequency converter, the input end of the frequency converter is connected to the contactor Q2, and the input end of the contactor Q2 is connected to the power supply through a circuit breaker and a fuse.

[0069] The contactor Q2 is used to control the start-up of the screw pump MA1, and the frequency converter can change the frequency to control the rotation speed of the screw pump MA1.

[0070] The inlet end of the electromagnetic actuator MA2 of the electromagnetic proportional valve OV4 is respectively connected to a forward control contactor Q4 and a reverse control contactor Q5 for controlling the forward or reverse rotation of the electromagnetic proportional valve OV4.

[0071] The forward control contactor Q4 and the reverse control contactor Q5 are used to control the forward or reverse rotation of the electromagnetic actuator MA2 of the electromagnetic proportional valve OV4 respectively.

[0072] The inlet end of the first solenoid valve M2 is connected to a contactor Q6 for controlling the first solenoid valve M2 to be turned on or off.

[0073] The inlet end of the second solenoid valve M3 is connected to a contactor Q7 for controlling the second solenoid valve M3 to be turned on or off.

[0074] The inlet end of the electromagnetic air pump MA3 is connected to a contactor Q8 for controlling the electromagnetic air pump MA3 to be turned on or off.

[0075] The inlet end of the jet pump MA4 is connected to a contactor Q9 for controlling the jet pump MA4 to be turned on or off.

[0076] like Figure 1-6 As shown, the automatic control system includes a PLC controller, and the control input end of the PLC controller is connected to a touch screen 3. The touch screen 3 can clearly and intuitively see the flow distribution and pressure changes, and can issue instructions to output control signals through the PLC controller.

[0077] The PLC controller is a Siemens S7-1500 PLC controller.

[0078] The signal output end of the PLC controller is electrically connected to the control ends of the electromagnetic air pump MA3, the metering pump MA5, the screw pump MA1, the pneumatic valve OV3; the electromagnetic proportional valve OV4; the first solenoid valve M2, the jet pump MA4, and the second solenoid valve M3. The PLC controller can send out electrical signals to control the operation of the corresponding execution elements.

[0079] The signal input end of the PLC controller is electrically connected to the first pressure sensor 10 and the second pressure sensor 13 respectively. The pressure values ​​monitored by the first pressure sensor 10 and the second pressure sensor 13 are transmitted to the PLC controller, and then the touch screen 3 can display the pressure changes in real time.

[0080] The PLC controller is also provided with an emergency stop switch S0, a manual start button S1, a reset switch S2, and a manual or automatic program switching switch S3.

[0081] like Figure 1-6 As shown, the present invention adopts the above-mentioned pump system teaching and training equipment to carry out a teaching method, which specifically includes the following steps:

[0082] 1. Turn on the power, all actions are in the closed state, turn on S3 first (must be satisfied), then turn on S1, P1, contactor Q2, and PLC controller to start.

[0083] 2. After the system is started, press the air pump start button, contactor Q8 is energized, and electromagnetic air pump MA3 starts. Press the air pump stop button and electromagnetic air pump MA3 stops.

[0084] 3. After the system is started, press the metering pump start button, contactor Q10 is energized, and metering pump MA5 starts; press the metering pump stop button, and metering pump MA5 stops.

[0085] 4. After the system starts, press the pneumatic valve start button, contactor Q3 is energized, and pneumatic valve OV3 starts. Press the pneumatic valve close button, and pneumatic valve OV3 stops.

[0086] 5. After the system is started, press the forward button of the electromagnetic proportional valve, contactor Q4 is closed, and the electromagnetic proportional valve OV4 starts to rotate forward; press the close button, and the electromagnetic proportional valve OV4 stops;

[0087] Press the reverse button of the electromagnetic proportional valve, contactor Q5 is energized, and the electromagnetic proportional valve OV4 starts to reverse; press the close button, and the electromagnetic proportional valve OV4 stops.

[0088] 6. After the system is started, press the water inlet solenoid valve button, the contactor Q6 is energized, and the first solenoid valve M2 is started; press the close button and the first solenoid valve M2 is stopped.

[0089] 7. After the system is started, open the first butterfly valve LV1, open the second ball valve OV1, open the second butterfly valve OV2, open the pneumatic valve OV3, close the fourth ball valve OV5, close the first ball valve LV2, press the forward button of the screw pump, the screw pump MA1 starts forward rotation, press the close button, and the screw pump MA1 stops running.

[0090] In the step 7, when the screw pump MA1 rotates forward, the frequency of the power supply driving the screw pump MA1 can be regulated by the frequency converter to adjust the rotation speed of the screw pump MA1.

[0091] 8. After the system is started, open the first butterfly valve LV1, close the first ball valve LV2, open the second ball valve OV1, open the second butterfly valve OV2, close the fourth ball valve OV5, open the pneumatic valve OV3, and open the electromagnetic proportional valve OV4. Press the reverse button of the screw pump to reverse the screw pump MA1 and press the close button to stop the screw pump MA1.

[0092] In the step 8, when the screw pump MA1 is reversed, the frequency of the power supply driving the screw pump MA1 can be regulated by the frequency converter to adjust the rotation speed of the screw pump MA1.

[0093] 9. After the system is started, open the first butterfly valve LV1, open the third ball valve LV3, open the first solenoid valve M2, open the fourth ball valve OV5, close the second ball valve OV1, open the second butterfly valve OV2, and open the pneumatic valve OV3; press the jet pump start button, the jet pump MA4 starts, and the second solenoid valve M3 opens after five seconds; press the jet pump close button, and the jet pump MA4 closes.

[0094] In step 9, the second solenoid valve M3 is controlled by a time delay relay and a PLC controller. The PLC controller can set the delay action time of the time delay relay. When the time is up, the time delay relay is actuated and the solenoid valve M3 is opened.

[0095] The pump system teaching and training equipment can be used for cold start-up of screw pumps, troubleshooting of motor reversal, cold start-up of jet pumps, air binding solution of jet pumps, calculation of aeration oxygen demand, metering pump adjustment, valve and pump maintenance, electrical wiring, software configuration, safe power-on and other teaching and assessment. The specific operations include the following steps:

[0096] 1) Cold start of screw pump:

[0097] Turn on the power, all actions are closed, first open the manual or automatic program switching switch S3, and switch to the manual program (must be satisfied), then turn on the manual start button S1, P1, contactor Q2, and the system starts. When the manual or automatic program switching switch S3 is closed, all actions stop; after the system starts, open the first butterfly valve LV1, open the second ball valve OV1, open the second butterfly valve OV2, open the pneumatic valve OV3, close the fourth ball valve OV5, close the first ball valve LV2, press the screw pump forward button, the screw pump MA1 starts forward (frequency conversion speed regulation), and the cold start is completed.

[0098] 2) Troubleshooting of motor reversal:

[0099] After the system is started, open the first butterfly valve LV1, close the first ball valve LV2, open the second ball valve OV1, open the second butterfly valve OV2, close the fourth ball valve OV5, open the pneumatic valve OV3, and open the electromagnetic proportional valve OV4; press the screw pump reverse button, and the screw pump MA1 starts reversely. The contestant needs to judge whether the actual direction of the screw pump is the same as the specified direction based on the pressure changes displayed on the touch screen 3, the flow changes of the flow meter 17, and the direction of the screw pump MA1 fan.

[0100] 3) Cold start of injection pump:

[0101] After the system is started, open the first butterfly valve LV1, open the third ball valve LV3, open the first solenoid valve M2, open the fourth ball valve OV5, close the second ball valve OV1, open the second butterfly valve OV2, and open the pneumatic valve OV3. Press the injection pump start button, the injection pump MA4 starts, and the second solenoid valve M3 opens after five seconds (the opening time is adjustable), and the centrifugal pump is cold-started.

[0102] 4) Solution to centrifugal pump air binding:

[0103] After the system is started, open the first butterfly valve LV1, open the third ball valve LV3, and open the first solenoid valve M2 (this step is called priming the pump).

[0104] 5) Calculation of aeration oxygen demand:

[0105] First, measure the COD content of the water entering pool 1. For example: assuming the inlet COD is 200 mg / l, the outlet COD is required to be 50 mg / l. 0.87 kg of oxygen is needed to remove 1 kg of COD. How much oxygen is needed to treat 1 cubic meter of water?

[0106] (Inlet COD - Outlet COD)*1000L*0.87 / 1000000kg=0.1305kg oxygen.

[0107] 6) Metering pump adjustment:

[0108] The metering pump is provided with three buttons, namely a switch button, an increment button, and a decrement button. Pressing the increment button increases the dosage, and pressing the decrement button decreases the dosage.

[0109] 7) Maintenance of valves and pumps:

[0110] Disassemble the valve and replace the packing seal; disassemble the pump and replace the flange seal, mechanical shaft seal, stator or rotor, O-ring, etc.

[0111] 8) Electrical wiring, software configuration, and safe power-on:

[0112] Replace the sensor line according to the circuit diagram; use programming software to configure the inverter, PLC, and touch screen; power on the equipment step by step according to technical specifications, and do not perform illegal operations that may cause personal injury (such as touching the wires with your hands, pouring water into the electrical control cabinet, etc.).

[0113] For those skilled in the art, according to the teachings of the present invention, without departing from the principles and spirit of the present invention, changes, modifications, substitutions and variations made to the implementation methods are still within the protection scope of the present invention.

Claims

1. A pump system teaching and training device, comprising a water tank (1) for simulating water storage in a water plant, characterized in that: A main pipeline constituting a circulating water circuit is arranged below the water pool (1), an auxiliary pipeline is connected to the main pipeline, a water treatment device for simulating water treatment is arranged on one side of the water pool (1), and the main pipeline, the auxiliary pipeline and the water treatment device are all controlled and operated by an automatic control system; The water treatment device comprises an electromagnetic air pump (MA3) installed outside the water pool (1), the output end of the electromagnetic air pump (MA3) is connected to an air supply pipe, and the other end of the air supply pipe extends below the liquid surface in the water pool (1); A water tank (6) is arranged outside the water pool (1), a metering pump (MA5) is fixedly mounted on the water tank (6), a water inlet end of the metering pump (MA5) is connected to the water tank (6), and a water outlet end of the metering pump (MA5) is connected to the water tank (6) via a water delivery pipe; The main pipeline comprises a main pipe (26), the water inlet end of the main pipe (26) being installed at the bottom of the pool (1) and being in communication with the pool (1), the water outlet end of the main pipe (26) being bifurcated into two water outlet branches, one of which is installed at the bottom of the pool (1) and being in communication with the pool (1), and the other of which is installed above the pool (1) and being in communication with the pool (1); The main pipe (26) is provided with a first butterfly valve (LV1), a Y-type filter (8), a screw pump (MA1), a second ball valve (OV1), a second butterfly valve (OV2), a flow meter (17), a pneumatic valve (OV3), and an electromagnetic proportional valve (OV4) in series in the direction of water flow; The pneumatic valve (OV3) is arranged in series on the main pipe (26) and is located on the water outlet side of the flow meter (17); the pneumatic actuator of the pneumatic valve (OV3) is connected to an external air compressor; the pneumatic valve (OV3) is used to automatically control whether the water in the main pipe (26) flows back into the pool (1); The electromagnetic proportional valve (OV4) is arranged in series on the main pipe (26) and is located on the water outlet branch at the bottom of the pool (1); the electromagnetic actuator (MA2) of the electromagnetic proportional valve (OV4) can open any opening as required, thereby controlling the size of the flow rate, thereby controlling the flow rate of the water outlet branch of the main pipe (26) located at the bottom of the pool (1), and allowing the water in the main pipe (26) to enter the bottom of the pool (1); A drainage and exhaust port (9) is provided on one side of the main pipe (26) close to the outlet of the Y-type filter (8), and a control ball valve is provided on the drainage and exhaust port (9); The main pipe (26) is also connected to a shunt pressure relief circuit, which includes a safety valve (11) and a first ball valve (LV2). The water inlet and water outlet of the safety valve (11) are respectively connected to the main pipe (26) at the water inlet and water outlet of the screw pump (MA1) through connecting pipes. The main pipeline (26) and the bypass pressure relief circuit are respectively provided with a first pressure sensor (10) and a second pressure sensor (13) for monitoring the water pressure in the pipeline; The auxiliary pipeline comprises an auxiliary pipeline (27), on one side of which a third ball valve (LV3), a first solenoid valve (M2), a jet pump (MA4), a second solenoid valve (M3), and a fourth ball valve (OV5) are arranged in series according to the direction of water flow, the water inlet end of the auxiliary pipeline (27) is connected to the side of the main pipeline (26) close to the water outlet end of the Y-type filter (8), and the water outlet end of the auxiliary pipeline (27) is connected to the side of the main pipeline (26) close to the water inlet end of the second butterfly valve (OV2); The automatic control system comprises a PLC controller, wherein a signal output end of the PLC controller is electrically connected to a solenoid air pump (MA3), a metering pump (MA5), a screw pump (MA1), a pneumatic valve (OV3); a solenoid proportional valve (OV4); a first solenoid valve (M2), a jet pump (MA4), and a control end of a second solenoid valve (M3), respectively, and a control input end of the PLC controller is connected to a touch screen (3).

Citation Information

Patent Citations

  • Multifunctional pump principle teaching demonstration device

    CN104599581A

  • Fluid transfer technology practical training device

    CN201359806Y

  • Practical training device for disassembly, assembly and operation of pump

    CN208969996U

  • Automatic control simulation device

    CN209486483U

  • Pump system teaching practical training equipment

    CN210667283U