Construction structure and construction method for installing large diameter steel pipes using shield tunnel
By using concrete support structures and waterproof layers to fix large-diameter steel pipes in shield tunnels, and using trackless transportation equipment to simplify steel pipe installation, the problem of high difficulty in urban building demolition and construction is solved, the construction period is shortened, and construction efficiency and safety are improved. sex.
Patent Information
- Application Number
- CN202010216861.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-03-25
- Publication Date
- 2024-10-15
- Estimated Expiration
- 2040-03-25
AI Technical Summary
In urban construction, when installing large-diameter urban water diversion steel pipes, the existing technology requires the demolition of urban buildings, which is difficult and costly to construct. Moreover, during the transportation and installation of steel pipes in shield tunnels, the narrow space makes track removal difficult and the cycle long. .
The steel pipe formed by shield tunnel construction is used to install the tunnel, the steel pipe is fixed through the concrete support structure and waterproof layer, and the steel pipe is transported directly into the tunnel using trackless transportation equipment, avoiding the track disassembly and assembly process, using a curved concrete base and steel bracket Fixing the steel pipe simplifies the construction process.
It solves the problem of high difficulty in urban building demolition and construction, shortens the construction period, improves construction efficiency, ensures construction safety, avoids the difficulty of track disassembly and assembly, and simplifies the installation process of steel pipes.
Smart Images

Figure CN111305322B_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the field of underground pipeline installation, and in particular relates to a construction method for installing large-diameter steel pipes by using a shield tunnel. Background Art
[0002] With the continuous development of urban construction, more and more municipal pipelines are buried underground. Generally, underground pipelines are installed by burying. However, for large-diameter urban water diversion steel pipes, due to the large diameter of the steel pipes, it is inconvenient to bury them. In addition, there are many urban buildings, and the burying process requires the demolition of surrounding buildings. The engineering workload is large, so the construction is difficult and the cost is high.
[0003] Pipeline installation in shield tunnels is often encountered in water conservancy projects, mining projects, petroleum, and nuclear power pipeline projects. However, for some large-diameter heavy pipelines, due to the large volume of the pipelines and the circular segments of the shield tunnels with a certain curvature at the bottom, it is necessary to use the original tracks in the shield tunnel or install tracks in the tunnel to transport the steel pipes. After the steel pipes are transported to the destination, the steel pipes are supported by brackets, and the tracks in the tunnel are removed before the steel pipes are installed. Due to the limited space in the shield tunnel and the large diameter of the steel pipes, the area between the steel pipes and the tracks is relatively narrow after the steel pipes are transported into the tunnel, which brings a lot of inconvenience to the removal of the tracks and the installation of the steel pipes. Summary of the invention
[0004] In view of the problems existing in the prior art, the present invention provides a construction method for installing large-diameter steel pipes using a shield tunnel. The construction method can solve the problem that when burying large-diameter municipal pipelines, urban buildings need to be disassembled and assembled, which is difficult and costly to construct, and can also solve the problem that the installation of large-diameter steel pipes in shield tunnels requires laying tracks due to transportation requirements, and after the pipelines are transported to their destination, the tracks are difficult to dismantle, resulting in a long steel pipe installation period.
[0005] In order to solve the above problems, the present invention provides a construction structure for installing large-diameter steel pipes using a shield tunnel, characterized in that: the construction structure includes a steel pipe installation tunnel formed by shield construction and a steel pipe placed in the steel pipe installation tunnel, the steel pipe installation tunnel is composed of a shield segment and a grouting layer placed behind the segment, the steel pipe is placed in the middle or lower middle part of the steel pipe installation tunnel, and is fixed by a concrete support structure, and a waterproof layer is provided between the concrete support structure and the shield segment; The concrete support structure includes a concrete pouring platform, a curved concrete base and multiple steel brackets. The concrete pouring platform is a horizontal support platform constructed at the bottom of the steel pipe installation tunnel before the steel pipe is transported to the shield tunnel. The steel bracket and the curved concrete base are constructed after the steel pipe is transported to the shield tunnel. Multiple steel brackets are dispersedly erected between the steel pipe and the concrete pouring platform. The bottom of each steel bracket is fixed on the concrete pouring platform and the top is welded to the steel pipe. The curved concrete base is formed after concrete is poured between the bottom of the steel pipe and the concrete pouring platform after the steel bracket is erected, and the curved concrete base covers the lower part of the steel pipe; a drainage ditch is provided on the curved concrete base.
[0006] A further technical solution of the present invention is as follows: cables and light strips are arranged in the steel pipe installation tunnel. After the steel pipes are transported to the steel pipe installation tunnel, walkway plates are set up on both sides of the steel pipes. The walkway plates on each side are fixed to the inner wall of the shield segment through a support frame, and the walkway plates are removed during the pouring of the arc concrete base.
[0007] A further technical solution of the present invention is as follows: after the steel pipe is erected by the steel bracket, the distance between its bottom surface and the bottom shield segment is 60 to 80 cm; the height of the arc-shaped concrete base covering the steel pipe is at least higher than 1 / 3 of the diameter of the steel pipe; the arc-shaped concrete base is a construction unit of 5 to 7 m, and is formed by building a template on a concrete pouring platform, laying steel bars and then pouring concrete; an expansion joint of 1.5 to 2.5 cm is provided between two adjacent construction units, pine boards are used to fill the expansion joints, and rubber waterstops are attached to the joints.
[0008] The better technical solution of the present invention is as follows: the steel support is a support frame welded by steel sections, multiple steel supports are evenly distributed, the spacing between adjacent steel supports is 3 to 5m, and the contact surface between each steel support and the steel pipe is set to be an arc surface with the same curvature as the steel pipe; the waterproof layer is formed by directly laying 2 to 4 layers of SBS self-adhesive waterproof membrane on the shield segment, and its thickness is 10 to 16mm.
[0009] The preferred technical solution of the present invention is as follows: the concrete pouring platform is distributed along the axial direction of the shield tunnel and completely covers the bottom of the shield tunnel to form a horizontal transport walkway. The height of the concrete pouring platform is 30 to 40 cm; the steel pipe is transported into the shield tunnel along the concrete pouring platform by transportation equipment.
[0010] The present invention also provides a construction method for installing a large-diameter steel pipe using a shield tunnel, which is characterized by the following specific steps:
[0011] (1) Use shield construction technology to construct a shield tunnel for installing steel pipes along the designed steel pipe installation route. The diameter of the shield tunnel formed by the construction is at least 1.5m larger than the diameter of the steel pipe;
[0012] (2) After the shield tunnel construction is completed, the tracks and construction pipelines in the shield tunnel are removed, the lighting strips in the tunnel are retained, the bolt holes of the shield tunnel bottom segments are sealed with cement mortar, and the shield tunnel bottom segments are cleaned. Then, 2 to 4 layers of self-adhesive waterproof layer are laid on the bottom surface of the shield tunnel. The laying range of the waterproof layer is equal to or higher than the design height of the concrete support platform.
[0013] (3) After the waterproof layer in step (2) is laid, concrete is poured in the arc-shaped area at the bottom of the shield tunnel to form a concrete support platform with a height of 30 to 40 cm, and maintenance is carried out until the concrete support platform reaches the designed strength;
[0014] (4) After the concrete support platform in step (3) reaches the design strength, the steel pipe is hoisted from the shield shaft to the starting end of the shield tunnel, and the steel pipe is transported into the shield tunnel by trackless transportation equipment. After the steel pipe is transported to the right place, multiple steel brackets are installed at the bottom of the steel pipe to erect the steel pipe to the design height. The spacing between adjacent steel brackets is 3 to 5 m. The bottom of the steel bracket is fixed on the concrete support platform, and the upper part of the steel bracket is welded to the surface of the steel pipe;
[0015] (5) After the steel pipe is erected in step (4), the steel pipe transportation equipment is withdrawn, and 2 to 4 layers of self-adhesive waterproof layers are continuously laid on both sides of the steel pipe, each layer of waterproof layers being seamlessly connected to the waterproof layers laid in step (2), and the laying range is an area above 1 / 3 of the shield tunnel diameter. After the waterproof layers are laid, templates are constructed in sections on both sides of the steel pipe and concrete is continuously poured to form an arc-shaped concrete base covering the lower part of the steel pipe, and the steel pipe is fixed by the arc-shaped concrete base. When pouring the arc-shaped concrete base, a drainage ditch is reserved at the position of the arc-shaped concrete base near the inner wall of the tunnel.
[0016] A further technical solution of the present invention is as follows: a shield shaft is provided at a spacing of 2.5 to 3.5 km between the shield tunnels, and the steel pipe is hoisted from the shield shaft to the shield tunnel by unloading with a crawler crane or a gantry crane; the steel pipe is formed by splicing multiple sections of steel pipes with a length of 10 to 13 m. After each section of steel pipe is installed, the next section of steel pipe is installed, and adjacent steel pipes are welded to form an integral structure.
[0017] The preferred technical solution of the present invention is as follows: in the step (4), the steel pipe is transported to the shield tunnel along the concrete support platform by a forklift and an electric flatbed truck with steering wheels, a support plate is installed at the front end of the forklift, an arc-shaped groove with the same arc as the steel pipe is provided on the flatbed truck, and the front running wheel of the flatbed truck is a universal wheel; when the steel pipe is transported, the front part of the steel pipe is placed in the arc-shaped groove of the electric flatbed truck, and a connector is welded on the steel pipe to fix the flatbed truck to the steel pipe, and the rear end of the steel pipe is placed on the support plate at the front end of the forklift, and a temporary support is provided inside the steel pipe, wherein the temporary support is a steel pipe with a diameter of 60 to 90 mm arranged in a cross shape, and the steel pipe is pushed forward by a forklift and transported along the concrete support platform to the installation position in the shield tunnel. After the steel pipe is transported to the right position, the height and installation position of the steel pipe are adjusted by an internal jacking device installed inside the steel pipe. After the steel pipe is in place by adjusting the four degrees of freedom of up, down, left and right, a steel bracket is installed at the bottom of the steel pipe, and the flatbed truck and forklift are removed at the same time.
[0018] A further technical solution of the present invention is as follows: the pouring of the arc-shaped concrete base in step (5) is carried out by construction workers through walkway slabs erected on both sides of the steel pipe, the walkway slabs are directly laid on the walkway slab brackets, the walkway slabs are removed during the concrete pouring, and the walkway slab brackets are poured into the concrete; the arc-shaped concrete base cast in sections has a length of 5 to 7 m per section, and an expansion joint of 1.5 to 2.5 cm is formed between two adjacent sections of the arc-shaped concrete base, wooden boards are used for caulking in the expansion joints, and rubber waterstops are attached to the joints.
[0019] The preferred technical solution of the present invention is as follows: before the steel pipe is installed, a fused epoxy powder anti-corrosion layer is coated on the outer wall of the steel pipe for external anti-corrosion work, and the coating thickness shall not be less than 400 μm; after the steel pipe is installed in place, the inner wall of the steel pipe is cleaned and rust-removed, and then a cement mortar lining is sprayed on it for internal anti-corrosion work. The cement mortar lining adopts ordinary silicate M30 cement mortar, and specifically adopts an axial 360-degree spraying machine with a high-speed 360-degree nozzle in an umbrella shape to evenly spray the mortar on the inner wall of the steel pipe. The spraying is done twice, and the thickness of the first coat is 8 to 12 mm. After the mortar solidifies for 22 to 26 hours, the second coat is sprayed, and the thickness is not less than 10 mm. After spraying, it is manually pressed to make the surface smooth and traceless, and water is sprinkled for maintenance after 24 hours.
[0020] Beneficial effects of the present invention:
[0021] (1) The present invention uses a shield tunnel to install municipal pipelines. Since the shield construction is completed in an underground shield tunnel, there is no need to demolish ground buildings during the construction process, and it will not cause much impact on ground buildings. It solves the problems of inconvenience in burying large-diameter steel pipes in existing cities, great construction difficulty and high cost. In addition, the pipeline is installed in the tunnel, and the safety of construction workers is ensured;
[0022] (2) When installing the pipeline, the present invention first waterproofs the bottom of the shield tunnel and constructs a concrete horizontal support platform. Then, the steel pipe is directly transported to the tunnel through the concrete horizontal support platform by trackless transportation equipment. There is no need to set up a separate track, and the process of dismantling the track when the steel pipe is transported to the tunnel is avoided. This solves the problem of difficulty in disassembling and assembling the track due to narrow space after the steel pipe is transported to the tunnel.
[0023] (3) The pipeline of the present invention is fixed by directly pouring concrete. After the steel pipe is transported to the place, a steel bracket is set up on the concrete horizontal support platform to support the steel pipe, and then a template is built at the bottom of the steel pipe to directly pour concrete to fix the bottom of the steel pipe. There is no need to install any additional fixing parts. A walkway board can be directly built in the tunnel, and construction can be carried out by standing on the walkway board. The construction is simple and convenient.
[0024] The present invention utilizes a shield tunnel to install pipelines, thus avoiding the impact on urban buildings during the steel pipe burial process, and adopts a concrete pouring platform to transport steel pipes, thus avoiding the track disassembly and assembly process. The steel pipes are also fixed by directly pouring concrete, thus simplifying the construction process, facilitating the overall construction, and greatly shortening the construction period. BRIEF DESCRIPTION OF THE DRAWINGS
[0025] Figure 1 It is a schematic diagram of an axial cross section of the construction structure of the present invention;
[0026] Figure 2 It is a longitudinal cross-sectional schematic diagram of the construction structure of the present invention;
[0027] Figures 3 to 5 It is the construction process of the present invention;
[0028] Figure 6 It is a schematic diagram of steel pipe transportation of the present invention;
[0029] Figures 7 to 9 It is a schematic diagram of splicing two adjacent steel pipe sections in the present invention.
[0030] In the figure: 1—steel pipe installation tunnel, 100—shield segment, 101—grouting layer, 2—steel pipe, 3—concrete pouring platform, 4—steel bracket, 5—walkway board, 501—support frame, 6—waterproof layer, 7—cable, 8—light strip, 9—arc concrete base, 10—drainage ditch, 11—formwork, 12—flatbed car, 1200—connecting parts, 13—forklift, 14—lifting equipment, 15—installed steel pipe section, 16—steel pipe section to be installed. DETAILED DESCRIPTION
[0031] The present invention will be further described below in conjunction with the accompanying drawings and embodiments. Figures 1 to 9The accompanying drawings of the embodiments are drawn in a simplified manner and are only used to clearly and concisely illustrate the embodiments of the present invention. The technical solutions shown in the following drawings are specific solutions of the embodiments of the present invention and are not intended to limit the scope of the invention claimed for protection. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0032] In the description of the present invention, it should be understood that the terms "upper", "lower", "inside", "outside", "left", "right", etc. indicate directions or positional relationships based on the directions or positional relationships shown in the accompanying drawings, or are directions or positional relationships in which the product of the invention is usually placed when in use, or are directions or positional relationships commonly understood by those skilled in the art. These directions or positional relationships are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and therefore should not be understood as a limitation on the present invention.
[0033] The construction structure provided in the embodiment for installing a large diameter steel pipe using a shield tunnel is as follows: Figure 1 and Figure 2 As shown, it includes a steel pipe installation tunnel 1 formed by shield construction and a steel pipe 2 placed in the steel pipe installation tunnel. The steel pipe installation tunnel 1 is composed of a grouting layer 101 with a shield segment 100 placed behind the segment. Its shield construction process is the same as the existing shield construction process. Cables 7 and light strips 8 are arranged in the steel pipe installation tunnel 1. The steel pipe 2 is placed in the middle or lower middle part of the steel pipe installation tunnel 1. After the steel pipe 2 is erected by the steel bracket 4, the bottom surface of the steel pipe 2 is 60 to 80 cm away from the bottom shield segment 100, and it is fixed by a concrete support structure. A new waterproof layer 6 is provided between the concrete support structure and the shield segment 100. The waterproof layer 6 is formed by directly laying 2 to 4 layers of SBS self-adhesive waterproof membrane on the shield segment 100, and its thickness is 10 to 16 mm. Figure 4 As shown, after the steel pipe 2 is transported to the steel pipe installation tunnel 1, walkway plates 5 are set up on both sides of the steel pipe 2. The walkway plates 5 on each side are fixed to the inner wall of the shield segment 100 through a support frame 501, and the walkway plates 5 are removed during the pouring of the arc concrete base 9.
[0034] The construction structure provided in the embodiment for installing a large diameter steel pipe using a shield tunnel is as follows: Figure 1 and Figure 2As shown, the concrete support structure includes a concrete pouring platform 3, an arc-shaped concrete base 9 and a plurality of steel brackets 4. The concrete pouring platform 3 is a horizontal support platform constructed at the bottom of the steel pipe installation tunnel 1 before the steel pipe 2 is transported to the steel pipe installation tunnel 1. The concrete pouring platform 3 is distributed axially along the steel pipe installation tunnel 1 and completely covers the bottom of the steel pipe installation tunnel 1 to form a horizontal transportation walkway. The height of the concrete pouring platform 3 is 30-40 cm. The steel pipe 2 is transported to the steel pipe installation tunnel 1 along the concrete pouring platform 3 by transportation equipment. The steel bracket 4 and the arc-shaped concrete base 9 are constructed after the steel pipe 2 is transported to the steel pipe installation tunnel 1. The steel bracket 4 is a support frame welded by section steel. A plurality of steel brackets 4 are equidistantly dispersedly erected between the steel pipe 2 and the concrete pouring platform 3. The spacing between adjacent steel brackets 4 is 3-5 m. The bottom of each steel bracket 4 is fixed on the concrete pouring platform 3, and the top is welded to the steel pipe 2. The contact surface between each steel bracket 4 and the steel pipe 2 is set to be an arc surface with the same curvature as the steel pipe 2. The arc-shaped concrete base 9 is formed after the steel support 4 is erected and concrete is poured between the bottom of the steel pipe 2 and the concrete pouring platform 3, and the arc-shaped concrete base 9 covers the lower part of the steel pipe 2. The height of the arc-shaped concrete base 9 covering the steel pipe 2 is at least higher than 1 / 3 of the diameter of the steel pipe 2, and a drainage ditch 10 is provided on the arc-shaped concrete base 9. The arc-shaped concrete base 9 is formed by pouring concrete after building a template 11 on the concrete pouring platform 3, with 5 to 7 meters as a construction unit. A 1.5 to 2.5 cm expansion joint is provided between two adjacent construction units, and pine wood boards are used to fill the expansion joints, and rubber waterstops are attached to the joints.
[0035] The construction process of the present invention is further described below in conjunction with the embodiments. The embodiment is for a water supply pipeline project in Hangzhou. The project diverts water to two water plants in the city, with a water diversion scale of 710,000 m3 / d. The project runs along the ring road to the water plant water diversion store. The total length of the line is 20.2 km, which will pass through urban buildings. The diameter of the water diversion steel pipe is large, and it is difficult to bury. In order to avoid affecting the surrounding buildings and urban roads, the project adopts the method of first constructing a shield tunnel in the present invention, and then installing a steel pipe in the shield tunnel to install the water diversion pipe. The shield tunnel of the project is divided into seven sections, and 8 shield shafts are set up with an average spacing of about 3.0 km.
[0036] The shield tunnel excavation diameter is 6.2m, the inner diameter after lining is 5.5m, the water diversion steel pipe is DN3496 pipe, the outer diameter of the steel pipe is 3496mm, the steel pipe is made of multiple sections of 12m long steel pipes, the water diversion steel pipe is installed after the shield tunnel, the vertical distance between the top of the steel pipe and the top shield segment is 130.4mm, the vertical distance between the bottom of the steel pipe 2 and the bottom of the shield tunnel segment is 70mm, and the bottom of the steel pipe is equipped with φ22 fixed anchor bars, and the row spacing is 1m*2m. The specific installation process of the steel pipe of this project is as follows:
[0037] (1) According to the design requirements, a shield construction process is adopted to construct a steel pipe installation tunnel 1 for installing steel pipes along the designed steel pipe installation route. The shield tunnel 1 is constructed using the existing shield construction method. Cables 7 and light strips 8 are installed in the shield tunnel. The shield segment 100 is a shield segment with a thickness of 35 cm.
[0038] (2) After the shield tunnel construction is completed, the track and construction pipeline at the bottom of the shield tunnel are removed, the lighting strip in the tunnel is retained, and the bolt holes of the pipe segments at the bottom of the shield tunnel are sealed with M10 cement mortar; after the track is removed, the SBS cushion area is cleaned and kept dry, and then three layers of self-adhesive SBS waterproof membrane are laid on the bottom of the shield tunnel. The thickness of each layer is 4 mm, and the overall thickness of the waterproof layer is 12 mm. The SBS cushion is a modified asphalt waterproof membrane with a glass fiber reinforced polyester felt as the base and a polyethylene film (PE film) as the surface. ; The laying of SBS waterproofing membrane is synchronized with the concrete pouring construction. The SBS membrane laying area in this step is the pouring area of the concrete support platform. During the laying process, the overlap length is reserved so that it can be seamlessly connected with the SBS membrane laid during the later pouring of the arc-shaped concrete base; the waterproof cushion layer can isolate the pipes and pipe segments to prevent stress damage caused by uneven shrinkage and deformation; the SBS membrane laying process specifically includes: base inspection and cleaning → brushing base treatment agent → positioning, drawing reference lines, trial laying → peeling off the isolation paper at the bottom of the membrane → laying Self-adhesive roll → roller pressure to vent → lap joint bonding, roller pressure to vent → second layer roll positioning, reference line marking → laying second layer self-adhesive roll → roller pressure to vent → lap joint bonding, roller pressure to vent → third layer roll positioning, reference line marking → laying third layer self-adhesive roll → seal lap edge with sealant → SBS cushion layer acceptance; the base layer to be coated with the base treatment agent must be dry, with a moisture content of less than 9%. The cushion layer is constructed using the cold bonding method, and the polymer modified asphalt adhesive is evenly applied to the base surface with a rubber scraper, and the thickness is controlled to be uniform; the upper and lower layers of adjacent rolls must not overlap The rolls should be laid perpendicular to each other, and the joints of the upper and lower adjacent layers should be staggered, with the long and short sides staggered by 1 / 3-1 / 2 of the width of the roll. During the laying process, the rolls are not allowed to be stretched, and there should be no wrinkles. After laying each roll, a steel roller should be used to roll it from one end to the horizontal direction to completely eliminate the air between the rolls and the base layer to ensure a firm bond. Check while laying, and use a screwdriver to check the interface during inspection. If any false welding is found, repair it in time. Only after passing the inspection can the next process be carried out.
[0039] (3) After the waterproof layer in step (2) is laid, C25 concrete is poured in the arc area at the bottom of the shield tunnel to form a concrete support platform with a height of 35 cm, and maintenance is carried out until the concrete support platform reaches the designed strength.
[0040] (4) After the concrete support platform in step (3) reaches the design strength, the steel pipe is unloaded from the truck using a 150t crawler crane and hoisted down the shaft to the starting end of the shield tunnel. The lifting method uses an iron shoulder beam to lift the pipe down the shaft. The lifting equipment uses two 30t slings. The shoulder beam and rope are all made by professional qualified manufacturers. The steel pipe transportation equipment in the tunnel includes a forklift and an electric flatbed truck with steering wheels. It is transported along the concrete support platform to the shield tunnel. A support plate is installed at the front end of the forklift. The flatbed truck is provided with an arc-shaped groove with the same arc as the steel pipe. The front running wheel of the flatbed truck is a universal wheel. When the steel pipe is hoisted down the shaft, if Figure 6 As shown, it is directly placed on the transportation equipment, the front part of the steel pipe is placed in the arc-shaped groove of the electric flatbed truck, and a connector is welded on the steel pipe to fix the flatbed truck and the steel pipe. The rear end of the steel pipe is placed on the support plate at the front end of the forklift, and a temporary support is arranged in the steel pipe. The temporary support is a steel pipe with a diameter of 60 to 90 mm arranged in a cross shape. The steel pipe is pushed forward by a forklift and transported along the concrete support platform to the installation position in the shield tunnel; after the steel pipe is transported to the place, the height and installation position of the steel pipe are adjusted by the internal jacking equipment installed inside the steel pipe; the internal jacking equipment is divided into a lower support and an upper jacking device, and the jacking device can rotate 360° to achieve full pipe mouth adjustment. The internal jacking equipment is provided with two jacks, and the cylinder stroke can be adjusted. The pipe mouth adjustment of 360° is achieved by rotating the upper jacking device; when two adjacent sections of steel pipe are butt-jointed, such as Figure 7 As shown, the support of the jacking device is installed in the installed steel pipe, and the jacking device is extended into the steel pipe to be installed. After the two steel pipes are adjusted to be completely butted by the jacking device, the steel bracket is installed at the bottom of the steel pipe, and the flatbed truck and forklift are removed at the same time. Three steel brackets are installed at the bottom of each section of the steel pipe, two of which are placed at both ends of the steel pipe and one is placed in the middle of the steel pipe. Each steel bracket is composed of two vertical supports and one horizontal support steel. When installing it specifically, first after the two sections of the steel pipe are butted, the steel bracket at the adjacent end of the installed steel pipe is installed, and two vertical support rods are first welded on both sides of the steel pipe, and then the two vertical support rods are connected by the horizontal support rod. After the steel bracket at the end is installed and welded, the flatbed truck is removed and removed to the forklift end, and then the steel brackets in the middle and forklift ends are installed in turn, and finally the adjacent steel pipe butt interfaces are welded, and the bottom of the steel bracket is fixed on the concrete support platform.
[0041] (5) After the steel pipes are erected in step (4) and the steel pipe transport equipment is removed, the self-adhesive SBS waterproof membrane is continued to be laid in the pouring area of the curved concrete base on both sides of the steel pipe. The laying process is the same as step (2), and each layer of the self-adhesive SBS waterproof membrane is seamlessly connected to the waterproof layer laid in step (2). After the waterproof layer is laid, the templates are built in sections on both sides of the steel pipe and the steel bars are laid. The steel bars are welded to the surface of the steel pipe. The steel bars can be used as walkway slab supports, and the walkway slabs are laid on the steel bar supports. Construction Workers poured concrete on the walkway slab and dismantled it while pouring to form a curved concrete base that covers the lower part of the steel pipe. The steel pipe is fixed through the curved concrete base, and a drainage ditch is reserved at the position of the curved concrete base near the inner wall of the tunnel when pouring the curved concrete base. The drainage ditch template uses 15cm*10cm square wood. After the concrete pouring is completed, the prepared 15cm*10cm square wood is pressed into both sides of the concrete foundation before the concrete begins to set. Steel blocks are placed on the square wood to prevent it from floating up. Each section of the segmented cast arc concrete base is 6m long, and an expansion joint of 1.5 to 2.5cm is formed between two adjacent arc concrete bases. Wooden boards are used to fill the expansion joints, and rubber waterstops are attached to the joints. The external waterstops use rubber waterstops. During construction, fasteners or bolts must be used for fixing. The fasteners must be airtight and reliable. The fasteners should be poured into the concrete. When the waterstop is fixed with bolts, the bolt holes should be backfilled with anchoring agent, and the template is also fixed with anchoring screws.
[0042] (6) After the steel pipe is installed in place, the inner wall of the steel pipe is cleaned and rust-free, and then cement mortar lining is sprayed for internal anti-corrosion work. Rust removal is carried out using water sandblasting technology. The axial automatic water sandblasting machine can remove rust quickly even if floating rust occurs during the roll transportation or at the installation site. The roughness can meet the standard. Since water sandblasting uses clean water and high pressure to remove rust, it avoids the disadvantages of poor ventilation conditions in the pipeline, long pipeline spacing and other disadvantages that cannot be implemented. Use a high-pressure water gun cleaning machine to clean the oxide scale, floating rust, dirt, grease, welding slag, dirt and other attachments on the inner wall of the pipeline, and then clean out the garbage and accumulated water. After rust removal and cleaning, the inner wall of the pipeline is inspected. After meeting the lining construction requirements, cement mortar lining is constructed. The cement mortar lining adopts ordinary silicate M30 cement mortar, and the strength of cement mortar is not less than 30MPa. The spraying machine adopts an axial 360-degree spraying machine. This spraying machine has an adjustable nozzle. According to the size of the cylinder diameter, the nozzle is always at the center of the circle to avoid unevenness, and the machine can move forward and backward by itself. The speed can be adjusted according to the thickness during the spraying process. The high-speed 360-degree nozzle is in an umbrella shape to spray the mortar forcefully and evenly on the cylinder, avoiding hollowing, cracking and other phenomena, and enhancing adhesion. Pour the well-mixed mortar into the mortar sprayer and spray it evenly on the cylinder. The first coat is preferably 10mm. After about 24 hours of solidification, spray the second coat with a thickness of not less than 10mm. Since the calendering will press on the surface, the mortar should be sprayed 2mm more than the predetermined thickness. After spraying, it should be manually calendered to make the surface smooth and traceless. Sprinkle water for maintenance after 24 hours. Maintenance must be timely, effective and long-lasting. The hole must be closed and water must always be stored in the cylinder.
[0043] In the above embodiment, before the steel pipe is installed, sufficient lighting equipment and ventilation equipment are equipped in the interval tunnel according to the construction needs. The lighting equipment for the steel pipe installation construction is intended to retain the light strips and light strip electrical boxes in the tunnel for construction lighting, and the light strips are laid along the inner wall of the steel pipe for internal lighting of the steel pipe; ventilation facility layout method: 4 axial flow fans are arranged at 10m and 20m in front of the first section of the steel pipe respectively, and 1 is arranged near the steel pipe welding operation surface. 5 fans blow air towards the tunnel exit at the same time to promote air circulation in the tunnel. At the same time, in order to ensure the air quality near the welding operation surface, an air adsorption purifier is added near the welding surface. Axial flow fan: 5 sets of fire smoke exhaust axial flow fans are selected, with a power of 5.5Kw and an air volume of 13197-16090m3 / h, which is converted into an air supply volume of 16090 / 60=268.2m3 / Mim per minute.
[0044] In the above embodiment, the pressure steel pipe is to be manufactured in the factory and the outer wall is anticorrosive. The length of each section of the steel pipe is 12m, the outer diameter of the steel pipe is 3496mm, the wall thickness is 30mm, and the weight of a single piece is 30.8 tons. After the production is completed, it is transported to the construction site by a flatbed truck with a width of 3 meters, a length of 16 meters and a length of 17.5 meters. The outer anticorrosion of the pressure steel pipe is set with a 400μm (dry film thickness) thick fused epoxy powder. The steel pipe is made of a steel plate with a diameter of 3m and rolled by a plate rolling machine. The inner and outer straight seams are welded by submerged arc automatic welding, one inner straight seam and two outer straight seams. Before welding the outer straight seam, it is necessary to clean the root with a φ10 carbon rod before welding. The weld shall not have defects such as cracks, slag inclusions, pores, fusion splashes, etc. The undercut depth is ≤0.5mm and the length is ≤100mm. The weld shall not have depressions, and the surface reinforcement height is ≤4mm. The welded 3.0-meter-long pipes are spliced into 12.0-meter-long single-section pipes. The splicing of single-section pipes needs to be carried out on a special assembly frame to ensure the straightness of the pipe section. The joints between the pipes are firmly fixed with manual welding points, and the outer tube body is sealed with manual welding to prevent the submerged arc automatic welding from burning through. After assembly, the misalignment error of adjacent pipe sections is ≤2mm. The gap between the longitudinal seams after assembly is controlled within the range of 2 (+1, -2) mm. The longitudinal seams of adjacent pipe sections are >300mm, the farther the better, and no cross welds are allowed. The inner and outer ring seams are welded by submerged arc automatic welding, with two straight seams for the inner ring and one straight seam for the outer ring. Before welding the outer ring seam, a φ10mm carbon rod needs to be used to plan out the groove shape, and the root needs to be cleaned before welding. After welding, the weld should not have defects such as cracks, pores, slag inclusions, and soluble splashes. The undercut depth is ≤0.5mm and the length is ≤100mm. The weld should not have depressions, and the surface reinforcement height is ≤4mm. After the pipe body is manufactured, a temporary radial support is added, using 6 80mm diameter steel pipes arranged in a M shape to prevent the pipe body from deforming during transportation and lifting.
[0045] In the embodiment, the butt joint of two adjacent steel pipes is welded by manual gas shielded welding, the groove adopts V-shaped groove, the welding wire used is Jinqiao brand flux-cored welding wire, the diameter of the welding wire is 1.2mm, and the welding material matches the parent material; the carbon arc gouging carbon rod used for welding root cleaning is B510 type, φ10mm*355mm carbon rod. Before using the automatic welding wire, ensure that the surface is free of impurities such as oil, rust, etc., otherwise it should be removed; the impurity content of the shielding gas used for automatic welding meets the relevant standards, and the purity of CO2 is above 99.5%.
[0046] The two concrete pourings in the embodiment both use HBT8018 concrete drag pump. When pouring concrete, the drag pump is set at a wellhead position that is close to the distance. Each time the concrete is poured, the height of the pump pipe is higher than the height of the designed concrete surface. When the first layer of concrete is poured, the concrete is poured while the pipe is removed. After the first layer of concrete is poured, the pump pipe of the pouring section is removed (the remaining pump pipes in the tunnel are retained), and the pump pipe is immediately cleaned. After waiting for the initial setting of the concrete, the pump pipe of the pouring section is reconnected to pour the second layer of concrete. After the steel pipe is installed, the deadweight of the steel pipe and the steel support is used to overcome the buoyancy of the concrete pouring. After the concrete is poured, it should be maintained in time. After the concrete surface is flattened, a layer of plastic film is covered on the concrete surface for maintenance. Fly ash should be added to the premixed concrete to improve the workability of the premixed concrete and reduce the slump loss of the premixed concrete. The sand ratio should be controlled in the pumped concrete mix ratio. A high sand ratio can increase the pumpability of the concrete, but a too high sand ratio will increase the cracks on the concrete surface. Therefore, the sand ratio should be controlled within a reasonable range. The general rule is to control it at around 38% to 40%.
[0047] In summary, the above is an embodiment of the present invention, but the present invention is not limited to the above embodiment. As long as the technical effect of the present invention is achieved by any same or similar means, it should fall within the scope of protection of the present invention.
Claims
1. A construction structure for installing large-diameter steel pipes using a shield tunnel, characterized in that: The construction structure comprises a steel pipe installation tunnel (1) formed by shield construction and a steel pipe (2) placed in the steel pipe installation tunnel. The steel pipe installation tunnel (1) is composed of shield segments (100) and a grouting layer (101) placed behind the segments. The steel pipe (2) is placed in the middle or lower middle part of the steel pipe installation tunnel (1) and fixed by a concrete support structure. A waterproof layer (6) is provided between the concrete support structure and the shield segments (100). The concrete support structure comprises a concrete pouring platform (3), an arc-shaped concrete base (9) and a plurality of steel brackets (4). The concrete pouring platform (3) is provided on the steel pipe installation tunnel before the steel pipe (2) is transported to the shield tunnel (1). A horizontal support platform for the bottom construction of a shield tunnel (1); the steel bracket (4) and the arc-shaped concrete base (9) are constructed after the steel pipe (2) is transported to the shield tunnel (1); a plurality of steel brackets (4) are dispersedly erected between the steel pipe (2) and the concrete pouring platform (3); the bottom of each steel bracket (4) is fixed on the concrete pouring platform (3), and the top is welded to the steel pipe (2); the arc-shaped concrete base (9) is formed after concrete is poured between the bottom of the steel pipe (2) and the concrete pouring platform (3) after the steel bracket (4) is erected, and the arc-shaped concrete base (9) covers the lower part of the steel pipe (2); and a drainage ditch (10) is provided on the arc-shaped concrete base (9).
2. The construction structure for installing large-diameter steel pipes using a shield tunnel according to claim 1, characterized in that: The steel pipe installation tunnel (1) is provided with cables (7) and light strips (8). After the steel pipe (2) is transported to the steel pipe installation tunnel (1), walkway plates (5) are set up on both sides of the steel pipe (2). The walkway plates (5) on each side are fixed to the inner wall of the shield segment (100) through a support frame (501), and the walkway plates (5) are removed during the pouring of the arc-shaped concrete base (9).
3. A construction structure for installing large-diameter steel pipes using a shield tunnel according to claim 1 or 2, characterized in that: After the steel pipe (2) is erected by the steel support (4), the distance between its bottom surface and the bottom shield segment (100) is 60 to 80 cm; the height of the arc-shaped concrete base (9) covering the steel pipe (2) is at least higher than 1 / 3 of the diameter of the steel pipe (2); the arc-shaped concrete base (9) is formed by pouring concrete after building a template (11) on a concrete pouring platform (3) with a construction unit of 5 to 7 m; an expansion joint of 1.5 to 2.5 cm is provided between two adjacent construction units, pine wood boards are used to fill the expansion joints, and rubber waterstop strips are attached to the joints.
4. A construction structure for installing large-diameter steel pipes using a shield tunnel according to claim 1 or 2, characterized in that: The steel bracket (4) is a support frame welded by steel sections, a plurality of steel brackets (4) are evenly spaced, the spacing between adjacent steel brackets (4) is 3 to 5 m, and the contact surface between each steel bracket (4) and the steel pipe (2) is configured to be an arc surface with the same arc as the steel pipe (2); the waterproof layer (6) is formed by directly laying 2 to 4 layers of SBS self-adhesive waterproof membrane on the shield segment (100), and the thickness thereof is 10 to 16 mm.
5. A construction structure for installing large-diameter steel pipes using a shield tunnel according to claim 1 or 2, characterized in that: The concrete pouring platform (3) is distributed axially along the steel pipe installation tunnel (1) and completely covers the bottom of the steel pipe installation tunnel (1) to form a horizontal transport walkway. The height of the concrete pouring platform (3) is 30 to 40 cm. The steel pipe (2) is transported along the concrete pouring platform (3) into the steel pipe installation tunnel (1) by means of transport equipment.
6. A construction method for installing large-diameter steel pipes using a shield tunnel, characterized in that: The construction structure for installing large-diameter steel pipes by using a shield tunnel as described in any one of claims 1 to 5 is constructed in the following specific steps: (1) Use shield construction technology to construct a shield tunnel for installing steel pipes along the designed steel pipe installation route. The diameter of the shield tunnel formed by the construction is at least 1.5m larger than the diameter of the steel pipe; (2) After the shield tunnel construction is completed, the tracks and construction pipelines in the shield tunnel are removed, the lighting strips in the tunnel are retained, the bolt holes of the shield tunnel bottom segments are sealed with cement mortar, and the shield tunnel bottom segments are cleaned. Then, 2 to 4 layers of self-adhesive waterproof layers are laid on the bottom surface of the shield tunnel. The laying range of the waterproof layer is equal to or higher than the design height of the concrete support platform; (3) After the waterproof layer in step (2) is laid, concrete is poured in the arc-shaped area at the bottom of the shield tunnel to form a concrete support platform with a height of 30 to 40 cm, and maintenance is performed until the concrete support platform reaches the designed strength; (4) After the concrete support platform in step (3) reaches the design strength, the steel pipe is hoisted from the shield shaft to the starting end of the shield tunnel, and the steel pipe is transported into the shield tunnel by trackless transportation equipment. After the steel pipe is transported to the right place, multiple steel brackets are installed at the bottom of the steel pipe to erect the steel pipe to the design height. The spacing between adjacent steel brackets is 3 to 5 m. The bottom of the steel bracket is fixed on the concrete support platform, and the upper part of the steel bracket is welded to the surface of the steel pipe; (5) After the steel pipe is installed in step (4), the steel pipe transportation equipment is withdrawn, and 2 to 4 layers of self-adhesive waterproof layers are continuously laid on both sides of the steel pipe, each layer of waterproof layer is seamlessly connected with the waterproof layer laid in step (2), and the laying range is an area above 1 / 3 of the shield tunnel diameter. After the waterproof layer is laid, formwork is constructed in sections on both sides of the steel pipe, steel bars are arranged, and concrete is continuously poured to form an arc-shaped concrete base covering the lower part of the steel pipe, and the steel pipe is fixed by the arc-shaped concrete base. When pouring the arc-shaped concrete base, a drainage ditch is reserved at the position of the arc-shaped concrete base near the inner wall of the tunnel.
7. The construction method for installing large-diameter steel pipes using a shield tunnel according to claim 6, characterized in that: The shield tunnels are provided with shield shafts at intervals of 2.5 to 3.5 km. The steel pipes are unloaded from the shield shafts by crawler cranes or gantry cranes and lifted into the shield tunnels. The steel pipes are spliced together by multiple sections of steel pipes with a length of 10 to 13 m. After each section of steel pipe is installed, the next section of steel pipe is installed, and adjacent steel pipes are welded to form an integral structure.
8. The construction method for installing large diameter steel pipes using a shield tunnel according to claim 6, characterized in that: In the step (4), the steel pipe is transported to the shield tunnel along the concrete support platform by a forklift and an electric flatbed truck with steering wheels. A support plate is installed at the front end of the forklift, and an arc-shaped groove with the same arc as the steel pipe is provided on the flatbed truck. The front running wheel of the flatbed truck is a universal wheel. When the steel pipe is transported, the front part of the steel pipe is placed in the arc-shaped groove of the electric flatbed truck, and a connecting piece is welded on the steel pipe to fix the flatbed truck and the steel pipe. The rear end of the steel pipe is placed on the support plate at the front end of the forklift, and a temporary support is provided inside the steel pipe. The temporary support is a steel pipe with a diameter of 60 to 90 mm arranged in a cross shape. The steel pipe is pushed forward by a forklift and transported along the concrete support platform to the installation position in the shield tunnel. After the steel pipe is transported to the right position, the height and installation position of the steel pipe are adjusted by an internal jacking device installed inside the steel pipe. After the steel pipe is in place by adjusting the four degrees of freedom of up, down, left and right, a steel bracket is installed at the bottom of the steel pipe, and the flatbed truck and forklift are removed at the same time.
9. The construction method for installing large diameter steel pipes using a shield tunnel according to claim 6, characterized in that: The pouring of the arc-shaped concrete base in step (5) is carried out by construction workers through walkway slabs erected on both sides of the steel pipe. The walkway slabs are directly laid on the walkway slab brackets. The walkway slabs are removed during the concrete pouring, and the walkway slab brackets are poured into the concrete. The arc-shaped concrete base cast in sections has a length of 5 to 7 meters per section, and an expansion joint of 1.5 to 2.5 cm is formed between two adjacent sections of the arc-shaped concrete base. Wooden boards are used to fill the expansion joints, and rubber waterstops are attached to the joints.
10. The construction method for installing large diameter steel pipes using a shield tunnel according to claim 6, characterized in that: Before the installation of the steel pipe, the outer wall of the steel pipe is coated with a fused epoxy powder anti-corrosion layer for external anti-corrosion work, and the coating thickness shall not be less than 400μm; after the steel pipe is installed in place, the inner wall of the steel pipe is cleaned and rusted, and then sprayed with cement mortar lining for internal anti-corrosion work. The cement mortar lining adopts ordinary silicate M30 cement mortar. Specifically, an axial 360-degree spraying machine is used with a high-speed 360-degree nozzle in an umbrella shape to evenly spray the mortar on the inner wall of the steel pipe. It is sprayed twice, and the thickness of the first coat is 8-12mm. After 22-26 hours of the mortar solidification, the second coat is sprayed, and its thickness is not less than 10mm. After spraying, it is manually pressed to make the surface smooth and traceless, and it is watered for maintenance after 24 hours.