A pretreatment system and pretreatment method for comprehensive utilization of coal gangue
By combining multiple methods in the coal gangue pretreatment system, the specific surface area and adsorption performance of coal gangue are improved, the problems of low utilization rate of coal gangue and waste of resources are solved, and efficient pretreatment effect is provided, which is a high level of coal gangue. Value-based utilization lays the foundation.
Patent Information
- Application Number
- CN201911227680.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2019-12-04
- Publication Date
- 2024-12-06
- Estimated Expiration
- 2039-12-04
AI Technical Summary
During the application process, coal gangue has low utilization rate, serious resource waste, and poor pretreatment effect, resulting in its failure to fully utilize its potential utilization value.
A comprehensive utilization pretreatment system for coal gangue is designed, including crushing, drying, combustion, grinding, acid etching and alkaline etching pore making. Combined with the raw material crushing, drying and preheating, combustion and pore making processes, it is carried out through combustion aids. Full contact with solvents or chemical additives can improve the specific surface area and adsorption performance of coal gangue.
It improves the specific surface area of coal gangue, increases its adsorption performance, provides high-quality high-value raw materials, avoids resource waste and environmental pollution, and achieves efficient pretreatment of coal gangue.
Smart Images

Figure CN110822453B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a coal gangue pretreatment system and a pretreatment method, in particular to a coal gangue comprehensive utilization pretreatment system and a pretreatment method, belonging to the technical field of coal gangue comprehensive utilization. Background Art
[0002] With the development of my country's coal industry, along with the mining of coal resources, a large amount of solid waste coal gangue will be produced, accounting for about 15% of the annual coal production. Coal gangue is a black solid composed of clay rock, sandstone, carbonate rock and aluminous rock. It is mainly an inorganic mixture, which is mainly composed of aluminum silicate and contains different amounts of inorganic substances such as iron oxide, calcium oxide and magnesium oxide. After burning, it is usually loose in structure and light yellow. The accumulation of a large amount of coal gangue will not only cause water, air and soil pollution, but also occupy a large amount of land area. In addition, coal gangue contains sulfides, which are easy to spontaneously combust and cause natural disasters such as forest fires. Therefore, the comprehensive utilization of coal gangue has become an issue that people pay attention to and study.
[0003] Gangue has various uses, but the utilization rate of gangue in my country has been very low since ancient times. It is mainly used for power generation, brick making, road construction and other engineering applications. Due to the limitation of immature development technology, gangue has not played its potential utilization value. Therefore, with the country's emphasis on the comprehensive utilization of gangue resources and the improvement of scientific research level, it is necessary to produce various products with high added value using gangue as raw materials, which are applied to all walks of life, realize the transformation of waste into treasure, and improve the utilization efficiency of gangue, so as to solve the problem of idle and waste resources in my country.
[0004] The raw material gangue has a tight structure, and minerals such as kaolinite are well crystallized and highly ordered. The silicon-oxygen polyhedrons are closely arranged and have low activity. Even if its specific surface area is increased by grinding, causing partial lattice distortion, most of the minerals inside it still have a stable composition and complete crystal shape at low temperatures, with few internal pores, and still show inertness in chemical reactions. At this time, the adsorption capacity of the gangue is not strong. Gangue contains a certain amount of carbon. After the crushed, pulverized, and sieved gangue is calcined at high temperature, there will be pores on the surface, which increases the specific surface area of the gangue. In order to improve the activity of the gangue and increase its adsorption performance, it must be modified and pretreated. Therefore, it is urgent to design a safe, reliable, convenient, easy to control, and efficient gangue modification pretreatment system and method. Summary of the invention
[0005] The purpose of the present invention is to provide a pretreatment system and a pretreatment method for comprehensive utilization of coal gangue, so as to solve the technical problems of low utilization rate, waste of resources and unsatisfactory pretreatment effect of existing coal gangue in the application process.
[0006] To achieve the above object, the present invention adopts the following technical solutions:
[0007] Solution 1: A pretreatment system for comprehensive utilization of coal gangue, comprising:
[0008] A storage tank, wherein the storage tank has a coal gangue outlet;
[0009] a first gangue crusher, the first gangue crusher having a gangue inlet and a primary crushed particle outlet, the gangue inlet being connected to the gangue outlet;
[0010] A dryer, the dryer having a primary crushed particle inlet and a dry gangue particle outlet, the primary crushed particle inlet being connected to the primary crushed particle outlet;
[0011] A combustion furnace, wherein the combustion furnace has a combustion furnace inlet and a coal gangue particle outlet for combustion heat generation, and the combustion furnace inlet is connected to the dry coal gangue particle outlet through a conveyor;
[0012] A second gangue crusher, wherein the second gangue crusher has a combustion heat generating gangue particle inlet and a secondary crushing particle outlet, and the combustion heat generating gangue particle inlet is connected to the combustion heat generating gangue particle outlet;
[0013] A ball mill, wherein the ball mill has a ball mill inlet and a ball mill outlet, and the ball mill inlet is connected to the secondary crushed particle outlet;
[0014] A first solid-liquid mixing mixer, wherein the first solid-liquid mixing mixer has a first mixing inlet and a first mixing outlet, and the ball mill outlet is connected to the acid storage tank and then connected to the first mixing inlet;
[0015] a first filter screen, the first filter screen being connected to the first stirring outlet and being used for solid-liquid separation;
[0016] A second solid-liquid mixing mixer, wherein the second solid-liquid mixing mixer has a second mixing inlet and a second mixing outlet, and the coal gangue on the first filter screen is mixed with the liquid in the alkali storage tank and then poured into the second solid-liquid mixing mixer;
[0017] a second filter screen, the second filter screen being connected to the second stirring outlet and used for solid-liquid separation;
[0018] Product storage tank; the product storage tank is used to store coal gangue products.
[0019] Preferably: the combustion furnace also has a waste gas outlet, and the pretreatment system for comprehensive utilization of coal gangue also includes a waste gas combustion purification device, and the waste gas outlet is connected to the waste gas combustion purification device.
[0020] Preferably: the combustion furnace further has an air inlet, and the pretreatment system for comprehensive utilization of coal gangue further includes a blower, and the air inlet is connected to the blower.
[0021] Preferably: the second gangue crusher further has a cooling port, and the gangue comprehensive utilization pretreatment system further includes a cooling device, and the cooling port is connected to the cooling device.
[0022] Preferably: a pretreatment system for comprehensive utilization of coal gangue further comprises a first water storage tank, wherein the first water storage tank is used for cleaning the coal gangue on the first filter screen.
[0023] Preferably: a pretreatment system for comprehensive utilization of coal gangue further comprises a first air blast dryer, wherein the first air blast dryer is used for drying the coal gangue on the first filter screen.
[0024] Preferably: a pretreatment system for comprehensive utilization of coal gangue further comprises a second water storage tank, wherein the second water storage tank is used for cleaning the coal gangue on the second filter screen.
[0025] Preferably: a pretreatment system for comprehensive utilization of coal gangue further comprises a second air blast dryer, wherein the second air blast dryer is used for drying the coal gangue on the second filter screen.
[0026] Scheme 2: A pretreatment method for comprehensive utilization of coal gangue, which is realized by relying on a pretreatment system for comprehensive utilization of coal gangue described in Scheme 1, and the specific steps are as follows:
[0027] Step 1: crushing raw materials: crush the raw coal gangue into block solids with a particle size of less than 10 cm, and the crushing frequency is 40-60Hz;
[0028] Step 2: Drying and preheating: Preheat the crushed gangue by ventilation drying at 30-60 degrees Celsius, and then 3 The feed rate of / h is transported to the combustion furnace by a conveyor;
[0029] Step 3, combustion and heat generation: add combustion aid to the combustion furnace, increase the amount of oxygen in the combustion process through the blower, the coal gangue particles burn and generate heat, add an exhaust gas purification device on the top of the combustion furnace to reduce the emission of harmful gases such as sulfur dioxide, the combustion aid: coal gangue = 1:20-30 (mass ratio);
[0030] Step 4, ash grinding: the ash obtained in step 3 enters a crusher, is cooled to 20-40°C by a condenser, and is crushed at a crushing frequency of 50-80Hz to a particle size of 1-3cm after crushing, and then is ground in a ball mill to a particle size of less than 1mm after grinding;
[0031] Step 5, acid etching pore making: the ash after ball milling is mixed with acid solution, fully mixed and stirred in a solid-liquid mixing mixer, then separated by a filter screen, washed with a water storage tank for many times, and then dried with a blast dryer, ash: acid solution = 1: 2-4, stirring time 1-2.5h, filter screen mesh size 100-800 mesh, washing times 1-5 times, blast dryer wind speed 100-500m 3 / h;
[0032] Step 6, alkali etching and pore making: the product obtained in step 5 is mixed with alkali solution, fully mixed and stirred in a solid-liquid mixing mixer, then separated by a filter screen, washed with a water storage tank for many times, and then dried with a blast dryer to obtain a pre-treated coal gangue product. Ash: alkali solution = 1:2-4, stirring time 1-2.5h, filter screen mesh size 100-800 mesh, washing times 1-5 times, blast dryer wind speed 100-500m 3 / h.
[0033] Furthermore: the auxiliary agent is ethanol, methanol or gasoline.
[0034] Further: The wind force of the blower is 200-600m 3 / h.
[0035] Furthermore: the acid solution is 10-35% hydrochloric acid, sulfuric acid, phosphoric acid or nitric acid.
[0036] Further: the alkali solution is 10-35% potassium hydroxide or sodium hydroxide.
[0037] The effects achieved by the present invention are:
[0038] The present invention combines a variety of methods such as raw material crushing, drying and preheating, combustion, and pore making, thereby realizing the three processes of combustion, grinding, and pore making for the gangue in the pretreatment process at the same time. The gangue is fully in contact with the solvent or chemical additive, thereby improving the pore making efficiency. The specific surface area of the pretreatment product is increased, which is more than 20% higher than that of ordinary gangue lime slag, thereby providing high-quality raw materials for the high-value utilization of gangue. BRIEF DESCRIPTION OF THE DRAWINGS
[0039] Figure 1 This is a structural diagram of a pretreatment system for comprehensive utilization of coal gangue according to the present invention;
[0040] In the figure: 1-storage tank 2-first coal gangue crusher 3-dryer 4-conveyor 5-combustion furnace 6-blower 7-waste gas combustion purification device 8-second coal gangue crusher 9-cooling device 10-ball mill 11-acid storage tank 12-first solid-liquid mixing mixer 13-first water storage tank 14-first filter screen 15-first air drier 16-second solid-liquid mixing mixer 17-alkali storage tank 18-second water storage tank 19-second filter screen 20-second air drier 21-product storage tank. DETAILED DESCRIPTION
[0041] Exemplary embodiments of the present invention will be described below in conjunction with the accompanying drawings. For the sake of clarity and conciseness, not all features of the actual implementation are described in the specification. However, it should be understood that many implementation-specific decisions must be made in the process of developing any such actual implementation in order to achieve the developer's specific goals, such as meeting those constraints related to the system and business, and these constraints may vary from implementation to implementation. In addition, it should be understood that although the development work may be very complex and time-consuming, it is only a routine task for those skilled in the art who benefit from the disclosure of the present invention.
[0042] It will be understood by those skilled in the art that, unless otherwise defined, all terms (including technical and scientific terms) used herein have the same meaning as those generally understood by those skilled in the art in the art to which the present invention belongs. It should also be understood that terms such as those defined in common dictionaries should be understood to have meanings consistent with the meanings in the context of the prior art, and will not be interpreted with idealized or overly formal meanings unless defined as herein.
[0043] The meaning of "inside" and "outside" in the present invention refers to the direction pointing to the inside of the device as inside, and the opposite direction as outside, relative to the device itself, rather than being a specific limitation on the device mechanism of the present invention.
[0044] The meaning of "left and right" in the present invention refers to that when the reader is facing the accompanying drawings, the left side of the reader is left and the right side of the reader is right, rather than a specific limitation on the device mechanism of the present invention.
[0045] The term “connection” as used in the present invention may mean a direct connection between components or an indirect connection between components via other components.
[0046] Here, it is also necessary to explain that, in order to avoid obscuring the present invention due to unnecessary details, only the device structures and / or processing steps closely related to the solution according to the present invention are shown in the drawings, and other details that are not closely related to the present invention are omitted. The preferred embodiments of the present invention are described in detail below according to the drawings.
[0047] Example: Figure 1 As shown, a pretreatment system for comprehensive utilization of coal gangue described in this embodiment includes:
[0048] A storage tank 1, wherein the storage tank 1 has a coal gangue outlet;
[0049] A first gangue crusher 2, wherein the first gangue crusher 2 has a gangue inlet and a primary crushed particle outlet, and the gangue inlet is connected to the gangue outlet;
[0050] A dryer 3, wherein the dryer 3 has a primary crushed particle inlet and a dry gangue particle outlet, and the primary crushed particle inlet is connected to the primary crushed particle outlet;
[0051] A combustion furnace 5, wherein the combustion furnace 5 has a combustion furnace inlet, an outlet for coal gangue particles for combustion and heat generation, an air inlet, and an exhaust gas outlet. The combustion furnace inlet is connected to the dry coal gangue particle outlet through a conveyor 4, the air inlet is connected to a blower 6, and the exhaust gas outlet is connected to an exhaust gas combustion purification device 7;
[0052] A second gangue crusher 8, wherein the second gangue crusher 8 has a combustion heat generating gangue particle inlet, a secondary crushing particle outlet, and a cooling port, wherein the combustion heat generating gangue particle inlet is connected to the combustion heat generating gangue particle outlet, and the cooling port is connected to a cooling device 9;
[0053] A ball mill 10, wherein the ball mill has a ball mill inlet and a ball mill outlet, and the ball mill inlet is connected to the secondary crushed particle outlet;
[0054] A first solid-liquid mixing mixer 12, wherein the first solid-liquid mixing mixer 12 has a first mixing inlet and a first mixing outlet, and the ball mill outlet is connected to the acid storage tank 11 and then connected to the first mixing inlet;
[0055] A first filter screen 14, which is connected to the first stirring outlet and is used for solid-liquid separation;
[0056] A first water storage tank 13, wherein the first water storage tank 13 is used to clean the coal gangue on the first filter screen;
[0057] A first blast dryer 15, which is used to dry the coal gangue on the first filter screen;
[0058] A second solid-liquid mixing mixer 16, wherein the second solid-liquid mixing mixer 16 has a second mixing inlet and a second mixing outlet, and the gangue on the first filter screen is mixed with the liquid in the alkali storage tank 17 and poured into the second solid-liquid mixing mixer 16;
[0059] A second filter screen 19, which is connected to the second stirring outlet and is used for solid-liquid separation;
[0060] A second water storage tank 18, wherein the second water storage tank 18 is used to clean the coal gangue on the second filter screen;
[0061] A second blast dryer 20, the second blast dryer 20 is used to dry the coal gangue on the second filter screen;
[0062] Product storage tank 21: The product storage tank 21 is used to store coal gangue products.
[0063] This embodiment designs a pretreatment system for comprehensive utilization of coal gangue, combines coal gangue combustion, waste gas treatment, and coal gangue lime slag pore making technology to pretreat coal gangue. The system is safe and reliable, convenient and easy to control, and has high processing efficiency. The pretreated coal gangue porous material can be further utilized, avoiding waste of resources and pollution of the environment while realizing the high value of low value-added products.
[0064] Embodiment 2: A pretreatment method for comprehensive utilization of coal gangue, which is implemented by relying on a pretreatment system for comprehensive utilization of coal gangue described in Embodiment 1, and the specific steps are as follows:
[0065] Step 1: crushing raw materials: crush the raw coal gangue into block solids with a particle size of 10 cm, and the crushing frequency is 40 Hz;
[0066] Step 2: Drying and preheating: Preheat the crushed gangue by ventilation drying at 30 degrees Celsius, and then 3 The feed rate of / h is transported to the combustion furnace by a conveyor;
[0067] Step 3: Combustion and heat generation: add a combustion aid into the combustion furnace, the auxiliary agent is ethanol, and increase the amount of oxygen in the combustion process through a blower. The wind force of the blower is 200m 3 / h, coal gangue particles burn and generate heat, and an exhaust gas purification device is added to the top of the combustion furnace to reduce the emission of harmful gases such as sulfur dioxide. The combustion aid: coal gangue = 1:20 (mass ratio);
[0068] Step 4, ash grinding: the ash obtained in step 3 enters the crusher, is cooled to 20°C by a condenser, and is crushed at a crushing frequency of 50 Hz to a particle size of 2 cm after crushing, and then is ground in a ball mill to a particle size of less than 1 mm after grinding;
[0069] Step 5, acid etching pore making: the ash after ball milling is mixed with acid solution, the acid solution is hydrochloric acid with a concentration of 10-35%, fully mixed and stirred in a solid-liquid mixing mixer, and then separated by a filter screen, washed with a water storage tank for many times, and then dried with a blast dryer, ash: acid solution = 1:2, stirring time 1h, filter screen mesh size 100 mesh, washing times 1 time, blast dryer wind speed 100m 3 / h;
[0070] Step 6, alkali etching and pore making: the product obtained in step 5 is mixed with alkali solution, the alkali solution is 10-35% potassium hydroxide, and is fully mixed and stirred in a solid-liquid mixing mixer, and then separated by a filter screen, washed with a water storage tank for many times, and then dried with a blast dryer to obtain a pre-treated coal gangue product. Ash: alkali solution = 1:2, stirring time 1h, filter screen mesh size 100 mesh, washing times 1 time, blast dryer wind speed 100 3 / h.
[0071] Embodiment 3: A pretreatment method for comprehensive utilization of coal gangue, which is implemented by relying on a pretreatment system for comprehensive utilization of coal gangue described in Embodiment 1, and the specific steps are as follows:
[0072] Step 1: crushing raw materials: crush the raw coal gangue into block solids with a particle size of 8 cm, and the crushing frequency is 60 Hz;
[0073] Step 2: Drying and preheating: The crushed gangue is preheated by ventilation drying at 60 degrees Celsius, and then the treated gangue is 3 The feed rate of / h is transported to the combustion furnace by a conveyor;
[0074] Step 3: Combustion and heat generation: Add a combustion aid, methanol, to the combustion furnace, and use a blower to increase the amount of oxygen in the combustion process. The wind speed of the blower is 600m / s. 3 / h, coal gangue particles burn and generate heat, and an exhaust gas purification device is added to the top of the combustion furnace to reduce the emission of harmful gases such as sulfur dioxide. The combustion aid: coal gangue = 1:30 (mass ratio);
[0075] Step 4, ash grinding: the ash obtained in step 3 enters the crusher, is cooled to 40°C by a condenser, and is crushed at a crushing frequency of 80 Hz to a particle size of 3 cm after crushing, and then is ground in a ball mill to a particle size of less than 1 mm after grinding;
[0076] Step 5, acid etching pore making: the ash after ball milling is mixed with acid solution, the acid solution is 10-35% sulfuric acid, fully mixed and stirred in a solid-liquid mixing mixer, and then separated by a filter screen, washed with a water storage tank for many times, and then dried with a blast dryer, ash: acid solution = 1:4, stirring time 2.5h, filter screen mesh size 800 mesh, washing times 5 times, blast dryer wind speed 500m 3 / h;
[0077] Step 6, alkali etching and pore making: the product obtained in step 5 is mixed with alkali solution, the alkali solution is 10-35% sodium hydroxide, and is fully mixed and stirred in a solid-liquid mixing mixer, and then separated by a filter screen, washed with a water storage tank for many times, and then dried with a blast dryer to obtain a pre-treated coal gangue product. Ash: alkali solution = 1:4, stirring time 2.5h, filter screen mesh size 800 mesh, washing times 5 times, blast dryer wind speed 500m 3 / h.
[0078] Embodiment 4: A pretreatment method for comprehensive utilization of coal gangue, which is implemented by relying on a pretreatment system for comprehensive utilization of coal gangue described in Embodiment 1, and the specific steps are as follows:
[0079] Step 1: crushing raw materials: crush the raw coal gangue into block solids with a particle size of 5 cm, and the crushing frequency is 50 Hz;
[0080] Step 2: Drying and preheating: Preheat the crushed gangue by ventilation drying at 50 degrees Celsius, and then 3 The feed rate of / h is transported to the combustion furnace by a conveyor;
[0081] Step 3: Combustion and heat generation: Add a combustion aid, such as gasoline, to the combustion furnace, and use a blower to increase the amount of oxygen in the combustion process. The wind speed of the blower is 400m / s. 3 / h, coal gangue particles burn and generate heat, and an exhaust gas purification device is added to the top of the combustion furnace to reduce the emission of harmful gases such as sulfur dioxide. The combustion aid: coal gangue = 1:25 (mass ratio);
[0082] Step 4, ash grinding: the ash obtained in step 3 enters the crusher, is cooled to 30°C by a condenser, and is crushed at a crushing frequency of 60Hz to a particle size of 2cm after crushing, and then is ground in a ball mill to a particle size of less than 1mm after grinding;
[0083] Step 5, acid etching pore making: the ash after ball milling is mixed with acid solution, the acid solution is 20% nitric acid, and is fully mixed and stirred in a solid-liquid mixing mixer, and then separated by a filter screen, washed with a water storage tank for many times, and then dried with a blast dryer, ash: acid solution = 1:3, stirring time 3h, filter screen mesh size 500 mesh, washing times 3 times, blast dryer wind speed 300m 3 / h;
[0084] Step 6, alkali etching and pore making: the product obtained in step 5 is mixed with alkali solution, the alkali solution is 20% potassium hydroxide, and is fully mixed and stirred in a solid-liquid mixing mixer, and then separated by a filter screen, washed with a water storage tank for many times, and then dried with a blast dryer to obtain a pre-treated coal gangue product. Ash: alkali solution = 1:3, stirring time 2h, filter screen mesh size 500 mesh, washing times 3 times, blast dryer wind speed 300m 3 / h.
[0085] Embodiment 2-4 combines a variety of methods such as raw material crushing, drying and preheating, combustion, and pore making, thereby achieving the three processes of combustion, grinding, and pore making for the gangue during the pretreatment process. The gangue is fully in contact with the solvent or chemical additive to improve the pore making efficiency. The specific surface area of the pretreatment product is increased, which is more than 20% higher than that of ordinary gangue lime slag, providing high-quality raw materials for the high-value utilization of gangue.
[0086] The above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit the same. Although the present invention has been described in detail with reference to the above embodiments, those skilled in the art should understand that the technical solutions described in the above embodiments may still be modified, or some or all of the technical features may be replaced by equivalents. However, these modifications or replacements do not deviate the essence of the corresponding technical solutions from the scope of the technical solutions of the embodiments of the present invention.
[0087] In addition, it should be understood that although the present specification is described according to implementation modes, not every implementation mode contains only one independent technical solution. This description of the specification is only for the sake of clarity. Those skilled in the art should regard the specification as a whole. The technical solutions in each embodiment may also be appropriately combined to form other implementation modes that can be understood by those skilled in the art.
Claims
1. A pretreatment method for comprehensive utilization of coal gangue, which is realized by relying on a pretreatment system for comprehensive utilization of coal gangue, a pretreatment system for comprehensive utilization of coal gangue, comprising: A material storage tank (1), wherein the material storage tank (1) has a coal gangue outlet; A first gangue crusher (2), the first gangue crusher (2) having a gangue inlet and a primary crushed particle outlet, the gangue inlet being connected to the gangue outlet; A dryer (3), the dryer (3) having a primary crushed particle inlet and a dried gangue particle outlet, the primary crushed particle inlet being connected to the primary crushed particle outlet; A combustion furnace (5), the combustion furnace (5) comprising a combustion furnace inlet and an outlet for coal gangue particles that burn and generate heat, the combustion furnace inlet being connected to the outlet for dry coal gangue particles via a conveyor (4); a second gangue crusher (8), the second gangue crusher (8) having a combustion heat generating gangue particle inlet and a secondary crushing particle outlet, the combustion heat generating gangue particle inlet being connected to the combustion heat generating gangue particle outlet; A ball mill (10), wherein the ball mill (10) has a ball mill inlet and a ball mill outlet, and the ball mill inlet is connected to the secondary crushed particle outlet; A first solid-liquid mixing mixer (12), wherein the first solid-liquid mixing mixer (12) has a first mixing inlet and a first mixing outlet, and the ball mill outlet is connected to the acid storage tank (11) and then connected to the first mixing inlet; A first filter screen (14), the first filter screen (14) being connected to the first stirring outlet and used for solid-liquid separation; a second solid-liquid mixing mixer (16), the second solid-liquid mixing mixer (16) having a second mixing inlet and a second mixing outlet, the coal gangue on the first filter screen is mixed with the liquid in the alkali storage tank (17) and then poured into the second solid-liquid mixing mixer (16); a second filter screen (19), the second filter screen (19) being connected to the second stirring outlet and used for solid-liquid separation; A product storage tank (21); the product storage tank (21) is used to store coal gangue products; The combustion furnace (5) also has a waste gas outlet. The coal gangue comprehensive utilization pretreatment system also includes a waste gas combustion purification device (7), and the waste gas outlet is connected to the waste gas combustion purification device (7); The combustion furnace (5) also has an air inlet. The coal gangue comprehensive utilization pretreatment system also includes a blower (6), and the air inlet is connected to the blower (6); The second gangue crusher (8) further comprises a cooling port, and the gangue comprehensive utilization pretreatment system further comprises a cooling device (9), and the cooling port is connected to the cooling device (9); A coal gangue comprehensive utilization pretreatment system further comprises a first water storage tank (13), wherein the first water storage tank (13) is used to clean the coal gangue on the first filter screen; A coal gangue comprehensive utilization pretreatment system further comprises a first air blast dryer (15), wherein the first air blast dryer (15) is used to dry the coal gangue on the first filter screen; A coal gangue comprehensive utilization pretreatment system further comprises a second water storage tank (18), wherein the second water storage tank (18) is used to clean the coal gangue on the second filter screen; A coal gangue comprehensive utilization pretreatment system further comprises a second air blast dryer (20), wherein the second air blast dryer (20) is used to dry the coal gangue on the second filter screen; The method is characterized in that the pretreatment method for comprehensive utilization of coal gangue comprises the following specific steps: Step 1: crushing raw materials: crush the raw coal gangue into block solids with a particle size of less than 10 cm, and the crushing frequency is 40-60Hz; Step 2: Drying and preheating: Preheat the crushed gangue by ventilation drying at 30-60 degrees Celsius, and then 3 The feed rate of / h is transported to the combustion furnace by a conveyor; Step 3, combustion and heat generation: add combustion aid to the combustion furnace, increase the amount of oxygen in the combustion process through the blower, the coal gangue particles burn and generate heat, add an exhaust gas purification device on the top of the combustion furnace to reduce the emission of harmful sulfur dioxide gases, and the mass ratio of the combustion aid to the coal gangue is 1:20-30; Step 4, ash grinding: the ash obtained in step 3 enters a crusher, is cooled to 20-40°C by a condenser, and is crushed at a crushing frequency of 50-80Hz to a particle size of 1-3cm after crushing, and then is ground in a ball mill to a particle size of less than 1mm after grinding; Step 5, acid etching pore making: the ash after ball milling is mixed with acid solution, fully mixed and stirred in a solid-liquid mixing mixer, then separated by a filter screen, washed with a water storage tank for many times, and then dried with a blast dryer, ash: acid solution = 1:2-4, stirring time 1-2.5h, filter screen mesh size 100-800 mesh, washing times 1-5 times, blast dryer wind speed 100-500m 3 / h; Step 6, alkali etching and pore making: the product obtained in step 5 is mixed with alkali solution, fully mixed and stirred in a solid-liquid mixing mixer, then separated by a filter screen, washed with a water storage tank for many times, and then dried with a blast dryer to obtain a pretreated product of coal gangue, ash: alkali solution = 1:2-4, stirring time 1-2.5h, filter screen mesh size 100-800 mesh, washing times 1-5 times, blast dryer wind speed 100-500m 3 / h.