A continuous beam pushing device, use method and continuous beam construction method

By designing the structure of the automatically moving thrust block and reaction block, the low construction efficiency and safety problems of the continuous beam pushing device in the existing technology are solved, and an efficient and safe steel beam segment pushing process is realized.

CN112195795BActive Publication Date: 2024-10-01CHINA RAILWAY BRIDGE BUREAU GRP EIGHTH ENG CO LTD
View PDF 15 Cites 0 Cited by

Patent Information

Application Number
CN202011191347.0
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2020-10-30
Publication Date
2024-10-01
Estimated Expiration
2040-10-30

AI Technical Summary

Technical Problem

The existing continuous beam pushing device cannot automatically and continuously push steel beam segments, resulting in low construction efficiency and high labor costs. Steel beam segments are prone to slide downward during the pushing process, posing safety risks.

Method used

A continuous beam pushing device including a slide beam, a push jack, a thrust piece and a reaction block is designed. Through the notch and chamfer structure on the slide beam, the automatic movement of the thrust block and reaction block is realized. movement to prevent steel beam segments and pushing devices from sliding, improving construction efficiency and safety.

Benefits of technology

It improves construction efficiency, reduces labor costs, effectively prevents steel beam segments from sliding downward during the pushing process, and improves safety during the construction process.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN112195795B_ABST
    Figure CN112195795B_ABST
Patent Text Reader

Abstract

The present application relates to a continuous beam jacking device, a method of using the device and a method of constructing a continuous beam, and relates to the technical field of bridge construction, including a slideway beam, a jacking jack, a thrust piece and a reaction seat. When the thrust piece and the steel beam segment move to the left, a first thrust block in the thrust piece will be separated from a notch through a first chamfer, and after the steel beam segment moves a preset distance, the first thrust block will move downward and fall into the next notch; when the return oil of the jacking jack is moved in a direction away from the first thrust block, the first thrust block will apply a reaction force to the jacking jack, so that the jacking jack can automatically pull the reaction seat to move in a direction close to the first thrust block, and the second thrust block in the reaction seat will be separated from another notch through a second chamfer, and after the reaction seat moves a preset distance, the second thrust block will move downward and fall into the next notch. Therefore, the present application can not only improve construction efficiency and reduce labor costs, but also effectively prevent the sliding of the steel beam segment.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of bridge construction, and in particular to a continuous beam jacking device, a use method and a continuous beam construction method. Background Art

[0002] Because the negative bending moment of the support generated by the continuous beam under the action of constant live load has the effect of unloading the positive bending moment in the middle of the span, making the internal force state more uniform and reasonable, the beam height can be reduced, thereby increasing the clearance under the bridge, and it has the advantages of saving materials, high rigidity, good integrity, high overload capacity, high safety, and few bridge deck expansion joints. Therefore, continuous beams are widely used in large-span bridges. The construction methods of continuous beam bridges generally include full-span support method, cantilever method, top-pushing method and mobile formwork method. Among them, the top-pushing method is the most commonly used method in the construction of continuous beam bridges because it does not interrupt the existing traffic under the bridge, can save a lot of construction scaffolding, reduces high-altitude operations, and is safe and reliable.

[0003] In the related art, when a jacking device is used to carry out jacking construction on the steel beam segment of the erected continuous beam, since the jacking device cannot automatically and continuously jack the steel beam segment, after the jack completes a jacking operation of its own maximum stroke, it is necessary to manually push the jacking device to the left for multiple times to continue the jacking operation of the steel beam segment until the steel beam segment reaches the preset position. Therefore, it has the problems of low construction efficiency and high labor cost. In addition, if there is a slope during the jacking process, the steel beam segment may slide downward, thus causing safety problems. Summary of the invention

[0004] The embodiments of the present application provide a continuous beam pushing device, a method of use, and a method for constructing a continuous beam, so as to solve the problems in the related art of low construction efficiency and high labor costs caused by the inability of the pushing device to automatically and continuously push the steel beam segments, as well as the safety problems caused by the steel beam segments being prone to sliding downward during the pushing process.

[0005] In a first aspect, a continuous beam jacking device is provided, comprising: a slideway beam, the slideway beam being arranged on an abutment and having a plurality of notches thereon;

[0006] A jacking jack, wherein the jacking jack is arranged on the slideway beam;

[0007] A thrust piece, wherein the thrust piece is arranged on the slideway beam, one end of which is clamped on the steel beam segment, and the other end is fixedly connected to one end of the jacking jack, a first thrust block is clamped on the thrust piece, a first chamfer is arranged at the lower part of the first thrust block, the first thrust block is clamped in one of the notches and can be separated from the notch through the first chamfer;

[0008] A reaction seat, the reaction seat is arranged on the slide beam and fixedly connected to the other end of the push jack, a second thrust block is clamped on the reaction seat, a second chamfer is arranged at the lower part of the second thrust block, the second thrust block is clamped in the other notch and can be separated from the notch through the second chamfer;

[0009] Wherein, the jacking jack can push the thrust piece and drive the reaction seat to move toward the direction of the steel beam segment.

[0010] In some embodiments, a stop piece is provided on the thrust piece, and the upper portion of the first thrust block is clamped on the stop piece and can move up and down between the top of the thrust piece and the stop piece.

[0011] A pin is passed through the upper portion of the second thrust block, and the pin is located above the top surface of the reaction seat.

[0012] The jacking device also includes a guide beam bracket, which is detachably fixed to the thrust piece or the steel beam segment.

[0013] The pushing device also includes a plurality of first rollers, which are detachably fixed to the slideway beam, and the top surfaces of the first rollers are in close contact with the steel beam segment.

[0014] The pushing device also includes a plurality of first pads, which are detachably fixed on the slideway beam, and the top surfaces of the first pads are in close contact with the steel beam segment.

[0015] The pushing device also includes a pushing bracket, which includes multiple cross bars and multiple parallel columns. The two ends of the cross bar are respectively fixed to two adjacent columns. The bottoms of the multiple columns are fixed to the ground, and the tops are fixed to the bottom surface of the slide beam.

[0016] The jacking device also includes a steel corbel, one side of which is fixed to the bottom surface of the slideway beam, and the other side of which is fixed to the abutment.

[0017] In a second aspect, a method for using a continuous beam pushing device is provided, comprising the following steps:

[0018] A slideway beam provided with a plurality of notches is installed on the abutment, and a thrust piece, a jacking jack and a reaction seat which are fixedly connected in sequence are arranged on the slideway beam;

[0019] One end of the thrust piece is clamped with the steel beam segment, and the jacking jack is started, so that the thrust piece and the steel beam segment move to the left, and the first thrust block on the thrust piece is clamped in the notch or is separated from the notch through the first chamfer;

[0020] Return the oil of the push jack, so that the push jack and the reaction seat move to the left, and the second thrust block on the reaction seat is stuck in the other notch or is separated from the other notch through the second chamfer.

[0021] In a third aspect, a method for constructing a continuous beam is provided, comprising the following steps:

[0022] A slideway beam provided with a plurality of notches is installed on the abutment, and a thrust piece, a jacking jack and a reaction seat which are fixedly connected in sequence are arranged on the slideway beam;

[0023] One end of the thrust piece is clamped with the steel beam segment, and the jacking jack is started, so that the thrust piece and the steel beam segment move to the left, and the first thrust block on the thrust piece is clamped in the notch or is separated from the notch through the first chamfer;

[0024] Return the oil to the push jack, so that the push jack and the reaction seat move to the left, and the second thrust block on the reaction seat is stuck in the other notch or is separated from the other notch through the second chamfer;

[0025] Start the jacking jack again and repeat the above steps until the steel beam segment moves to the preset position, release the connection between the thrust piece and the steel beam segment, and carry out the jacking construction of the next steel beam segment.

[0026] The beneficial effects brought about by the technical solution provided in this application include: not only can the construction efficiency be improved and the labor cost be reduced, but also the steel beam segments can be effectively prevented from sliding downward during the jacking process, thereby improving the safety during the construction process.

[0027] The embodiment of the present application provides a continuous beam pushing device, a method of using and a method of constructing a continuous beam, which includes a slide beam, a pushing jack, a thrust piece and a reaction seat. Since the slide beam is provided with multiple notches, a first thrust block is clamped on the thrust piece, a first chamfer is provided at the lower portion of the first thrust block, and the first thrust block is clamped in one notch and can be detached from the notch through the first chamfer; a second thrust block is clamped on the reaction seat, a second chamfer is provided at the lower portion of the second thrust block, and the second thrust block is clamped in another notch and can be detached from the notch through the second chamfer; the two ends of the pushing jack are fixedly connected to the thrust piece and the reaction seat respectively, and can push the thrust piece and drive the reaction seat to move in the direction of the steel beam segment; when the pushing jack pushes the thrust piece, the thrust piece and the steel beam segment move together When moving to the left, the first thrust block in the thrust member will be separated from the notch through the first chamfer. After the steel beam segment moves a preset distance, the first thrust block will move downward and fall into the next notch, effectively preventing the steel beam segment and the jacking device from sliding to the right as a whole; when the return oil of the jacking jack is moved in the direction away from the first thrust block, the first thrust block will apply a reaction force to the jacking jack, so that the jacking jack can automatically pull the reaction seat to move in the direction close to the first thrust block, without the need to manually push the jacking device multiple times. At this time, the second thrust block in the reaction seat will be separated from another notch through the chamfer. After the reaction seat moves a preset distance, the second thrust block will move downward and fall into the next notch to prevent the reaction seat from moving backward. Therefore, the present application can not only improve construction efficiency and reduce labor costs, but also effectively prevent the steel beam segment from sliding downward during the jacking process, thereby improving the safety during the construction process. BRIEF DESCRIPTION OF THE DRAWINGS

[0028] In order to more clearly illustrate the technical solutions in the embodiments of the present application, the drawings required for use in the description of the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.

[0029] Figure 1 A schematic structural diagram of a continuous beam pushing device provided in an embodiment of the present application;

[0030] Figure 2 A schematic diagram of the partial structure of a continuous beam pushing device provided in an embodiment of the present application;

[0031] Figure 3 A schematic diagram of the working principle of the pushing device provided in the embodiment of the present application;

[0032] Figure 4 A schematic diagram of the structure of a thrust member provided in an embodiment of the present application;

[0033] Figure 5 for Figure 4Schematic diagram of the cross section at AA;

[0034] Figure 6 A schematic diagram of the structure of the reaction seat provided in the embodiment of the present application;

[0035] Figure 7 A schematic flow chart of a method for using a continuous beam pushing device provided in an embodiment of the present application;

[0036] Figure 8 A schematic diagram of a process flow of a continuous beam construction method provided in an embodiment of the present application;

[0037] Fig. 9 A schematic diagram of a method for constructing a continuous beam according to an embodiment of the present invention Figure 1 ;

[0038] Fig.10 A schematic diagram of a method for constructing a continuous beam according to an embodiment of the present invention Figure 2 ;

[0039] Fig.11 A schematic diagram of a method for constructing a continuous beam according to an embodiment of the present invention Figure 3 ;

[0040] Fig.12 A schematic diagram of a method for constructing a continuous beam according to an embodiment of the present invention Figure 4 ;

[0041] Fig.13 A schematic diagram of a method for constructing a continuous beam according to an embodiment of the present invention Figure 5 ;

[0042] Fig.14 A schematic diagram of a method for constructing a continuous beam according to an embodiment of the present invention Figure 6 ;

[0043] Fig.15 A schematic diagram of a method for constructing a continuous beam according to an embodiment of the present invention Figure 7 .

[0044] In the figure: 1- slideway beam, 1A- slot, 2- thrust piece, 21- first thrust block, 211- first chamfer, 22- cut-off piece, 3- reaction seat, 31- second thrust block, 311- pin shaft, 312- second chamfer, 4- push jack, 5- guide beam bracket, 6- first roller, 7- first cushion block, 8- push bracket, 81- cross bar, 82- column, 83- enlarged foundation, 9- steel corbel, 10- second roller, 11- second cushion block, 12- weight block, 13- steel beam segment, 14- abutment. DETAILED DESCRIPTION

[0045] In order to make the purpose, technical solution and advantages of the embodiments of the present application clearer, the technical solution in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of this application.

[0046] The embodiments of the present application provide a continuous beam pushing device, a method of use, and a method for constructing a continuous beam, which can solve the problems in the related art of low construction efficiency and high labor costs caused by the inability of the pushing device to automatically and continuously push the steel beam segments, as well as the safety problems caused by the steel beam segments being prone to sliding downward during the pushing process.

[0047] See also Figure 1 and Figure 2 As shown, the embodiment of the present application provides a continuous beam jacking device, including a slideway beam 1, a thrust piece 2, a reaction seat 3 and a jacking jack 4. The slideway beam 1 is arranged on the abutment 14, and a plurality of slots 1A with the same diameter are evenly spaced thereon; the jacking jack 4 is arranged on the slideway beam 1, one end of which is welded or bolted to the thrust piece 2, and the other end is welded or bolted to the reaction seat 3. The jacking jack 4 can push the thrust piece 2 and drive the reaction seat 3 to move in the direction of the steel beam segment 13; the thrust piece 2 is arranged on the slideway beam 1, and one end of which is clamped on the steel beam segment 13. A first thrust block 21 is clamped on the thrust member 2, and the first thrust block 21 can move up and down along the thrust member 2. A first chamfer 211 is provided at the lower portion thereof. The first thrust block 21 is clamped in a slot 1A and can be separated from the slot 1A through the first chamfer 211; a reaction seat 3 is provided on the slide beam 1, and a second thrust block 31 is clamped on the reaction seat 3. The second thrust block 31 can move up and down along the reaction seat 3. A second chamfer 312 is provided at the lower portion thereof. The second thrust block 31 is clamped in another slot 1A and can be separated from the slot 1A through the second chamfer 312.

[0048] See also Figure 2 and Figure 3As shown, when the jacking jack 4 pushes the thrust member 2 so that the thrust member 2 and the steel beam segment 13 move to the left together, the first thrust block 21 in the thrust member 2 will be separated from the notch 1A through the first chamfer 211, and after the steel beam segment 13 moves a preset distance, the first thrust block 21 will move downward and fall into the next notch 1A, effectively preventing the steel beam segment 13 and the jacking device from sliding to the right as a whole; then the jacking jack 4 is moved away from the first thrust block 21 by returning the oil, and the first thrust block 21 will apply a reaction force to the jacking jack 4, so that the jacking jack 4 can automatically pull the reaction seat 3 toward Move in the direction close to the first thrust block 21. At this time, the second thrust block 31 in the reaction seat 3 will disengage from the other slot 1A through the second chamfer 312. After the reaction seat 3 moves a preset distance, the second thrust block 31 will move downward and fall into the next slot 1A to prevent the reaction seat 3 from moving backward. Until the steel beam segment 13 moves to the designed position, there is no need to manually push the jacking device multiple times. Therefore, the present application can not only improve construction efficiency and reduce labor costs, but also effectively prevent the steel beam segment 13 from sliding downward during the jacking process, thereby improving safety during construction.

[0049] Preferably, see Figure 4 and Figure 5 As shown, the cross section of the thrust piece 2 is an I-shape, on which a cut-off piece 22 is provided. The upper part of the first thrust block 21 is clamped on the cut-off piece 22 and can move up and down between the top of the thrust piece 2 and the cut-off piece 22, thereby preventing the first thrust block 21 from falling off the thrust piece 2.

[0050] Preferably, see Figure 6 As shown, a pin shaft 311 is passed through the upper portion of the second thrust block 31 , and the pin shaft 311 is located above the top surface of the reaction seat 3 , which can prevent the second thrust block 31 from falling off from the reaction seat 3 .

[0051] Preferably, the pushing device also includes a guide beam bracket 5, which can be detachably fixed on the thrust piece 2 or the steel beam segment 13. The guide beam bracket 5 is light in weight, which can reduce the bending moment exerted on the steel beam segment 13 during the pushing process, thereby ensuring the stability of the steel beam segment 13 and reducing the possibility of instability of the continuous beam.

[0052] Preferably, the pushing device also includes a plurality of first rollers 6, which are detachably fixed on the slide beam 1, and the top surfaces of the first rollers 6 are in close contact with the steel beam segment 13. Since the friction force on the slide beam 1 is relatively large, the pushing device needs to use a relatively large pushing force to push the steel beam segment 13 to the left. When the steel beam segment 13 is placed on the first roller 6 and moved by the first roller 6, the pushing device can push the steel beam segment 13 to the left with a relatively small pushing force, thereby extending the service life of the pushing jack 4.

[0053] Preferably, the pushing device also includes a plurality of first pads 7, which are detachably fixed on the slide beam 1, and whose top surfaces are in close contact with the steel beam segment 13, and can withstand part of the force transmitted by the steel beam segment 13, thereby reducing the force transmitted to the slide beam 1, thereby reducing the bending moment and shear force on the slide beam 1, and ensuring the stability of the slide beam 1.

[0054] Preferably, the pushing device also includes a pushing bracket 8, which is arranged on the ground and has a top fixed to the bottom surface of the slide beam 1. The pushing bracket 8 includes multiple cross bars 81 and multiple parallel columns 82. The two ends of the cross bar 81 are respectively fixed to two adjacent columns 82. The bottoms of the multiple columns 82 are fixed to the ground through an enlarged foundation 83, and the tops are fixed to the bottom surface of the slide beam 1, which can further improve the stability of the slide beam 1.

[0055] Preferably, the jacking device also includes a steel corbel 9, one side of the steel corbel 9 is fixed to the bottom surface of the slide beam 1, and the other side is fixed to the abutment 14. The steel corbel 9 can provide a reaction force for the slide beam 1, that is, the thrust of the jacking jack 4 on the reaction seat 3 can be transmitted to the slide beam 1, the steel corbel 9 and the abutment 14 in sequence through the reaction seat 3, and then a reaction force is provided to the slide beam 1 through the abutment 14. The reaction force can offset part of the vertical force transmitted to the slide beam 1 by the steel beam segment 13, thereby reducing the vertical force applied to the slide beam 1, thereby reducing the bending moment and shear force applied to the slide beam 1, improving its bearing capacity performance, and thus improving the stability and safety of the slide beam 1.

[0056] Preferably, a third chamfer is provided on the slot 1A, which is beneficial to reducing the friction between the first chamfer 211, the second chamfer 312 and the slot 1A. The jacking device can push the steel beam segment 13 to the left using a smaller jacking force, thereby extending the service life of the jacking jack 4.

[0057] See also Figure 7 As shown, the embodiment of the present application also provides a method for using a continuous beam pushing device, comprising the following steps:

[0058] S1: Install the slideway beam 1 provided with a plurality of notches 1A on the abutment 14 , and arrange the thrust piece 2 , the jacking jack 4 and the reaction seat 3 which are fixedly connected in sequence on the slideway beam 1 .

[0059] S2: one end of the thrust piece 2 is clamped with the steel beam segment 13, and the jacking jack 4 is started, so that the thrust piece 2 and the steel beam segment 13 move to the left, and the first thrust block 21 on the thrust piece 2 is clamped in the notch 1A or is separated from the notch 1A through the first chamfer 211.

[0060] S3: Return the oil to the push jack 4 so that the push jack 4 and the reaction seat 3 move leftward, and the second thrust block 31 on the reaction seat 3 is stuck in the other notch 1A or is separated from the other notch 1A through the second chamfer 312 .

[0061] like Figure 8 As shown, the embodiment of the present application also provides a construction method of a continuous beam, comprising the following steps:

[0062] S1: Install the slideway beam 1 provided with a plurality of notches 1A on the abutment 14 , and arrange the thrust piece 2 , the jacking jack 4 and the reaction seat 3 which are fixedly connected in sequence on the slideway beam 1 .

[0063] S2: one end of the thrust piece 2 is clamped with the steel beam segment 13, and the jacking jack 4 is started, so that the thrust piece 2 and the steel beam segment 13 move to the left, and the first thrust block 21 on the thrust piece 2 is clamped in the notch 1A or is separated from the notch 1A through the first chamfer 211.

[0064] S3: Return the oil to the push jack 4 so that the push jack 4 and the reaction seat 3 move leftward, and the second thrust block 31 on the reaction seat 3 is stuck in the other notch 1A or is separated from the other notch 1A through the second chamfer 312 .

[0065] S4: Start the pushing jack 4 again and repeat the above steps until the steel beam segment 13 moves to the preset position, release the connection between the thrust piece 2 and the steel beam segment 13, and push the next steel beam segment 13.

[0066] Among them, the specific construction steps of the continuous beam construction method are as follows:

[0067] See also Fig. 9 As shown, a thrust bracket 8 is set up and pre-stressed, and a second roller 10 and a second pad 11 are installed at the designed positions of all pier cap beams and abutment 14 caps; the slideway beam 1 is installed on the thrust bracket 8 and the abutment 14, and the thrust piece 2, the thrust jack 4 and the reaction seat 3 that are fixedly connected in sequence are installed at the designed positions on the slideway beam 1, and the lower part of the first thrust block 21 on the thrust piece 2 is clamped on a slot 1A, and the lower part of the second thrust block 31 on the reaction seat 3 is clamped on another slot 1A; a plurality of first rollers 6 and a plurality of first pads 7 are installed on the slideway beam 1, and the guide beam bracket 5 is placed on the first roller 6 and the first pad 7, and one end of the thrust piece 2 is in close contact with both sides of the guide beam bracket 5.

[0068] See also Fig.10As shown, the push jack 4 pushes the thrust member 2, so that the guide beam bracket 5 and the thrust member 2 move to the left together, and the first thrust block 21 is separated from the slot 1A through the first chamfer 211. After the guide beam bracket 5 moves to the left by a preset distance, the first thrust block 21 moves downward and is stuck in the next slot 1A; the push jack 4 is returned to the oil, so that the push jack 4 and the reaction seat 3 move to the left, and the second thrust block 31 is separated from another slot 1A through the second chamfer 312, and the reaction seat After the guide beam support 5 moves to the left by a preset distance, the second thrust block 31 moves downward and is locked in the next notch 1A to prevent the pushing device from sliding backward as a whole; the pushing jack 4 is started again and the above steps are repeated until the guide beam support 5 moves to the preset position, the connection between the thrust member 2 and the guide beam support 5 is released, and a second cushion block 11 is added under the first roller 6 or the guide beam support 5 is pushed up on the pier cap beam by a jack, so that the deflection value of the front end of the guide beam support 5 reaches the designed value. In the pushing process, the first cushion block 7 and the first roller 6 need to be removed in time when they are encountered, and only the first roller 6 on the end of the slideway beam 1 and the first cushion block 7 under the guide beam support 5 are retained.

[0069] See also Fig.11 As shown, the removed first pad 7 is continued to be installed on the slideway beam 1, and the first steel beam segment 13 is placed on the first pad 7, and the first steel beam segment 13 is bolted to the guide beam bracket 5; the second pad 11 under the first roller 6 and the first pad 7 under the guide beam bracket 5 are removed, and the thrust piece 2 is in close contact with the first steel beam segment 13.

[0070] See also Fig.12 As shown, the guide beam support 5 and the first steel beam segment 13 are pushed to the left by 12 m (the specific pushing method is similar to the pushing method of the guide beam support 5). During the pushing process, the first cushion block 7 is removed in time when encountered.

[0071] See also Fig.13 As shown, after the guide beam support 5 and the first steel beam segment 13 are moved to the left by 12m, the thrust piece 2, the pushing jack 4 and the reaction seat 3 are moved to the right by 12m as a whole, the removed first cushion block 7 is continued to be installed on the slideway beam 1, and the second steel beam segment 13 is placed on the first cushion block 7; the first steel beam segment 13 is welded to the second steel beam segment 13 and the weld is checked until it meets the design requirements, and two ballast blocks 12 with a specification of 5t are set at the rear end position of the second steel beam segment 13; the thrust piece 2 is brought into close contact with the second steel beam segment 13, and the second steel beam segment 13 is pushed to move to the left by 12m along the slideway beam 1. During the pushing process, the first cushion block 7 is removed in time when encountered.

[0072] See also Fig.14 and Fig.15As shown, after the second steel beam segment 13 moves 12m to the left, the thrust piece 2, the jacking jack 4 and the reaction seat 3 are moved rightward by 12m as a whole, the first cushion block 7 that has been removed is continued to be installed on the slideway beam 1, and the third steel beam segment 13 is placed on the first cushion block 7; the second steel beam segment 13 is welded with the third steel beam segment 13 and the weld is checked until the design requirements are met, and a ballast block 12 at the rear end position of the second steel beam segment 13 is removed, and the remaining ballast block 12 is moved to the third steel beam segment 13; the thrust piece 2 is closely contacted with the third steel beam segment 13, and the third steel beam segment 13 is pushed to move 12m to the left along the slideway beam 1. During the pushing process, the first cushion block 7 is removed in time. Among them, when the front end of the guide beam support 5 is about to reach the top of the P8 pier, the maximum cantilever state of the steel beam push in this span is reached.

[0073] Repeat the above steps until all steel beam segments 13 are erected.

[0074] In the description of the present application, it should be noted that the terms "upper", "lower", etc. indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present application and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present application. Unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be an indirect connection through an intermediate medium, or it can be a connection between the two elements. For those of ordinary skill in the art, the specific meanings of the above terms in the present application can be understood according to the specific circumstances.

[0075] It should be noted that, in this application, relational terms such as "first" and "second" are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of further restrictions, the elements defined by the sentence "comprise a ..." do not exclude the presence of other identical elements in the process, method, article or device including the elements.

[0076] The above description is only a specific implementation of the present application, so that those skilled in the art can understand or implement the present application. Various modifications to these embodiments will be apparent to those skilled in the art, and the general principles defined herein can be implemented in other embodiments without departing from the spirit or scope of the present application. Therefore, the present application will not be limited to the embodiments shown herein, but will conform to the widest range consistent with the principles and novel features applied for herein.

Claims

1. A continuous beam pushing device, characterized in that: include: A slideway beam (1), the slideway beam (1) being arranged on a bridge abutment (14), and having a plurality of notches (1A) thereon, wherein the notches (1A) are provided with a third chamfer; A push jack (4), wherein the push jack (4) is arranged on the slideway beam (1); A thrust member (2), the thrust member (2) being arranged on the slideway beam (1), one end of which is clamped on the steel beam segment (13), and the other end of which is fixedly connected to one end of the jacking jack (4), the thrust member (2) being clamped on a first thrust block (21), the lower part of the first thrust block (21) being provided with a first chamfer (211), the first thrust block (21) being clamped in one of the slots (1A) and being able to be separated from the slot (1A) through the first chamfer (211); A reaction seat (3), the reaction seat (3) being arranged on the slideway beam (1) and fixedly connected to the other end of the push jack (4), a second thrust block (31) being clamped on the reaction seat (3), a second chamfer (312) being provided at the lower portion of the second thrust block (31), the second thrust block (31) being clamped in another of the slots (1A) and being able to be separated from the slot (1A) through the second chamfer (312), a pin shaft (311) being passed through the upper portion of the second thrust block (31), the pin shaft (311) being located above the top surface of the reaction seat (3); The jacking jack (4) can push the thrust member (2) and drive the reaction seat (3) to move in the direction of the steel beam segment (13).

2. A continuous beam pushing device according to claim 1, characterized in that: The thrust member (2) is provided with a stop member (22), the upper portion of the first thrust block (21) is clamped on the stop member (22) and can move up and down between the top of the thrust member (2) and the stop member (22).

3. A continuous beam pushing device according to claim 1, characterized in that: The jacking device further comprises a guide beam bracket (5), and the guide beam bracket (5) is detachably fixed on the thrust member (2) or the steel beam segment (13).

4. A continuous beam pushing device according to claim 1, characterized in that: The pushing device further comprises a plurality of first rollers (6), wherein the plurality of first rollers (6) are detachably fixed to the slideway beam (1), and the top surfaces of the first rollers (6) are in close contact with the steel beam segment (13).

5. A continuous beam pushing device according to claim 1, characterized in that: The pushing device further comprises a plurality of first pads (7), wherein the plurality of first pads (7) are detachably fixed on the slideway beam (1), and the top surfaces of the first pads (7) are in close contact with the steel beam segment (13).

6. A continuous beam pushing device according to claim 1, characterized in that: The pushing device further comprises a pushing bracket (8), wherein the pushing bracket (8) comprises a plurality of cross bars (81) and a plurality of parallel upright columns (82), wherein the two ends of the cross bar (81) are respectively fixed to two adjacent upright columns (82), the bottoms of the plurality of upright columns (82) are all fixed to the ground, and the tops are all fixed to the bottom surface of the slideway beam (1).

7. A continuous beam pushing device according to claim 1, characterized in that: The jacking device also includes a steel bracket (9), one side of the steel bracket (9) is fixed to the bottom surface of the slideway beam (1), and the other side is fixed to the abutment (14).

8. A method for using a continuous beam pushing device, characterized in that: The following steps are involved: A slideway beam (1) provided with a plurality of notches (1A) is installed on an abutment (14), and a thrust piece (2), a thrust jack (4) and a reaction seat (3) which are fixedly connected in sequence are arranged on the slideway beam (1); One end of the thrust piece (2) is clamped to the steel beam segment (13), and the jacking jack (4) is started, so that the thrust piece (2) and the steel beam segment (13) move to the left, and the first thrust block (21) on the thrust piece (2) is clamped in the notch (1A) or is separated from the notch (1A) through the first chamfer; The oil of the push jack (4) is returned, so that the push jack (4) and the reaction seat (3) move leftward, and the second thrust block (31) on the reaction seat (3) is stuck in the other notch (1A) or is separated from the other notch (1A) through the second chamfer.

9. A method for constructing a continuous beam, characterized in that: The following steps are involved: A slideway beam (1) provided with a plurality of notches (1A) is installed on an abutment (14), and a thrust piece (2), a thrust jack (4) and a reaction seat (3) which are fixedly connected in sequence are arranged on the slideway beam (1); One end of the thrust piece (2) is clamped to the steel beam segment (13), and the jacking jack (4) is started, so that the thrust piece (2) and the steel beam segment (13) move to the left, and the first thrust block (21) on the thrust piece (2) is clamped in the notch (1A) or is separated from the notch (1A) through the first chamfer; Returning oil to the push jack (4) causes the push jack (4) and the reaction seat (3) to move leftward, and the second thrust block (31) on the reaction seat (3) is stuck in the other notch (1A) or is separated from the other notch (1A) through the second chamfer; The jacking jack (4) is started again and the above steps are repeated until the steel beam segment (13) moves to the preset position, the connection between the thrust piece (2) and the steel beam segment (13) is released, and the jacking construction of the next steel beam segment (13) is carried out.

Citation Information

Patent Citations

  • Pushing system and method for factory method segment prefabrication construction

    CN103711986A

  • Cable crane tower self-balancing system and installing method thereof

    CN107673239A

  • Rolling friction walkingjacking and pushing device for bridge segment installation

    CN109736212A

  • Bridge jacking and pushing swiveling system and method

    CN110468739A

  • Power device of C-shaped hook for hanging basket walking

    CN111155448A