A railway freight car longitudinal and transverse combined vehicle depot and its application

By adopting a vertical and horizontal vehicle depot layout scheme in railway truck depots, the problems of frequent folding times and unclean operating environment when pre-inspection and pre-repair and vehicle cleaning processes are solved, and efficient maintenance and cleaning of railway trucks are achieved. Improve the overall operating efficiency and environmental quality of the vehicle depot.

CN111994126BActive Publication Date: 2024-12-03CHINA RAILWAY SIYUAN SURVEY & DESIGN GRP CO LTD
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
CN202011056421.8
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2020-09-29
Publication Date
2024-12-03
Estimated Expiration
2040-09-29

AI Technical Summary

Technical Problem

When the pre-inspection and pre-repair and vehicle cleaning process are combined with the existing railway truck depot, there are problems such as frequent folding times, unclear operating environment and unsmooth process, which is difficult to effectively solve the needs of railway truck skins and bogies cleaning.

Method used

Adopt a vertical and horizontal vehicle depot layout scheme, including entry and exit lines, image pre-checking and retrieval library, whole-train storage lines, exchange lines, car wash lines, garage washing lines, semi-train storage lines, pre-checking pre-repair lines, pre-checking and pre-checking lines, pre-checking pre-checking lines The repair warehouse, repair line and repair garage are connected by the cross-frigeration line and turntable to improve the flexibility and efficiency of the vehicle cleaning and pre-inspection and pre-repair process of railway trucks.

Benefits of technology

Improve the maintenance efficiency of railway truck depots, solve the problem of cleaning of railway truck skins and bogies, improve the operating environment in the warehouse, realize the clever combination of vertical and horizontal lines layout, and adapt to pre-inspection and pre-repair and complete vehicles. Cleaning process requirements.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN111994126B_ABST
    Figure CN111994126B_ABST
Patent Text Reader

Abstract

The present invention discloses a railway freight car depot combining vertical and horizontal combination, including entry and exit lines, image pre-inspection and verification and preparation warehouse, full train storage line, exchange line, car washing line, car washing depot, half train storage line, pre-inspection and pre-repair line, pre-inspection and pre-repair depot, car repair line and repair depot, the entry and exit lines are respectively connected to the full train storage line and the exchange line through a turnout; the car washing line is connected to the half train storage line through a crossover line to allow the half train railway freight car split on the exchange line to enter the half train storage line; the crossover line also connects the pre-inspection and pre-repair line, the car repair line and the full train storage line respectively, the pre-inspection and pre-repair line passes through the pre-inspection and pre-repair depot, and the car repair line extends into the repair depot. The present invention can operate in the order of image pre-inspection, full train storage, car washing, half train storage, pre-inspection and pre-repair, storage inspection and maintenance, storage car out of the depot, and image verification and preparation, the process is clear and smooth, and the operation efficiency can be effectively improved. The present invention also combines the advantages of horizontal and vertical vehicle depots, with flexible process and improved maintenance efficiency.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention belongs to the field of railway freight car depots, and more specifically, relates to a railway freight car depot combined longitudinally and transversely and an application thereof. Background Art

[0002] In recent years, all railway freight car depots across the country have been carrying out the construction of pre-inspection and pre-repair facilities. The former Ministry of Railways promulgated and implemented the "Railway Freight Car Depot Repair Regulations" (Tieyun

[2012] No. 202) in early 2013. Article 2.2.1 of the regulations states: "Pre-inspection and pre-repair should be carried out before the depot repair car is put into storage." In addition, the "Railway Freight Car Equipment Design Specification" (TB10031-2009) has been implemented for 11 years, but it does not include new processes such as pre-inspection and pre-repair. China Railway Fourth Engineering Bureau is revising this specification and plans to include new processes such as pre-inspection and pre-repair. It is urgent to propose a complete railway freight car depot repair overall process flow and general layout process based on the process requirements of pre-inspection and pre-repair, image pre-inspection and verification, and the addition of outdoor cleaning of railway freight cars, as well as the analysis of the existing single horizontal layout, the longitudinal layout general layout has multiple corners, and it is difficult to adapt to new processes.

[0003] The outer skin of railway freight cars was not cleaned, and a lot of dust fell into the warehouse during the car body inspection. In addition, the bogie was only cleaned for 5 minutes on the bogie maintenance line after being removed from the car body. Due to the short cleaning time of the bogie, the water could not be controlled and dried, and the bogie washing water was spilled everywhere along the maintenance line, resulting in an unclean working environment in the warehouse.

[0004] At present, there are two layout schemes for railway freight car depots. The first one is that pre-inspection and pre-repair (as well as storage lines) are arranged in parallel with the repair garage. After pre-inspection and pre-repair, it is necessary to turn a corner to enter the repair garage. If the whole railway freight car cleaning process is added, only a wash garage can be set up on the storage line, and each car wash requires turning a corner to shunt. The second one is that pre-inspection and pre-repair and the storage line and the repair garage are arranged in parallel. This layout method adds the whole railway freight car cleaning process, and only a wash garage can be set up on the storage line. Each car wash requires pulling the car from the storage line to the pull-out line, and then turning a corner to the storage line with a wash garage. After that, it turns a corner again to pre-inspection and pre-repair, and can be directly put into storage after pre-inspection and pre-repair. The above two general layouts have many shunting corners, and at the same time, they do not solve the problem of combining the outer cleaning of railway freight cars with pre-inspection and pre-repair processes. Summary of the invention

[0005] In view of the above defects or improvement needs of the prior art, the present invention provides a railway freight car longitudinal and transverse combined vehicle section and its application, which can adapt to the section maintenance to increase pre-inspection and pre-repair, railway freight car whole vehicle cleaning process, and the semi-train storage line plays the role of caching after railway freight car cleaning or pre-inspection and pre-repair. The process is flexible and the maintenance efficiency is improved, realizing a clever combination of longitudinal and transverse combined layout processes of a railway freight car section.

[0006] To achieve the above-mentioned object, according to one aspect of the present invention, a railway freight car vertical and horizontal combined vehicle depot is provided, characterized in that it includes an entry and exit line, an image pre-inspection and verification warehouse, a full train storage line, an exchange line, a car washing line, a car washing garage, a half train storage line, a pre-inspection and pre-repair line, a pre-inspection and pre-repair warehouse, a car repair line and a car repair garage, wherein:

[0007] The entry and exit lines pass through the image pre-inspection and verification warehouse, and the entry and exit lines are respectively connected to the whole train storage line and the exchange line through a switch, the exchange line is connected to the car washing line, the car washing line passes through the car washing garage, and the car washing equipment is arranged in the car washing garage;

[0008] The car wash line is connected to the half-train storage line through a crossover line, so that the half-train railway freight cars split on the exchange line can enter the half-train storage line;

[0009] The crossover also connects the pre-inspection and pre-repair line, the repair line and the whole train storage line respectively, the pre-inspection and pre-repair line passes through the pre-inspection and pre-repair garage, and the repair line extends into the repair garage;

[0010] The full train storage line has a first straight line segment for storing a full train of railway freight cars, the half train storage line has a second straight line segment for storing a half train of railway freight cars, the pre-inspection and pre-repair line has a third straight line segment for pre-inspection and pre-repair of a half train of railway freight cars, the repair line has a fourth straight line segment for repairing a half train of railway freight cars, and the exchange line has a fifth straight line segment for storing and splitting a full train of railway freight cars, the first straight line segment, the second straight line segment, the third straight line segment, the fourth straight line segment and the fifth straight line segment are parallel to each other, and the first straight line segment, the third straight line segment and the fifth straight line segment are arranged in a horizontal row, the second straight line segment and the fourth straight line segment are arranged in a horizontal row, and the third straight line segment and the fourth straight line segment are arranged in a vertical row.

[0011] Preferably, the operations of the pre-inspection and pre-repair warehouse include: dismantling defective accessories, replacing defective car doors, adjusting and repairing the steel structure of the car body, laying wooden structure floors, disassembling pull rings, stop keys, anti-theft cover devices and / or welding and repairing the car body.

[0012] Preferably, a plurality of the whole-row car storage lines are provided, and one end of one of the whole-row car storage lines is connected to the car washing line via a switch.

[0013] Preferably, the first straight section can store no less than 54 railway freight cars.

[0014] Preferably, a plurality of the semi-train storage lines are provided, and each of the semi-train storage lines is connected to a semi-train storage main connection line via a switch, and the semi-train storage main connection line is connected to the crossover line.

[0015] Preferably, a plurality of the repair lines are provided, and each of the repair lines is connected to a main repair connection line via a switch, and the main repair connection line is connected to the crossover line.

[0016] Preferably, a plurality of the pre-inspection and pre-maintenance lines are provided, and each of the pre-inspection and pre-maintenance lines is connected to a pre-inspection and pre-maintenance main connecting line via a turnout, and the pre-inspection and pre-maintenance main connecting line is connected to the crossover line.

[0017] According to another aspect of the present invention, there is also provided an application of the longitudinal and transverse combined vehicle section of a railway freight car, characterized in that it comprises the following steps:

[0018] 1) The station shunting locomotive pulls the entire railway freight train to the entry and exit line, and the image pre-inspection and verification warehouse on the entry and exit line conduct image pre-inspection;

[0019] 2) The station shunted the locomotive to pull the entire train of railway freight cars to the exchange line, and the entire train of railway freight cars was split into two and a half trains of railway freight cars on the exchange line, and then the station shunted the locomotive back to the station;

[0020] 3) The in-section shunting locomotive pulls a half-train of railway freight cars to the car wash garage on the car wash line to clean the outer skin and bogies;

[0021] 4) The in-section shunting locomotive pulls the cleaned half-train railway freight cars through the crossover line to the half-train storage line for outer skin and internal slag cleaning;

[0022] 5) The locomotive within the section pulls the half-train of railway freight cars that have been cleared of slag to the pre-inspection and pre-repair depot on the pre-inspection and pre-repair line for pre-inspection and pre-repair;

[0023] 6) If there is a spare maintenance line in the repair garage, the locomotive in the section will pull the half-train of railway freight cars that have completed pre-inspection and pre-repair to the repair garage via the crossover line;

[0024] If there is no vacant maintenance line in the repair garage, the locomotive will pull the half-train of railway freight cars that have completed pre-inspection and pre-repair to the half-train storage line to wait for the repair garage;

[0025] 7) The locomotive is used to pull the half-train of railway freight cars that have been repaired in the repair garage to the full-train storage line;

[0026] 8) Combining two sections of half-trained railway freight cars into a complete railway freight car on the full train storage line;

[0027] 9) The station shunting locomotive pulls the entire train of railway freight cars. After the image pre-inspection and verification of the entire train of railway freight cars in the verification warehouse, the station shunting locomotive pulls the entire train of railway freight cars to the station.

[0028] In general, the above technical solutions conceived by the present invention can achieve the following beneficial effects compared with the prior art:

[0029] 1) The present invention aims at new technologies such as pre-inspection and pre-repair, as well as the drawbacks of the existing railway freight car bogie cleaning technology in the depot, and reorganizes and optimizes the railway freight car whole vehicle section repair process. The operation can be carried out in the order of image pre-inspection, whole train storage, car washing, half train storage, pre-inspection and pre-repair, storage and maintenance, storage and removal, and image verification. The process is clear and smooth, which can effectively improve the operation efficiency.

[0030] 2) The present invention combines the advantages of the horizontal and longitudinal vehicle sections, and proposes a combination of longitudinal and horizontal arrangements for railway freight car sections, that is, the pre-inspection and pre-repair line and the repair line are arranged in a longitudinal manner, the full-row storage line and the pre-repair and pre-repair line are arranged in a horizontal manner, and the half-row storage line and the repair line are arranged in a horizontal manner, and a car wash line and a car wash garage are added between the full-row storage line, the half-row storage line, and the repair garage. The use of this line layout can well solve the problem of multiple corner adjustments and unsmooth processes after the railway freight car section repairs add new processes such as pre-inspection and pre-repair, and railway freight car washing. It can also solve the problem that the site selection width does not meet the requirements of horizontal arrangement and general layout. This process layout can adapt to the addition of pre-inspection and pre-repair in the section repair, and can solve the problem of cleaning the outer skin and bogies of railway freight cars outside the warehouse, greatly improving the working environment in the warehouse. The half-row storage line serves as a cache after the railway freight car is washed or pre-inspected and repaired. The process is flexible and can improve the maintenance efficiency, realizing a clever combination of the longitudinal and horizontal arrangement processes of the railway freight car section. BRIEF DESCRIPTION OF THE DRAWINGS

[0031] Figure 1 It is a schematic diagram of the structure of the present invention;

[0032] Figure 2 It is a schematic diagram of the circuit arrangement of the present invention. DETAILED DESCRIPTION

[0033] In order to make the purpose, technical solutions and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not intended to limit the present invention. In addition, the technical features involved in the various embodiments of the present invention described below can be combined with each other as long as they do not conflict with each other.

[0034] like Figure 1 , Figure 2 As shown, a railway freight car vertical and horizontal combined vehicle depot includes an entry and exit line, an image pre-inspection and verification warehouse 1, a full train storage line 2, an exchange line 7, a car washing line, a car washing garage 3, a half train storage line 4, a pre-inspection and pre-repair line, a pre-inspection and pre-repair warehouse 5, a car repair line and a car repair garage 6, wherein:

[0035] The entry and exit lines pass through the image pre-inspection and verification warehouse 1, and the entry and exit lines are respectively connected to the whole train storage line 2 and the exchange line 7 through switches, the exchange line 7 is connected to the car washing line, and the car washing line passes through the car washing garage 3, and the car washing equipment is arranged in the car washing garage 3; the image pre-inspection and verification warehouse 1 is used to perform image pre-inspection on the whole train of railway freight cars to be repaired, and to perform image verification on the whole train of railway freight cars that have been repaired; the exchange line 7 is used to store the whole train of railway freight cars to be repaired, and to split the whole train of railway freight cars into two sections and half trains of railway freight cars, and the whole train storage line 2 is used for a whole train of railway freight cars to be repaired.

[0036] The car wash line is connected to the half-train storage line 4 through a crossover line, so that the half-train railway freight cars split at the exchange line 7 can enter the half-train storage line 4;

[0037] The crossover also connects the pre-inspection and pre-repair line, the car repair line and the whole train storage line 2 respectively. The pre-inspection and pre-repair line passes through the pre-inspection and pre-repair depot 5, and the car repair line extends into the repair depot 6. The setting of the special repair depot 6 can solve the problem of cleaning the outer skin and bogie of railway freight cars outside the depot, greatly improving the working environment in the depot. The car repair line extends into the repair depot 6, and the pre-inspection and pre-repair line passes through the pre-inspection and pre-repair depot 5. The work content of the pre-inspection and pre-repair depot 5 includes: dismantling defective accessories, replacing defective car doors, adjusting and repairing the steel structure of the car body, laying wooden structure floors, disassembling pull rings, blocking keys, anti-theft cover devices and / or car body welding and repair. Railway freight cars pull half-train railway freight cars to the car wash depot 3, half-train storage line 4, pre-inspection and pre-repair depot 5 or repair depot 6 through intra-section shunting locomotives.

[0038] The full train storage line 2 has a first straight line segment for storing a full train of railway freight cars, the half train storage line 4 has a second straight line segment for storing a half train of railway freight cars, the pre-inspection and pre-repair line has a third straight line segment for pre-inspection and pre-repair of a half train of railway freight cars, the repair line has a fourth straight line segment for repairing a half train of railway freight cars, and the exchange line 7 has a fifth straight line segment for storing and splitting a full train of railway freight cars. The first straight line segment, the second straight line segment, the third straight line segment, the fourth straight line segment and the fifth straight line segment are parallel to each other, and the first straight line segment, the third straight line segment and the fifth straight line segment are arranged in a horizontal row, the second straight line segment and the fourth straight line segment are arranged in a horizontal row, and the third straight line segment and the fourth straight line segment are arranged in a vertical row. The horizontal row refers to the layout of various related equipment inside a railway station or a transportation system parallel to the longitudinal axis (or main line) of the station and the vertical row refers to the layout of various related equipment inside a railway station or a transportation system arranged in sequence along the longitudinal axis (or main line) of the station. Generally speaking, stations or equipment arranged in a horizontal arrangement have a compact layout and are easy to manage; they occupy less land and have less engineering investment, while stations or equipment arranged in a vertical arrangement have a straight operation process and a larger operation capacity. The present invention combines the advantages of the horizontal and vertical vehicle depots, making the maintenance of railway freight cars smoother and improving the maintenance efficiency.

[0039] Furthermore, the operations of the pre-inspection and pre-repair warehouse 5 include: dismantling defective parts, replacing defective car doors, adjusting and repairing the steel structure of the car body, laying wooden structure floors, disassembling pull rings, blocking keys, anti-theft cover devices and / or car body welding repairs.

[0040] Furthermore, the whole train storage lines 2 are provided with a plurality of them, and one end of one of the whole train storage lines 2 is connected to the car washing line through a switch. The plurality of whole train storage lines 2 facilitates the storage of a plurality of railway freight cars, thereby improving the maintenance quantity and maintenance efficiency. The first straight section of the whole train storage line 2 can store no less than 54 railway freight cars.

[0041] Furthermore, the semi-train storage lines 4 are provided in plurality, and each of the semi-train storage lines 4 is connected to the semi-train storage main connection line through a turnout, and the semi-train storage main connection line is connected to the crossover. The repair lines are provided in plurality, and each of the repair lines is connected to the repair main connection line through a turnout, and the repair main connection line is connected to the crossover. The pre-inspection and pre-repair lines are provided in plurality, and each of the pre-inspection and pre-repair lines is connected to the pre-inspection and pre-repair main connection line through a turnout, and the pre-inspection and pre-repair main connection line is connected to the crossover.

[0042] According to another aspect of the present invention, there is also provided an application of the railway freight car longitudinally and transversely combined vehicle depot (a method for railway freight cars to enter and exit the vehicle depot), comprising the following steps:

[0043] 1) The station shunting locomotive pulls the entire railway freight train to the entry and exit line, and the image pre-inspection and verification warehouse 1 on the entry and exit line are performed for image pre-inspection;

[0044] 2) The station shunted the locomotive to pull the entire train of railway freight cars to the exchange line, and the entire train of railway freight cars was split into two and a half trains of railway freight cars on the exchange line, and then the station shunted the locomotive back to the station;

[0045] 3) The in-section shunting locomotive pulls a half-train of railway freight cars to the car wash garage 3 on the car wash line to clean the outer skin and bogies;

[0046] 4) The in-section shunting locomotive pulls the cleaned half-train railway freight cars through the crossover line to the half-train storage line 4 for outer skin and internal slag cleaning;

[0047] 5) The locomotive within the section pulls half of the railway freight train to the pre-inspection and pre-repair depot 5 on the pre-inspection and pre-repair line for pre-inspection and pre-repair;

[0048] 6) If there is a spare maintenance line in the repair garage 6, the locomotive in the section will pull the half-train of railway freight cars that have completed pre-inspection and pre-repair to the repair garage 6 via the crossover line;

[0049] If there is no vacant repair line in the repair garage 6, the locomotive in the section will pull the semi-train of railway freight cars that have completed pre-inspection and pre-repair to the semi-train storage line 4 to wait for the repair garage 6;

[0050] 7) The in-section shunting locomotive pulls the half-train of railway freight cars that have been repaired in the repair garage 6 to the full-train storage line 2;

[0051] 8) Combining two sections of the repaired half-train railway freight cars into a complete railway freight car on the complete train storage line 2;

[0052] 9) The station shunting locomotive pulls the entire train of railway freight cars, and after the image pre-inspection and verification library 1 performs image verification of the entire train of railway freight cars, the station shunting locomotive pulls the entire train of railway freight cars to the station.

[0053] The descriptions of the lines mentioned in the present invention, such as the entry and exit lines, the full train storage lines, the exchange lines, the car washing lines, the half train storage lines, the pre-inspection and pre-repair lines, the repair lines, the first straight segment, the second straight segment, the third straight segment, the fourth straight segment and the fifth straight segment, the half train storage main connecting line, the modified main connecting line, the pre-inspection and pre-repair main connecting line, etc. are all lines formed by rails, on which railway freight cars can run.

[0054] The image pre-inspection and verification warehouse, the car wash warehouse, and the pre-inspection and pre-repair warehouse 5 all include warehouses and equipment inside the warehouse. For example, the image pre-inspection and verification warehouse has image pre-inspection equipment and image verification equipment, the car wash warehouse 3 has car washing equipment, and the pre-inspection and pre-repair warehouse 5 has pre-inspection and pre-repair equipment.

[0055] Aiming at the actual situation that railway freight car depots have added pre-inspection and pre-repair facilities in recent years, the present invention considers improving the working environment in the depot, increasing the outdoor cleaning operation of the whole vehicle, and applying image processing technology, and proposes a new railway freight car depot repair process overall process, and applies it in actual engineering. With the purpose of reasonable layout of the overall process flow and general diagram of railway freight car depot repair, improving the working environment, improving the maintenance quality, and improving the maintenance efficiency, the process flow and general diagram are arranged smoothly, and the logistics, time flow, and space flow are reasonable.

[0056] The image pre-inspection and verification warehouse 1 of the present invention is placed on the entry and exit line as a house for installing image pre-inspection and verification equipment. The effective length of each full-train storage line 2 exceeds 780 meters. The car wash garage 3 is arranged between the full-train storage line 2 and the repair garage 6, which serves as a house for installing the washing equipment for the whole train of railway freight cars. Preferably, three half-train storage lines 4 are arranged, and the effective length of each half-train storage line 4 exceeds 450 meters. Each half-train storage line 4 can store 27 cars, which can be used as a replenishment washing line, a pre-inspection, pre-repair and repair storage line, etc.

[0057] The pre-inspection and pre-repair warehouse is equipped with pre-inspection and pre-repair equipment, including several 10t electric double-beam cranes, one maintenance trench and one beam adjusting machine to meet the needs of railway freight station maintenance and pre-inspection and pre-repair.

[0058] There are multiple car repair lines extending into the repair garage 6, and a new joint garage is built and set up in parallel with the repair garage 6. The repair garage 6 and the joint garage are arranged in a horizontal row and connected by a bogie running line. The bogie running mode adopts four bogie running lines with two in and two out. Among them, the bogie large disassembly and maintenance facilities are set on the bogie inlet line, and the large assembly and test bench is set on the bogie outlet line.

[0059] The exchange line 7 of the present invention is a parking line with an effective length exceeding 780 meters.

[0060] See also Figure 2 There is a circle of roads around the depot, and some areas are reserved as reserved lines, which can be constructed later.

[0061] The "connection" mentioned above in the present invention can be a direct connection or an indirect connection through a line and a switch.

[0062] It will be easily understood by those skilled in the art that the above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. A railway freight car longitudinal and transverse combined vehicle section, characterized in that: It includes entry and exit lines, image pre-inspection and review warehouse, full train storage line, exchange line, car wash line, car wash garage, half train storage line, pre-inspection and pre-repair line, pre-inspection and pre-repair warehouse, car repair line and repair garage, among which, The entry and exit lines pass through the image pre-inspection and verification warehouse, and the entry and exit lines are respectively connected to the whole train storage line and the exchange line through a switch, the exchange line is connected to the car washing line, the car washing line passes through the car washing garage, and the car washing equipment is arranged in the car washing garage; The car wash line is connected to the half-train storage line through a crossover line, so that the half-train railway freight cars split on the exchange line can enter the half-train storage line; The crossover also connects the pre-inspection and pre-repair line, the repair line and the whole train storage line respectively, the pre-inspection and pre-repair line passes through the pre-inspection and pre-repair garage, and the repair line extends into the repair garage; The full train storage line has a first straight line segment for storing a full train of railway freight cars, the half train storage line has a second straight line segment for storing a half train of railway freight cars, the pre-inspection and pre-repair line has a third straight line segment for pre-inspection and pre-repair of a half train of railway freight cars, the repair line has a fourth straight line segment for repairing a half train of railway freight cars, and the exchange line has a fifth straight line segment for storing and splitting a full train of railway freight cars, the first straight line segment, the second straight line segment, the third straight line segment, the fourth straight line segment and the fifth straight line segment are parallel to each other, and the first straight line segment, the third straight line segment and the fifth straight line segment are arranged in a horizontal row, the second straight line segment and the fourth straight line segment are arranged in a horizontal row, and the third straight line segment and the fourth straight line segment are arranged in a vertical row.

2. A railway freight car longitudinal and transverse combined vehicle section according to claim 1, characterized in that: The operations of the pre-inspection and pre-repair warehouse include: dismantling defective parts, replacing defective car doors, adjusting and repairing the steel structure of the car body, laying wooden structure floors, disassembling pull rings, blocking keys, anti-theft cover devices and / or welding and repairing the car body.

3. A railway freight car longitudinal and transverse combined vehicle section according to claim 1, characterized in that: There are multiple whole-row car storage lines, and one end of one of the whole-row car storage lines is connected to the car washing line through a switch.

4. A railway freight car longitudinal and transverse combined vehicle section according to claim 1, characterized in that: The first straight section can store no less than 54 railway freight cars.

5. The railway freight car longitudinal and transverse combined vehicle section according to claim 1, characterized in that: There are multiple semi-train storage lines, and each of the semi-train storage lines is connected to a semi-train storage main connection line through a switch, and the semi-train storage main connection line is connected to the crossover line.

6. The railway freight car longitudinal and transverse combined vehicle section according to claim 1, characterized in that: There are multiple repair lines, and each of the repair lines is connected to a main repair connection line through a switch, and the main repair connection line is connected to the crossover line.

7. The railway freight car longitudinal and transverse combined vehicle section according to claim 1, characterized in that: There are multiple pre-inspection and pre-maintenance lines, and each of the pre-inspection and pre-maintenance lines is connected to a pre-inspection and pre-maintenance main connecting line through a turnout, and the pre-inspection and pre-maintenance main connecting line is connected to the crossover line.

8. Application of a railway freight car longitudinal and transverse combined vehicle section as claimed in any one of claims 1 to 7, characterized in that: The following steps are involved: 1) The station shunting locomotive pulls the entire railway freight train to the entry and exit line, and the image pre-inspection and verification warehouse on the entry and exit line conduct image pre-inspection; 2) The station shunted the locomotive to pull the entire train of railway freight cars to the exchange line, and the entire train of railway freight cars was split into two and a half trains of railway freight cars on the exchange line, and then the station shunted the locomotive back to the station; 3) The in-section shunting locomotive pulls a half-train of railway freight cars to the car wash garage on the car wash line to clean the outer skin and bogies; 4) The in-section shunting locomotive pulls the cleaned half-train railway freight cars through the crossover line to the half-train storage line for outer skin and internal slag cleaning; 5) The locomotive within the section pulls the half-train of railway freight cars that have been cleared of slag to the pre-inspection and pre-repair depot on the pre-inspection and pre-repair line for pre-inspection and pre-repair; 6) If there is a spare maintenance line in the repair garage, the locomotive in the section will pull the half-train of railway freight cars that have completed pre-inspection and pre-repair to the repair garage via the crossover line; If there is no vacant maintenance line in the repair garage, the locomotive will pull the half-train of railway freight cars that have completed pre-inspection and pre-repair to the half-train storage line to wait for the repair garage; 7) The locomotive is used to pull the half-train of railway freight cars that have been repaired in the repair garage to the full-train storage line; 8) Combining two sections of half-trained railway freight cars into a complete railway freight car on the full train storage line; 9) The station shunting locomotive pulls the entire train of railway freight cars. After the image pre-inspection and verification of the entire train of railway freight cars in the verification warehouse, the station shunting locomotive pulls the entire train of railway freight cars to the station.

Citation Information

Patent Citations

  • Base structure of one warehouse line to two warehouse lines and a shunting method thereof

    CN109249941A

  • Integral layout structure for urban railway vehicle sections and joint stations

    CN202429199U

  • Rail wagon longitudinal and transverse combined vehicle section

    CN212354003U

  • Improvements in or relating to Shunting Yards for Railways.

    GB191406557A