A multi-channel composite continuous pipe cable

By designing multi-channel composite continuous pipe cables, the problems of complicated processes, cumbersome tests and difficult water injection in continuous oil pipe operations are solved, and the effects of simplified operations, flexible water injection and cost reduction are achieved.

CN111075368BActive Publication Date: 2024-11-12XINDA KECHUANG TANGSHAN PETROLEUM EQUIP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN201911418591.3
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2019-12-31
Publication Date
2024-11-12
Estimated Expiration
2039-12-31

AI Technical Summary

Technical Problem

The existing continuous oil pipes have complex operational processes, cumbersome testing processes, and difficult pressure finding in oil and gas fields, and it is impossible to select different injected water additives according to the matching properties of different reservoirs.

Method used

A multi-channel composite continuous pipe cable is designed, including three inner pipes, insulators, leather case, protective layer, compressive layer, armored pipe layer, fiber layer and corrosion protection layer. Through material selection and structural design, multi-channel is realized The optimization of the layout scheme simplifies the operation process and testing process, and allows the selection of appropriate injected water additives based on the reservoir characteristics.

Benefits of technology

It has achieved simplification of operation and testing processes, easy pressure measurement, and can select injected water additives according to different reservoirs, which improves the toughness and softness of the pipe cable, extends the service life, and reduces material and production costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN111075368B_ABST
    Figure CN111075368B_ABST
Patent Text Reader

Abstract

The invention discloses a multi-channel composite continuous pipe cable, comprising three inner pipes and an insulator, wherein the insulator is filled with a plurality of inner pipes, the outer side of the insulator is sleeved with a leather cover, the outer side of the leather cover is welded with a protective layer, the outer side of the protective layer is welded with a pressure-resistant layer, the outer side of the pressure-resistant layer is bonded with a plurality of armor tube layers, and the outer side of the armor tube layer is bonded with a fiber layer. The invention has a scientific and reasonable structure, is safe and convenient to use, has a simple operation procedure, a simple testing process, is easy to measure pressure, and can select different injection water additives according to the matching of different reservoirs. It also has heat preservation, can not only meet the pressure transmission, but also can perform well logging through two cables. The pressure-resistant layer and the armor tube layer improve the capacity of the pipe cable itself, thereby facilitating the improvement of its service life, and the armor tube layer and the fiber layer can further improve the toughness and softness of the pipe gallery, which is convenient for terrain use, and the anti-corrosion layer can facilitate the improvement of its service life.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of pipe and cable, in particular to a multi-channel composite continuous pipe and cable. Background Art

[0002] Coiled tubing is widely used in well repair, drilling, completion, logging and other operations in oil and gas fields. It runs through the entire process of oil and gas extraction and is known as a "universal operating machine". However, coiled tubing has only a single channel, so it often has great limitations in oil and gas field operations, especially in stratified water injection. Due to the complex geological conditions in my country, the reservoirs of most domestic oil fields are highly heterogeneous, and the porosity and permeability between reservoirs vary greatly. Directly using a channel-based general water injection method will cause the high permeability layer to absorb more water, the medium and low permeability layers to absorb less water, or even no water, resulting in a large amount of water injection in the high permeability layer, poor oil displacement effect, and water injection surges, leading to premature flooding of the oil well. Since the medium and low permeability layers cannot be effectively injected with water, the recovery rate is low and they become residual oil-rich areas. Therefore, the stratified water injection method is generally used for water injection of multi-layer oil reservoirs at home and abroad. The currently used stratified water injection method usually uses oil pipes as the main channel for water injection, and eccentric water injectors are hung at the bottom of the oil pipes. The eccentric water injectors are connected to the ground control system through cables. The water injection and formation pressure testing are completed through cable testing. The oil pipes need to be connected one by one during the lowering process, and the cables are tied to the outside of the oil pipes. The operation procedures are complicated, the testing process is cumbersome, and it is difficult to obtain pressure. In addition, different injection water additives cannot be selected according to the matching of different reservoirs. Summary of the invention

[0003] The present invention provides a multi-channel composite continuous pipe cable, which can effectively solve the problems in the above background technology, such as complicated operation procedures, cumbersome testing process, difficult pressure determination, and inability to select different injection water additives according to the compatibility of different reservoirs.

[0004] To achieve the above-mentioned purpose, the present invention provides the following technical solutions: a multi-channel composite continuous tube cable, comprising three inner tubes and an insulator, wherein the interior of the insulator is filled with a plurality of inner tubes, the outer side of the insulator is sleeved with a leather sheath, the outer side of the leather sheath is welded with a protective layer, the outer side of the protective layer is welded with a pressure-resistant layer, the outer side of the pressure-resistant layer is bonded with a plurality of armor tube layers, the outer side of the armor tube layer is bonded with a fiber layer, the gap between the fiber layer and the pressure-resistant layer is filled with filling glue, and the outer side of the fiber layer is bonded with an anti-corrosion layer.

[0005] According to the above technical solution, the armor tube layer is arranged in a ring shape, and the armor tube layer is provided with - roots.

[0006] According to the above technical solution, a conduit is embedded and installed on the side of the inner tube of the insulator, and a shielding layer is applied to the outside of the conduit.

[0007] According to the above technical solution, an armor layer is sleeved on the outer sides of the three inner tubes.

[0008] According to the above technical solution, the shielding layer is a shielding mesh and the conduit is a copper wire.

[0009] A method for preparing a multi-channel composite continuous pipe cable comprises the following steps:

[0010] S1. Investigation and function analysis of the service conditions of three-channel combined coiled tubing;

[0011] S2. Material optimization, mechanical property design and structural selection for pipes and cables;

[0012] S3, carry out fine wrapping, wiring heat pipe protection and heat treatment molding;

[0013] S4. Inspection and testing are carried out after production is completed;

[0014] S5. After passing the inspection and test, apply it and record the data.

[0015] According to the above technical solution, the mechanical properties design in step S2 includes the tensile strength, collapse strength and internal pressure resistance of the tube body;

[0016] The material is preferably selected according to the general flow requirements of the coiled tubing operation, and the structural parameters of the multi-channel pipe for stratified water injection are designed to determine the outer diameter of the multi-channel pipe for stratified water injection and the geometric dimensions of each channel, tensile strength, and pressure bearing capacity. At the same time, the optimal multi-channel arrangement scheme is selected to organically combine the coiled tubing together to avoid the problems of low space utilization, difficult processing, large gaps between each other, easy loosening and mutual sliding, and reduce material costs and production costs through material selection and structural design;

[0017] The structural selection includes that during use, the continuous pipe is in a state of plastic deformation, and repeated lifting and lowering causes relative displacement of the channel, destroying the product structure. Based on the existing production processes and technologies of continuous oil pipes and cables, we actively explore the production technology of multi-channel pipes for stratified water injection to achieve the goals of functional design, structural design, and continuity design and manufacturing feasibility.

[0018] According to the above technical solution, in step S3, the inner tube and the conduit are placed in the mold, and then the insulator raw material is melt-cast into the mold, followed by sleeve connection and melting of the outer layer, and finally the molding is tested.

[0019] According to the above technical solution, in step S3, the inner tube and the armor layer are fixed, and then the insulator raw material is melted and cast into the mold, and then the outer layer is sleeved and cast, and finally the molding is tested.

[0020] According to the above technical solution, the data in step S5 is the saved expenses.

[0021] Compared with the prior art, the present invention has the following beneficial effects: the present invention has a scientific and reasonable structure and is safe and convenient to use:

[0022] 1. The operation procedure is simple, the test process is simple, the pressure measurement is easy, and different injection water additives can be selected according to the matching of different reservoirs. There is also heat preservation, which can not only meet the pressure transmission, but also can be used for logging through two cables.

[0023] 2. The compression-resistant layer and armored tube layer improve the capacity of the pipe and cable itself, thereby increasing its service life. The armored tube layer and fiber layer can further improve the toughness and softness of the pipeline corridor, making it easier to use on terrain. The anti-corrosion layer can increase its service life.

[0024] 3. Through the service condition investigation and functional analysis of the three-channel combined continuous tubing, the normal data collection can be achieved, and through the optimization of materials, mechanical property design and structural selection, the rational use of materials can be realized. By selecting the best multi-channel arrangement scheme, the continuous oil tubing can be organically combined together to avoid the problems of low space utilization, difficult processing, large gaps between each other, easy loosening and sliding, and reduce material and production costs through material selection and structural design.

[0025] 4. It can provide normal use and save costs. BRIEF DESCRIPTION OF THE DRAWINGS

[0026] The accompanying drawings are used to provide further understanding of the present invention and constitute a part of the specification. They are used to explain the present invention together with the embodiments of the present invention and do not constitute a limitation of the present invention.

[0027] In the attached picture:

[0028] Figure 1 It is a schematic diagram of the structure of the present invention;

[0029] Figure 2 It is a schematic diagram of the catheter installation structure of the present invention;

[0030] Figure 3 It is a schematic diagram of the armor layer installation structure of the present invention;

[0031] Figure 4 It is a schematic diagram of the preparation process of the present invention;

[0032] Numbers in the figure: 1. inner tube; 2. insulator; 3. leather cover; 4. protective layer; 5. pressure-resistant layer; 6. armor tube layer; 7. filling glue; 8. fiber layer; 9. anti-corrosion layer; 10. armor layer; 11. conduit; 12. shielding layer. DETAILED DESCRIPTION

[0033] The preferred embodiments of the present invention are described below in conjunction with the accompanying drawings. It should be understood that the preferred embodiments described herein are only used to illustrate and explain the present invention, and are not used to limit the present invention.

[0034] Example 1: Figure 1 As shown, the present invention provides a technical solution, a multi-channel composite continuous cable, comprising three inner tubes 1 and an insulator 2, wherein the insulator 2 is filled with a plurality of inner tubes 1, the inner tube 1 is convenient for oil transportation of the pipeline, and is convenient and fast. The insulator 2 can also play a role of heat preservation, and a leather sheath 3 is sleeved on the outside of the insulator 2, a protective layer 4 is welded on the outside of the leather sheath 3, and a pressure-resistant layer 5 is welded on the outside of the protective layer 4 to improve the toughness of the cable itself, and a plurality of armor tube layers 6 are bonded to the outside of the pressure-resistant layer 5. For normal use, the armor tube layers 6 are arranged in a ring, and 15 armor tube layers 6 are provided. A fiber layer 8 is bonded to the outside of the armor tube layer 6, and a filling glue 7 is filled in the gap of the armor tube layer 6 between the fiber layer 8 and the pressure-resistant layer 5. The pressure-resistant layer 5 and the armor tube layer 6 improve the ability of the cable itself, thereby facilitating the improvement of its service life, and the armor tube layer 6 and the fiber layer 8 can further improve the toughness and softness of the pipeline corridor, which is convenient for terrain use, and an anti-corrosion layer 9 is bonded to the outside of the fiber layer 8, and the anti-corrosion layer 9 can facilitate the improvement of its service life.

[0035] Example 2: Figure 1 and 2 As shown, the present invention provides a technical solution, a multi-channel composite continuous cable, including three inner tubes 1 and an insulator 2, the insulator 2 is filled with a plurality of inner tubes 1, the inner tube 1 is convenient for oil transportation of the pipeline, and the insulator 2 can also play a role in heat preservation, and the outer side of the insulator 2 is sleeved with a leather cover 3, the outer side of the leather cover 3 is welded with a protective layer 4, and the outer side of the protective layer 4 is welded with a pressure-resistant layer 5 to improve the toughness of the cable itself, and the outer side of the pressure-resistant layer 5 is bonded with a plurality of armored tube layers 6. For normal use, the armored tube layers 6 are arranged in a ring, and 20 armored tube layers 6 are provided, and the outer side of the armored tube layer 6 is bonded with fiber The gap between the fiber layer 8 and the compression layer 5 is filled with filling glue 7. The compression layer 5 and the armored tube layer 6 improve the capacity of the cable itself, thereby improving its service life. The armored tube layer 6 and the fiber layer 8 can further improve the toughness and softness of the pipeline corridor, which is convenient for terrain use. The outer side of the fiber layer 8 is bonded with an anti-corrosion layer 9, and the anti-corrosion layer 9 can improve its service life. The insulator 2 is embedded with a conduit 11 on the side of the inner tube 1, and a shielding layer 12 is applied to the outer side of the conduit 11. In order to improve the signal transmission quality, the shielding layer 12 is a shielding net and the conduit 11 is a copper wire.

[0036] Example 3: Figure 1 and 3As shown, the present invention provides a technical solution, a multi-channel composite continuous cable, including three inner tubes 1 and an insulator 2, the insulator 2 is filled with a plurality of inner tubes 1, the inner tube 1 is convenient for oil transportation of the pipeline, and the insulator 2 can also play a role in heat preservation, and the outer side of the insulator 2 is sleeved with a leather cover 3, the outer side of the leather cover 3 is welded with a protective layer 4, and the outer side of the protective layer 4 is welded with a pressure-resistant layer 5 to improve the toughness of the cable itself, and the outer side of the pressure-resistant layer 5 is bonded with a plurality of armored tube layers 6. For normal use, the armored tube layer 6 is arranged in a ring shape, and 20 armored tube layers 6 are provided. A fiber layer 8 is bonded to the outside of the armored tube layer 6. The gap between the fiber layer 8 and the pressure-resistant layer 5 is filled with a filling glue 7. The pressure-resistant layer 5 and the armored tube layer 6 improve the capacity of the pipe cable itself, thereby facilitating the improvement of its service life. The armored tube layer 6 and the fiber layer 8 can further improve the toughness and softness of the pipe gallery, which is convenient for terrain use. An anti-corrosion layer 9 is bonded to the outside of the fiber layer 8, and an armor layer 10 is sleeved on the outside of the three inner tubes 1 to prevent deformation of the inner tubes 1.

[0037] Example 4: Figure 4 As shown, the present invention provides a technical solution, a method for preparing a multi-channel composite continuous cable, comprising the following steps:

[0038] S1. Investigation and function analysis of the service conditions of three-channel combined coiled tubing;

[0039] S2. Material optimization, mechanical property design and structural selection for pipes and cables;

[0040] S3, carry out fine wrapping, wiring heat pipe protection and heat treatment molding;

[0041] S4. Inspection and testing are carried out after production is completed;

[0042] S5. After passing the inspection and test, apply it and record the data.

[0043] According to the above technical solution, the mechanical properties design in step S2 includes the tensile strength, collapse strength and internal pressure resistance of the tube body;

[0044] Material optimization is based on the general flow requirements of coiled tubing operations. The structural parameters of the multi-channel pipe for stratified water injection are designed to determine the outer diameter of the multi-channel pipe for stratified water injection and the geometric dimensions of each channel, tensile strength, and pressure bearing capacity. At the same time, the optimal multi-channel arrangement scheme is selected to organically combine the coiled tubing together to avoid problems such as low space utilization, difficult processing, large gaps between each other, easy loosening and sliding between each other. The material cost and production cost are reduced through material selection and structural design;

[0045] Structural selection includes the process in which the continuous pipe is in a state of plastic deformation during use, and repeated lifting and lowering causes relative displacement of the channel, destroying the product structure. Based on the existing production processes and technologies of continuous oil pipes and cables, we actively explore the production technology of multi-channel pipes for stratified water injection to achieve the goals of functional design, structural design, and continuity design and manufacturing feasibility.

[0046] According to the above technical solution, in step S3, the inner tube and the conduit are placed in the mold, and then the insulator raw material is melt-cast into the mold, followed by the sleeve connection and melting of the outer layer, and finally the molding is tested.

[0047] According to the above technical solution, in step S3, the inner tube and the armor layer are fixed, and then the insulator raw material is melted and cast into the mold, and then the outer layer is sleeved and cast, and finally the molding is tested.

[0048] According to the above technical solution, the data in step S5 is the saved cost.

[0049] Through production, we make the following table:

[0050]

[0051] The present application has simple operation procedures, simple testing process, easy pressure measurement, and can select different injection water additives according to the compatibility of different reservoirs. It also has thermal insulation, which can not only meet the pressure transmission requirements, but also can perform well logging through two cables. In addition, the service condition survey and function analysis of the three-channel combined continuous pipe can be used to achieve normal data collection. The rational use of materials is achieved through material optimization, mechanical property design and structural selection. The continuous oil pipes are organically combined together by selecting the optimal multi-channel arrangement scheme to avoid problems such as low space utilization, difficult processing, large gaps between each other, easy loosening and sliding between each other. The material cost and production cost are reduced through material selection and structural design, which can provide normal use while saving costs.

[0052] Finally, it should be noted that the above description is only a preferred example of the present invention and is not intended to limit the present invention. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art can still modify the technical solutions described in the aforementioned embodiments or replace some of the technical features therein by equivalents. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.

Claims

1. A multi-channel composite continuous cable, characterized in that: The invention comprises three inner tubes (1) and an insulator (2), wherein the inner tube (1) is filled inside the insulator (2), the outer side of the insulator (2) is sleeved with a leather cover (3), the outer side of the leather cover (3) is welded with a protective layer (4), the outer side of the protective layer (4) is welded with a pressure-resistant layer (5), the outer side of the pressure-resistant layer (5) is bonded with a plurality of armor tube layers (6), the outer side of the armor tube layer (6) is bonded with a fiber layer (8), the gap between the fiber layer (8) and the pressure-resistant layer (5) of the armor tube layer (6) is filled with a filling glue (7), and the outer side of the fiber layer (8) is bonded with an anti-corrosion layer (9).

2. A multi-channel composite continuous cable according to claim 1, characterized in that: The armor tube layer (6) is arranged in a ring shape, and 15 to 35 armor tube layers (6) are provided.

3. The multi-channel composite continuous cable according to claim 1, characterized in that: The insulator (2) is embedded with a conduit (11) on the side of the inner tube (1), and a shielding layer (12) is applied to the outside of the conduit (11).

4. The multi-channel composite continuous cable according to claim 1, characterized in that: The three inner tubes (1) are sleeved with an armor layer (10) on their outer sides.

5. The multi-channel composite continuous cable according to claim 3, characterized in that: The shielding layer (12) is a shielding mesh, and the conduit (11) is a copper wire.

6. A method for preparing a multi-channel composite continuous cable according to any one of claims 1 to 5, characterized in that: The steps include: S1. Investigation and function analysis of the service conditions of three-channel combined coiled tubing; S2. Material optimization, mechanical property design and structural selection for pipes and cables; S3, carry out fine wrapping, wiring heat pipe protection and heat treatment molding; S4. Inspection and testing are carried out after production is completed; S5. After passing the inspection and test, apply it and record the data.

7. The method for preparing a multi-channel composite continuous cable according to claim 6, characterized in that: The mechanical properties design in step S2 includes the tensile strength, collapse strength and internal pressure resistance of the tube body; The material is preferably selected according to the general flow requirements of the continuous pipe operation, and the structural parameters of the multi-channel pipe for stratified water injection are designed to determine the outer diameter of the multi-channel pipe for stratified water injection and the geometric dimensions of each channel, tensile strength, and pressure bearing capacity. At the same time, the optimal multi-channel arrangement scheme is selected to organically combine the inner pipes together to avoid the problems of low space utilization, difficult processing, large gaps between each other, easy loosening and sliding between each other, and reduce material costs and production costs through material selection and structural design; The structural selection includes that during use, the continuous pipe is in a state of plastic deformation, and repeated lifting and lowering causes relative displacement of the channel, destroying the product structure. Based on the existing production processes and technologies of inner pipes and cables, actively explore the production technology of multi-channel pipes with layered water injection to achieve the goals of functional design, structural design, and continuous design and manufacturing feasibility.

8. The method for preparing a multi-channel composite continuous tube cable according to claim 6, characterized in that: In step S3, the inner tube and the conduit are placed in a mold, and then the insulator raw material is melt-cast into the mold, followed by sleeve connection and melting of the outer layer, and finally the molding is tested.

9. The method for preparing a multi-channel composite continuous tube cable according to claim 6, characterized in that: In step S3, the inner tube and the armor layer are fixed, and then the insulator raw material is melted and cast into the mold, and then the outer layer is sleeved and melted, and finally the molding is tested.