A high efficiency waste heat boiler
By setting up a cyclone separator and filter device in front of the waste heat boiler, and setting up a high-pressure flushing nozzle and a removable filter in the boiler, the problem of reducing energy recovery efficiency caused by ash accumulation in the waste heat boiler is solved, and effective filtration of waste gas and sufficient heat is achieved Absorption, reducing air pollution.
Patent Information
- Application Number
- CN202010982946.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-09-17
- Publication Date
- 2024-11-19
- Estimated Expiration
- 2040-09-17
AI Technical Summary
The severe ash accumulation in waste heat boilers after long-term use leads to a decrease in energy recovery efficiency, and the emission of harmful substances in the waste gas leads to air pollution.
Design a high-efficiency waste heat boiler, including a cyclone separator, filter device, boiler, desulfurization device and chimney, filter waste gas through a cyclone separator and filter device, set up a high-pressure flushing nozzle to clean the dust of the heat collector plate, and set up multiple layers on the periphery of the boiler Remove the filter and support mount, and the cigarette inlet is close to the bottom and the cigarette outlet is close to the top to improve heat absorption efficiency.
Effectively remove large and small particulate matter, keep the smoke-opening pipes unobstructed, improve the heat absorption efficiency of the heat collecting plate, extend the service life of the equipment, and reduce air pollution.
Smart Images

Figure CN111998323B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of waste heat boilers, and in particular to a high-efficiency waste heat boiler. Background Art
[0002] Waste heat boilers are commonly used devices for energy recovery from industrial high-temperature exhaust gas and are used in various industrial fields. Some industrial exhaust gases contain a large number of large particle impurities. After long-term use, the collector plates in the waste heat boilers are prone to dust accumulation, which leads to reduced heat absorption efficiency. At the same time, there are a large number of harmful substances in the exhaust gas, such as acidic substances and sulfides. Direct discharge will cause air pollution. Summary of the invention
[0003] The object of the present invention is to provide a high-efficiency waste heat boiler to solve the problem that after the waste heat boiler is used for a long time, the energy recovery efficiency is reduced due to serious dust accumulation.
[0004] The present invention is achieved through the following technical solutions:
[0005] A high-efficiency waste heat boiler comprises a cyclone separator, a filtering device, a boiler, a desulfurization device, a deacidification device and a chimney which are connected in sequence. The boiler comprises a heat collecting plate water inlet, a heat collecting plate water outlet, a high-pressure water injection pipe, a sewage outlet arranged at the bottom of the boiler and a plurality of high-pressure flushing nozzles arranged on the inner wall of the upper end of the boiler for flushing the heat collecting plate. The heat collecting plate water inlet, the heat collecting plate water outlet and the high-pressure water injection pipe are all arranged on the outer wall of the boiler, and the plurality of high-pressure flushing nozzles are connected to the high-pressure water injection pipe.
[0006] By sequentially arranging a cyclone separator for filtering large particles and a filter device for filtering smaller particles in front of the smoke inlet of the boiler, clean exhaust gas can be introduced into the smoke inlet. After long-term use, the dust attached to the heat collecting plate can still be washed away by the high-pressure washing nozzle arranged on the top of the inner wall of the boiler, and the sewage after washing is discharged through the sewage outlet arranged at the bottom of the boiler.
[0007] Furthermore, a dust collection box is arranged below the cyclone separator.
[0008] Furthermore, the filtering device is provided with multiple layers of detachable filter screens.
[0009] It is convenient to replace the filter regularly to keep the smoke duct unobstructed.
[0010] Furthermore, a supporting mounting frame is arranged on the periphery of the boiler.
[0011] Furthermore, the smoke inlet of the boiler is arranged near the bottom of the boiler.
[0012] Furthermore, the smoke outlet of the boiler is arranged near the top of the boiler.
[0013] This allows the heat in the exhaust gas to be more fully absorbed by the collector plate.
[0014] Furthermore, a guide plate for preventing sewage from flowing back is provided on the smoke inlet.
[0015] Compared with the prior art, the present invention has the following advantages and beneficial effects:
[0016] 1. The invention discloses a high-efficiency waste heat boiler, which can pass clean exhaust gas into the smoke inlet by sequentially arranging a cyclone separator for filtering large particles and a filter device for filtering smaller particles in front of the smoke inlet of the boiler. After long-term use, the dust attached to the heat collecting plate can still be washed by a high-pressure washing nozzle arranged on the top of the inner wall of the boiler, and the sewage after washing is discharged through a sewage outlet arranged at the bottom of the boiler.
[0017] 2. The high-efficiency waste heat boiler of the present invention is provided with multiple layers of detachable filter screens on the filter device, so that the filter screens can be replaced regularly to keep the smoke duct unobstructed;
[0018] 3. The high-efficiency waste heat boiler of the present invention arranges the smoke inlet of the boiler near the bottom of the boiler and the smoke outlet near the top of the boiler, so that the heat in the exhaust gas can be more fully absorbed by the heat collecting plate. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0020] Figure 1 It is a schematic diagram of the structure of the present invention.
[0021] Figure 2 It is a schematic diagram of the boiler structure of the present invention.
[0022] Figure 3 It is a schematic diagram of the structure of the filtering device of the present invention.
[0023] Marks and corresponding parts names in the attached drawings:
[0024] 1-ash box, 2-cyclone separator, 3-filtering device, 4-boiler, 5-desulfurization device, 6-deacidification device, 7-chimney, 8-support mounting frame, 31-filter, 41-high-pressure water injection pipe, 42-water inlet of collector plate, 43-high-pressure flushing nozzle, 44-water outlet of collector plate, 45-drainage outlet, 46-collector plate, 47-smoke inlet, 48-smoke outlet, 471-guide plate. DETAILED DESCRIPTION
[0025] To make the purpose, technical solution and advantages of the present invention clearer, the technical solution of the present invention will be described in detail below. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all the embodiments. Based on the embodiments of the present invention, all other implementation methods obtained by ordinary technicians in this field without creative work belong to the scope of protection of the present invention.
[0026] The present invention is further described below in conjunction with the accompanying drawings, but the protection scope of the present invention is not limited to the following description.
[0027] Example 1
[0028] like Figure 1-3 As shown, a high-efficiency waste heat boiler of the present invention comprises a cyclone separator 2, a filtering device 3, a boiler 4, a desulfurization device 5, a deacidification device 6 and a chimney 7 connected in sequence, the boiler 4 comprises a heat collecting plate water inlet 42, a heat collecting plate water outlet 44, a high-pressure water injection pipe 41, a sewage outlet 45 arranged at the bottom of the boiler 4 and a plurality of high-pressure flushing nozzles 43 for flushing the heat collecting plate 46 arranged on the inner wall of the upper end of the boiler 4, the heat collecting plate water inlet 42, the heat collecting plate water outlet 44 and the high-pressure water injection pipe 41 are all arranged on the outer wall of the boiler 4, and the plurality of high-pressure flushing nozzles 43 are connected to the high-pressure water injection pipe 41.
[0029] By sequentially arranging a cyclone separator 2 for filtering large particles and a filter device 3 for filtering smaller particles in front of the smoke inlet 47 of the boiler 4, clean exhaust gas can be introduced into the smoke inlet 47. After long-term use, the dust attached to the heat collecting plate 46 can still be washed away by the high-pressure washing nozzle 43 arranged on the top of the inner wall of the boiler 4, and the sewage after washing is discharged through the sewage outlet 45 arranged at the bottom of the boiler 4.
[0030] Example 2
[0031] Based on Embodiment 1, the dust box 1 is disposed below the cyclone separator 2 .
[0032] The filtering device 3 is provided with multiple layers of detachable filter screens 31 .
[0033] It is convenient to replace the filter 31 regularly to keep the smoke duct unobstructed.
[0034] A supporting mounting frame 8 is arranged on the periphery of the boiler.
[0035] Example 3
[0036] Based on Example 2, the smoke inlet 47 of the boiler 4 is arranged near the bottom of the boiler 4 .
[0037] The smoke outlet 48 of the boiler 4 is arranged near the top of the boiler 4 .
[0038] This allows the heat in the exhaust gas to be more fully absorbed by the heat collecting plate 46 .
[0039] Example 4
[0040] Based on Example 3, a guide plate 471 for preventing sewage from flowing back is provided on the smoke inlet 47 .
[0041] The present invention is a high-efficiency waste heat boiler, which realizes the introduction of clean exhaust gas into the smoke inlet 47 by sequentially arranging a cyclone separator 2 for filtering large particles and a filter device 3 for filtering smaller particles in front of the smoke inlet 47 of the boiler 4. After long-term use, the dust attached to the heat collecting plate 46 can still be washed away by a high-pressure washing nozzle 43 arranged on the top of the inner wall of the boiler 4, and the sewage after washing is discharged through a sewage outlet 45 arranged at the bottom of the boiler 4. By arranging multiple layers of detachable filter screens on the filter device, it is convenient to regularly replace the filter screen 31 to keep the smoke duct unobstructed. By arranging the smoke inlet of the boiler near the bottom of the boiler and the smoke outlet near the top of the boiler, the heat in the exhaust gas can be more fully absorbed by the heat collecting plate 46.
[0042] The specific implementation methods described above further illustrate the objectives, technical solutions and beneficial effects of the present invention in detail. It should be understood that the above description is only a specific implementation method of the present invention and is not intended to limit the scope of protection of the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the scope of protection of the present invention.
Claims
1. A high-efficiency waste heat boiler, characterized in that: The invention comprises a cyclone separator (2), a filter device (3), a boiler (4), a desulfurization device (5), a deacidification device (6) and a chimney (7) connected in sequence, wherein a dust collecting box (1) is arranged below the cyclone separator (2), and a multi-layer detachable filter screen (31) is arranged on the filter device (3); the boiler (4) comprises a heat collecting plate water inlet (42), a heat collecting plate water outlet (44), a high-pressure water injection pipe (41), a sewage outlet (45) arranged at the bottom of the boiler (4) and a sewage outlet (46) arranged at the bottom of the boiler (4). ) is provided on the inner wall of the upper end thereof with a plurality of high-pressure flushing nozzles (43) for flushing the heat collecting plate (46); the heat collecting plate water inlet (42), the heat collecting plate water outlet (44) and the high-pressure water injection pipe (41) are all arranged on the outer wall of the boiler (4); the plurality of high-pressure flushing nozzles (43) are connected to the high-pressure water injection pipe (41); the smoke inlet (47) of the boiler (4) is arranged near the bottom of the boiler (4); and a guide plate (471) for preventing sewage from flowing back is arranged on the smoke inlet (47).
2. A high-efficiency waste heat boiler according to claim 1, characterized in that: A supporting mounting frame (8) is arranged on the periphery of the boiler.
3. The high-efficiency waste heat boiler according to claim 1, characterized in that: The smoke outlet (48) of the boiler (4) is arranged near the top of the boiler (4).
Citation Information
Patent Citations
Multilevel purifier for disacidifying using dry and wet method and for removing dust by using cloth bag
CN101112669A
Glass kiln smoke deep purification process
CN106123613A
Waste incineration waste heat boiler
CN111578248A
Heat exchanger type waste heat steam boiler
CN201697096U
High -efficient gaseous indirect heating equipment
CN204806950U