Installation method of a visual plug template group device for template trolley plug
By installing a visual plug template group device on the template trolley, the combined structure of telescopic plug mold and elastic pad block is used to solve the problem of mismatch between the tunnel arch wall and the steel plug template, and better sealing is achieved and real-time construction monitoring have improved the quality of tunnel lining construction.
Patent Information
- Application Number
- CN202110936994.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2021-08-16
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2041-08-16
AI Technical Summary
The plug formwork of the existing formwork trolley is inconsistent with the gap between the tunnel arch wall and the steel plug formwork, resulting in uneven pressure of the rubber strip, which affects the sealing property. The steel plug formwork is opaque and cannot observe the concrete pouring status in real time, making it easy to have hollows or Bubbles affect construction quality.
A visual plug template set device was designed. Through a four-layer combined telescopic plug mold, a medium-buried water stop belt, a telescopic plug template, a plug pad lift module and an elastic pad block are installed, and the width is adjusted using a telescopic screw. and elastic seal to increase the sealing effect, and observe the construction status through perspective-blocking formwork to ensure full concrete pouring.
The sealing and construction quality of the plug formwork are improved, the hollows and bubbles in concrete pouring are reduced, and the construction efficiency and quality are improved.
Smart Images

Figure CN113622953B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the installation of a plugging template of a template trolley, and in particular to an installation method of a visualized plugging template group device of a template trolley plugging. Background Art
[0002] At present, both ends of the template trolley template for pouring concrete in the tunnel need to be sealed by plugging templates before construction. Most of the existing template plugs are steel plugging templates. During construction, the gap between the edge of the steel plugging template and the tunnel arch wall is raised and sealed by rubber strips. Since the gap between the tunnel arch wall and the steel plugging template is inconsistent, the rubber strip inserted in the gap is raised to the same thickness, the rubber strip does not match the gap, and the pressure of the rubber strip squeezed through the steel plugging template is uneven, which affects the sealing of the template plug. In addition, during the construction process, the pouring port is located in the middle of the template. Since the steel plugging template is opaque, it is impossible to judge the construction status of the concrete pouring inside the steel plugging template. The concrete pouring inside the steel plugging template is not full, and voids or bubbles are prone to occur. It needs to be repaired manually, which cannot meet the construction requirements and affects the construction quality of the tunnel donor lining. In view of the above reasons, an installation method for a visual plugging template group device of a template trolley plug is proposed. Summary of the invention
[0003] The purpose of the present invention is to overcome the problem that during the construction of steel plugging formwork, due to the inconsistent gap between the tunnel arch wall and the steel plugging formwork, the rubber strip does not match the gap, and the pressure of the rubber strip squeezed through the steel plugging formwork is uneven, which affects the sealing of the formwork plug; in addition, during the construction process, it is impossible to judge the construction status of the concrete pouring inside the steel plugging formwork, the concrete pouring inside the steel plugging formwork is not full, and voids or bubbles are prone to occur, which cannot meet the construction requirements and affect the construction quality of the tunnel donor lining; now, through reasonable design, an installation method for a visualized plugging formwork group device of a formwork trolley plug is provided; the visualized plugging formwork group device of the present invention is a four-layer combined telescopic plugging form, and the plugging steel formwork is sequentially installed with embedded water-stop The gap between the template and the tunnel is telescopically blocked by belts, telescopic plugging templates, plugging heightening modules and elastic pads. The width of the blockage is adjusted by a telescopic screw between the telescopic plugging template and the telescopic module. The telescopic plugging template is raised by a plugging heightening module. The telescopic plugging template and the plugging heightening module can block larger gaps. The plugging heightening module is elastically sealed by elastic pads to increase the sealing effect. During the construction process, the construction status can be observed through the plugging template through the perspective of the plugging heightening module. The construction can be controlled and adjusted by observation to ensure that the concrete on the inside of the plugging template is full, reduce voids or bubbles in the concrete and repair, thereby speeding up the construction progress and improving the construction quality of the tunnel lining.
[0004] In order to achieve the above-mentioned purpose, the present invention adopts the following technical scheme: a method for installing a visual plugging template group device for a template trolley plug; the visual plugging template group device for the template trolley plug is composed of a template trolley, a template flange, a template, a Joule, a plugging steel template, a telescopic plugging template, a telescopic module, a screw seat, a telescopic screw, a slider positioning pin, a slide groove, a plugging pad module, a perspective rear plugging template, a padding block partition, an elastic pad, an outer slope of a joint, an inner slope of a joint, a plugging support frame, a supporting partition, a frame supporting plugging column, a steel mold turning frame, a steel mold bracket, an inclined support positioning rod, an upper end support plate, a plugging column screw, and an arch wall It is composed of a waterstop, an embedded waterstop, an inclined support seat, a steel mold support frame, and a steel mold limit top screw; it is characterized in that: the top and both sides of the template trolley are set as arched templates, the inner sides of the two ends of the template are respectively set as template flanges, and the outer sides of the template flanges are evenly set as three groups of plugging steel templates; the three groups of plugging steel templates on the outer sides of the template flanges are combined to form an arched plugging steel template, and the outer sides of the arched plugging steel templates are respectively set as four-layer combined telescopic plugging molds, and the telescopic plugging molds are respectively set as embedded waterstop, telescopic plugging template, plugging pad module, elastic pad from inside to outside, and the upper end of the elastic pad corresponds to the arch wall waterstop of the inner wall of the tunnel;
[0005] A pair of steel mold turning frames are respectively arranged between the outer side of the template flange and the plugging steel template, a Joule is respectively arranged between the lower end of the pair of steel mold turning frames and one side of the template flange, and a pin is respectively arranged between the Joule and the lower end of the pair of steel mold turning frames; a double-layer steel mold bracket is arranged on the outer side of the plugging steel template, and a pair of through holes are reserved at the outer end of the double-layer steel mold bracket, and a pair of fence support plug columns are arranged in the pairs of through holes; a fixed plate is arranged on the outer side of the double-layer steel mold bracket corresponding to the fence support plug columns, and a pair of plug column screws are arranged on the fixed plate; an embedded water stop belt is arranged inside the steel mold bracket, and fixed clamping parts are evenly distributed between the steel mold bracket and the embedded water stop belt; a pair of upper end support plates are arranged between the middle part of the double-layer steel mold bracket, a steel mold support frame is arranged on the outer edge of the template flange corresponding to the pair of support plates, and the end of the steel mold support frame is arranged as an inclined support seat, a steel mold limiting top screw is arranged between the inclined support seat and the steel mold support frame, an inclined support positioning rod is arranged between the inclined support seat and the pair of support plates, and a pin is arranged between the upper end of the inclined support positioning rod and the pair of upper end support plates;
[0006] A telescopic plug template is arranged on the embedded water stop belt, a telescopic module is arranged on the outside of the telescopic plug template, the telescopic plug template and the telescopic module are respectively arranged as L-shaped structures, a slide groove is arranged correspondingly between the telescopic plug template and the side plate of the telescopic module, a screw seat and a slide groove seat are respectively arranged on the inside of the telescopic plug template, a slider locating pin is arranged on the slide groove seat, a slider is arranged at one end of the slider locating pin, and a slider is arranged in the slide groove; a screw hole is reserved in the middle of the upper end of the screw seat, a telescopic screw is arranged in the screw hole, a thread is arranged between the telescopic screw and the screw seat, the upper end of the telescopic screw is arranged corresponding to the inner side of the telescopic module, a support pad is arranged between the upper end of the telescopic screw and the telescopic module, and a nut is arranged at the lower end of the telescopic screw;
[0007] A plugging heightening module is arranged on the telescopic plugging template, the plugging heightening module is arranged as a frame-shaped structure, the middle part of the frame of the plugging heightening module is arranged as a heightening block partition, and a perspective rear plugging template is arranged behind the plugging heightening module; an elastic pad is arranged on the plugging heightening module, a weight reduction and pressure relief hole is reserved in the middle of the elastic pad, one end of the elastic pad is arranged as a joint outer slope, and the other end of the elastic pad is arranged as a joint inner slope;
[0008] The inner side of the telescopic plug template and the plug heightening module corresponds to the construction end of the template for concrete pouring, and a plug support fence is set between the outer side of the telescopic plug template and the plug heightening module and a pair of fence support plug columns. The plug support fence is set as a frame-shaped structure, and a support partition is set in the plug support fence;
[0009] Before the formwork trolley is used to pour tunnel concrete, the three sets of plugging steel formworks on the outside of the formwork flange are respectively flipped up 90° by the steel formwork flipping frame, and the inclined support positioning rod is manually rotated downward to the corresponding inclined support seat at the lower end and then stopped, and the inclined support seat is pushed to fix the lower end of the inclined support positioning rod by manually rotating the steel formwork limit screw; the three sets of plugging steel formworks are all flipped and fixed to form an arch; an embedded waterstop is manually laid on the arched plugging steel formwork, and at the same time, the embedded waterstop and the arched plugging steel formwork are respectively fixed with clamping pieces manually;
[0010] After the embedded waterstop and the arched plugging steel formwork are fixed, the gap between the embedded waterstop on the outside of the plugging steel formwork and the inner wall of the tunnel is sealed from one end of the formwork trolley to the other end. The telescopic plugging formwork, plugging heightening module and elastic pad are manually installed in blocks and layers on the outside of the plugging steel formwork.
[0011] When sealing the gap between the outside of the first plugging steel template at one end of the template trolley and the inner wall of the tunnel, the telescopic plugging template, the plugging heightening module and the elastic pad are manually straightened corresponding to the outer edges of the plugging steel template respectively, and then the telescopic screw is manually rotated to push the telescopic module, the plugging heightening module and the elastic pad outward to contact the inner wall of the tunnel and squeeze and seal. Then the rotation of the telescopic screw is stopped to complete the sealing of the gap outside the first plugging steel template.
[0012] After the gap between the plugging steel formwork and the inner wall of the tunnel is sealed, a plugging support frame is placed on the outside of the telescopic plugging formwork and the plugging pad module, and a pair of frame support plugs at the outer end of the double-layer steel formwork bracket are manually inserted upward to the outside of the plugging support frame. A pair of plug screws are manually rotated and fixed to fix a pair of frame support plugs, thereby completing the gap sealing between the outside of the first plugging steel formwork and the inner wall of the tunnel;
[0013] According to the above operation method, each plugging steel formwork is installed from one end of the formwork trolley to the other end to seal the gap between the outside of the tunnel and the inner wall. After the gaps between the outside of all the plugging steel formworks at both ends of the formwork trolley and the inner wall of the tunnel are sealed, the installation of the visual plugging formwork group device is completed. After the installation of the visual plugging formwork group device is completed, concrete pouring construction is carried out on the formwork.
[0014] Beneficial effects: The present invention performs telescopic plugging of the gap between the template and the tunnel by sequentially installing a telescopic plugging template, a plugging raising module and an elastic pad on the plugging steel template; the plugging width is adjusted by a telescopic screw between the telescopic plugging template and the telescopic module; the telescopic plugging template is raised by the plugging raising module; the telescopic plugging template and the plugging raising module can block a larger gap; the plugging raising module is elastically sealed by the elastic pad to increase the sealing effect; during the construction process, the construction status can be observed through the plugging template through the perspective of the plugging raising module; the construction can be controlled and adjusted by observation to ensure that the concrete on the inner side of the plugging template is fully poured, reduce voids or bubbles in the concrete pouring and repairs, thereby accelerating the construction progress and improving the construction quality of the tunnel lining. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] The present invention will be further described below in conjunction with the accompanying drawings:
[0016] Figure 1 It is a schematic diagram of the general assembly structure;
[0017] Figure 2 yes Figure 1 Schematic diagram of the local structure;
[0018] Figure 3 yes Figure 1 Schematic diagram of the plugging steel formwork structure;
[0019] Figure 4 yes Figure 3 Schematic diagram of the local structure;
[0020] Figure 5 yes Figure 1 A schematic diagram of a side cross-sectional local structure of;
[0021] Figure 6 yes Figure 5 Schematic diagram of the local plugging steel formwork structure;
[0022] Figure 7 yes Figure 5 Schematic diagram of the working state structure of the local plugging steel formwork;
[0023] Figure 8 yes Figure 5 Schematic diagram of the local telescopic plug template structure;
[0024] Fig. 9 yes Figure 8 A side view structural schematic diagram of;
[0025] Fig.10 yes Fig. 9 Schematic diagram of the working state structure;
[0026] Fig.11 yes Figure 5 Schematic diagram of the three-dimensional structure of the plug raising module;
[0027] Fig.12 yes Figure 5 Schematic diagram of the three-dimensional structure of the plug support frame;
[0028] Fig.13 yes Figure 5 Schematic diagram of the three-dimensional structure of the elastic pad;
[0029] Figure 1 , 2 , 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13: template trolley 1, template flange 2, template 2-1, Joule 2-2, plug steel template 3, telescopic plug template 4, telescopic module 4-1, screw seat 4-2, telescopic screw 4-3, slider positioning pin 4-4, slide groove 4-5, plug height module 5, perspective rear plug template 5-1, height block partition 5-2, elastic pad 6, joint outer slope 6-1, joint inner slope 6-2, plug support frame 7, support partition 7-1, frame support column 8, steel mold turning frame 9, steel mold bracket 10, inclined support positioning rod 11, upper end support plate 11-1, column screw 12, arch wall waterstop 13, embedded waterstop 14, inclined support seat 15, steel mold support frame 16, steel mold limit top screw 17. DETAILED DESCRIPTION
[0030] The present invention is further described in detail below in conjunction with embodiments and specific implementation modes:
[0031] Example 1
[0032] The top and both sides of the template trolley 1 are set as an arched template 2-1, the inner sides of the two ends of the template 2-1 are respectively set as template flanges 2, and the outer sides of the template flanges 2 are respectively evenly set as three groups of plugging steel templates 3; the three groups of plugging steel templates 3 on the outer side of the template flange 2 are combined to form an arched plugging steel template, and the outer sides of the arched plugging steel template are respectively set as four-layer combined telescopic plugging molds, and the telescopic plugging molds are respectively set from the inside to the outside as a buried waterstop 14, a telescopic plugging template 4, a plugging pad module 5, and an elastic pad 6, and the upper end of the elastic pad 6 corresponds to the arch wall waterstop 13 of the inner wall of the tunnel;
[0033] A pair of steel mold flip frames 9 are respectively arranged between the outer side of the template flange 2 and the plugging steel template 3, and a joule 2-2 is respectively arranged between the lower end of the pair of steel mold flip frames 9 and one side of the template flange 2, and a pin is respectively arranged between the joule 2-2 and the lower end of the pair of steel mold flip frames 9; a double-layer steel mold bracket 10 is arranged on the outer side of the upper part of the plugging steel template 3, and a pair of through holes are reserved at the outer end of the double-layer steel mold bracket 10, and a pair of fence support plug columns 8 are arranged in the pairs of through holes; a fixed plate is arranged on the outer side of the double-layer steel mold bracket 10 corresponding to the fence support plug columns 8, and a pair of plug column screws 12 are arranged on the fixed plate; the upper inner side of the steel mold bracket 10 An embedded water stop 14 is arranged at the bottom, and fixed clamping parts are evenly distributed between the steel mold bracket 10 and the embedded water stop 14; a pair of upper support plates 11-1 are arranged between the middle parts of the double-layer steel mold bracket 10, and a steel mold support frame 16 is arranged at the outer edge of the template flange 2 corresponding to the pair of support plates, and the end of the steel mold support frame 16 is arranged as an inclined support seat 15, and a steel mold limiting top screw 17 is arranged between the inclined support seat 15 and the steel mold support frame 16, and an inclined support positioning rod 11 is arranged between the inclined support seat 15 and the pair of support plates, and a pin is arranged between the upper end of the inclined support positioning rod 11 and the pair of upper support plates 11-1;
[0034] A telescopic plug template 4 is arranged on the embedded water stop belt 14, a telescopic module 4-1 is arranged on the outside of the telescopic plug template 4, the telescopic plug template 4 and the telescopic module 4-1 are respectively arranged as L-shaped structures, and a slide groove 4-5 is correspondingly arranged between the side plates of the telescopic plug template 4 and the telescopic module 4-1, a screw seat 4-2 and a slide groove seat are respectively arranged on the inside of the telescopic plug template 4, a slider locating pin 4-4 is arranged on the slide groove seat, a slider is arranged at one end of the slider locating pin 4-4, and a slider is arranged in the slide groove 4-5; a screw hole is reserved in the middle of the upper end of the screw seat 4-2, a telescopic screw 4-3 is arranged in the screw hole, a thread is arranged between the telescopic screw 4-3 and the screw seat 4-2, the upper end of the telescopic screw 4-3 is arranged corresponding to the inner side surface of the telescopic module 4-1, a support pad is arranged between the upper end of the telescopic screw 4-3 and the telescopic module 4-1, and a nut is arranged at the lower end of the telescopic screw 4-3;
[0035] A plugging heightening module 5 is arranged on the telescopic plugging template 4, and the plugging heightening module 5 is arranged as a frame-shaped structure, and the middle part of the frame of the plugging heightening module 5 is arranged as a heightening block partition 5-2, and a perspective rear plugging template 5-1 is arranged behind the plugging heightening module 5; an elastic pad 6 is arranged on the plugging heightening module 5, and a weight reduction and pressure relief hole is reserved in the middle of the elastic pad 6, one end of the elastic pad 6 is arranged as a joint outer slope 6-1, and the other end of the elastic pad 6 is arranged as a joint inner slope 6-2;
[0036] The inner side of the telescopic plug template 4 and the plug heightening module 5 corresponds to the construction end of the concrete pouring of the template 2-1, and a plug support fence 7 is arranged between the outer side of the telescopic plug template 4 and the plug heightening module 5 and a pair of fence support plug columns 8. The plug support fence 7 is arranged as a frame-shaped structure, and a support partition 7-1 is arranged in the plug support fence 7;
[0037] Before the formwork trolley 1 is used for tunnel concrete pouring, the three groups of plugging steel formworks 3 on the outer side of the formwork flange 2 are respectively flipped upward at an angle of 90° by the steel formwork flipping frame 9, and the inclined support positioning rod 11 is manually rotated downward to the corresponding inclined support seat 15 at the lower end and then stopped, and the inclined support seat 15 is pushed to fix the lower end of the inclined support positioning rod 11 by manually rotating the steel formwork limit top screw 17; the three groups of plugging steel formworks 3 are all flipped and fixed to form an arch; an embedded waterstop 14 is manually laid on the arched plugging steel formwork 3, and at the same time, the embedded waterstop 14 and the arched plugging steel formwork 3 are respectively fixed with clamping pieces by manual means;
[0038] After the embedded waterstop 14 and the arched plugging steel formwork 3 are fixed, the gap between the embedded waterstop 14 on the outside of the plugging steel formwork 3 and the inner wall of the tunnel is sealed from one end of the formwork trolley 1 to the other end, and the telescopic plugging formwork 4, the plugging heightening module 5, and the elastic pad 6 are manually installed in blocks and layers on the outside of the plugging steel formwork 3.
[0039] Example 2
[0040] When the gap between the outside of the first plugging steel template 3 at one end of the template trolley 1 and the inner wall of the tunnel is blocked, the telescopic plugging template 4, the plugging heightening module 5, and the elastic pad 6 are manually straightened corresponding to the outer edges of the plugging steel template 3, and then the telescopic screw 4-3 is manually rotated. The telescopic screw 4-3 pushes the telescopic module 4-1, the plugging heightening module 5, and the elastic pad 6 to move outward and contact the inner wall of the tunnel, and after squeezing and sealing, the rotation of the telescopic screw 4-3 is stopped to complete the blocking of the gap outside the first plugging steel template 3.
[0041] Example 3
[0042] After the gap between the plugging steel formwork 3 and the inner wall of the tunnel is sealed, a plugging support fence 7 is placed on the outside of the telescopic plugging formwork 4 and the plugging heightening module 5, and a pair of fence support plugs 8 at the outer end of the double-layer steel formwork bracket 10 are manually inserted upward to the outside of the plugging support fence 7, and a pair of plug screws 12 are manually rotated and fixed to fix the pair of fence support plugs 8, thereby completing the gap sealing between the outside of the first plugging steel formwork 3 and the inner wall of the tunnel;
[0043] According to the above operation method, each plugging steel formwork 3 is installed from one end of the formwork trolley 1 to the other end to seal the gap between the outside of the tunnel and the inner wall. After the gaps between the outside of all the plugging steel formworks 3 at both ends of the formwork trolley 1 and the inner wall of the tunnel are sealed, the installation of the visual plugging formwork group device is completed. After the installation of the visual plugging formwork group device is completed, concrete pouring construction is carried out on the formwork 2-1.
Claims
1. A method for installing a visualized plugging template assembly device for a template trolley plug, wherein the visualized plugging template assembly device for the template trolley plug comprises a template trolley (1), a template flange (2), a template (2-1), a Joule (2-2), a plugging steel template (3), a telescopic plugging template (4), a telescopic module (4-1), a screw seat (4-2), a telescopic screw (4-3), a slider positioning pin (4-4), a slide groove (4-5), a plugging pad module (5), a perspective rear plugging template (5-1), a pad The structure is composed of a high block partition (5-2), an elastic pad (6), a joint outer slope (6-1), a joint inner slope (6-2), a plug support frame (7), a support partition (7-1), a frame support plug column (8), a steel mold turning frame (9), a steel mold bracket (10), an oblique support positioning rod (11), an upper end support plate (11-1), a plug column screw (12), an arch wall water stop (13), a middle embedded water stop (14), an oblique support seat (15), a steel mold support frame (16), and a steel mold limit top screw (17); Features: The top and both sides of the template trolley (1) are arranged as an arched template (2-1), the inner sides of both ends of the template (2-1) are respectively arranged as template flanges (2), and the outer sides of the template flanges (2) are respectively evenly arranged as three groups of plugging steel templates (3); the three groups of plugging steel templates (3) on the outer sides of the template flanges (2) are combined to form an arched plugging steel template, and the outer sides of the arched plugging steel template are respectively arranged as four-layer combined telescopic plugging molds, and the telescopic plugging molds are respectively arranged from the inside to the outside as a buried water stop (14), a telescopic plugging template (4), a plugging pad module (5), and an elastic pad (6), and the upper end of the elastic pad (6) corresponds to the arch wall water stop (13) of the inner wall of the tunnel; A pair of steel mold flip frames (9) are respectively arranged between the outer side of the template flange (2) and the plug steel template (3), and a joule (2-2) is respectively arranged between the lower end of the pair of steel mold flip frames (9) and one side of the template flange (2), and a pin is respectively arranged between the joule (2-2) and the lower end of the pair of steel mold flip frames (9); a double-layer steel mold bracket (10) is arranged on the outer side of the upper part of the plug steel template (3), and a pair of through holes are reserved at the outer end of the double-layer steel mold bracket (10), and a pair of fence support plugs (8) are arranged in the pairs of through holes; a fixed plate is arranged on the outer side of the double-layer steel mold bracket (10) corresponding to the fence support plugs (8), and a pair of plug screws (12) are arranged on the fixed plate; the upper inner side of the steel mold bracket (10) is provided with a pair of through holes, and a pair of through holes are arranged in the pairs of through holes; An embedded water stop belt (14) is arranged at the top of the steel mold bracket (10), and fixed clamping parts are evenly distributed between the top of the steel mold bracket (10) and the embedded water stop belt (14); a pair of upper support plates (11-1) are arranged between the middle parts of the double-layer steel mold bracket (10), and a steel mold support frame (16) is arranged at the outer edge of the template flange (2) corresponding to the pair of support plates, and the end of the steel mold support frame (16) is arranged as an inclined support seat (15), and a steel mold limiting top screw (17) is arranged between the inclined support seat (15) and the steel mold support frame (16), and an inclined support positioning rod (11) is arranged between the inclined support seat (15) and the pair of support plates, and a pin shaft is arranged between the upper end of the inclined support positioning rod (11) and the pair of upper support plates (11-1); A telescopic plug template (4) is arranged on the embedded water stop belt (14), a telescopic module (4-1) is arranged outside the telescopic plug template (4), the telescopic plug template (4) and the telescopic module (4-1) are respectively arranged in an L-shaped structure, a slide groove (4-5) is correspondingly arranged between the side plates of the telescopic plug template (4) and the telescopic module (4-1), a screw seat (4-2) and a slide groove seat are respectively arranged inside the telescopic plug template (4), a slider positioning pin (4-4) is arranged on the slide groove seat, and the slider positioning pin (4-5) is arranged on the slide groove seat. A slider is provided at one end of the pin (4-4), and a slider is provided in the slide groove (4-5); a screw hole is reserved in the middle of the upper end of the screw seat (4-2), a telescopic screw (4-3) is provided in the screw hole, a thread is provided between the telescopic screw (4-3) and the screw seat (4-2), the upper end of the telescopic screw (4-3) is provided corresponding to the inner side surface of the telescopic module (4-1), a support pad is provided between the upper end of the telescopic screw (4-3) and the telescopic module (4-1), and a nut is provided at the lower end of the telescopic screw (4-3); A plugging heightening module (5) is arranged on the telescopic plugging template (4), the plugging heightening module (5) is arranged as a frame-shaped structure, the middle of the frame of the plugging heightening module (5) is arranged as a heightening block partition (5-2), and a perspective rear plugging template (5-1) is arranged behind the plugging heightening module (5); an elastic pad (6) is arranged on the plugging heightening module (5), a weight reduction and pressure relief hole is reserved in the middle of the elastic pad (6), one end of the elastic pad (6) is arranged as a joint outer slope (6-1), and the other end of the elastic pad (6) is arranged as a joint inner slope (6-2); The inner side surfaces of the telescopic plug template (4) and the plug elevation module (5) correspond to the construction end of the concrete pouring of the template (2-1); a plug support fence (7) is arranged between the outer sides of the telescopic plug template (4) and the plug elevation module (5) and a pair of fence support plug posts (8); the plug support fence (7) is arranged as a frame-shaped structure, and a support partition (7-1) is arranged in the plug support fence (7); Before the template trolley (1) is used for tunnel concrete pouring, the three groups of plugging steel templates (3) on the outer side of the template flange (2) are respectively turned up by 90 degrees through the steel template turning frame (9), and the inclined support positioning rod (11) is manually rotated downward to the corresponding inclined support seat (15) at the lower end and then stopped, and the inclined support seat (15) is pushed to fix the lower end of the inclined support positioning rod (11) by manually rotating the steel template limit top screw (17); the three groups of plugging steel templates (3) are all turned over and fixed to form an arch; a buried water stop strip (14) is manually laid on the arched plugging steel template (3), and at the same time, the buried water stop strip (14) and the arched plugging steel template (3) are respectively fixed by manually fixing clamping pieces; After the embedded water stop (14) and the arched plugging steel formwork (3) are fixed, the gap between the embedded water stop (14) on the outside of the plugging steel formwork (3) and the inner wall of the tunnel is blocked from one end to the other end of the formwork trolley (1), and the telescopic plugging formwork (4), the plugging heightening module (5), and the elastic pad (6) are manually installed in blocks and layers on the outside of the plugging steel formwork (3).
2. According to claim 1, a method for installing a visual plug template assembly device for a template trolley plug, Features: When the gap between the outside of the first plugging steel template (3) at one end of the template trolley (1) and the inner wall of the tunnel is blocked, the telescopic plugging template (4), the plugging pad module (5), and the elastic pad (6) are manually aligned corresponding to the outer edges of the plugging steel template (3), and then the telescopic screw (4-3) is manually rotated, and the telescopic screw (4-3) pushes the telescopic module (4-1), the plugging pad module (5), and the elastic pad (6) to move outwards and contact with the inner wall of the tunnel, and after squeezing and sealing, the rotation of the telescopic screw (4-3) is stopped, and the blocking of the gap outside the first plugging steel template (3) is completed.
3. According to claim 1, a method for installing a visual plug template assembly device for a template trolley plug, Features: After the gap between the plugging steel formwork (3) and the inner wall of the tunnel is sealed, a plugging support frame (7) is placed on the outer side of the telescopic plugging formwork (4) and the plugging heightening module (5), and a pair of frame support plugs (8) at the outer end of the double-layer steel formwork bracket (10) are manually inserted upward to the outer side of the plugging support frame (7), and then a pair of plug screws (12) are manually rotated and fixed to fix the pair of frame support plugs (8), thereby completing the sealing of the gap between the outer side of the first plugging steel formwork (3) and the inner wall of the tunnel; According to the above operation method, each plugging steel template (3) is installed from one end of the template trolley (1) to the other end to seal the gap between the outside and the inner wall of the tunnel. After the gaps between the outside and the inner wall of the tunnel of all the plugging steel templates (3) at both ends of the template trolley (1) are sealed, the installation of the visual plugging template group device is completed; after the installation of the visual plugging template group device is completed, the template (2-1) is poured with concrete.