Precast concrete component and construction method for tunnel TBM stepping
The TBM stepping platform and permanent tunnel pavement are formed by splicing precast concrete components, which solves the problems of waste and safety risks of traditional TBM stepping resources, and achieves efficient utilization of resources and improves safety.
Patent Information
- Application Number
- CN202110454594.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2021-04-26
- Publication Date
- 2024-11-12
- Estimated Expiration
- 2041-04-26
AI Technical Summary
During the stepping process of traditional TBM, the supporting tracks need to be disassembled, resulting in waste of resources and poses safety risks.
Precast concrete components are used, and multiple components are spliced into platforms by setting up a combination device on their end walls, and drainage channels are provided at the lower part to replace the traditional rear matching track rows for TBM stepping and tunnel permanent pavement foundations to avoid Disassembly waste and improve safety.
It effectively avoids the dismantling and waste of rear supporting walking track rows, improves the safety of the stepping process, and converts components into permanent pavement foundations and drainage channels for use.
Smart Images

Figure CN113153370B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of tunnel construction, and in particular to a precast concrete component for TBM stepping in a tunnel and a construction method thereof. Background Art
[0002] The tunnel boring machine (TBM) is a systematic, intelligent, and factory-based high-efficiency tunnel excavation construction machinery that can excavate a tunnel in one go and simultaneously complete the entire process of tunnel construction, including excavation and advancement, slag transportation, ventilation and dust removal, guidance control, support lining and advance treatment, wind, water, electricity and material supply, and realizes automated monitoring, making it suitable for tunnel construction in ultra-long underground caverns.
[0003] like Fig.10 As shown, during the construction process, after the TBM is assembled, it needs to step forward to the starting face before it can start excavation, which requires a stepping device to achieve. Traditional TBM stepping generally uses the rear supporting walking rail 18 as the support system for the TBM rear supporting forward movement. During the construction process, the rear supporting walking rail 18 needs to be corrected and reinforced at any time, which has a high safety risk. In addition, the rear supporting walking rail 18 needs to be removed after the TBM steps forward, resulting in a waste of resources. Therefore, it is necessary to explore a method with a simple structure, low construction cost, and easy construction.
[0004] like Figure 1 As shown, the TBM starting cavern includes an initial support 1 and a secondary lining 2. The initial support is located on the outer surface of the TBM starting cavern, and the secondary lining is located on the inner surface of the TBM starting cavern. Summary of the invention
[0005] The purpose of the present invention is to overcome the problem in the prior art that a matching walking rail 18 is required for use and the waste of resources caused after disassembly, and to provide a precast concrete component and construction method for a tunnel TBM step.
[0006] In order to achieve the above-mentioned object of the invention, the present invention provides the following technical solutions:
[0007] A precast concrete component for tunnel TBM stepping, characterized in that it comprises a precast concrete component body, wherein the precast concrete component body comprises an end wall;
[0008] A connecting device is provided on the end wall of at least one end of the precast concrete component body, and the connecting device is used to connect adjacent precast concrete component bodies;
[0009] A drainage channel is provided at the lower part of the precast concrete component body.
[0010] Based on the above structure, a combining device is arranged on the end wall of the precast concrete component body, which can splice several precast concrete component bodies together to form a platform required for TBM stepping. At the same time, a drainage channel is also arranged at the lower part of the precast concrete component body. When it is no longer used as a platform required for TBM stepping in the future, it can be used not only as a permanent pavement foundation of the tunnel but also as a drainage channel, replacing the traditional TBM stepping construction method of laying the matching walking rails, thereby avoiding the waste caused by the need to disassemble the matching walking rails after use, and also greatly improving the safety during the stepping process.
[0011] As a preferred embodiment of the present invention, the combining device includes a reserved groove and a connecting steel plate, wherein the reserved groove is arranged on the end wall, the connecting steel plate is fixed in the reserved groove, and the connecting steel plate is used to connect with the corresponding connecting steel plate on the adjacent precast concrete component body.
[0012] As a preferred solution of the present invention, at least three top suspension rods are embedded in the upper end surface of the precast concrete component body, wherein at least three top suspension rods are distributed in a triangle.
[0013] As a preferred solution of the present invention, the top suspension rod is formed by embedded steel bar components with enlarged ends at upper and lower ends.
[0014] Based on the above structure, three top hangers and embedded steel bar components at the upper and lower ends are used, which can facilitate the hoisting construction of the subsequent components and ensure their safety.
[0015] As a preferred solution of the present invention, a track groove is provided on the upper end surface of the precast concrete component body, and the track grooves are of the same shape and size and are symmetrical about the tunnel center line.
[0016] As a preferred solution of the present invention, each track groove is provided with at least four reserved holes for track spikes.
[0017] Based on the above structure, two track grooves are set to place the TBM stepping track unit, and the spike reserved holes are used to fix and install the TBM stepping track unit.
[0018] As a preferred solution of the present invention, a longitudinal water stop groove is provided at the bottom of the precast concrete component body, located on both sides of the drainage channel, and a transverse water stop groove is provided on the end wall.
[0019] Based on the above structure, the expansion water stop strip can be installed through the transverse water stop groove and the first longitudinal water stop groove to achieve the purpose of waterproofing.
[0020] A tunnel comprises a TBM starting cavern, the TBM starting cavern comprises an initial support, a secondary lining, and at least two precast concrete component bodies, the top of the precast concrete component body is provided with a TBM stepping track unit, and all the precast concrete component bodies are sequentially connected along the longitudinal direction of the tunnel.
[0021] A method for constructing a precast concrete component for a tunnel TBM stepping includes the precast concrete component body for a tunnel TBM stepping described in the above structure, and further includes the following steps:
[0022] S1: Prefabricate the precast concrete component body in the prefabrication yard;
[0023] S2: Construct TBM stepping platforms in the stepping cavern and TBM starting cavern, and reserve stepping guide grooves and grooves that match the longitudinal water stop grooves in the precast concrete component body along the longitudinal direction of the tunnel;
[0024] S3: When the TBM starts to move forward, the stepping trolley and the stepping frame are installed, and the precast concrete component body is installed simultaneously during the moving process;
[0025] S4: Measure and set out the design axis and pile number;
[0026] S5: Install longitudinal water stop strips and side transverse water stop strips at the bottom of the precast concrete component body, transport the precast concrete component body to the TBM stepping platform, and install the precast concrete component body in sequence along the TBM stepping direction;
[0027] S6: The adjacent precast concrete component bodies are fixed by bolts and connecting steel plates, and the adjacent precast concrete component bodies are fixed by bolts and connecting steel plates, and the gap between two adjacent connecting steel plates connected by bolts is filled with concrete;
[0028] S7: Each time the TBM moves forward by one stroke, a precast concrete component is installed;
[0029] S8: After installing at least one precast concrete component body, pour concrete on both sides to the top surface of the precast concrete component body.
[0030] In step S3, when the TBM starts to step, the rear support is lifted, and the stepping cylinder is used to push the TBM main machine to slide forward on the slide. After each stepping process is completed, the TBM main machine is lifted by the joint action of the lifting cylinder at the cutter head and the rear support, and the push cylinder pushes the slide forward one stroke.
[0031] The installation of the design axis and pile number in step S4 is mainly for accurately positioning the longitudinal and transverse positions of the precast concrete component body.
[0032] In step S6, adjacent components are integrated in this way.
[0033] In step S7, this installation method is to ensure that the component installation is synchronized with the TBM stepping.
[0034] In step S8, pouring concrete on both sides to the top surface of the precast concrete component body can increase the overall stability of the precast concrete component body.
[0035] Compared with the prior art, the present invention has the following beneficial effects:
[0036] Based on the above structure, a combining device is arranged on the end wall of the precast concrete component body, which can splice several precast concrete component bodies together to form a platform required for TBM stepping. At the same time, a drainage channel is also arranged at the lower part of the precast concrete component body. When it is no longer used as a platform required for TBM stepping in the future, it can be used not only as a permanent pavement foundation of the tunnel but also as a drainage channel, replacing the traditional TBM stepping construction method of laying the matching walking rails, thereby avoiding the waste caused by the need to disassemble the matching walking rails after use, and also greatly improving the safety during the stepping process. BRIEF DESCRIPTION OF THE DRAWINGS
[0037] Figure 1 It is a schematic diagram of the cross-sectional structure of the front side of the tunnel of the present invention;
[0038] Figure 2 The overall structural diagram of the tunnel of the present invention is shown in FIG.
[0039] Figure 3 It is a schematic diagram of the overall structure of the precast concrete component body of the present invention;
[0040] Figure 4 It is a front view of the precast concrete component body of the present invention;
[0041] Figure 5 A top view of the precast concrete component body of the present invention;
[0042] Figure 6 It is a schematic diagram of the overall structure of the top suspension rod of the present invention;
[0043] Figure 7 A schematic diagram of the connection between the connecting steel plates of the present invention;
[0044] Figure 8 It is a structural schematic diagram of the longitudinal water stop groove of the present invention;
[0045] Fig. 9 It is a schematic diagram of the structure of the TBM of the present invention;
[0046] Fig.10It is a schematic diagram of the prior art of the present invention;
[0047] Markings in the figure: 1-initial support, 2-secondary lining, 3-precast concrete component body, 4-TBM stepping track unit, 5-top hanger, 6-track groove, 7-reserved groove, 8-connecting steel plate, 9-longitudinal water stop groove, 10-spike reserved hole, 11-transverse water stop groove, 12-bolt, 13-nut, 14-slide plate, 15-thrust cylinder, 16-thrust cylinder, 17-rear support, 18-rear supporting walking rail, 19-TBM rear supporting, 20-stepping guide groove, 21-drainage channel, 22-groove, 23-combination device, 24-end wall. DETAILED DESCRIPTION
[0048] The present invention is further described in detail below in conjunction with test examples and specific implementation methods. However, this should not be understood as the scope of the above subject matter of the present invention being limited to the following embodiments, and all technologies realized based on the content of the present invention belong to the scope of the present invention.
[0049] Example 1
[0050] refer to Figure 1-4 and Figure 7 As shown, a precast concrete component for TBM stepping in a tunnel provided by the present invention includes a TBM starting cavern, wherein the TBM starting cavern includes an initial support 1, a secondary lining 2 and a precast concrete component body 3, wherein the initial support is located on the outer surface of the TBM starting cavern, and the secondary lining is located on the inner surface of the TBM starting cavern.
[0051] It also includes a precast concrete component body 3, which includes an end wall 24. A combining device 23 is provided on the end wall 24 of at least one end of the precast concrete component body 3. The end wall 24 at only one end is provided with the combining device 23 and is placed at the head and tail ends of the entire platform. The end walls 24 at both ends are provided with the combining device 23 and are placed in the middle of the entire platform except the head and tail ends. The combining device 23 is used to connect adjacent precast concrete component bodies 3. A drainage channel 21 is provided at the lower part of the precast concrete component body 3.
[0052] Based on the above structure, a combining device 23 is provided on the end wall 24 of the precast concrete component body 3. The combining device 23 splices several precast concrete component bodies 3 together to form a platform required for TBM stepping. At the same time, a drainage channel 21 is also provided at the lower part of the precast concrete component body 3. When it is no longer used as a platform required for TBM stepping in the future, it can be used not only as a permanent pavement foundation of the tunnel but also as a drainage channel, replacing the traditional TBM stepping construction method of laying the matching walking rail, thereby avoiding the waste caused by the need to disassemble the matching walking rail after use, and also greatly improving the safety during the stepping process.
[0053] In the above device, it is preferred that the combining device 23 includes a reserved groove 7 and a connecting steel plate 8, the connecting steel plate 8 is fixed in the reserved groove 7, the reserved groove 7 is arranged on the end wall 24, four bolt holes are opened on the connecting steel plate 8, and the connecting steel plates 8 on each adjacent two precast concrete component bodies 3 are connected by bolts 12, nuts 13 and bolt holes.
[0054] Based on the above structure, the connecting steel plate 8 is directly fixed inside the reserved groove 7 during the casting process of the reserved groove 7, and then screwed into the bolt hole through the bolt 12, and then nuts 13 are added to both ends of the bolt 12 for fixed installation to form the platform required for TBM stepping.
[0055] refer to Figure 6 As shown, in the above device, as a preference, three top suspension rods 5 are embedded in the upper end surface of the precast concrete component body 3, and one end of the triangular suspension rod 5 is buried inside the precast concrete component body 3, and the top suspension rod 5 is formed by an embedded steel bar component with enlarged ends at the upper and lower ends, and the enlarged end refers to Figure 6 The two ends shown have larger diameter ends relative to the steel column, which can facilitate the subsequent lifting and construction of components and their safety.
[0056] refer to Figure 5 As shown, in the above device, it is preferred that two track grooves 6 are provided on the upper end surface of the precast concrete component body 3. On the other hand, the track grooves 6 are of the same shape and size and are symmetrical about the center line of the tunnel. The track grooves 6 are mainly used to place and locate the installation position of the TBM stepping track unit 4. Each of the track grooves 6 is provided with four spike reserved holes 10. The size and depth of the reserved holes 10 can be determined according to actual conditions. The spike reserved holes are used to fix the TBM stepping track unit 4.
[0057] refer to Figure 4 and Fig. 9As shown, longitudinal water stop grooves 9 are respectively provided at the bottom of the precast concrete component body 3, located on both sides of the drainage channel 21, and transverse water stop grooves 11 are provided on the front and rear end walls 24, and the longitudinal water stop grooves 9 are arranged along the longitudinal direction of the tunnel.
[0058] Used to install water-swelling waterstop strips during the construction process to achieve the purpose of waterproofing.
[0059] Example 2
[0060] refer to Figure 1-Figure 10 As shown, a method for constructing precast concrete components for TBM stepping in a tunnel is provided, including a concrete component introduced in Example 1, specifically: including a precast concrete component body 3, the precast concrete component body 3 includes an end wall 24, and a coupling device 23 is provided on the end wall 24 of at least one end of the precast concrete component body 3, and the coupling device 23 is used to connect adjacent precast concrete component bodies 3, and a drainage channel 21 is provided at the lower part of the precast concrete component body 3, and the coupling device 23 includes a reserved groove 7 and a connecting steel plate 8, and the reserved groove 7 is provided on the end wall 24, and the connecting steel plate 8 is fixed in the reserved groove 7, and the connecting steel plate 8 is used to connect with the corresponding connecting steel plate 8 on the adjacent precast concrete component body 3, and the bottom of the precast concrete component body 3 is provided with a longitudinal water stop groove 9, which is located on both sides of the drainage channel 21, and the end wall 24 is provided with a transverse water stop groove 11. In further combining the specific structure of the TBM stepping to explain and illustrate the present invention in detail, it also includes the following steps:
[0061] S1: Prefabricate the precast concrete components in the prefabrication yard;
[0062] S2: constructing a TBM stepping platform in the stepping cavern and the TBM starting cavern, and reserving a stepping guide groove 20 and a groove 22 matching the longitudinal water stop groove 9 in the precast concrete component body 3 along the longitudinal direction of the tunnel;
[0063] S3: When the TBM starts to move forward, the moving carriage and the moving frame are installed, and the precast concrete component body 3 is installed simultaneously during the moving process;
[0064] In step S3, when the TBM starts to step, the rear support 17 is lifted, and the thrust cylinder 16 is used to push the TBM main machine to slide forward on the slide plate 14. After each stepping process is completed, the TBM main machine is lifted by the joint action of the lifting cylinder 15 at the cutter head and the rear support 17, and the thrust cylinder 15 pushes the slide plate 14 forward by one stroke.
[0065] S4: Measure and set out the design axis and pile number;
[0066] The purpose of installing the design axis and pile number in step S4 is to accurately locate the longitudinal and transverse positions of the precast concrete component body 3 .
[0067] S5: installing longitudinal water stop strips and side transverse water stop strips at the bottom of the precast concrete component body 3, transporting the precast concrete component body 3 to the TBM stepping platform, and sequentially installing the precast concrete component body 3 along the TBM stepping direction;
[0068] S6: The adjacent precast concrete component bodies 3 are fixed by bolts 13 and connecting steel plates 8, and the gap between two adjacent connecting steel plates 8 connected by bolts 13 is filled with concrete;
[0069] In step S6, adjacent components are integrated in this way.
[0070] S7: Each time the TBM advances one stroke, a precast concrete component body 3 is installed;
[0071] In step S7, this installation method is to ensure that the component installation is synchronized with the TBM stepping.
[0072] S8: After installing at least one precast concrete component body 3, pouring concrete on both sides to the top surface of the precast concrete component body 3;
[0073] In step S8 , pouring concrete on both sides to the top surface of the precast concrete component body 3 can increase the overall stability of the precast concrete component body 3 .
[0074] It should be noted that, in combination with the prior art Fig.10 As shown, further support and explanation of the beneficial effects of the present invention are as follows:
[0075] The TBM rear-end 19 stepping requires the rear-end walking track 18 underneath. The track of the present invention is installed on the concrete component and can be disassembled and reused. The previous rear-end walking track 18 underneath was processed using I-beams and the like. After use, these I-beams need to be disassembled, and the space behind needs to be poured with concrete or otherwise processed, which wastes materials. The present invention replaces the rear-end walking track 18 with a precast concrete component body 3 as the platform required for the TBM stepping. After the TBM stepping track unit 4 is disassembled, it can be used as a permanent pavement structure and drainage channel for the tunnel in subsequent construction, which greatly reduces the waste caused by the disassembly of the rear-end walking track 18 after use in the prior art, and also greatly improves the safety during the stepping process.
[0076] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the protection scope of the present invention.
Claims
1. A precast concrete component for TBM stepping in a tunnel, characterized in that: It comprises a precast concrete component body (3), wherein the precast concrete component body (3) comprises an end wall (24); A connecting device (23) is provided on the end wall (24) of at least one end of the precast concrete component body (3), and the connecting device (23) is used to connect adjacent precast concrete component bodies (3); A drainage channel (21) is provided at the lower part of the precast concrete component body (3); The combining device (23) comprises a reserved groove (7) and a connecting steel plate (8), wherein the reserved groove (7) is arranged on the end wall (24), the connecting steel plate (8) is fixedly arranged in the reserved groove (7), and the connecting steel plate (8) is used to connect with the corresponding connecting steel plate (8) on the adjacent precast concrete component body (3); The bottom of the precast concrete component body (3) is provided with longitudinal water stop grooves (9) located on both sides of the drainage channel (21); The end wall (24) is provided with a transverse water stop groove (11); A TBM stepping platform with a reserved groove (22) is provided below the precast concrete component body (3), and the groove (22) cooperates with the longitudinal water stop groove (9); A track groove (6) is provided on the top of the precast concrete component body (3), and the track groove (6) is used to fix the TBM stepping track.
2. A precast concrete component for tunnel TBM stepping according to claim 1, characterized in that: At least three top suspension rods (5) are pre-buried on the upper end surface of the precast concrete component body (3), wherein the at least three top suspension rods (5) are distributed in a triangular shape.
3. A precast concrete component for tunnel TBM stepping according to claim 2, characterized in that: The upper and lower ends of the top suspension rod (5) are composed of embedded steel bar components with enlarged ends.
4. A precast concrete component for tunnel TBM stepping according to claim 1, characterized in that: The track groove (6) is provided with at least four track spike reserved holes (10).
5. A tunnel, comprising a TBM starting cavern, wherein the TBM starting cavern comprises an initial support (1) and a secondary lining (2), characterized in that: It also comprises at least two precast concrete component bodies (3) according to any one of claims 1 to 4, a TBM stepping track unit (4) being arranged on the top of the precast concrete component bodies (3), and all the precast concrete component bodies (3) are sequentially connected along the longitudinal direction of the tunnel.
6. A method for constructing precast concrete components by TBM stepping in a tunnel, characterized in that: The precast concrete component body according to claim 1 or 3 further comprises the following steps: S1: Prefabricate the precast concrete components in the prefabrication yard; S2: constructing a TBM stepping platform in the stepping cavern and the TBM starting cavern, and reserving a stepping guide groove (20) and a groove (22) matching the longitudinal water stop groove (9) in the precast concrete component body (3) along the longitudinal direction of the tunnel; S3: When the TBM starts to move forward, the moving carriage and the moving frame are installed, and the precast concrete component body (3) is installed simultaneously during the moving process; S4: Measure and set out the design axis and pile number; S5: installing longitudinal water stop strips and side transverse water stop strips at the bottom of the precast concrete component body (3), transporting the precast concrete component body (3) to the TBM stepping platform, and installing the precast concrete component body (3) in sequence along the TBM stepping direction; S6: Adjacent precast concrete component bodies (3) are fixed by bolts (13) and connecting steel plates (8), and the gap between two adjacent connecting steel plates (8) connected by bolts (13) is filled with concrete; S7: Each time the TBM moves forward by one stroke, a precast concrete component body (3) is installed. S8: After installing at least one precast concrete component body (3), pour concrete on both sides to the top surface of the precast concrete component body (3).