A variable width platform device and construction method for a hydraulic climbing formwork for rapid construction of a double-leg cable tower
The hydraulic climbing formwork widening platform device for rapid construction of double-limb cable towers has solved the problem of insufficient operating space for hydraulic climbing formwork in the construction of high-pier cable towers of bridges, enabling safe and efficient rebar binding and adaptive adjustment of tower column spacing, thus improving construction efficiency and safety.
Patent Information
- Application Number
- CN202010307764.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-04-17
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2040-04-17
AI Technical Summary
In the construction of high-pier cable towers for bridges, the variation in the spacing between the tower columns of double-limb cable towers leads to insufficient operating space for hydraulic climbing formwork. Existing technologies suffer from high safety risks, long construction periods, and low efficiency.
The hydraulic climbing formwork widening platform device, which adopts a rapid construction double-limb cable tower, includes embedded parts, wall attachment devices, vertical guide rails, hydraulic climbing formwork device, operating platform, formwork system, inclined support device, and rebar tying platform. Through inclined supports, spacing adjustment devices, and suspension bridge devices, the stability and adaptability of the platform can be adjusted.
It provides a safe and reliable environment for rebar tying, shortens the construction period, improves work efficiency, adapts to changes in tower spacing, prevents tower column alignment differences caused by asymmetrical loads, and enhances platform stability and operating space.
Smart Images

Figure CN111379227B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a variable width platform device of a hydraulic climbing formwork for quickly constructing a double-limb cable tower and a construction method, belonging to the field of bridge construction devices. Background Art
[0002] At present, the construction of high pier cable towers of bridges generally adopts hydraulic climbing formwork. When the cable tower has two legs, the distance between the tower columns increases or decreases. The formwork generally adopts hydraulic climbing formwork in combination with an external cantilever platform, and a temporary platform is used for the steel bar binding platform, which has high safety risks, long construction period and low efficiency. Summary of the invention
[0003] The purpose of the present invention is to provide a variable width platform device and a construction method for a hydraulic climbing formwork for rapid construction of a double-legged cable tower. This device is specifically designed for a large-scale construction platform device in situations where there is insufficient operating space for the hydraulic climbing formwork on the inner side of the cable tower column, the hydraulic climbing formwork has no steel bar binding platform or the platform is not sufficient to ensure the safety of steel bar binding.
[0004] In order to realize the above-mentioned technical features, the object of the present invention is achieved as follows: a variable-width platform device of a hydraulic climbing formwork for quickly constructing a double-legged cable tower, which includes an embedded part, a wall attachment device is fixedly installed on the embedded part, a vertical guide rail is fixedly installed on the outer side wall of the wall attachment device, a hydraulic climbing formwork device is installed on the vertical guide rail, an operating platform is fixedly installed on the top of the hydraulic climbing formwork device, a formwork system is installed on the top of the operating platform through a lateral sliding device, and the tower column on one side where the formwork system is located is connected to the formwork system on the other side of the double-legged tower column through a spacing adjustment device.
[0005] An oblique support device is installed between the operating platform and the hydraulic climbing formwork system. The oblique support device includes a double-threaded sleeve. The two ends of the double-threaded sleeve are respectively connected to the screws hinged on the operating platform and the hydraulic climbing formwork system through threaded cooperation.
[0006] A steel bar binding platform is fixedly installed on the top of the hydraulic climbing formwork device. The steel bar binding platform adopts a polygonal hollow skeleton structure, and a steel wire mesh is arranged on the outside of the polygonal hollow skeleton structure.
[0007] The template system is supported on the top of the operating platform through a transverse moving device, and the transverse moving device adopts a track wheel mechanism.
[0008] The spacing adjustment device includes a double V linkage device and multiple groups of pin hole sliding rod mechanisms. The two ends of the double V linkage device are respectively hingedly connected to the two sides of the double-limb tower column. One end of the pin hole sliding rod mechanism is hinged on the tower column, and the other end is connected to the template system on the other side of the double-limb tower column through a pin shaft.
[0009] The pin hole slide rod mechanism comprises a pin hole rod hinged on a tower column, on which a plurality of pin holes arranged side by side are processed, and the pin holes are connected with a pin rod slide groove fixed on the tower column on the other side by means of a latch pin.
[0010] The double V linkage device includes a double-ended T-shaped rod, and the two ends of the double-ended T-shaped rod are respectively hinged with a first connecting rod and a second connecting rod, the other end of the first connecting rod located on the same side is hinged to one of the tower columns of the double-limb tower column, and the other end of the second connecting rod located on the same side is hinged to the other tower column of the double-limb tower column.
[0011] A plurality of suspension bridge devices for connecting the two towers of the double-limb tower are installed between the two towers, and the suspension bridge device includes a bridge plate, one end of which is hingedly connected to the tower on one side through a hinged ear plate, and the top of the other end of the bridge plate is connected to a suspension bridge cable through a pull rope ear, and the other end of the suspension bridge cable is connected to the tower.
[0012] The steel bar binding platform adopts an octagonal hollow steel bar binding platform.
[0013] The method for constructing a double-legged cable tower by using a variable-width platform device of a hydraulic climbing formwork for rapidly constructing a double-legged cable tower comprises the following steps:
[0014] Step 1: Fix the wall attachment device on the embedded parts of the cast cable tower, install the vertical guide rail on the wall attachment device, and slide the hydraulic climbing formwork device on the vertical guide rail;
[0015] Step 2: Install a steel bar binding platform on the top support of the hydraulic climbing formwork device located on the outside of the cable tower, and install a formwork system on the top support of the hydraulic climbing formwork device located on the inside of the cable tower. The other end of the tower column where the formwork system is located is connected to the tower column of the other side of the cable tower through a double V linkage device and a plurality of sets of pin hole sliding rod mechanisms;
[0016] Step 3: According to the spacing of the cable towers of the double-limb tower column, adjust the extension length of the pin hole slide rod mechanism so that the formwork systems on both sides can match the spacing of the cable towers to be cast on both sides, and then lock the pins to fix the formwork systems on both sides;
[0017] Step 4: After the formwork systems on both sides are fixed, lower the suspension bridge device, and then connect the towers on both sides to cast the cable towers of this casting layer;
[0018] Step 5: After the pouring of this pouring layer is completed, the tower columns on both sides are adjusted to move closer to the middle part of the cable tower through the lateral movement device in conjunction with the pin hole sliding rod mechanism and the double V linkage device to adapt to the double-limb cable tower with a smaller upper spacing;
[0019] Step 6: Repeat steps 2 to 5 to complete the pouring construction of the next pouring layer of the cable tower until the pouring of the entire cable tower is completed.
[0020] The present invention has the following beneficial effects:
[0021] 1. The traditional steel bar binding is to use the rigid frame of the tower column to build a platform, which is slow. The present invention uses an octagonal hollow steel bar binding platform, which is light in weight, has low wind resistance, is convenient for operators to pass through, can provide a safe and reliable steel bar binding environment, avoids repeated construction of temporary operating platforms, shortens the construction period, and makes steel bar binding construction efficient.
[0022] 2. By adopting the combination of the pin hole sliding rod mechanism and the double V linkage device of the present invention, the stability of the platform is increased and it can adapt to the changes in the distance between the cable towers, so that the distance between the two tower columns can be easily adjusted, thereby solving the problem of changes in the inner side distance requirements of the cable tower columns, insufficient operating space for the hydraulic climbing formwork, and inability to symmetrically construct the two tower columns at the same time, thereby preventing asymmetric loads from being applied to the cable tower, resulting in poor tower column linearity.
[0023] 3. By adding a suspension bridge device, the width of the working platform is increased, and the platforms are connected as a whole, which reduces the number of operators running up and down and improves the work efficiency of the operators.
[0024] 4. The above-mentioned transverse shifting device can be used to adjust the lateral position of the formwork system on one side, thereby adapting to the changing requirements of the spacing between the double-legged cable towers. BRIEF DESCRIPTION OF THE DRAWINGS
[0025] The present invention will be further described below in conjunction with the accompanying drawings and embodiments.
[0026] Figure 1 It is the overall elevation layout diagram of the present invention.
[0027] Figure 2 It is the front view of the steel bar binding platform of the present invention.
[0028] Figure 3 It is a front view of the pin hole sliding rod mechanism of the present invention.
[0029] Figure 4 It is a front view of the double V linkage device of the present invention.
[0030] Figure 5 It is a front view of the suspension bridge device of the present invention.
[0031] In the figure: steel bar binding platform 1, pin hole slide rod mechanism 2, double V linkage device 3, suspension bridge device 4, formwork system 5, embedded parts 6, inclined support device 7, transverse movement device 8, operating platform 9, wall attachment device 10, vertical guide rail 11, bottom platform 12, hydraulic climbing formwork device 13, tower column 14, cable tower 15;
[0032] Pin hole rod 201, pin hole 202, pin rod slide slot 203;
[0033] A first connecting rod 301, a double-ended T-shaped rod 302, and a second connecting rod 303;
[0034] Articulated ear plate 401, bridge plate 402, suspension bridge cable 403, and pull rope eye 404. DETAILED DESCRIPTION
[0035] The embodiments of the present invention are further described below in conjunction with the accompanying drawings.
[0036] Embodiment 1:
[0037] See also Figure 1-5 A variable width platform device for a hydraulic climbing formwork for rapid construction of a double-leg cable tower comprises an embedded part 6, a wall attaching device 10 is fixedly mounted on the embedded part 6, a vertical guide rail 11 is fixedly mounted on the outer wall of the wall attaching device 10, a hydraulic climbing formwork device 13 is mounted on the vertical guide rail 11, an operating platform 9 is fixedly mounted on the top of the hydraulic climbing formwork device 13, a formwork system 5 is mounted on the top of the operating platform 9 via a lateral sliding device 8, and a tower column 14 on one side where the formwork system 5 is located is connected to the formwork system on the other side of the double-leg tower column via a spacing adjustment device. By adopting the variable width platform device of the above structure, it can be used for the casting construction of double-legged cable towers. In the specific construction process, by setting an octagonal hollow steel bar binding platform, the problem of no steel bar binding platform or insufficient steel bar platform to ensure the safety of steel bar binding operation during hydraulic climbing formwork construction is solved; by setting a spacing adjustment device on the hydraulic climbing formwork, the transformation of the conventional hydraulic climbing formwork is realized, and the requirement for changing the distance on the inner side of the cable tower column, the problem of insufficient operating space for the hydraulic climbing formwork and the inability to symmetrically construct the two-legged tower columns at the same time is solved, thereby preventing asymmetric loads from being applied to the cable tower, resulting in poor tower column linearity.
[0038] Furthermore, an oblique support device 7 is installed between the operating platform 9 and the hydraulic climbing formwork system 13, and the oblique support device 7 includes a double-threaded sleeve 7, and the two ends of the double-threaded sleeve 7 are respectively connected to the screws hinged on the operating platform 9 and the hydraulic climbing formwork system 13 through threaded matching. The above-mentioned oblique support device 7 enhances the stability and reliability of the support between the operating platform 9 and the hydraulic climbing formwork system 13, thereby ensuring the safety of the entire platform construction.
[0039] Furthermore, a steel bar tying platform 1 is fixedly installed on the top of the hydraulic climbing formwork device 13. The steel bar tying platform 1 adopts a polygonal hollow skeleton structure, and a wire mesh is arranged on the outside of the polygonal hollow skeleton structure. The steel bar tying platform 1 with the above structure can provide a steel bar tying platform during the hydraulic climbing formwork construction to ensure the safety of the steel bar tying operation. In addition, since the wire mesh is hollow on all four sides, the high-altitude wind resistance is reduced to avoid shaking caused by the heightening of the hydraulic climbing formwork; chamfered diagonal bars are added to the vertical poles of the main truss of the platform, which is arranged in an octagonal shape, which ensures the load-bearing capacity of the platform while also facilitating the passage of operators.
[0040] Furthermore, the template system 5 is supported on the top of the operating platform 9 by a transverse moving device 8, and the transverse moving device 8 adopts a track wheel mechanism. The transverse moving device 8 can be used to adjust the installation position of the template system 5, thereby adapting to the change of the tower column spacing.
[0041] Furthermore, the spacing adjustment device includes a double V linkage device 3 and multiple sets of pin hole slide rod mechanisms 2, the two ends of the double V linkage device 3 are respectively hingedly connected to the two sides of the double-limb tower column, one end of the pin hole slide rod mechanism 2 is hingedly connected to the tower column 14, and the other end is connected to the formwork system on the other side of the double-limb tower column through a pin shaft. The above-mentioned spacing adjustment device can be used to adjust the spacing between the two tower columns, thereby solving the problem of the change in the inner distance requirement of the cable tower column, insufficient operating space for the hydraulic climbing formwork, and the inability to symmetrically construct the two-limb tower columns at the same time, and preventing the asymmetric load on the cable tower from causing the tower column linear difference.
[0042] Furthermore, the pin hole slide bar mechanism 2 comprises a pin hole bar 201 hinged on the tower column 14, and a plurality of pin holes 202 arranged side by side are processed on the pin hole bar 201, and the pin holes 202 are connected to the pin bar slide groove 203 fixed on the tower column on the other side by plugging and matching through a latch. The above pin hole slide bar mechanism 2 can be used to adjust the spacing. In the specific working process, the position of the pin hole bar 201 on the pin bar slide groove 203 is adjusted to change the spacing. After the adjustment is completed, the two are locked by a latch.
[0043] Furthermore, the double V linkage device 3 includes a double-ended T-shaped rod 302, and the two ends of the double-ended T-shaped rod 302 are respectively hinged with a first connecting rod 301 and a second connecting rod 303, the other end of the first connecting rod 301 on the same side is hinged on one of the tower columns 14 of the double-limb tower column, and the other end of the second connecting rod 303 on the same side is hinged on the other tower column 14 of the double-limb tower column. The double V linkage device 3 can adapt to the change of the distance between the two, and the connection strength and stability of the two are enhanced by adopting an inclined support.
[0044] Furthermore, a plurality of suspension bridge devices 4 for connecting the two towers 14 of the double-limb tower are installed between the two towers, and the suspension bridge device 4 includes a bridge plate 402, one end of which is hingedly connected to the tower 14 on one side through a hinged ear plate 401, and the top of the other end of the bridge plate 402 is connected to a suspension bridge cable 403 through a rope lug 404, and the other end of the suspension bridge cable 403 is connected to the tower 14. The towers on both sides can be connected through the suspension bridge device 4, thereby forming a connected working platform.
[0045] Furthermore, the steel bar binding platform 1 adopts an octagonal hollow steel bar binding platform.
[0046] Embodiment 2:
[0047] The method for constructing a double-legged cable tower by using a variable-width platform device of a hydraulic climbing formwork for rapidly constructing a double-legged cable tower comprises the following steps:
[0048] Step 1: fix the wall attachment device 10 on the embedded part 6 on the cast cable tower 15, install the vertical guide rail 11 on the wall attachment device 10, and slide the hydraulic climbing formwork device 13 on the vertical guide rail 11;
[0049] Step 2: Install a steel bar binding platform 1 on the top support of the hydraulic climbing formwork device 13 located outside the cable tower 15, and install a formwork system 5 on the top support of the hydraulic climbing formwork device 13 located inside the cable tower 15. The other end of the tower column 14 where the formwork system 5 is located is connected to the tower column 14 of the cable tower 15 on the other side through a double V linkage device 3 and a plurality of sets of pin hole slide rod mechanisms 2;
[0050] Step 3: According to the spacing of the cable towers 15 of the double-limb tower column, adjust the extension length of the pin hole slide rod mechanism 2 so that the template systems 5 on both sides can match the spacing of the cable towers 15 to be cast on both sides, and then lock the latch to fix the template systems 5 on both sides;
[0051] Step 4: After the formwork systems 5 on both sides are fixed, the suspension bridge device 4 is lowered to connect the tower columns 14 on both sides, and the cable tower 15 of this pouring layer is poured;
[0052] Step 5: After the pouring of this pouring layer is completed, the tower columns 14 on both sides are adjusted to move closer to the middle part of the cable tower 15 through the lateral movement device 8 in cooperation with the pin hole slide rod mechanism 2 and the double V linkage device 3, so as to adapt to the double-limb cable tower with a smaller upper spacing;
[0053] Step 6, repeating steps 2 to 5 to complete the pouring construction of the next pouring layer of the cable tower 15, until the pouring of the entire cable tower 15 is completed.
[0054] The working principle of the present invention is:
[0055] 1. An octagonal hollow steel bar binding platform is formed by arranging a steel mesh on the upper platform of the hydraulic climbing formwork device 13, thereby solving the problem that there is no steel bar binding platform or the steel bar platform is not sufficient to ensure the safety of steel bar binding operation during hydraulic climbing formwork construction.
[0056] 2. By setting a pin hole slide rod mechanism 2 and a double V linkage device 3 on the hydraulic climbing formwork, the double-limb tower column climbing formwork platform is connected, the climbing formwork spacing is changing, and the pin hole slide rod mechanism 2 slides into place and then the pin is locked, thereby increasing the stability of the hydraulic climbing formwork.
[0057] 3. By arranging a suspension bridge device 4 in the middle, it is convenient for personnel to pass through the double-limb tower column, making the operating platform an integral whole.
Claims
1. A variable width platform device for a hydraulic climbing formwork for rapid construction of a double-limb cable tower, characterized in that: It comprises an embedded part (6), a wall attachment device (10) is fixedly mounted on the embedded part (6), a vertical guide rail (11) is fixedly mounted on the outer wall of the wall attachment device (10), a hydraulic climbing formwork device (13) is mounted on the vertical guide rail (11), an operating platform (9) is fixedly mounted on the top of the hydraulic climbing formwork device (13), a template system (5) is mounted on the top of the operating platform (9) via a lateral sliding device (8), and a tower column (14) on one side where the template system (5) is located is connected to a template system on the other side of a double-limb tower column via a spacing adjustment device; A steel bar binding platform (1) is fixedly installed on the top of the hydraulic climbing formwork device (13); the steel bar binding platform (1) adopts a polygonal hollow skeleton structure, and a steel wire mesh is arranged outside the polygonal hollow skeleton structure; The template system (5) is supported on the top of the operating platform (9) via a transverse movement device (8), and the transverse movement device (8) adopts a track wheel mechanism; The spacing adjustment device comprises a double V linkage device (3) and a plurality of sets of pin hole slide rod mechanisms (2), the two ends of the double V linkage device (3) are respectively hingedly connected to the two sides of the double-limb tower column, one end of the pin hole slide rod mechanism (2) is hingedly connected to the tower column (14), and the other end is connected to the template system on the other side of the double-limb tower column through a pin shaft; The pin hole slide rod mechanism (2) comprises a pin hole rod (201) hinged on the tower column (14), the pin hole rod (201) being processed with a plurality of pin holes (202) arranged side by side, the pin holes (202) being connected to a pin rod slide groove (203) fixed on the tower column on the other side by means of a latch pin; The double V linkage device (3) comprises a double-ended T-shaped rod (302), the two ends of the double-ended T-shaped rod (302) being hinged with a first connecting rod (301) and a second connecting rod (303) respectively, the other end of the first connecting rod (301) located on the same side being hinged to one of the tower columns (14) of the double-limb tower column, and the other end of the second connecting rod (303) located on the same side being hinged to the other tower column (14) of the double-limb tower column; A plurality of suspension bridge devices (4) for connecting the two towers (14) of the double-limb tower are installed between the two towers, and the suspension bridge devices (4) include a bridge plate (402), one end of the bridge plate (402) is hingedly connected to the tower (14) on one side through a hinged ear plate (401), and the top of the other end of the bridge plate (402) is connected to a suspension bridge cable (403) through a pull rope lifting ear (404), and the other end of the suspension bridge cable (403) is connected to the tower (14).
2. According to claim 1, a variable width platform device for a hydraulic climbing formwork for rapid construction of a double-leg cable tower, characterized in that: An oblique support device (7) is installed between the operating platform (9) and the hydraulic climbing formwork system (13), and the oblique support device (7) comprises a double-threaded sleeve, and the two ends of the double-threaded sleeve are respectively connected to screw rods hinged on the operating platform (9) and the hydraulic climbing formwork system (13) through threaded engagement.
3. According to claim 1, a variable width platform device for a hydraulic climbing formwork for rapid construction of a double-leg cable tower, characterized in that: The steel bar binding platform (1) is an octagonal hollow steel bar binding platform.
4. A method for constructing a double-legged cable tower using a variable width platform device of a hydraulic climbing formwork for rapidly constructing a double-legged cable tower according to any one of claims 1 to 3, characterized in that It includes the following steps: Step 1: fix the wall attachment device (10) on the embedded part (6) on the cast cable tower (15), install the vertical guide rail (11) on the wall attachment device (10), and slide the hydraulic climbing formwork device (13) on the vertical guide rail (11); Step 2: installing a steel bar binding platform (1) on the top support of the hydraulic climbing formwork device (13) located outside the cable tower (15), installing a formwork system (5) on the top support of the hydraulic climbing formwork device (13) located inside the cable tower (15), and connecting the other end of the tower column (14) where the formwork system (5) is located to the tower column (14) of the cable tower (15) on the other side via a double V linkage device (3) and a plurality of sets of pin hole slide rod mechanisms (2); Step 3: According to the spacing of the cable towers (15) of the double-limb tower column, the extension length of the pin hole slide rod mechanism (2) is adjusted so that the template systems (5) on both sides can match the spacing of the cable towers (15) to be cast on both sides, and then the latch is locked to fix the template systems (5) on both sides; Step 4: After the formwork systems (5) on both sides are fixed, the suspension bridge device (4) is lowered, and the tower columns (14) on both sides are connected, and the cable tower (15) of this pouring layer is poured; Step 5, after the pouring of the pouring layer is completed, the tower columns (14) on both sides are adjusted to move closer to the middle part of the cable tower (15) through the transverse movement device (8) in cooperation with the pin hole sliding rod mechanism (2) and the double V linkage device (3) to adapt to the double-limb cable tower with a smaller upper spacing; Step 6: Repeat steps 2 to 5 to complete the pouring construction of the next pouring layer of the cable tower (15), until the pouring of the entire cable tower (15) is completed.