Instantaneous pipe heater and manufacturing method thereof

By using the tubular heating element with energized heating in the instant heater directly placed on the outer wall of the insulated non-metal water pipe, combined with the inter-groove and conical cooperation, the scale problem and structural complexity are solved, and simple installation and high efficiency are achieved Heat transfer.

CN112524794BActive Publication Date: 2024-12-06GUANGDONG OUYAGUAN METAL NEW MATERIAL CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202011362374.X
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2020-11-27
Publication Date
2024-12-06
Estimated Expiration
2040-11-27

AI Technical Summary

Technical Problem

Traditional instant heating pipes are made of conductive metal materials, and are prone to scale in the tube cavity, and have a complex structure and difficult winding process, which affects the heat transfer effect.

Method used

The tubular heating element that is powered and heated is directly placed on the outer wall of the water pipe. The water pipe is made of insulated non-metallic material. The tubular heating element is divided into an energized heating line through the inter-groove, and combined with a conical fit, simplifying the structure and installation process.

Benefits of technology

It effectively avoids the formation of scale, ensures drinking water sanitation, simplifies structure and installation, and improves heat transfer effect and production efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN112524794B_ABST
    Figure CN112524794B_ABST
Patent Text Reader

Abstract

The present invention discloses an instant heating pipe heater, comprising a water pipe and a tubular heating element, wherein the tubular heating element comprises a first conductive end, a second conductive end and a tubular heating wall, wherein a groove divides the tubular heating wall into an energized heating circuit connected between the first conductive end and the second conductive end, and the tubular heating element is sleeved and tightly attached to the outer wall of the water pipe. The heater is not easy to form scale, and the drinking water is hygienic, and the structure is simple and the installation is easy. The present invention also discloses a manufacturing method of the instant heating pipe heater, wherein the first step is to prepare the water pipe first; the second step is to use a laser grooving device to cut the required grooves on the tubular heating wall, and the grooves process the tubular heating wall into an energized heating circuit connected to the first conductive end and the second conductive end to obtain the required tubular heating element; the third step is to sleeve the tubular heating element obtained in the second step tightly on the outer wall of the water pipe. The above-mentioned manufacturing method is simple to process and has high production efficiency.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of instant heating type pipe heaters, in particular to an instant heating type pipe heater and a manufacturing method thereof. Background Art

[0002] At present, instant hot water dispensers have entered more and more homes or offices. The most important component of an instant hot water dispenser is the instant hot heating tube. Traditional instant hot heating tubes, such as China Utility Model Patent No.: 2019200951537, Name: An instant hot heating tube and water dispenser, Authorization Announcement Date: November 22, 2019, include a heating conduit, the outer side of the heating conduit is provided with a first insulating layer, the outer side of the first insulating layer is provided with a heating body and a second insulating layer, and the second insulating layer is distributed between the heating bodies; the heating body is a spiral heating wire, the second insulating layer is a spirally coiled insulator, and the heating body and the second insulating layer are coiled on the outer wall of the first insulating layer at intervals; the instant hot heating tube, by providing a second insulating layer between the heating bodies, avoids some safety hazards caused by long-term use of the heating tube.

[0003] However, the instant heating tube has the following disadvantages: (1) Since a first insulating layer is provided on the outside of the heating tube to prevent contact and conduction between the heating body and the heating tube, the heating tube is made of a conductive metal material, and scale is easily generated in the tube cavity (inside) thereof, thereby polluting the drinking water; (2) Furthermore, the first insulating layer is provided between the outside of the heating tube and the heating body, and the heating wire and the second insulating layer are provided on the surface of the first insulating layer in an intermittently coiled manner. The structure is complex, the coiling process is difficult, and the heating wire is difficult to be in close contact with the first insulating layer. The heat transfer effect is easily affected by the gap between the heating wire and the first insulating layer. Summary of the invention

[0004] The purpose of the present invention is to overcome the shortcomings of the above-mentioned prior art and to provide an instant pipe heater which is not easy to form scale in the pipe to ensure the hygiene of drinking water and has a simple structure and is easy to install.

[0005] Another object of the present invention is to provide a method for manufacturing an instant heating pipe heater which is simple to process and has high production efficiency.

[0006] The object of the present invention is achieved in that:

[0007] An instant hot pipe heater comprises a water pipe, characterized in that it also comprises a tubular heating element that generates heat when powered on, the tubular heating element comprising a first conductive end, a second conductive end and a tubular heating wall, the first conductive end and the second conductive end are respectively connected to the tubular heating wall, a groove is formed on the tubular heating wall, the groove divides the tubular heating wall into an electrically powered heating circuit connected between the first conductive end and the second conductive end, the tubular heating element is sheathed and closely attached to the outer wall of the water pipe; in this instant hot pipe heater, the tubular heating element generates heat when powered on The heat body is directly sheathed and tightly attached to the outer wall of the water pipe, and the water pipe is made of insulating non-metallic material, so there is no need to worry about the contact and conduction between the tubular heating body and the water pipe. The water pipe made of non-metallic material is not easy to produce scale inside the pipe, thereby ensuring the hygiene of drinking water. Furthermore, the tubular heating wall of the tubular heating body is divided into an energized heating circuit connected between the first conductive end and the second conductive end by the intermediate groove, so that the entire tubular heating body is directly sheathed and tightly attached to the outer wall of the water pipe, and there is no need to be arranged on the outer wall of the water pipe in a spiral winding manner. The structure is simple and the installation is easy.

[0008] The present invention can also be solved by the following technical measures:

[0009] Furthermore, the tubular heating element includes a short front section, a long middle section and a short rear section, the first conductive end and the second conductive end constitute the short front section and the short rear section respectively, the tubular heating wall constitutes the tubular long middle section, and the intermediate groove is arranged on the tubular long middle section; since the first conductive end and the second conductive end are integrally formed with the long middle section of the middle "tubular heating wall", the intermediate groove can be formed directly by slotting the long middle section, so that the processing and forming of the entire tubular heating element is simple and quick, and the overall connection strength is large.

[0010] Furthermore, the short front section and the short rear section of the tubular heating element are respectively bent to have integrally connected sheet-like conductive ends, which respectively constitute the first conductive end and the second conductive end. In this way, there is no need to additionally connect (add) the first conductive end and the second conductive end, and the process is simpler.

[0011] Furthermore, a conical section with an outer diameter gradually increasing is provided on the outer wall of the water pipe, and the inner cavity of the tubular heating element is a conical cavity, which is adapted to the shape of the conical section. The tubular heating element is inserted through the conical cavity and tightly attached to the conical section of the outer wall of the water pipe. The conical matching of the water pipe and the tubular heating element makes it easier to insert the two and further improves the close connection between the two.

[0012] Furthermore, the water pipe includes a water inlet and a water outlet, the end of the conical section with a smaller outer diameter is the water inlet, and the end with a larger outer diameter is the water outlet; this scheme of a narrow water inlet section and a wide water outlet section allows the narrower water inlet to have a certain pressure, providing power for the water outlet and ensuring a stable water outlet flow rate.

[0013] Furthermore, the energized heating circuit is a spirally extending conductive strip or conductive belt; the spirally extending conductive strip or conductive belt can be easily sheathed on the outer wall of the water pipe and can also make the water pipe be heated more evenly.

[0014] Furthermore, the water pipe and the tubular heating element are connected by threads or by fixings; the tubular heating element is sleeved on the water pipe by threads or fixings, and its firmness and tightness are better.

[0015] Another object of the present invention is achieved by:

[0016] A method for manufacturing an instant pipe heater comprises the following steps:

[0017] Step 1: Prepare the water pipe for use;

[0018] Step 2: using laser slotting equipment to cut the required slots on the tubular heating wall of the tubular heating element, and processing the tubular heating wall into an energized heating circuit connecting the first conductive end and the second conductive end, so as to obtain the required tubular heating element;

[0019] Step three, tightly wrap the tubular heating element obtained in the above step two around the outer wall of the water pipe.

[0020] The manufacturing method of this instant pipe heater is to groove the heating element to obtain the required tubular heating element, and the whole tubular heating element can be directly put on the water pipe without the need for spiral winding with difficult process. The whole manufacturing method is simple and has high production efficiency.

[0021] Furthermore, in the step one, a conical section with an outer diameter gradually increasing from small to large is processed on the outer wall of the water pipe. In the step two, before the groove is opened, the inner cavity of the tubular heating element is pre-processed into a conical cavity that matches the shape of the conical section to facilitate the subsequent grooving process.

[0022] Furthermore, in step two or step three, the outer diameter of the tubular heating wall is between 8 and 100 mm, the thickness of the tube wall is between 0.05 and 2 mm, and the power of the laser for cutting is between 300-3000W, so as to obtain the required tubular heating element. The setting is reasonable and can well achieve the purpose of this patent.

[0023] The beneficial effects of the present invention are as follows:

[0024] (1) In the instant pipe heater of the present invention, the tubular heating element that generates heat when powered is directly mounted and closely adheres to the outer wall of the water pipe. Therefore, the water pipe is made of insulating non-metallic material, and there is no need to worry about the tubular heating element and the water pipe being in contact and conducting electricity. The water pipe made of non-metallic material is not easy to produce scale inside the pipe, thereby ensuring the hygiene of drinking water. Furthermore, the tubular heating wall of the tubular heating element is divided into an electrically powered heating circuit connected between the first conductive end and the second conductive end by a groove, so that the entire tubular heating element is directly mounted and closely adheres to the outer wall of the water pipe, and does not need to be arranged on the outer wall of the water pipe in a spiral winding manner. The structure is simple and the process is simple.

[0025] (2) Furthermore, since the first conductive end and the second conductive end are integrally formed with the long middle section of the middle "tubular heating wall", the intermediate groove can be formed directly by cutting grooves in the long middle section, making the processing and forming of the entire tubular heating element simple and quick, and the overall connection strength is large.

[0026] (3) The tubular heating element is tightly sleeved on the conical section of the outer wall of the water pipe through the conical cavity. The conical shape of the water pipe and the tubular heating element is matched, which not only makes it easier for the two to be sleeved together, but also further improves the tight connection between the two.

[0027] (4) The manufacturing method of the instant heating pipe heater of the present invention is to groove the heating element to obtain the desired tubular heating element, and then directly put the entire tubular heating element on the water pipe without the need for spiral winding, which is difficult to process. The entire manufacturing method is simple and has high production efficiency. BRIEF DESCRIPTION OF THE DRAWINGS

[0028] Figure 1 It is a schematic diagram of the first embodiment of the instant heating type pipe heater of the present invention.

[0029] Figure 2 yes Figure 1 Split diagram of .

[0030] Figure 3 It is a schematic diagram of the second embodiment of the instant pipe heater of the present invention.

[0031] Figure 4 It is a schematic diagram of the third embodiment of the instant pipe heater of the present invention. DETAILED DESCRIPTION

[0032] Example 1: Figure 1 and Figure 2As shown, an instant hot pipe heater includes a water pipe 1, characterized in that it also includes a tubular heating element 2 that generates heat when powered on, the tubular heating element includes a first conductive end 21, a second conductive end 22 and a tubular heating wall 23, the first conductive end 21 and the second conductive end 22 are respectively connected to the tubular heating wall 23, a groove 231 is formed on the tubular heating wall 23, the groove 231 divides the tubular heating wall 23 into an electrically powered heating line 232 connected between the first conductive end 21 and the second conductive end 22, the tubular heating element 2 is sleeved and tightly attached to the outer wall of the water pipe 1. This instant pipe heater has a tubular heating element 2 that generates heat when powered on and is directly mounted on and tightly attached to the outer wall of a water pipe 1. The water pipe 1 is made of insulating non-metallic material, so there is no need to worry about the tubular heating element 2 and the water pipe 1 being in contact and conducting electricity. The water pipe 1 made of non-metallic material is not prone to scale formation inside the pipe, thus ensuring the hygiene of drinking water. Furthermore, the entire tubular heating element 2 is directly mounted on and tightly attached to the outer wall of the water pipe 1, and does not need to be arranged on the outer wall of the water pipe 1 in a spiral winding manner. The structure is simple and the installation is easy.

[0033] As a specific solution, the tubular heating element 2 includes a short front section, a long middle section and a short rear section, the first conductive end 21 and the second conductive end 22 constitute the short front section and the short rear section respectively, the tubular heating wall 23 constitutes the long middle section of the tubular shape, and the intermediate groove 231 is arranged on the long middle section of the tubular shape; the first conductive end 21 and the second conductive end 222 are integrally formed with the middle tubular heating wall 23, and the intermediate groove 231 can be formed directly by slotting the long middle section, so that the processing and forming of the entire tubular heating element 2 is simple and quick, and the overall connection strength is large; the short front section and the short rear section of the tubular heating element 2 are respectively bent with integrally connected sheet-like conductive ends, and the sheet-like conductive ends constitute the first conductive end 21 and the second conductive end 22 respectively.

[0034] In this embodiment, a conical section 10 with an outer diameter gradually increasing is provided on the outer wall of the water pipe 1, and the inner cavity of the tubular heating element 2 is a conical cavity 20, and the conical cavity 20 is adapted to the shape of the conical section 10. The tubular heating element 2 is sleeved through the conical cavity 20 and tightly attached to the conical section 10 of the outer wall of the water pipe 1; the tubular heating element 2 is tightly sleeved on the conical section 10 of the outer wall of the water pipe 1 through the conical cavity 20. This conical matching of the water pipe 1 and the tubular heating element 2 is conducive to easier sleeve connection between the two and further improves the tight connection between the two.

[0035] In this embodiment, the water pipe 1 includes a water inlet 11 and a water outlet 12, the end of the conical section 10 with a smaller outer diameter is the water inlet 11, and the end with a larger outer diameter is the water outlet 12; the energized heating circuit 232 is a spirally extended conductive strip or conductive belt.

[0036] Working principle: The tubular heating wall 23 of the tubular heating element 2 is divided into an energized heating circuit 232 connected between the first conductive end 21 and the second conductive end 22 by the intermediate groove 231, so that the entire tubular heating element 2 can be directly placed and tightly attached to the outer wall of the water pipe 1 without being arranged on the outer wall of the water pipe 1 in a spiral winding manner. The structure is simple and easy to install.

[0037] A method for manufacturing the instant hot pipe heater of the first embodiment comprises the following steps:

[0038] Step 1: Prepare the water pipe 1 for standby use;

[0039] Step 2: Using laser slotting equipment to cut the required slots 231 on the tubular heating wall 23 of the tubular heating element 2. The slots 231 process the tubular heating wall 23 into an energized heating line 232 connecting the first conductive end 21 and the second conductive end 22, thereby obtaining the required tubular heating element 2;

[0040] Step three, tightly sleeve the tubular heating element 2 obtained in step two onto the outer wall of the water pipe 1.

[0041] The manufacturing method of this instant pipe heater is to groove the heating element to obtain the required tubular heating element 2, and directly put the whole tubular heating element 2 on the water pipe 1 without the need for spiral winding with high process difficulty. The whole manufacturing method is simple and has high production efficiency.

[0042] As a specific solution, in the step 1, a conical section 10 with a gradually increasing outer diameter is processed on the outer wall of the water pipe 1, and in the step 2, before the slot 231 is formed, the inner cavity of the tubular heating element 2 is pre-processed into a conical cavity 20 that matches the shape of the conical section 10, so as to facilitate the processing of the slot 231 later.

[0043] In step 2 or step 3, the outer diameter of the tubular heating wall 23 is between 8 and 100 mm, the wall thickness is between 0.05 and 2 mm, and the power of the laser for cutting is between 300-3000W; the setting is reasonable and can well achieve the purpose of this patent.

[0044] Example 2: Figure 3 As shown, this embodiment is similar to Embodiment 1, except that: the outer wall of the water pipe 1 is a cylindrical segment with the same outer diameter, the inner cavity of the tubular heating element 2 is a cylindrical cavity, the cylindrical cavity is adapted to the shape of the cylindrical segment, the tubular heating element 2 is sleeved on the water pipe 1, and fixings 30 are provided at both ends of the tubular heating element 2, and the water pipe 1 and the tubular heating element 2 are connected by the fixings 30; the working principle of this embodiment is similar to that of Embodiment 1, and will not be described in detail here.

[0045] Example 3: Figure 4 As shown, this embodiment is similar to Embodiment 1, except that: the outer wall of the water pipe 1 is a cylindrical segment with the same outer diameter, the inner cavity of the tubular heating element 2 is a cylindrical cavity, the cylindrical cavity is adapted to the shape of the cylindrical segment, internal threads 40 are provided at both ends of the inner side of the tubular heating element, and corresponding external threads 50 are provided on the outer wall of the water pipe, and the water pipe 1 and the tubular heating element 2 are threadedly connected; the working principle of this embodiment is similar to that of Embodiment 1, and will not be described in detail here.

Claims

1. An instantaneous pipe heater, comprising a water pipe (1), characterized in that: The invention also comprises a tubular heating element (2) for heating when electricity is supplied, the tubular heating element (2) comprising a first conductive end (21), a second conductive end (22) and a tubular heating wall (23), the first conductive end (21) and the second conductive end (22) being respectively connected to the tubular heating wall (23), the tubular heating wall (23) being provided with a groove (231), the groove (231) dividing the tubular heating wall (23) into a line connected to the first conductive end (21) and the second conductive end (22). 2), the tubular heating element (2) is sleeved on and tightly attached to the outer wall of the water pipe (1); the tubular heating element (2) comprises a short front section, a long middle section and a short rear section, the first conductive end (21) and the second conductive end (22) respectively constitute the short front section and the short rear section, the tubular heating wall (23) constitutes the long middle section of the tubular shape, and the intermediate groove (231) is arranged on the long middle section of the tubular shape; the energized heating circuit (232) is a spirally extending conductive strip or conductive belt.

2. The instant pipe heater according to claim 1, characterized in that: The short front section and the short rear section of the tubular heating element (2) are respectively bent to form integrally connected sheet-shaped conductive ends, and the sheet-shaped conductive ends respectively constitute a first conductive end (21) and a second conductive end (22).

3. The instant pipe heater according to claim 1, characterized in that: A conical section (10) whose outer diameter gradually increases from small to large is provided on the outer wall of the water pipe (1); the inner cavity of the tubular heating element (2) is a conical cavity (20); the conical cavity (20) is adapted in shape to the conical section (10); the tubular heating element (2) is sleeved through the conical cavity (20) and is tightly attached to the conical section (10) on the outer wall of the water pipe (1).

4. The instant pipe heater according to claim 3, characterized in that: The water pipe (1) comprises a water inlet (11) and a water outlet (12); the end of the conical section (10) with a smaller outer diameter is the water inlet (11), and the end of the conical section (10) with a larger outer diameter is the water outlet (12).

5. The instant pipe heater according to claim 1, characterized in that: The water pipe (1) and the tubular heating element (2) are connected by threads or by a fixing member.

6. A method for manufacturing the instant pipe heater according to any one of claims 1 to 5, characterized in that: The steps include: Step 1: Prepare the water pipe (1) and set it aside; Step 2: using a laser slotting device to cut a desired slot (231) on the tubular heating wall (23) of the tubular heating element (2); the slot (231) processes the tubular heating wall (23) into an energized heating circuit (232) connecting the first conductive end (21) and the second conductive end (22), thereby obtaining the desired tubular heating element (2); Step three, tightly sleeve the tubular heating element (2) obtained in step two onto the outer wall of the water pipe (1).

7. The method for manufacturing the instantaneous pipe heater according to claim 6, characterized in that In the step one, a conical section (10) whose outer diameter gradually increases from small to large is processed on the outer wall of the water pipe (1), and in the step two, before the slot (231) is opened, the inner cavity of the tubular heating element (2) is pre-processed into a conical cavity (20) that matches the shape of the conical section (10).

8. The method for manufacturing the instantaneous pipe heater according to claim 7, characterized in that In step 2 or step 3, the outer diameter of the tubular heating wall (23) is between 8 and 100 mm, the thickness of the tube wall is between 0.05 and 2 mm, and the power of the laser used for cutting is between 300 and 3000 W.