A plastic casing concrete pile structure capable of eliminating soil squeezing effect and a construction method thereof

By using components such as spiral blades, deformed drill teeth and composite drill bits in plastic casing concrete piles, the problem of soil extrusion effect is solved, the excavation efficiency and construction applicability are improved, the cost is reduced, and it is suitable for the treatment of different formations.

CN110644476BInactive Publication Date: 2024-12-03ZHEJIANG JINLAN CONSTR CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN201910959488.3
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2019-10-10
Publication Date
2024-12-03
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

Existing plastic casing concrete piles are prone to extrusion when constructed in soft soil areas, resulting in soil bulge and lateral extrusion, increasing construction difficulty and causing damage to surrounding road surfaces and buildings. The existing solutions have long construction periods and costs. High and small scope of application.

Method used

The structural design adopts components including plastic casing, concrete pipe, drill rod, spiral blade, composite drill bit and other components. The slag is rotated and discharged by spiral blades, deformed drill teeth and pile tips form ratchet excavation surfaces, linkage fixing rings and The sliding device realizes the shrinkability of the composite drill bit, and combines the linkage force transmission rod and the sliding device to improve the excavation efficiency and reduce the soil extrusion effect.

Benefits of technology

It effectively reduces the resistance when the drill rod enters the formation, avoids the occurrence of soil extrusion effect, improves the excavation efficiency of the pile machine, shortens the construction period, reduces construction costs, and is suitable for the treatment of different formations.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN110644476B_ABST
    Figure CN110644476B_ABST
Patent Text Reader

Abstract

The present invention relates to a plastic sleeve concrete pile structure capable of eliminating soil squeezing effect, comprising a plastic sleeve, a concrete delivery pipe, a drill rod, a spiral blade, a concrete outlet, a linkage fixing ring a, a linkage fixing ring b, a linkage fixing ring c, a linkage force transmission rod, a sliding device, a pressure bearing rod, a deformed drill tooth, a pile tip, a soil drilling collection ring, a soil discharge plastic pipe and a composite drill bit; a drill rod of equal height is arranged inside the plastic sleeve, a spiral blade is arranged on the entire length of the drill rod surface, a concrete delivery pipe is arranged inside the drill rod, the upper part of the concrete delivery pipe is a slurry delivery end, and the lower part of the concrete delivery pipe is provided with a concrete outlet; the bottom end of the drill rod is a retractable and expandable composite drill bit, the bottom of the composite drill bit is a pile tip, and deformed drill teeth are arranged circumferentially around the pile tip, and the deformed drill teeth are arc-shaped structures. The beneficial effects of the present invention are: the excavation efficiency of the pile driver can be greatly enhanced through the ratchet teeth on the surface of the pile tip and the deformed drill teeth and the larger excavation surface design, so that it can be applied to more different strata.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of pile foundation construction, and particularly relates to a plastic sleeve concrete pile structure and a construction method capable of eliminating soil squeezing effect, which is suitable for foundation reinforcement in soft soil areas, especially for soil bodies prone to soil squeezing effect. Background Art

[0002] With the increasing demand for transportation in my country, the investment in infrastructure construction is increasing, and road construction on soft soil foundations is becoming more and more frequent. Among the many soft soil foundation treatment solutions currently available, bored cast-in-place piles are the most commonly used. However, bored cast-in-place piles have the problems of high cost and long construction period, and are not suitable for soft soil foundation treatment in road projects. Plastic casing concrete piles (TC piles for short) are a new type of pile developed on the basis of AUGEO piles abroad. TC piles have the advantages of good reinforcement effect, short construction period, good quality, reasonable cost, no noise, and no mud pollution. However, since the plastic casing is directly pressed into the foundation soil by the equipment, it is inevitable that there will be a soil squeezing effect: when the soil around the pile is saturated soft soil, the volume of the soil will not shrink or the shrinkage is very small when it is squeezed, and the squeezing stress is mainly reduced by soil displacement, resulting in the uplift of the shallow soil and the lateral extrusion of the deep soil, causing damage to the surrounding road surface and buildings. Not only that, the soil squeezing effect will also make the soil more dense, increasing the difficulty of pressing in adjacent plastic casings.

[0003] In the current engineering community, in order to eliminate the soil squeezing effect, a large number of experts and scholars have conducted inventions and research on it. Common measures include changing the shape of the bottom of the pile, setting up anti-squeezing trenches, and using spiral blade drill rods. Among them, although changing the shape of the bottom of the pile can reduce the resistance of the pile when it is pressed down to a certain extent, it still cannot solve the adverse effects of the soil squeezing effect on the soil; setting up anti-squeezing trenches can better prevent the soil squeezing effect from damaging the surrounding roads and buildings, but the construction process is more complicated, and it is easy to produce many uncontrollable factors when setting up anti-squeezing trenches between the construction area and the non-construction area; using spiral blade drill rods is simple to construct and can excavate and transport the soil in the pile, but it is easy to cause hole collapse in poor soil layers, which is quite difficult to handle.

[0004] In summary, although the existing construction methods can eliminate some of the adverse effects of the soil squeezing effect under certain conditions, there are still problems such as slowing down the construction period, high cost, small scope of application, and imperfect functions, which urgently need to be solved by improving technology. Summary of the invention

[0005] The purpose of the present invention is to overcome the deficiencies in the prior art and provide a plastic sleeve concrete pile structure and a construction method which can eliminate the soil squeezing effect.

[0006] The plastic casing concrete pile structure capable of eliminating soil squeezing effect comprises a plastic casing, a concrete delivery pipe, a drill rod, spiral blades, a concrete outlet, a linkage fixing ring a, a linkage fixing ring b, a linkage fixing ring c, a linkage force transmission rod, a sliding device, a pressure bearing rod, a deformable drill tooth, a pile tip, a soil drilling collection ring, a soil discharge plastic pipe and a composite drill bit; a drill rod of equal height is arranged inside the plastic casing, spiral blades are arranged on the entire length of the drill rod surface, a concrete delivery pipe is arranged inside the drill rod, the upper part of the concrete delivery pipe is a slurry delivery end, and the lower part of the concrete delivery pipe is provided with a concrete outlet; the bottom end of the drill rod is a retractable and expandable composite drill bit, the bottom of the composite drill bit is a pile tip, and the pile Deformable drill teeth are arranged circumferentially around the tip, and the deformable drill teeth are of arc-shaped structure. A pressure-bearing rod and a sliding device are arranged on the upper part of each deformable drill tooth, and a rotating shaft is arranged at the connection points between the deformable drill teeth, the pressure-bearing rod and the sliding device of the same group; linkage force transmission rods are arranged circumferentially around the inside of the drill rod, and the linkage force transmission rods are fixed by linkage fixing rings a, linkage fixing rings b and linkage fixing rings c, and the sliding device is fixedly connected to the linkage fixing ring c; a drilling soil collection ring and a soil discharge plastic pipe are arranged on the top of the plastic casing, one end of the soil discharge plastic pipe is connected to the drilling soil collection ring, and the other end of the soil discharge plastic pipe leads to a drilling soil collection place on the ground.

[0007] Preferably, ratchets are provided on the lower surface of the deformed drill teeth and the pile tip surface. When the composite drill bit is in an open state, the deformed drill teeth and the pile tip surface are roughly in the same plane, forming a larger excavation surface with ratchets. The diameter of the composite drill bit in the open state is slightly larger than the plastic casing.

[0008] As a preferred embodiment, the linkage fixing ring a, the linkage fixing ring b, the linkage fixing ring c and the linkage force transmission rod form a linkage device, which can be mechanically pulled and pushed by the pile top to realize the up and down movement of the sliding device.

[0009] As a preferred embodiment, the width of the spiral blade matches the gap between the plastic casing and the drill rod, and the spiral blade can be basically embedded in the gap between the plastic casing and the drill rod to play an auxiliary fixing role.

[0010] As a preferred embodiment, a limit card a and a limit card b are arranged at the top of the drill rod, the limit card a is located above the limit card b (the limit card a is at the upper position, and the limit card b is at the lower position), and a card slot is arranged at the corresponding position on the top of the plastic sleeve. The distance between the two limit cards is equal to the sliding distance of the sliding device at the bottom of the drill rod.

[0011] As a preferred embodiment, a plurality of grouting holes are arranged at regular intervals along the circumferential direction on the surface of the plastic sleeve.

[0012] As a preferred embodiment, the composite drill bit is supported by a drill rod, and the linkage force transmission rod inside the drill rod only adjusts the upward and downward sliding of the linkage fixing ring c and the sliding device.

[0013] As a preferred embodiment, a rotation axis c is set at the connection point between the deformable drill bit and the pile tip, a rotation axis b is set at the connection point between the deformable drill bit and the pressure rod, and a rotation axis a is set at the connection point between the pressure rod and the sliding device.

[0014] As a preferred embodiment, a sliding groove for sliding of the sliding device is arranged at the bottom of the drill rod.

[0015] The construction method of the plastic sleeve concrete pile structure capable of eliminating soil squeezing effect comprises the following steps:

[0016] 1) Construction preparation: First, level the site, lay sand, gravel or crushed stone cushion, prepare plastic sleeves in advance, and connect the plastic sleeves in advance if they need to be extended. Lay out the lines and arrange the pile positions at the construction site;

[0017] 2) Assembly of the plastic sleeve: According to the actual situation, select several deformed drill teeth, assemble them with the pressure-bearing rod, rotating shaft a, rotating shaft b, rotating shaft c and sliding device at the corresponding position, and fix the sliding device on the linkage fixing ring c, and then insert the assembled drill rod from the bottom of the plastic sleeve and fix it in place;

[0018] 3) Expansion and excavation of the composite drill bit: fix the limit card a on the top of the drill rod in the card slot. At this time, the drill rod is in a push-down state, and the sliding device moves downward, so that the composite drill bit is in an open state. The rotation of the drill rod drives the spiral blade, deformed drill teeth and pile tip to rotate, and gradually excavate downward;

[0019] 4) Spiral blades discharge the soil: During the excavation process, the spiral blades rotate continuously and discharge the soil in the pile hole to the top of the plastic casing. The soil is then collected by the drilling collection ring and discharged to the special soil collection area on the ground through the soil discharge plastic pipe for centralized treatment to prevent soil from falling from high altitude, ensuring construction safety and cleanliness of the construction site;

[0020] 5) Retracting the composite drill bit: After excavating to the specified depth, the limit card b is fixed in the card slot by pulling up the linkage device. At this time, the sliding device is slid up through the linkage force transmission rod, and the composite drill bit is adjusted to the retracted state;

[0021] 6) Cut the pile and check the depth of the casing: Unfasten the plastic casing at the top of the drill pipe, use the plastic casing's own gravity to let its bottom fall to the bottom of the pile hole, then cut off the excess plastic casing at the top, check the depth of the plastic casing after tidying it up, and clean the inside to prevent debris from entering;

[0022] 7) Concrete pouring: Check and adjust the position of the plastic casing to avoid collision with the composite drill bit when it rises, slowly lift the drill rod, and use the concrete delivery pipe and concrete outlet to pour concrete at the same time. Use the rotating drill rod and drill bit to stir and vibrate. Part of the concrete injected into the plastic casing will penetrate into the outer wall of the plastic casing through the small holes reserved in the annular direction, filling the possible gaps between the outer wall and the surrounding soil. After the drill rod is completely lifted out of the plastic casing, the concrete pouring inside the plastic casing is completed synchronously;

[0023] 8) Recover the drill rod and composite drill bit: After the concrete pouring is completed, complete the corresponding pile head treatment, and repeat the above construction steps to complete the construction of other plastic casing piles. After all the piles are constructed, recover the drill rod and composite drill bit, remove the deformed drill teeth in time, and rinse and clean the drill rod, spiral blades and pile tip so that they can be used again in the next construction;

[0024] 9) Pile body inspection: After the pile body strength reaches the requirements, the pile will be inspected.

[0025] The beneficial effects of the present invention are:

[0026] 1) Efficient mining and strong adaptability

[0027] The pile tip and the deformed drill teeth surface ratchet and the larger excavation surface design can greatly enhance the excavation efficiency of the pile driver, making it applicable to more different strata.

[0028] 2) Integration of excavation and soil transportation to avoid soil squeezing effect

[0029] The deformed drill teeth and the pile tip form a ratchet excavation surface. The drill bit excavates the soil to make it loose, effectively reducing the resistance of the drill rod entering the formation, and greatly reducing the adverse effects of soil compaction caused by static pressure on pile driving. The spiral blades send out the slag in time, avoiding the squeezing effect and eliminating the adverse effects on nearby roads and other buildings during pile driving.

[0030] 3) Drilling, concrete injection and vibration are carried out simultaneously, which is efficient and economical

[0031] By combining concrete delivery pipes, concrete outlets, drill rods, composite drill bits, etc., after excavating to the designated position, concrete is poured directly from the concrete outlet at the bottom. At the same time, the drill rod and auxiliary devices can be used for vibration, which greatly improves the pile-making efficiency and shortens the construction period.

[0032] 4) Components can be disassembled and recycled, saving costs

[0033] Deformed drill teeth, pile tips, and drill rods can all be disassembled and replaced. If the device fails to work properly or its efficiency is reduced, you only need to find out the cause and replace the corresponding parts to avoid unnecessary waste. At the same time, the usable parts can still be recycled and reused after the project is completed, which greatly saves costs. BRIEF DESCRIPTION OF THE DRAWINGS

[0034] Figure 1 It is a schematic diagram of the composite drill bit of the present invention in an open state;

[0035] Figure 2 It is a schematic diagram of the composite drill bit of the present invention in a retracted state;

[0036] Figure 3 This is a schematic diagram of the internal linkage device of the drill rod of the present invention controlling the opening of the composite drill bit;

[0037] Figure 4 This is a schematic diagram of the internal linkage device of the drill rod of the present invention controlling the retraction of the composite drill bit;

[0038] Figure 5 It is a schematic diagram of the detailed structure of the composite drill bit of the present invention;

[0039] Figures 6 to 9 It is a construction flow chart of the present invention.

[0040] Explanation of the accompanying drawings: plastic casing 1, concrete delivery pipe 2, drill rod 3, spiral blade 4, concrete outlet 5, linkage fixing ring a6, linkage fixing ring b7, linkage fixing ring c8, linkage force transmission rod 9, sliding device 10, pressure bearing rod 11, rotating shaft a12, rotating shaft b13, rotating shaft c14, deformable drill tooth 15, pile tip 16, limit card a17, limit card b18, drill soil collection ring 19, soil discharge plastic pipe 20, composite drill bit 21. DETAILED DESCRIPTION

[0041] The present invention is further described below in conjunction with embodiments. The description of the following embodiments is only used to help understand the present invention. It should be noted that for those of ordinary skill in the art, without departing from the principles of the present invention, several improvements and modifications may be made to the present invention, and these improvements and modifications also fall within the scope of protection of the claims of the present invention.

[0042] like Figure 1As shown, the composite drill bit 21 is in an open state, and the bottom arc-shaped deformed drill teeth 15 and the pile tip 16 together form a cutting surface, and drill to form a hole with a diameter slightly larger than the plastic sleeve 1. The surface of the drill rod 3 is provided with a spiral blade 4. With the rotation of the drill rod 3 and the drilling and cutting of the composite drill bit 21, the soil is transported upward along the gap between the plastic sleeve 1 and the spiral blade 4 until it is finally discharged from the ground. A concrete delivery pipe 2 is provided inside the drill rod 3, and slurry can be injected through the ground and sprayed out at the concrete outlet 5 to reinforce the soil. The top of the drill rod 3 is provided with a limit card a17 and a limit card b18, which can be fixed in the card slot of the inner wall of the plastic sleeve 1, so as to facilitate the height adjustment of the internal linkage device up and down. When the limit card a17 in the upper position is fixed in the card slot, the linkage device pushes the sliding device 10 downward, and the composite drill bit 21 is in an open state; the top of the plastic sleeve 1 is provided with a drill soil collection ring 19 for collecting slag.

[0043] like Figure 2 As shown, the composite drill bit 21 is in a retracted state. By pulling up the linkage device inside the drill rod 3, the limit card b18 in the lower position is fixed in the card slot, the sliding device 10 slides upward, and the deformed drill teeth 15 are retracted. At this time, if the drill rod 3 is lifted upward, the composite drill bit 21 can smoothly pass through the inside of the plastic sleeve 1.

[0044] like Figure 3 As shown, the linkage device is composed of a linkage fixing ring a6, a linkage fixing ring b7, a linkage fixing ring c8, and a linkage force transmission rod 9. The linkage force transmission rod 9 is circumferentially arranged inside the drill rod 3 and fixed by the linkage fixing ring a6, the linkage fixing ring b7, and the linkage fixing ring c8. The linkage fixing ring c8 is then connected and fixed to the sliding device 10. When the linkage device pushes the sliding device 10 downward, the composite drill bit 21 is controlled to open.

[0045] like Figure 4 As shown, by pulling the linkage fixing ring a6, the linkage device drives the sliding device 10 to move upward, and the pressure-bearing rod 11, the rotating shaft a12, the rotating shaft b13, and the rotating shaft c14 are cooperated to retract the deformed drill teeth 15 upward, and the composite drill bit 21 is folded.

[0046] like Figure 5 As shown, the drill rod 3 is connected to the outer wall of the composite drill bit 21, and the drilling and pulling of the composite drill bit 21 are both subjected to corresponding force exerted through the drill rod 3; the linkage force transmission rod 9 inside the drill rod 3 only provides an adjustment function to control the sliding of the linkage fixing ring c8 and the sliding device 10.

[0047] like Figure 6As shown, the composite drill bit 21 is assembled on the ground and inserted into the plastic sleeve 1 from the bottom. A soil drilling collection ring 19 is set on the top of the plastic sleeve 1. The soil drilling collection ring 19 collects the debris rotated out from the inside to prevent the debris from falling directly from a high altitude; one end of the soil discharge plastic pipe 20 is connected to the soil drilling collection ring 19, and the other end is connected to the designated debris collection point on the ground, which plays the role of transporting high-altitude debris.

[0048] like Figure 7 As shown, the composite drill bit 21 is in an open state. While controlling the verticality, the plastic casing 1 is slowly drilled into the soil layer. The composite drill bit 21 at the bottom continuously cuts the soil, and the debris is transported from the inside of the plastic casing 1 to the top drilling soil collection ring 19 through the spiral blades 4, and then transported to the designated location through the soil discharge plastic pipe 20.

[0049] like Figure 8 As shown, when the plastic sleeve 1 pile is drilled to a specified depth, the soil collection ring 19 and the soil discharge plastic pipe 20 on the top of the plastic sleeve 1 are removed, and a sufficiently long concrete delivery pipe 2 is additionally connected to the existing concrete delivery pipe 2 inside the drill rod 3, so as to facilitate concrete injection on the ground; the composite drill bit 21 is retracted through the control of the linkage device, and then the drill rod 3 and the composite drill bit 21 are lifted up, and during the lifting process, concrete is simultaneously injected into the drill rod 3 through the concrete delivery pipe 2, and the concrete flows out from the concrete outlet 5 at the bottom of the drill rod 3 to pour the inside of the plastic sleeve 1; since some small holes are reserved in the circumferential direction of the plastic sleeve 1 at a certain interval, part of the concrete will penetrate into the soil gap behind the wall of the plastic sleeve 1, which plays a role in reinforcement and stabilization.

[0050] like Fig. 9 As shown, when the drill rod 3 and the composite drill bit 21 are completely pulled out of the plastic casing 1, the pouring of concrete is stopped and the casting of the plastic casing pile body is completed.

[0051] The construction method of the plastic sleeve concrete pile structure capable of eliminating soil squeezing effect comprises the following steps:

[0052] 1) Construction preparation: First, level the site, lay a cushion layer of sand, gravel or crushed stone, prepare the plastic sleeve 1 in advance, and connect the plastic sleeve 1 in advance if it needs to be extended, and lay out the lines and arrange the pile positions at the construction site;

[0053] 2) Assembly of the plastic sleeve 1: According to the actual situation, two or four deformable drill teeth 15 are selected, and assembled with the pressure-bearing rod 11, the rotating shaft a12, the rotating shaft b13, the rotating shaft c14 and the sliding device 10 at the corresponding position, and the sliding device 10 is fixed on the linkage fixing ring c8, and then the assembled drill rod 3 is inserted from the bottom of the plastic sleeve 1 and fixed in place;

[0054] 3) Drill bit expansion and excavation: fix the limit card a17 on the top of the drill rod 3 in the card slot, then the drill rod 3 is in a push-down state, the sliding device 10 moves downward, so that the composite drill bit 21 is in an open state, and the rotation of the drill rod 3 drives the spiral blade 4, the deformed drill teeth 15 and the pile tip 16 to rotate, and gradually excavate downward;

[0055] 4) Spiral blades 4 discharge the slag: During the excavation process, the spiral blades 4 rotate continuously and discharge the slag in the pile hole to the top of the plastic sleeve 1. The slag is then collected by the drilling soil collection ring 19 and discharged to a special slag collection place on the ground through the soil discharge plastic pipe 20 for centralized treatment to prevent soil from falling from high altitude, thereby ensuring construction safety and cleanliness of the construction site;

[0056] 5) The composite drill bit 21 is retracted: After excavating to a specified depth, the limit card b18 is fixed in the card slot by pulling up the linkage device, and the sliding device 10 is slid upward by the linkage force transmission rod 9, and the composite drill bit 21 is adjusted to a retracted state;

[0057] 6) Cut the pile and check the depth of the casing: release the plastic casing 1 at the top of the drill pipe, use the weight of the plastic casing 1 to let its bottom fall to the bottom of the pile hole, and then cut off the excess plastic casing 1 at the top. After sorting, check the depth of the plastic casing 1 and clean its interior to prevent debris from entering.

[0058] 7) Concrete pouring: Check and adjust the position of the plastic sleeve 1 to avoid collision with the composite drill bit 21 when it rises, slowly lift the drill rod 3, and use the concrete delivery pipe 2 and the concrete outlet 5 to pour concrete at the same time, and use the rotating drill rod 3 and the drill bit to stir and vibrate, so that part of the concrete injected into the plastic sleeve 1 will penetrate into the outer wall of the plastic sleeve 1 through the small holes reserved in the annular direction, filling the possible gaps between the outer wall and the surrounding soil. After the drill rod 3 is completely lifted out of the plastic sleeve 1, the concrete pouring inside the plastic sleeve 1 is completed synchronously;

[0059] 8) Recovering the drill rod 3 and the composite drill bit 21: After the concrete pouring is completed, the corresponding pile head treatment is completed, and the above-mentioned construction steps are repeated to complete the construction of other plastic casing piles. After all the pile construction is completed, the drill rod 3 and the composite drill bit 21 are recovered, the deformed drill teeth 15 are removed in time, and the drill rod 3, the spiral blade 4, the pile tip 16 and other components are rinsed and cleaned so that they can be used again in the next construction;

[0060] 9) Pile body inspection: After the pile body strength reaches the requirement, the pile will be inspected.

Claims

1. A plastic casing concrete pile structure that can eliminate soil squeezing effect. Features: The invention comprises a plastic sleeve (1), a concrete delivery pipe (2), a drill rod (3), a spiral blade (4), a concrete outlet (5), a linkage fixing ring a (6), a linkage fixing ring b (7), a linkage fixing ring c (8), a linkage force transmission rod (9), a sliding device (10), a pressure bearing rod (11), a deformable drill tooth (15), a pile tip (16), a soil collection ring (19), a soil discharge plastic pipe (20) and a composite drill bit (21); a drill rod (3) of equal height is arranged inside the plastic sleeve (1); a spiral blade (4) is arranged on the surface of the drill rod (3) over the entire length; a concrete delivery pipe (2) is arranged inside the drill rod (3); the upper part of the concrete delivery pipe (2) is a slurry delivery end; the lower part of the concrete delivery pipe (2) is provided with a concrete outlet (5); the bottom end of the drill rod (3) is a composite drill bit (21); the bottom of the composite drill bit (21) is a pile tip (16); the pile tip (16) has four Deformable drill teeth (15) are arranged in an annular direction, and the deformable drill teeth (15) are of an arc-shaped structure. A pressure-bearing rod (11) and a sliding device (10) are arranged on the upper part of each deformable drill tooth (15). A rotation axis is arranged at the connection points between the deformable drill teeth (15), the pressure-bearing rod (11) and the sliding device (10) of the same group. A linkage force transmission rod (9) is arranged in an annular direction around the drill rod (3). The linkage force transmission rod (9) is fixed by a linkage fixing ring a (6), a linkage fixing ring b (7) and a linkage fixing ring c (8). The sliding device (10) is fixedly connected to the linkage fixing ring c (8). A drilling soil collection ring (19) and a soil discharge plastic pipe (20) are arranged on the top of the plastic sleeve (1). One end of the soil discharge plastic pipe (20) is connected to the drilling soil collection ring (19), and the other end of the soil discharge plastic pipe (20) leads to a drilling soil collection point on the ground. Ratchet teeth are arranged on the lower surface of the deformable drill teeth (15) and the surface of the pile tip (16); when the composite drill bit (21) is in an open state, the deformable drill teeth (15) and the surface of the pile tip (16) are in the same plane, and the diameter of the composite drill bit (21) in the open state is larger than the plastic sleeve (1); A limit card a (17) and a limit card b (18) are arranged on the top of the drill rod (3), the limit card a (17) is located above the limit card b (18), and a card slot is arranged at a corresponding position on the top of the plastic sleeve (1); the distance between the two limit cards is equal to the sliding distance of the sliding device (10).

2. The plastic sleeve concrete pile structure capable of eliminating soil squeezing effect according to claim 1, Features: The linkage fixing ring a (6), the linkage fixing ring b (7), the linkage fixing ring c (8) and the linkage force transmission rod (9) form a linkage device.

3. The plastic sleeve concrete pile structure capable of eliminating soil squeezing effect according to claim 1, Features: The width of the spiral blade (4) matches the gap between the plastic casing (1) and the drill rod (3).

4. The plastic sleeve concrete pile structure capable of eliminating soil squeezing effect according to claim 1, Features: A plurality of grouting holes are arranged at regular intervals on the surface of the plastic sleeve (1) along the circumferential direction.

5. The plastic sleeve concrete pile structure capable of eliminating soil squeezing effect according to claim 1, Features: The composite drill bit (21) is supported by the drill rod (3).

6. The plastic sleeve concrete pile structure capable of eliminating soil squeezing effect according to claim 1, Features: A rotation axis c (14) is provided at a connection point between the deformable drill bit (15) and the pile tip (16), a rotation axis b (13) is provided at a connection point between the deformable drill bit (15) and the pressure-bearing rod (11), and a rotation axis a (12) is provided at a connection point between the pressure-bearing rod (11) and the sliding device (10).

7. The plastic sleeve concrete pile structure capable of eliminating soil squeezing effect according to claim 1, Features: A sliding groove is provided at the bottom of the drill rod (3) corresponding to the sliding device (10).

8. A construction method of a plastic sleeve concrete pile structure capable of eliminating soil squeezing effect as claimed in claim 6, Features: The following steps are involved: 1) Construction preparation: First, level the site, lay a cushion layer of sand, gravel or crushed stone, prepare plastic sleeves (1) in advance, and lay out the construction site to arrange the pile positions; 2) Assembly of the plastic sleeve (1): according to the actual situation, select a number of deformed drill teeth (15), assemble them with the pressure-bearing rod (11), the rotating shaft a (12), the rotating shaft b (13), the rotating shaft c (14) and the sliding device (10) at the corresponding positions, and fix the sliding device (10) on the linkage fixing ring c (8), and then insert the assembled drill rod (3) from the bottom of the plastic sleeve (1) and fix it in place; 3) Expansion and excavation of the composite drill bit (21): The limit card a (17) at the top of the drill rod (3) is fixed in the card slot. At this time, the drill rod (3) is in a downward push state, and the sliding device (10) moves downward, so that the composite drill bit (21) is in an open state. The rotation of the drill rod (3) drives the spiral blade (4), the deformable drill teeth (15) and the pile tip (16) to rotate, and the composite drill bit (21) gradually excavates downward; 4) The spiral blade (4) discharges the soil: During the excavation process, the spiral blade (4) continuously rotates and discharges the soil in the pile hole to the top of the plastic sleeve (1). The soil is then collected by the drilling soil collection ring (19) and discharged to a specially set soil collection place on the ground through the soil discharge plastic pipe (20) for centralized treatment; 5) The composite drill bit (21) is retracted: after excavation to a specified depth, the limit card b (18) is fixed in the card slot by pulling up the linkage device, and the sliding device (10) is slid upward by the linkage force transmission rod (9), and the composite drill bit (21) is adjusted to a retracted state; 6) Cutting the pile and checking the depth of the casing: Release the plastic casing (1) at the top of the drill pipe, and use the weight of the plastic casing (1) to let its bottom fall to the bottom of the pile hole, then cut off the excess plastic casing (1) at the top, check the depth of the plastic casing (1) after finishing, and clean the inside of the plastic casing (1); 7) Concrete pouring: Check and adjust the position of the plastic casing (1), lift the drill rod (3), and simultaneously use the concrete delivery pipe (2) and the concrete outlet (5) to pour concrete. Use the rotating drill rod (3) and the drill bit to stir and vibrate. The concrete partially injected into the plastic casing (1) will penetrate into the outer wall of the plastic casing (1) through the small holes reserved in the annular direction, filling the gap between the outer wall and the surrounding soil. After the drill rod (3) is completely lifted out of the plastic casing (1), the concrete pouring inside the plastic casing (1) is completed synchronously. 8) Recovering the drill rod (3) and the composite drill bit (21): After the concrete pouring is completed, the corresponding pile head treatment is completed, and the above construction steps are repeated to complete the construction of other plastic casing piles. After all the piles are constructed, the drill rod (3) and the composite drill bit (21) are recovered, the deformed drill teeth (15) are removed, and the drill rod (3), the spiral blades (4) and the pile tip (16) are washed and cleaned; 9) Pile body inspection: After the pile body strength reaches the requirement, the pile will be inspected.