A large-span steel truss floor deck without dismantling bottom formwork
Through the design of large-span steel truss floor bearing plates without dismantling, the problems of cumbersome construction and demolition process and large weight of the top beam in the existing technology are solved, and the effects of high construction efficiency, low cost and high strength are achieved. The bottom template is not Need to be removed for use as a ceiling.
Patent Information
- Application Number
- CN202010259992.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-04-03
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2040-04-03
AI Technical Summary
The existing reinforced truss bearing plates require more demolition processes during construction, which increases labor and time costs. At the same time, the weight of the top beam is large, resulting in high costs.
The large-span steel truss floor bearing plate is adopted without disassembly, including bottom formwork, steel bar truss, top beam, bottom steel bar, form frame connecting block and formwork connecting block. The concrete or mortar is poured on site, and the top beam is flipped 180° for grouting. L-shaped reinforced strips enhance the strength of the top beam and limit the concrete position. The bottom formwork does not need to be removed as a ceiling.
It reduces construction processes and improves work efficiency. The floor bearing plate has higher strength, lighter weight, lower cost and fewer processes, making it suitable for promotion and application.
Smart Images

Figure CN111364665B_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of building engineering construction, and in particular relates to a large-span steel truss floor decking plate without requiring removal of a bottom formwork. Background Art
[0002] The existing steel truss floor deck is composed of steel bars, trusses, and floor decks. The steel truss floor deck has a series of technical advantages such as fast construction speed, easy control of construction quality, and flexible structural layout. The scope of application in steel structure engineering construction is also expanding, playing an important role in improving the quality, progress and cost-effectiveness of steel structure engineering construction. During the installation of the bottom formwork of the steel truss floor deck, the two adjacent bottom formworks need to be supported at the joint. The existing support structure uses steel pipe scaffolding and steel sections for support. It takes more processes and time to build the support. After pouring concrete, the bottom formwork and steel pipe scaffolding steel support need to be removed. Although the bottom formwork can be reused, the removal process also increases the manpower and time cost, which is not worth the loss. In addition, the top beam of the truss uses square tubes or round tubes, and the upper end of the inclined support ribs must be welded to the pipe wall of the top beam. In order to weld firmly, this requires the pipe wall of the top beam to be thicker, which leads to a large weight and high cost of the entire floor deck. Summary of the invention
[0003] In order to solve the deficiencies in the prior art, the present invention provides a large-span steel truss floor deck that is easy to operate, reduces the labor intensity of workers, has high construction efficiency, is light in weight, and has high strength without requiring removal of bottom formwork.
[0004] To solve the above technical problems, the present invention adopts the following technical scheme: a large-span steel truss floor decking plate without disassembly of the bottom formwork, comprising a bottom formwork, a steel truss, a top beam, a bottom steel bar, a formwork connection block and a formwork connection block, the formwork connection block and the formwork connection block are fixed on the upper surface of the bottom formwork in a rectangular array, the length direction of the bottom formwork is the front-to-back direction, the bottom steel bar is fixedly arranged on the left and right sides of the lower part of the steel truss along the front-to-back direction, the top beam is fixedly arranged on the top of the steel truss along the front-to-back direction, the formwork connection blocks are evenly spaced along the left and right sides of the bottom formwork, and slots are provided between the corresponding adjacent formwork connection blocks and the formwork connection blocks, and between the formwork connection blocks and the formwork connection blocks, the steel bars on the left and right sides of the lower part of the steel truss are respectively assembled and connected in the slots on the corresponding sides, the left side surface of the formwork connection block on the left is flush with the left side of the bottom formwork, the left side surface of the formwork connection block on the left is provided with a positioning long groove, and the right side surface of the template connection block on the right is integrally provided with a positioning rib adapted to the positioning long groove.
[0005] The mold frame connecting block and the template connecting block are connected to the bottom template from bottom to top through countersunk screws.
[0006] Both ends of the top beam are blocked, and the cross-section of the top beam is an isosceles trapezoidal structure with an open top. The length of the upper base of the isosceles trapezoidal structure is smaller than the length of the lower base. The top of the left waist of the isosceles trapezoidal structure is first bent to the right and then downward to form a first left L-shaped reinforcing strip, and the top of the right waist of the isosceles trapezoidal structure is first bent to the left and then downward to form a first right L-shaped reinforcing strip. A gap is reserved between the right side of the first left L-shaped reinforcing strip and the left side of the first right L-shaped reinforcing strip for pouring concrete into the isosceles trapezoidal structure.
[0007] Both ends of the top beam are blocked, and the cross-section of the top beam is an isosceles trapezoidal structure with an open bottom. The length of the upper base of the isosceles trapezoidal structure is smaller than the length of the lower base. The left waist bottom of the isosceles trapezoidal structure is first bent to the right and then upward to form a second left L-shaped reinforcing strip, and the right waist bottom of the isosceles trapezoidal structure is first bent to the left and then upward to form a second right L-shaped reinforcing strip. A gap is reserved between the right side of the second left L-shaped reinforcing strip and the left side of the second right L-shaped reinforcing strip for pouring concrete into the isosceles trapezoidal structure.
[0008] The cross-section of the top beam is a U-shaped structure with an open top. The top of the left side wall of the U-shaped structure is bent first to the right and then downward to form a third left L-shaped reinforcing strip. The top of the right side wall of the U-shaped structure is bent first to the left and then downward to form a third right L-shaped reinforcing strip. A gap is reserved between the right side of the third left L-shaped reinforcing strip and the left side of the third right L-shaped reinforcing strip for pouring concrete into the U-shaped structure.
[0009] The cross-section of the top beam is a U-shaped structure with an open bottom. The bottom of the left side wall of the U-shaped structure is first bent to the right and then upward to form a fourth left L-shaped reinforcing strip. The bottom of the right side wall of the U-shaped structure is first bent to the left and then upward to form a fourth right L-shaped reinforcing strip. A gap is reserved between the right side of the fourth left L-shaped reinforcing strip and the left side of the fourth right L-shaped reinforcing strip for pouring concrete into the U-shaped structure.
[0010] With the above technical solution, the bottom formwork, steel truss, top beam, bottom steel bar, formwork connection block and formwork connection block are assembled into one in the factory, and then concrete or mortar is poured into the U-shaped structure or isosceles trapezoidal structure of the top beam (the two ends of the top beam are blocked). When pouring concrete for the isosceles trapezoidal structure and U-shaped structure with an open bottom, the top beam is turned 180° so that the opening of the isosceles trapezoidal structure faces upward and then extends into the slurry pool, and the slurry or concrete enters from the gap to directly carry out the grouting operation.
[0011] The L-shaped reinforcement strip not only enhances the strength of the top beam, but also limits the concrete or mortar poured inside the U-shaped structure or isosceles trapezoidal structure, further enhancing the connection strength with the concrete. The upper base length of the isosceles trapezoidal structure is shorter than the lower base length, which makes it easier for the concrete poured inside to form a whole with the top beam when under pressure, thereby enhancing the compression resistance of the top beam. Pouring concrete or mortar in advance inside the top beam can improve the overall compressive strength of the steel truss and make the span of the floor deck larger.
[0012] The bottom template is made of cement board, cement fiber board, magnesium oxysulfide board, calcium silicate board, fireproof decoration or various types of fireproof boards, with the smooth surface of the bottom template facing down and the rough surface of the bottom template facing up. When the present invention is assembled on site, the two adjacent bottom templates are assembled into the positioning long grooves through the positioning ribs, so that the two bottom templates are connected as a whole. Since the density of the mold frame connection block and the template connection block is relatively large, the connection strength of the two adjacent bottom templates can be ensured, and the stability of the workers standing on the bottom template for construction and after pouring concrete can be ensured. Concrete is poured on the upper surface of the bottom template, and the top beam is also poured in the concrete, which forms a cast-in-place floor slab after solidification. The bottom template does not need to be removed and is used as a ceiling. Since the present application adopts on-site casting throughout, compared with the composite floor slab (cast once in the factory and once on-site), it has fewer processes, better integrity, greater pressure-bearing strength, and during on-site hoisting operations, the weight of the hoisted components is lighter.
[0013] In summary, the present invention has a compact structure, does not need to dismantle the bottom formwork, reduces construction procedures, improves work efficiency, and has higher strength, lighter weight, and lower cost, making it easy to promote and apply in the market. BRIEF DESCRIPTION OF THE DRAWINGS
[0014] Figure 1 It is a schematic diagram of the top view of the structure of the present invention;
[0015] Figure 2 yes Figure 1 A schematic diagram of a cross-section of Embodiment 1;
[0016] Figure 3 yes Figure 1 A schematic diagram of a cross-sectional view of Embodiment 2;
[0017] Figure 4 yes Figure 1 A schematic diagram of a cross-section of Embodiment 3;
[0018] Figure 5 yes Figure 1 A schematic diagram of a cross-section of Embodiment 4;
[0019] Figure 6 It is a three-dimensional structural schematic diagram of a template connection block with a positioning long groove;
[0020] Figure 7 It is a schematic diagram of the three-dimensional structure of a template connection block with positioning edges. DETAILED DESCRIPTION
[0021] Embodiment 1: Figure 1 , Figure 2 , Figure 6 and Figure 7 As shown, a large-span steel truss floor deck without disassembly of the bottom formwork of the present invention comprises a bottom formwork 1, a steel bar truss 2, a top beam 3, a bottom steel bar 4, a formwork connection block 5 and a formwork connection block 6, wherein the formwork connection block 5 and the formwork connection block 6 are both plastic parts, and the formwork connection block 5 and the formwork connection block 6 are fixed on the upper surface of the bottom formwork 1 in a rectangular array, the length direction of the bottom formwork 1 is the front-to-back direction, the bottom steel bar 4 is fixedly arranged on the left and right sides of the lower part of the steel bar truss 2 along the front-to-back direction, the top beam 3 is fixedly arranged on the top of the steel bar truss 2 along the front-to-back direction, and the formwork connection block 5 is fixedly arranged on the top of the steel bar truss 2 along the front-to-back direction. The connecting blocks 6 are evenly spaced along the left and right sides of the bottom template 1, and slots 7 are provided between the corresponding adjacent formwork connecting blocks 5 and template connecting blocks 6, and between the formwork connecting blocks 5 and the formwork connecting blocks 5. The steel bars on the left and right sides of the lower part of the steel truss 2 are respectively assembled and connected in the slots 7 on the corresponding sides. The left side surface of the formwork connecting block 5 on the left is flush with the left side edge of the bottom template 1, and a positioning long groove 8 is provided on the left side surface of the formwork connecting block 5 on the left, and a positioning rib 9 adapted to the positioning long groove 8 is integrally provided on the right side surface of the template connecting block 6 on the right.
[0022] The mold frame connecting block 5 and the template connecting block 6 are connected to the bottom template 1 from bottom to top through countersunk screws 10 (preferably plastic parts).
[0023] Both ends of the top beam 3 are blocked, and the cross-section of the top beam 3 is an isosceles trapezoidal structure with an open top. The length of the upper base of the isosceles trapezoidal structure is smaller than the length of the lower base. The top of the left waist of the isosceles trapezoidal structure is first bent to the right and then downward to form a first left L-shaped reinforcing strip 11, and the top of the right waist of the isosceles trapezoidal structure is first bent to the left and then downward to form a first right L-shaped reinforcing strip 12. A gap is reserved between the right side of the first left L-shaped reinforcing strip 11 and the left side of the first right L-shaped reinforcing strip 12 for pouring concrete into the isosceles trapezoidal structure.
[0024] Embodiment 2: Figure 3 As shown, the difference between this embodiment and the first embodiment is that the cross-section of the top beam 3 is an isosceles trapezoidal structure with an open bottom, the left waist bottom of the isosceles trapezoidal structure is first bent to the right and then upward to form a second left L-shaped reinforcing strip 13, and the right waist bottom of the isosceles trapezoidal structure is first bent to the left and then upward to form a second right L-shaped reinforcing strip 14.
[0025] Embodiment 3: Figure 4As shown, the difference between this embodiment and embodiment one is that the cross-section of the top beam 3 is a U-shaped structure with an open top, the top of the left side wall of the U-shaped structure is first bent to the right and then bent downward to form a third left L-shaped reinforcing strip 15, and the top of the right side wall of the U-shaped structure is first bent to the left and then bent downward to form a third right L-shaped reinforcing strip 16.
[0026] Embodiment 4: Figure 5 As shown, the difference between this embodiment and embodiment one is that the cross-section of the top beam 3 is a U-shaped structure with an open bottom, the bottom of the left side wall of the U-shaped structure is first bent to the right and then upward to form a fourth left L-shaped reinforcing strip 17, and the bottom of the right side wall of the U-shaped structure is first bent to the left and then upward to form a fourth right L-shaped reinforcing strip 18.
[0027] Embodiment 5: The difference between this embodiment and embodiment 1 is that the top beam 3 is made of steel bars, round steel pipes or rectangular steel pipes. When the top beam 3 is made of steel bars, there is no need to pour concrete or mortar. When the top beam 3 is made of round steel pipes or rectangular steel pipes, the lower end of the steel pipe is blocked, and slurry or concrete is allowed to enter through the upper end buckle of the steel pipe, and the grouting operation is directly carried out. After completion, the upper end of the steel pipe is blocked.
[0028] The working process of the present invention is as follows: the bottom formwork 1, the steel bar truss 2, the top beam 3, the bottom steel bar 4, the formwork connection block 5 and the formwork connection block 6 are assembled into one in the factory, and then concrete or mortar is poured into the U-shaped structure or the isosceles trapezoidal structure (the two ends of the top beam 3 are blocked) of the top beam 3. When pouring concrete, the isosceles trapezoidal structure and the U-shaped structure with an open bottom are turned over 180 degrees so that the opening of the isosceles trapezoidal structure is facing upward and then extended into the slurry pool, and the slurry or concrete enters from the gap to directly carry out the grouting operation.
[0029] The L-shaped reinforcing strip not only plays a role in strengthening the top beam 3, but also plays a role in limiting the concrete or mortar poured inside the U-shaped structure or the isosceles trapezoidal structure, further enhancing the strength of the connection with the concrete. The upper base length of the isosceles trapezoidal structure is shorter than the lower base length, so that the concrete poured inside and the top beam 3 are more likely to form a whole when under pressure, thereby enhancing the compressive resistance of the top beam 3. Pre-pouring concrete or mortar inside the top beam 3 can improve the overall compressive strength of the steel truss 2 and make the span of the floor deck larger.
[0030] The bottom template 1 is made of cement board, cement fiber board, magnesium oxysulfide board, calcium silicate board, fireproof decoration or various types of fireproof boards, with the smooth surface of the bottom template 1 facing down and the rough surface of the bottom template 1 facing up. When the present invention is assembled on site, the two adjacent bottom templates 1 are assembled into the positioning long groove 8 through the positioning ribs 9, so that the two bottom templates 1 are connected as one. Since the density of the mold frame connection block 5 and the template connection block 6 is relatively large, the connection strength of the two adjacent bottom templates 1 can be ensured, and the stability of the workers standing on the bottom template 1 during construction and after pouring concrete can be ensured. Concrete is poured on the upper surface of the bottom template 1, and the top beam 3 is also poured in the concrete, and a cast-in-place floor slab is formed after solidification. The bottom template 1 does not need to be dismantled and is used as a ceiling. Since the present application adopts on-site casting in its entirety, compared with the composite floor slab (cast once in the factory and once on site), there are fewer processes, better integrity, greater pressure-bearing strength, and during on-site hoisting operations, the weight of the hoisted components is lighter.
[0031] This embodiment does not impose any formal limitation on the shape, material, structure, etc. of the present invention. Any simple modification, equivalent change and modification made to the above embodiment based on the technical essence of the present invention shall fall within the protection scope of the technical solution of the present invention.
Claims
1. A large-span steel truss floor deck without dismantling the bottom formwork, characterized in that: It includes a bottom formwork, a steel bar truss, a top beam, a bottom steel bar, a formwork connection block and a formwork connection block. The formwork connection block and the formwork connection block are fixed on the upper surface of the bottom formwork in a rectangular array. The length direction of the bottom formwork is the front-to-back direction. The bottom steel bar is fixedly arranged on the left and right sides of the lower part of the steel bar truss along the front-to-back direction. The top beam is fixedly arranged on the top of the steel bar truss along the front-to-back direction. The formwork connection blocks are evenly spaced along the left and right sides of the bottom formwork. Slots are provided between the corresponding adjacent formwork connection blocks and the formwork connection blocks, and between the formwork connection blocks and the formwork connection blocks. The steel bars on the left and right sides of the lower part of the steel bar truss are respectively assembled and connected in the slots on the corresponding sides. The left side surface of the formwork connection block on the left is flush with the left side of the bottom formwork. A positioning long groove is provided on the left side surface of the formwork connection block on the left. A positioning rib matching the positioning long groove is integrally provided on the right side surface of the formwork connection block on the right. Both ends of the top beam are blocked, and the cross section of the top beam is an isosceles trapezoidal structure with an open top. The length of the upper base of the isosceles trapezoidal structure is shorter than the length of the lower base. The top of the left waist of the isosceles trapezoidal structure is first bent to the right and then downward to form a first left L-shaped reinforcement strip. The top of the right waist of the isosceles trapezoidal structure is first bent to the left and then downward to form a first right L-shaped reinforcement strip. A gap is reserved between the right side of the first left L-shaped reinforcement strip and the left side of the first right L-shaped reinforcement strip for pouring concrete into the isosceles trapezoidal structure. The bottom formwork is made of cement board, cement fiber board, magnesium oxysulfate board or calcium silicate board.
2. A large-span steel truss floor deck without dismantling the bottom formwork, characterized in that: It includes a bottom formwork, a steel bar truss, a top beam, a bottom steel bar, a formwork connection block and a formwork connection block. The formwork connection block and the formwork connection block are fixed on the upper surface of the bottom formwork in a rectangular array. The length direction of the bottom formwork is the front-to-back direction. The bottom steel bar is fixedly arranged on the left and right sides of the lower part of the steel bar truss along the front-to-back direction. The top beam is fixedly arranged on the top of the steel bar truss along the front-to-back direction. The formwork connection blocks are evenly spaced along the left and right sides of the bottom formwork. Slots are provided between the corresponding adjacent formwork connection blocks and the formwork connection blocks, and between the formwork connection blocks and the formwork connection blocks. The steel bars on the left and right sides of the lower part of the steel bar truss are respectively assembled and connected in the slots on the corresponding sides. The left side surface of the formwork connection block on the left is flush with the left side of the bottom formwork. A positioning long groove is provided on the left side surface of the formwork connection block on the left. A positioning rib matching the positioning long groove is integrally provided on the right side surface of the formwork connection block on the right. Both ends of the top beam are blocked, and the cross section of the top beam is an isosceles trapezoidal structure with an open bottom. The length of the upper base of the isosceles trapezoidal structure is shorter than the length of the lower base. The left waist bottom of the isosceles trapezoidal structure is first bent to the right and then upward to form a second left L-shaped reinforcement strip. The right waist bottom of the isosceles trapezoidal structure is first bent to the left and then upward to form a second right L-shaped reinforcement strip. A gap is reserved between the right side of the second left L-shaped reinforcement strip and the left side of the second right L-shaped reinforcement strip for pouring concrete into the isosceles trapezoidal structure. The bottom formwork is made of cement board, cement fiber board, magnesium oxysulfate board or calcium silicate board.
3. A large-span steel truss floor deck without dismantling the bottom formwork, characterized in that: It includes a bottom formwork, a steel bar truss, a top beam, a bottom steel bar, a formwork connection block and a formwork connection block. The formwork connection block and the formwork connection block are fixed on the upper surface of the bottom formwork in a rectangular array. The length direction of the bottom formwork is the front-to-back direction. The bottom steel bar is fixedly arranged on the left and right sides of the lower part of the steel bar truss along the front-to-back direction. The top beam is fixedly arranged on the top of the steel bar truss along the front-to-back direction. The formwork connection blocks are evenly spaced along the left and right sides of the bottom formwork. Slots are provided between the corresponding adjacent formwork connection blocks and the formwork connection blocks, and between the formwork connection blocks and the formwork connection blocks. The steel bars on the left and right sides of the lower part of the steel bar truss are respectively assembled and connected in the slots on the corresponding sides. The left side surface of the formwork connection block on the left is flush with the left side of the bottom formwork. A positioning long groove is provided on the left side surface of the formwork connection block on the left. A positioning rib matching the positioning long groove is integrally provided on the right side surface of the formwork connection block on the right. Both ends of the top beam are blocked, and the cross section of the top beam is a U-shaped structure with an open top. The top of the left wall of the U-shaped structure is first bent to the right and then downward to form a third left L-shaped reinforcement strip, and the top of the right wall of the U-shaped structure is first bent to the left and then downward to form a third right L-shaped reinforcement strip. A gap is reserved between the right side of the third left L-shaped reinforcement strip and the left side of the third right L-shaped reinforcement strip for pouring concrete into the U-shaped structure; The bottom formwork is made of cement board, cement fiber board, magnesium oxysulfate board or calcium silicate board.
4. A large-span steel truss floor deck without dismantling the bottom formwork, characterized in that: It includes a bottom formwork, a steel bar truss, a top beam, a bottom steel bar, a formwork connection block and a formwork connection block. The formwork connection block and the formwork connection block are fixed on the upper surface of the bottom formwork in a rectangular array. The length direction of the bottom formwork is the front-to-back direction. The bottom steel bar is fixedly arranged on the left and right sides of the lower part of the steel bar truss along the front-to-back direction. The top beam is fixedly arranged on the top of the steel bar truss along the front-to-back direction. The formwork connection blocks are evenly spaced along the left and right sides of the bottom formwork. Slots are provided between the corresponding adjacent formwork connection blocks and the formwork connection blocks, and between the formwork connection blocks and the formwork connection blocks. The steel bars on the left and right sides of the lower part of the steel bar truss are respectively assembled and connected in the slots on the corresponding sides. The left side surface of the formwork connection block on the left is flush with the left side of the bottom formwork. A positioning long groove is provided on the left side surface of the formwork connection block on the left. A positioning rib matching the positioning long groove is integrally provided on the right side surface of the formwork connection block on the right. Both ends of the top beam are blocked, and the cross section of the top beam is a U-shaped structure with an open bottom. The bottom of the left wall of the U-shaped structure is first bent to the right and then upward to form a fourth left L-shaped reinforcement strip, and the bottom of the right wall of the U-shaped structure is first bent to the left and then upward to form a fourth right L-shaped reinforcement strip. A gap is reserved between the right side of the fourth left L-shaped reinforcement strip and the left side of the fourth right L-shaped reinforcement strip for pouring concrete into the U-shaped structure; The bottom formwork is made of cement board, cement fiber board, magnesium oxysulfate board or calcium silicate board.
5. A large-span steel truss floor deck without dismantling bottom formwork according to any one of claims 1 to 4, characterized in that: The mold frame connecting block and the template connecting block are connected to the bottom template from bottom to top through countersunk screws.