Transition section structure of overhead pile-sheet structure and embankment and construction method thereof

By using graded gravel mixed cement-filled embankment transition section, backpressure body and conical slope structure in high-speed railway, combined with joists and sealing layers, the uneven settlement of overhead pile plate structure and embankment transition section is solved. The problem is that the smooth transition of the track and the stability of the embankment are achieved, and the filling is leaked.

CN111519477BActive Publication Date: 2024-11-12CHINA RAILWAY ERYUAN ENGINEERING GROUP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202010478199.4
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2020-05-29
Publication Date
2024-11-12
Estimated Expiration
2040-05-29

AI Technical Summary

Technical Problem

The uneven settlement problem of the transition section of the overhead pile plate structure of high-speed railways and the embankment may lead to jumping, affecting driving comfort, and the existing technology lacks applicable transition plans, resulting in soil leakage of filler filling.

Method used

Design a transition section structure between an overhead pile plate structure and an embankment, adopts a mixed filling of the embankment transition section with graded gravel and cement, combining the backpressure body and the conical slope, the joists abut the foundation, the conical slope and the side slope Adapt to the matching, ensure the stability of the embankment foundation bed and slope, and prevent soil leakage through the sealing layer to achieve a uniform transition of the track structure.

Benefits of technology

It effectively avoids the soil leakage of filler in the fill transition section, realizes a uniform transition between the overhead pile plate structure and the filling roadbed, reduces the uneven settlement at the connection between the fill embankment and the pile plate structure, and ensures the stability of the embankment transition section. Smooth transitions between sex and track.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN111519477B_ABST
    Figure CN111519477B_ABST
Patent Text Reader

Abstract

The present invention relates to the field of geotechnical engineering, and in particular to a transition section structure between an overhead pile-sheet structure and an embankment and a construction method thereof, wherein the transition section structure comprises an earth-filled embankment and a pile-sheet structure sequentially arranged along the longitudinal direction of a line, an embankment transition section is arranged near the end of the pile-sheet structure of the earth-filled embankment, the embankment transition section comprises an embankment base and slopes arranged on both sides of the embankment base, the embankment transition section is a structural member formed by a mixture of graded crushed stone and cement, a counter-pressure body is filled between the support beam and the foundation, the support beam and the counter-pressure body are both in contact with the embankment base, cone slopes are arranged on both sides of the counter-pressure body, and the cone slopes are adapted to and in contact with adjacent slopes. The transition section structure between an overhead pile-sheet structure and an embankment of the present application not only avoids soil leakage of the filler in the fill transition section, but also realizes a uniform transition between the overhead pile-sheet structure and the fill roadbed, and reduces the uneven settlement at the connection between the fill embankment and the pile-sheet structure.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of geotechnical engineering, and in particular to a transition section structure of an overhead pile-slab structure and an embankment and a construction method thereof. Background Art

[0002] As high-speed railway technology continues to develop, new structures emerge one after another. There are more and more high-speed railway structures.

[0003] As a new type of structure, the overhead pile-sheet structure has many characteristics such as small foundation treatment project volume, small footprint, small amount of filler, controllable construction quality, and is economical and environmentally friendly. It has become a research hotspot in recent years.

[0004] like Figure 1 As shown, the overhead pile-sheet structure 2 includes a bearing plate 21 and a joist 22 disposed at the bottom of the bearing plate 21, and a supporting pile 23 is connected to the bottom of the joist 22. However, the high-speed railway has very strict requirements on the uneven settlement of the transition section between the overhead pile-sheet structure and the embankment. If it is not handled properly, it may cause the vehicle to jump at the transition section, affecting the driving comfort.

[0005] The "High-Speed ​​Railway Design Code" stipulates the transition form between embankments and general structures. Since there is no fill under the piles of the overhead pile-board structure, if this transition method is used, there will be the problem of soil leakage from the fill roadbed.

[0006] These transition forms are not applicable to this new structure, and there are no other solutions to refer to. Summary of the invention

[0007] The purpose of the present invention is to provide a transition section structure of an overhead pile-sheet structure and an embankment and a construction method thereof, which can avoid leakage of filler in the fill transition section, realize uniform transition between the overhead pile-sheet structure and the fill roadbed, and reduce the uneven settlement at the connection between the fill embankment and the pile-sheet structure.

[0008] In order to achieve the above object, the technical solution adopted by the present invention is:

[0009] A transition section structure between an overhead pile-sheet structure and an embankment, comprising a pile-sheet structure and an earth-filled embankment, wherein the earth-filled embankment and the pile-sheet structure are sequentially arranged along the longitudinal direction of a line, wherein an embankment transition section is arranged near an end of the pile-sheet structure on the earth-filled embankment, wherein the embankment transition section comprises an embankment base bed and side slopes arranged on both sides of the embankment base bed, wherein the embankment transition section is a structural member formed by a mixture of graded crushed stone and cement, wherein a counter-pressure body is filled between a support beam and a foundation, wherein the support beam and the counter-pressure body are both in contact with the embankment base bed, and conical slopes are arranged on both sides of the counter-pressure body, wherein the conical slopes are adapted to and in contact with the adjacent side slopes.

[0010] The structural parts formed by mixing graded crushed stone with cement meet the following requirements: compaction coefficient k≥0.95, foundation coefficient K 30 ≥150MPa / m, dynamic deformation modulus E vd ≥50MPa.

[0011] The working surface at the top of the embankment base bed is the surface at the top of the embankment base bed for installing the railway, and the working surface at the top of the bearing plate is the surface at the top of the bearing plate for installing the railway. Since the height of the track structure on the fill embankment is inconsistent with the height of the track structure on the pile-board structure, in the transition section structure of the present application, there will be a certain height difference between the working surface at the top of the embankment base bed and the working surface at the top of the bearing plate, thereby ensuring that the track surface height of the track structure on the fill embankment section is flush with the track structure on the pile-board structure, thereby ensuring a smooth transition of the train.

[0012] The present application describes a transition section structure between an overhead pile-board structure and an embankment, wherein the fill embankment is provided with an embankment transition section near the end of the pile-board structure, and the embankment transition section is a structural member formed by a mixture of graded crushed stone and cement, thereby ensuring uniform changes in stiffness between the fill embankment and the pile-board structure and effectively reducing uneven settlement at the connection between the fill embankment and the pile-board structure.

[0013] A counter-pressure body is filled between the support beam and the foundation, and the support beam and the counter-pressure body are both in contact with the embankment base bed to prevent the embankment base bed from sliding toward the pile-board structure, thereby ensuring the stability of the embankment base bed. At the same time, cone slopes are arranged on both sides of the counter-pressure body, and the cone slopes are adapted to and in contact with the adjacent side slopes to prevent the side slopes from sliding toward the pile-board structure along the longitudinal direction of the line, thereby ensuring that they form a uniform whole with the embankment transition section and the counter-pressure body, so that the side slopes on both sides of the embankment transition section and the sides of the counter-pressure body do not leak soil, thereby ensuring the stability of the slopes. By ensuring the stability of the embankment base bed and the slopes arranged on both sides of the embankment base bed, the stability of the embankment transition section is ensured, and soil leakage toward the pile-board structure when filling the embankment transition section is avoided, thereby effectively reducing the uneven settlement at the connection between the fill embankment and the pile-board structure.

[0014] To sum up, the transition section structure between an overhead pile-board structure and an embankment described in the present application not only avoids soil leakage in the fill transition section, but also achieves a uniform transition between the overhead pile-board structure and the fill roadbed, thereby reducing the uneven settlement at the connection between the fill embankment and the pile-board structure.

[0015] The width of the embankment base is greater than the width of the bearing plate, and a closed layer is arranged on the top of the cone slope, and the closed layer is respectively in contact with the embankment base and the bearing plate.

[0016] When the width of the embankment base bed is greater than the width of the bearing plate, parts on both sides of the embankment transition section will exceed the bearing plate or the joist. At this time, the parts on both sides of the embankment transition section that exceed the bearing plate or the joist are closed by the closing layer, thereby avoiding soil leakage from the parts on both sides of the embankment transition section that exceed the bearing plate or the joist, thereby ensuring the local stability of the embankment transition section.

[0017] Preferably, the sealing layer is a structural member filled with a material having a strength greater than that of C35 concrete, so as to ensure that the sealing layer has sufficient strength and will not be destroyed by itself under the dynamic load of the train.

[0018] Preferably, the counter-pressure body and the cone slope are both structural members formed by mixing graded crushed stone and cement.

[0019] Preferably, the embankment transition section is arranged in an inverted trapezoidal shape, so that the contact surface between the embankment transition section and other parts of the fill embankment is larger and more stable.

[0020] Specifically, the length L of the top of the embankment transition section along the line direction is:

[0021] L=a+(Hh)×n, and L≥20m

[0022] Wherein, L is the length of the top of the embankment transition section along the line direction, unit: m; H is the height of the embankment base bed, unit: m; h is the thickness of the base bed surface layer at the upper part of the embankment base bed, unit: m; a is the length of the bottom of the embankment base bed along the line direction, usually 3-5m, unit: m; n is a constant, usually 2-5m, unit: m.

[0023] Preferably, the supporting piles at the bottom of the joist pass through the counter-pressure body. The counter-pressure body can not only prevent the embankment base from sliding toward the pile-board structure to ensure the stability of the embankment base, but also effectively restrain the supporting piles at the bottom of the joist to increase the stability of the supporting piles, thereby increasing the structural stability of the pile-board structure near the end of the fill embankment.

[0024] The present application also discloses a construction method for forming the transition section structure as described in the present application, which comprises the following steps:

[0025] A1. Fill the embankment transition section, the counterpressure body and the cone slope in layers until the bottom elevation of the joist;

[0026] A2. Determine the support pile hole position at the bottom of the joist on the counter-pressure body, drill holes to the designed depth of the support piles, hoist the steel cage into the hole, and pour concrete into the hole to form the support piles;

[0027] A3. After the construction of the supporting piles is completed, the construction of the joists is carried out;

[0028] A4. Carry out the construction of the bearing plate;

[0029] A5. Continue to fill the embankment transition section in layers to the top elevation of the bearing plate.

[0030] A construction method described in the present application comprises filling the embankment transition section, the counter-pressure body and the tapered slope in layers until the bottom elevation of the support beam; drilling holes in the counter-pressure body to the designed depth of the support piles, hoisting a steel cage into the holes, and pouring concrete into the holes to form the support piles. By constructing support piles on the counter-pressure body, the counter-pressure body can not only prevent the embankment base bed from sliding toward the pile-board structure to ensure the stability of the embankment base bed, but also effectively restrain the support piles at the bottom of the support beam to increase the stability of the support piles, thereby increasing the structural stability of the pile-board structure near the end of the fill embankment; thereafter, the support beam and the bearing plate are constructed, and then the embankment transition section is filled in layers to the top elevation of the bearing plate to achieve a smooth transition of the train between the fill embankment and the pile-board structure.

[0031] Preferably, a construction method described in the present application also includes step A6, which is specifically: after filling the embankment transition section to the elevation of the top surface of the bearing plate, the part of the embankment transition section that exceeds the bearing plate is closed by a closing layer, thereby avoiding soil leakage from the parts on both sides of the embankment transition section that exceed the bearing plate or the supporting beam, thereby ensuring the local stability of the embankment transition section.

[0032] Preferably, a construction method described in the present application further includes step A7, specifically: after the construction of the closed layer is completed, the cone slope is brushed to make the slope ratio of the cone slope 1:1-2, so that the slope is more stable.

[0033] Preferably, step A3 is specifically as follows: after the construction of the supporting piles is completed, the formwork of the joist is set, the top of the supporting pile is roughened, the steel cage of the joist is tied, and the embedded steel bars of the bearing plate are set, and then concrete is poured into the formwork of the joist to complete the construction of the joist.

[0034] In summary, due to the adoption of the above technical solution, the beneficial effects of the present invention are:

[0035] 1. The transition section structure of an overhead pile-sheet structure and an embankment described in the present application not only avoids soil leakage of filler in the fill transition section, but also realizes a uniform transition between the overhead pile-sheet structure and the fill roadbed, thereby reducing the uneven settlement at the connection between the fill embankment and the pile-sheet structure.

[0036] 2. In the present application, the overhead pile-plate structure and the transition section structure of the embankment are described. When the width of the embankment base bed is greater than the width of the bearing plate, the parts on both sides of the embankment transition section will exceed the bearing plate or the joist. At this time, the parts on both sides of the embankment transition section that exceed the bearing plate or the joist are closed by a closing layer, thereby avoiding soil leakage from the parts on both sides of the embankment transition section that exceed the bearing plate or the joist, thereby ensuring the local stability of the embankment transition section.

[0037] 3. In the transition section structure between an overhead pile-sheet structure and an embankment described in the present application, the supporting piles at the bottom of the joist penetrate the counter-pressure body. The counter-pressure body can not only prevent the embankment base from sliding toward the pile-sheet structure, thereby ensuring the stability of the embankment base, but also effectively constrain the supporting piles at the bottom of the joist to increase the stability of the supporting piles, thereby increasing the structural stability of the pile-sheet structure near the end of the fill embankment.

[0038] 4. A construction method described in the present application comprises filling the embankment transition section, the counter-pressure body and the tapered slope in layers until the bottom elevation of the support beam; drilling holes in the counter-pressure body to the designed depth of the support piles, hoisting a steel cage into the holes, and pouring concrete into the holes to form the support piles. By constructing support piles on the counter-pressure body, the counter-pressure body can not only prevent the embankment base bed from sliding toward the pile-board structure to ensure the stability of the embankment base bed, but also effectively restrain the support piles at the bottom of the support beam to increase the stability of the support piles, thereby increasing the structural stability of the pile-board structure near the end of the fill embankment; thereafter, the support beam and the bearing plate are constructed, and then the embankment transition section is filled in layers to the top elevation of the bearing plate to achieve a smooth transition of the train between the fill embankment and the pile-board structure.

[0039] 5. A construction method described in the present application, after filling the embankment transition section to the elevation of the top surface of the bearing plate, the portion of the embankment transition section that exceeds the bearing plate is closed by a sealing layer, thereby avoiding soil leakage from the portions on both sides of the embankment transition section that exceed the bearing plate or the support beam, thereby ensuring the local stability of the embankment transition section.

[0040] 6. A construction method described in the present application, after the construction of the closed layer is completed, the cone slope is brushed to make the slope ratio of the cone slope 1:1-2, making the slope more stable. BRIEF DESCRIPTION OF THE DRAWINGS

[0041] Figure 1 The schematic diagram of the pile-plate structure is the background technology.

[0042] Figure 2 This is a schematic top view of the structure of a transition section between an overhead pile-sheet structure and an embankment described in this application.

[0043] Figure 3 The attached Figure 2 AA section diagram in .

[0044] Figure 4 The attached Figure 3 Schematic diagram of the BB cross section (removing the track structure).

[0045] Icons: 1-Embankment; 10-Embankment transition section; 11-Embankment subgrade; 111-Subgrade surface layer; 12-Slope; 2-Pile-board structure; 21-Bearing plate; 22-Joist; 23-Support pile; 24-Counterpressure body; 25-Cone slope; 26-Enclosed layer; 3-Foundation; 4-Track structure on the earth-filled embankment section; 5-Track structure on the pile-board structure. DETAILED DESCRIPTION

[0046] The present invention will be described in detail below in conjunction with the accompanying drawings.

[0047] In order to make the purpose, technical solution and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not used to limit the present invention.

[0048] Example 1

[0049] like Figure 2-4 As shown, a transition section structure of an overhead pile-sheet structure and an embankment comprises an earth-filled embankment 1 and a pile-sheet structure 2 arranged in sequence along the longitudinal direction of the line, wherein the earth-filled embankment 1 is provided with an embankment transition section 10 near the end of the pile-sheet structure 2, and there is a height difference between the working surface at the top of the embankment base bed 11 and the working surface at the top of the bearing plate 21, so as to ensure that the track surface height of the track structure 4 on the earth-filled embankment section is flush with the track structure 5 on the pile-sheet structure, so as to ensure smooth passage of the train, and the embankment transition section 10 comprises an embankment base bed 11 and slopes 12 arranged on both sides of the embankment base bed 11, and the embankment transition section 10 is a structural member formed by mixing graded crushed stone with cement, and a counter-pressure body 24 is filled between the support beam 22 and the foundation 3, and the support beam 22 and the counter-pressure body 24 are both in contact with the embankment base bed 11, and cone slopes 25 are arranged on both sides of the counter-pressure body 24, and the cone slopes 25 are adapted to and in contact with the adjacent slopes 12. The structural parts formed by mixing graded crushed stone with cement meet the following requirements: compaction coefficient k≥0.95, foundation coefficient K 30≥150MPa / m, dynamic deformation modulus E vd ≥50MPa, the sealing layer 26 is a structural member filled with a material with a strength greater than C35 concrete, so as to ensure that the sealing layer 26 has sufficient strength and will not be damaged by itself under the dynamic load of the train, the counter-pressure body 24 and the cone slope 25 are structural members filled with graded crushed stone mixed with cement, specifically, the embankment transition section 10, the counter-pressure body 24 and the cone slope 25 are structural members filled with graded crushed stone mixed with 3% cement, which can achieve a compaction coefficient k≥0.95 and a foundation coefficient K 30 ≥150MPa / m, dynamic deformation modulus E vd ≥50MPa, the embankment transition section 10 is arranged in an inverted trapezoidal shape, so that the contact surface between the embankment transition section 10 and other parts of the fill embankment 1 is larger and more stable.

[0050] In this field, the working surface at the top of the embankment base bed 11 is the surface at the top of the embankment base bed 11 for installing the railway, and the working surface at the top of the bearing plate 21 is the surface at the top of the bearing plate 21 for installing the railway. Since the height of the track structure on the fill embankment 1 and the height of the track structure on the pile-board structure 2 are inconsistent, in the transition section structure of the present application, there will be a certain height difference between the working surface at the top of the embankment base bed 11 and the working surface at the top of the bearing plate 21, thereby ensuring that the track surface height of the track structure 4 on the fill embankment section is flush with the track structure 5 on the pile-board structure, thereby ensuring a smooth transition of the train.

[0051] Specifically, the length L of the top of the embankment transition section 10 along the line direction is:

[0052] L=a+(Hh)×n, and L≥20m

[0053] Wherein, L is the length of the top of the embankment transition section 10 along the line direction, unit: m; H is the height of the embankment base bed 11, unit: m; h is the thickness of the base bed surface layer 111 on the upper part of the embankment base bed 11, unit: m; a is the length of the bottom of the embankment base bed 11 along the line direction, usually 3-5m, unit: m; n is a constant, usually 2-5m, unit: m.

[0054] On the basis of the above, a further preferred embodiment is that the width of the embankment base 11 is greater than the width of the bearing plate 21, and a closed layer 26 is provided on the top of the conical slope 25, and the closed layer 26 is respectively in contact with the embankment base 11 and the bearing plate 21. When the width of the embankment base 11 is greater than the width of the bearing plate 21, the parts on both sides of the embankment transition section 10 will exceed the bearing plate 21 or the joist 22. At this time, the parts on both sides of the embankment transition section 10 that exceed the bearing plate 21 or the joist 22 are closed by the closed layer 26, thereby avoiding the situation where the parts on both sides of the embankment transition section 10 that exceed the bearing plate 21 or the joist 22 leak soil, thereby ensuring the local stability of the embankment transition section 10.

[0055] On the basis of the above, in a further preferred manner, the support piles 23 at the bottom of the joist 22 penetrate the counter-pressure body 24. The counter-pressure body 24 can not only prevent the embankment base bed 11 from sliding toward the pile-sheet structure 2 to ensure the stability of the embankment base bed 11, but also can effectively restrain the support piles 23 at the bottom of the joist 22 to increase the stability of the support piles 23, thereby increasing the structural stability of the pile-sheet structure 2 near the end of the fill embankment 1.

[0056] The present application describes a transition section structure between an overhead pile-sheet structure and an embankment, wherein the fill embankment 1 is provided with an embankment transition section 10 near the end of the pile-sheet structure 2, and the embankment transition section 10 is a structural member formed by a mixture of graded crushed stone and cement, thereby ensuring uniform changes in stiffness between the fill embankment 1 and the pile-sheet structure 2, and effectively reducing uneven settlement at the connection between the fill embankment 1 and the pile-sheet structure 2.

[0057] A counter-pressure body 24 is filled between the joist 22 and the foundation 3. The joist 22 and the counter-pressure body 24 are both in contact with the embankment base 11 to prevent the embankment base 11 from sliding toward the pile-sheet structure 2, thereby ensuring the stability of the embankment base 11. At the same time, cone slopes 25 are provided on both sides of the counter-pressure body 24. The cone slopes 25 are adapted to and in contact with the adjacent side slopes 12 to prevent the side slopes 12 from sliding toward the pile-sheet structure 2 along the longitudinal direction of the line, thereby ensuring the stability of the embankment base 11. 0 and the counter-pressure body 24 form a uniform whole, so that the side slopes 12 on both sides of the embankment transition section 10 and the sides of the counter-pressure body 24 do not leak soil, thereby ensuring the stability of the slopes 12. By ensuring the stability of the embankment base bed 11 and the slopes 12 arranged on both sides of the embankment base bed 11, the stability of the embankment transition section 10 is ensured, and soil leakage toward the pile-sheet structure 2 when filling the embankment transition section 10 is avoided, thereby effectively reducing the uneven settlement of the connection between the fill embankment 1 and the pile-sheet structure 2.

[0058] Beneficial effects of this embodiment: The transition section structure of an overhead pile-board structure and an embankment described in this application not only avoids soil leakage of filler in the fill transition section, but also achieves a uniform transition between the overhead pile-board structure and the fill roadbed, reducing the uneven settlement at the connection between the fill embankment 1 and the pile-board structure 2.

[0059] Example 2

[0060] like Figure 2-4 As shown, a transition section structure between a pile-sheet structure 2 and an embankment includes an embankment transition section 10 of a fill embankment 1, a counterpressure body 24 and a cone slope 25 under the pile-sheet structure 2, and a C35 concrete sealing layer 26 at the connection between the pile-sheet structure 2 and the fill roadbed. The embankment transition section 10, the counterpressure body 24 and the cone slope 25 are all filled with graded crushed stone mixed with 3% cement. Among them, the cone slope 25 can ensure that it forms a uniform whole with the embankment transition section 10 and the counterpressure body 24, ensuring that the side slopes on both sides of the embankment transition section 10 and the two sides of the counterpressure body 24 do not leak soil.

[0061] The compaction standard of graded crushed stone mixed with 3% cement meets the following requirements: compaction coefficient k ≥ 0.95, foundation coefficient K 30 ≥150MPa / m, dynamic deformation modulus E vd ≥50MPa.

[0062] The counter-pressure body 24 is in the shape of a regular trapezoid and is connected to the embankment transition section 10 to ensure that the embankment transition section 10 does not leak soil. The counter-pressure body 24 is constructed simultaneously with the embankment transition section 10, and the filling and compaction standards are the same as the embankment transition section 10, and the two form a uniform whole. The outer edge of the top of the counter-pressure body 24 and the outer edge of the supporting beam 22 are 1m apart as a drilling construction platform to facilitate the construction of the supporting piles 23. The completed counter-pressure body 24 effectively constrains the supporting piles 23 and increases the stability of the supporting piles 23. The outer slope of the counter-pressure body 24 is generally a stable slope of 1:1.5, and the slope surface is generally protected by hollow bricks with soil and vegetation, which has a good landscape effect.

[0063] The transition section structure of the pile-board structure 2 and the embankment described in this embodiment includes a cone slope 25, which is located on both sides of the counter-pressure body 24 and connected to the embankment transition section 10. The cone slope 25 is constructed synchronously to ensure that the embankment transition section 10 does not leak soil. The filling and compaction standards of the cone slope 25 are the same as those of the embankment transition section 10. The slope surface is generally protected by planting soil in hollow bricks, which has a good landscape effect.

[0064] The transition section structure of a pile-sheet structure 2 and an embankment described in this embodiment includes a C35 concrete sealing layer 26 at the connection between the pile-sheet structure 2 and the fill embankment 1. The width of the fill roadbed surface is greater than the width of the bearing plate 21 of the pile-sheet structure 2. If no measures are taken, the problem of soil leakage from the surface filler of the base bed will be faced. The setting of the sealing layer 26 can ensure that the surface filler of the base bed of the fill embankment 1 does not leak soil. The use of C35 concrete filling can ensure that the sealing layer 26 has sufficient strength to avoid damage under the dynamic load of the train.

[0065] Example 2

[0066] like Figure 2-4 As shown, a construction method described in this embodiment is used to form the transition section structure described in the embodiment, which comprises the following steps:

[0067] S1. According to the construction drawing, level the site and then carry out foundation treatment of the embankment transition section 10.

[0068] S2. Accurately determine the boundary mileage between the pile-sheet structure 2 and the embankment transition section 10, determine the toe line of the cone slope 25 and the counterpressure body 24, and mark them with white gray lines.

[0069] S3. Fill the embankment transition section 10, the counterpressure body 24 and the cone slope 25 in layers. The filling thickness is determined by test. The filler is graded crushed stone mixed with 3% cement and compacted by large machinery. For the part that cannot be compacted by the roller, a small vibrating machine is used for compaction. Fill layer by layer to the bottom elevation of the pile-sheet structure 2 support beam 22.

[0070] S4. Verify the pile position and accurately locate it. Since the outer edge of the top of the counter-pressure body 24 and the outer edge of the joist 22 are 1m apart as a drilling construction platform, normal construction can be guaranteed. After drilling to the designed depth, the steel cage is hoisted and concrete is poured at one time.

[0071] S5. After the quality inspection of the supporting piles 23 is passed, the formwork of the joist 22 is set, the top of the supporting piles 23 is roughened, the steel cage of the joist 22 is tied, and the embedded steel bars of the bearing plate 21 are set, and concrete is poured on site. When the structural strength reaches more than 75% of the design strength, the formwork is removed to complete the construction of the joist 22.

[0072] S6. After the joist 22 passes the quality inspection, set the template of the bearing plate 21, tie the steel cage inside the bearing plate 21, pour concrete on site, and remove the mold when the structural strength reaches more than 75% of the design strength to complete the construction of the bearing plate 21;

[0073] S5. Continue to roll the embankment transition section 10 to the shoulder elevation in layers. Note that in order to avoid squeezing the support piles 23, large machinery is prohibited from entering within 2m of the bearing plate. Instead, small vibrating machines should be used for rolling.

[0074] S6. After filling is completed, the shoulder and pile-slab structure 2 are sealed with C35 concrete.

[0075] S7. After the filling is completed and the cone and the counter-pressure body 24 are stable, the layout and alignment are carried out, and the side slope of the counter-pressure body 24 and the cone slope 25 are brushed. Generally, an excavator is used for brushing. The slope rate adopts a stable slope rate of 1:1.5.

[0076] S8. Complete the installation of 24 hollow bricks of the cone and the counter-pressure body from bottom to top. The hollow bricks should be installed in straight lines. After paving, cement mortar is used to grout the blocks. After paving, the hollow part of the brick is backfilled with clear topsoil, planting soil, clay soil, etc. suitable for plant growth, and then grass seeds are spread.

[0077] Beneficial effects of this embodiment: A construction method described in this application, fills the embankment transition section 10, the counter-pressure body 24 and the tapered slope 25 in layers until the bottom elevation of the joist 22; drills holes in the counter-pressure body 24 to the designed depth of the support piles 23, hoists a steel cage into the hole, and pours concrete into the hole to form the support piles 23. By constructing the support piles 23 on the counter-pressure body 24, the counter-pressure body 24 can not only prevent the embankment base bed 11 from sliding toward the pile-sheet structure 2, thereby ensuring the stability of the embankment base bed 11, but also effectively restrain the support piles 23 at the bottom of the joist 22 to increase the stability of the support piles 23, thereby increasing the strength of the pile-sheet structure 2 near the end of the fill embankment 1. The structure is stable; the joist 22 and the bearing plate 21 are then constructed, and then the embankment transition section 10 is filled in layers to the elevation of the top surface of the bearing plate 21, so as to achieve a smooth transition of the train between the fill embankment 1 and the pile-sheet structure 2; after the embankment transition section 10 is filled to the elevation of the top surface of the bearing plate 21, the part of the embankment transition section 10 that exceeds the bearing plate 21 is closed by a closing layer 26, thereby avoiding the part of the embankment transition section 10 on both sides that exceeds the bearing plate 21 or the joist 22 from leaking soil, thereby ensuring the local stability of the embankment transition section 10; after the construction of the closing layer 26 is completed, the cone slope 25 is brushed to make the slope of the cone slope 25 1:1-2, so that the slope is more stable.

[0078] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. A construction method for forming a transition section structure between an overhead pile-sheet structure and an embankment, characterized in that: The transition section structure between the overhead pile-sheet structure and the embankment comprises a pile-sheet structure (2) and an earth-filled embankment (1). The earth-filled embankment (1) and the pile-sheet structure (2) are arranged in sequence along the longitudinal direction of the line. The earth-filled embankment (1) is provided with an embankment transition section (10) near the end of the pile-sheet structure (2). The embankment transition section (10) comprises an embankment base (11) and side slopes (12) arranged on both sides of the embankment base (11). The embankment transition section (10) is a structural member formed by mixing graded crushed stone with cement. A counter-pressure body (24) is filled between the support beam (22) and the foundation (3). The support beam (22) and the counter-pressure body (24) are both in contact with the embankment base (11). Conical slopes (25) are arranged on both sides of the counter-pressure body (24). The conical slopes (25) are adapted to and in contact with the adjacent side slopes (12). The support pile (23) at the bottom of the supporting beam (22) passes through the counter-pressure body (24); The length L of the top of the embankment transition section along the line direction is: L = a + (Hh) × n, and L ≥ 20m Wherein, L is the length of the top of the embankment transition section along the line direction; H is the height of the embankment base bed; h is the thickness of the base bed surface layer at the top of the embankment base bed; a is the length of the bottom of the embankment base bed along the line direction; n is a constant, which is 2-5m; The width of the embankment base bed (11) is greater than the width of the bearing plate (21); a sealing layer (26) is provided on the top of the conical slope (25); the sealing layer (26) is respectively in contact with the embankment base bed (11) and the bearing plate (21); The construction method comprises the following steps: A1. Filling the embankment transition section (10), the counterpressure body (24) and the cone slope (25) in layers, Until the bottom elevation of the joist (22); A2. Determine the hole position of the support pile (23) at the bottom of the joist (22) on the counter-pressure body (24), drill a hole to the designed depth of the support pile (23), hoist a steel cage into the hole, and pour concrete into the hole to form the support pile (23); A3. After the construction of the support piles (23) is completed, the construction of the joist (22) is carried out; A4. The construction of the bearing plate (21) is carried out; A5. Continue to fill the embankment transition section (10) in layers to the top elevation of the bearing plate (21); A6. After the embankment transition section (10) is filled to the elevation of the top surface of the bearing plate (21), the portion of the embankment transition section (10) that exceeds the bearing plate (21) is closed by a closing layer (26).

2. A construction method according to claim 1, characterized in that: The sealing layer (26) is a structural member filled with a material having a strength greater than that of C35 concrete.

3. A construction method according to claim 1, characterized in that: The counter-pressure body (24) and the conical slope (25) are both structural members formed by mixing graded crushed stone with cement.

4. A construction method according to claim 1, characterized in that: The embankment transition section (10) is arranged in an inverted trapezoidal shape.

5. A construction method according to any one of claims 1 to 4, characterized in that: The support piles (23) at the bottom of the supporting beam (22) penetrate the counter-pressure body (24).

6. A construction method according to any one of claims 1 to 4, characterized in that: The step A7 is further included, which specifically comprises: after the construction of the sealing layer (26) is completed, the conical slope (25) is subjected to a brushing construction so that the slope ratio of the conical slope (25) is 1:1-2.

7. A construction method according to any one of claims 1 to 4, characterized in that: The step A3 specifically comprises: after the construction of the support pile (23) is completed, the template of the support beam (22) is set, the top of the support pile (23) is roughened, the steel cage of the support beam (22) is tied, and the embedded steel bars of the bearing plate (21) are set, and then concrete is poured into the template of the support beam (22) to complete the construction of the support beam (22).