Key load grid-connected startup method for parallel-connected and off-grid energy storage inverter

By using DC power supply and detection pulse technology in the photovoltaic inverter system, the load capacity is estimated and key loads are gradually started, which solves the problem of damage caused by excessive output current of the inverter and achieves safe and reliable grid-connected power supply for the load. and rational use of inverters.

CN114123330BActive Publication Date: 2024-10-15NINGBO GINLONG TECH
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202111423052.6
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2021-11-26
Publication Date
2024-10-15
Estimated Expiration
2041-11-26

AI Technical Summary

Technical Problem

In the photovoltaic inverter system, when an unknown large-capacity load is connected to the BACKUP port of the inverter, the capacity cannot be effectively estimated before the inverter is connected to the grid, resulting in excessive output current of the inverter, which may cause damage to components or circuits. problem.

Method used

By putting the powered inverter into parallel off-grid mode, using DC power supply, detecting pulses to obtain the current and voltage values ​​​​of the BACKUP port, calculating the average apparent power and change rate of the key load, estimating the capacity, and determining based on the estimated value The number of inverters required to participate in parallel operation, gradually start up key loads, and connect to the grid after stabilization, adjust the number of inverters to avoid overcurrent.

Benefits of technology

It achieves reliable estimation of key load capacity, avoids damage caused by excessive output current of the inverter, ensures safe and reliable power supply of the energy storage inverter, and rationally utilizes the inverter to extend its service life.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114123330B_ABST
    Figure CN114123330B_ABST
Patent Text Reader

Abstract

The present invention discloses a method for starting up a critical load of an off-grid energy storage inverter that can be connected to the grid. Before an unknown large-capacity critical load is connected to the grid from the inverter, the powered-on inverter is first put into a parallel off-grid mode, and a detection pulse set by the inverter is output; the average apparent power at the BACKUP port is calculated based on the acquired information, and then it is determined whether the critical load is stable. According to the effective value of the current and the effective value of the voltage when the critical load is stable, an estimated value of the critical load capacity is obtained, and then the number of inverters required to participate in the parallel operation is calculated. After the estimation is completed, the critical load is powered by a DC power supply, and the inverter required to be connected to the grid is started, so that the critical load is started stably. It is ensured that before the unknown large-capacity critical load is connected to the grid, there are a sufficient number of inverters that can be powered on and connected to the grid, so as to avoid the situation where the inverter output current is too large due to insufficient inverters, causing damage to components or corresponding lines, and to ensure the safety and reliability of power supply to the critical load.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of grid-connected off-grid energy storage inverter loads, belongs to the field of photovoltaic inverters, and specifically relates to a grid-connected starting method for a key load of a parallelable off-grid energy storage inverter. Background Art

[0002] Photovoltaic inverters are required for solar photovoltaic power generation. The function of photovoltaic inverters is to connect the DC power generated by photovoltaic panels to the grid after boosting and inverting. They are one of the most important components in the photovoltaic power generation process. For some manufacturers, the grid power line and the inverter circuit are connected inside the machine, and the key load is connected to the inverter through the corresponding BACKUP port on the inverter. Switches are set between the grid, the inverter circuit and the key load to control whether the load or the inverter is connected to the grid.

[0003] In order to ensure the power demand on the user side, the energy storage inverters will be connected in parallel to draw power from the grid to jointly provide power to the key loads. In order to ensure the service life of the energy storage inverter and for safety reasons, when the inverter needs to be shut down for maintenance or other reasons, the switch at the grid connection point is usually turned off. However, due to the shutdown of some inverters, the number of BACKUP ports connected to the grid is reduced, and the output capacity of the BACKUP side is reduced accordingly. When the user connects a critical load with too large a capacity to the BACKUP port, and the number of circuits drawn from the grid is too small, it is very easy to cause overcurrent in the switch connecting the grid and the key load on the powered-on inverter and the components and lines on the BACKUP output side, causing the risk of overcurrent damage. Summary of the invention

[0004] In view of the above analysis, the present invention proposes a critical load grid-connected startup method that can be connected to an off-grid energy storage inverter to solve the deficiencies of the prior art.

[0005] The present invention is mainly achieved through the following technical solutions:

[0006] The key load grid-connected startup method of the grid-connected energy storage inverter provided by the present invention comprises the following steps:

[0007] Make the powered-on inverter enter the parallel off-grid mode and adopt DC power supply;

[0008] Each inverter outputs a set detection pulse, and within the set detection period T, the current value at the BACKUP port of all powered-on inverters is obtained in real time for n times and voltage value , where n≥2;

[0009] According to the obtained n current values and voltage value , calculate the average apparent power P of the key load at the BACKUP port within the detection period T, the change rate of the average apparent power between two adjacent times, and the effective value of the current And voltage RMS ;

[0010] Compare the change rate of two consecutive average apparent powers with the set change rate threshold to determine whether the critical load is stable;

[0011] If the critical load is stable, the current effective value when the critical load is stable And voltage RMS , calculate the equivalent impedance Z of the key load, and then obtain the estimated value A1 of the current key load capacity;

[0012] According to the estimated value A1 of the critical load capacity, calculate the number of inverters N1 required for parallel operation;

[0013] The critical load is powered by a DC power supply, the corresponding switch group on the N1 parallel inverters is closed, and the N1 inverters are made to output in turn according to the maximum output current of the inverter to try to start the critical load. When the critical load is stably started, the inverter is connected to the grid to connect the critical load to the grid.

[0014] According to the estimated capacity value A1 of the critical load and the output power of the BACKUP port of each inverter, the number of inverters that need to be connected in parallel is adjusted to prevent unknown large-capacity loads from being connected to the inverter. Due to the insufficient number of parallel inverters, the line between the BACKUP port and the grid port and the corresponding components may be damaged by overcurrent. This can reduce the number of unnecessary parallel inverters, the number of standby inverters and the working loss.

[0015] Furthermore, the method further comprises the following steps:

[0016] When trying to start a critical load, obtain the current value of the BACKUP port , voltage value And real-time detection of whether the inverter is outputting normally to confirm whether the key load is started stably.

[0017] Furthermore, the method further comprises the following steps:

[0018] If the critical load can be started stably, obtain the current value of the critical load when it is stable in real time And voltage value Update and save the average apparent power value calculated at this time , which is the capacity A2 of the critical load. At this time, the number of inverters participating in the output is N2 and the number information is saved;

[0019] After the N2 inverters start normally in the off-grid state, close the corresponding switch group to connect the inverter to the grid and re-obtain the current value at the BACKUP port after the grid connection. , voltage value , calculate the average apparent power value at this time , which is the capacity A3 of the critical load. According to the actual output power of the BACKUP port, the number of inverters N3 required to participate in the grid-connected power supply is calculated, and the corresponding switch group is disconnected to make the redundant parallel inverters disconnected from the grid.

[0020] Furthermore, the method further comprises the following steps:

[0021] If the critical load cannot be started normally, reset the output power of the N1 parallel inverters to zero, and gradually increase the number of parallel inverters based on the N1 parallel inverters. After restarting the initial N1 inverters and the corresponding increased inverters, try to start the critical load again. Repeat this operation until the critical load is successfully started.

[0022] If the critical load can start stably after increasing the number of parallel inverters, repeat the above operation and adjust the number of grid-connected inverters according to the actual output power of the BACKUP port.

[0023] Furthermore, the method further comprises the following steps:

[0024] If the critical load still cannot start normally after increasing the number of parallel inverters to the maximum, the inverter will issue an overload alarm and the output power of each parallel inverter will be reduced to 0.

[0025] Furthermore, the method further comprises the following steps:

[0026] If the calculated number of inverters required to participate in parallel operation N1 is greater than the actual number of inverters connected in parallel, the inverter will issue an overload alarm, and at the same time, the output power of each parallel inverter will be reduced to 0.

[0027] Furthermore, the method further comprises the following steps:

[0028] The inverter feeds back the grid-connected status of key loads to the user through the communication interface.

[0029] Furthermore, the calculation steps of the average apparent power value P at the BACKUP port within the detection period T are as follows:

[0030] (1)

[0031] in, is the nth sampling current at the BACKUP port, is the n+1th sampling current at the BACKUP port, is the nth sampling voltage at the BACKUP port, is the n+1th sampling voltage at the BACKUP port, n is the sampling number within a detection cycle T, and N is the total sampling number.

[0032] Furthermore, the peak value of the detection pulse is 10-380V, the frequency is the power frequency of the power grid, the detection period T is 0.04-4s, and the sampling frequency is 500HZ.

[0033] Furthermore, the DC power supply is a storage battery or a PV battery.

[0034] Compared with the prior art, the beneficial effects of the technical solution of the present invention are as follows:

[0035] 1. The present invention provides a method for starting up the key load of the grid-connected off-grid energy storage inverter. When an unknown large-capacity key load is connected to the BACKUP port of the inverter, before the inverter is connected to the grid, the powered-on inverter is first put into the parallel off-grid mode, and the inverter is powered by a DC power supply to ensure that when the switch between the inverter and the key load is turned on, energy support is provided for the start-up of the key load. The inverter outputs a detection pulse, estimates the capacity of the key load by obtaining the current and voltage values ​​of the port, and calculates the optimal number of inverters participating in the parallel operation; provides a reasonable power output value for the key load through the DC power supply, turns on the inverter that needs to be connected in parallel, and enables the DC power supply to power the key load through the inverter. After determining that the key load can be started stably, the inverter is connected to the grid to connect the key load to the grid. It can estimate the capacity of immutable loads, avoid damage to components or corresponding lines caused by excessive inverter output current, ensure safe and reliable power supply to key loads under parallel power supply of energy storage inverters, and make reasonable use of parallel inverters.

[0036] 2. Before the inverter is connected to the grid, the current value, voltage value and output status of the BACKUP port are detected in real time. When the voltage of the BACKUP port stabilizes to the grid voltage, the port current reaches a constant state, and the inverter outputs normally, it is judged that the critical load is started normally. It is ensured that the critical load can be connected to the grid only after it is started stably. If the critical load cannot be started normally, in the off-grid state, by gradually increasing the number of inverters involved in the parallel operation, restart the inverter and try to start the critical load until the load is successfully started. By using the method of gradually raising the low voltage to complete the startup of the critical load, the capacity of variable loads such as loads with step-down protection or large impact current can be estimated, and the appropriate number of inverters can be dispatched to the grid to meet the actual capacity requirements of the critical load. BRIEF DESCRIPTION OF THE DRAWINGS

[0037] In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the following briefly introduces the drawings required for use in the description of the embodiments. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.

[0038] Figure 1 1 is a circuit diagram of a parallel-connectable and grid-connected energy storage inverter provided by an embodiment of the present invention;

[0039] Figure 2 A schematic flow chart of a method for starting a critical load connected to the grid and connected to an off-grid energy storage inverter provided in an embodiment of the present invention. DETAILED DESCRIPTION

[0040] In order to enable those skilled in the art to better understand the present invention, and thus to more clearly define the scope of the present invention, the present invention is described in detail with respect to some specific embodiments of the present invention. It should be noted that the following are only some specific implementation methods of the present invention, which are only part of the embodiments of the present invention, wherein the specific and direct description of the relevant structure is only for the convenience of understanding the present invention, and each specific feature does not naturally and directly limit the scope of implementation of the present invention. The conventional selection and replacement made by those skilled in the art under the guidance of the present invention should be regarded as within the scope of the present invention.

[0041] The present invention will be further described below in conjunction with the accompanying drawings and specific embodiments.

[0042] Example 1

[0043] Figure 1A grid-connected and off-grid energy storage inverter is shown, comprising a plurality of inverters arranged in parallel. Taking one of the inverters as an example, an inverter circuit is provided in the inverter, and a grid port, a BACKUP port and a DC power supply access port electrically connected to the inverter circuit are provided on the inverter. One end of the grid port is electrically connected to the grid, and the other end of the grid port is provided with a first switch K1-1. One end of the inverter circuit is electrically connected to the PV cell and the energy storage battery respectively, and a second switch K2-1 is provided between the other end of the inverter circuit and the first switch K1-1. One end of the BACKUP port is connected in parallel to the key load, and a third switch K3-1 is provided between the other end of the BACKUP port and the second switch K2-1. The inverter determines whether to connect the key load or the inverter to the grid through the above switches, and meets the power supply, power generation and charging requirements in different modes by controlling the different closed or open states of the first switch K1-1, the second switch K2-1 and the third switch K3-1. In actual use, in order to ensure power demand, multiple machines will be used in parallel. In parallel mode, each inverter relies on its own communication interface, communication network and online control software to complete information and control command interaction. The inverter in parallel operation uses multiple parallel connections to draw power from the grid.

[0044] In the case of excessive load on the BACKUP port, it is essentially because the number of inverters connected to the grid is too small, making the total BACKUP output capacity of the inverter less than the load requirement. For example, 10 inverters with a maximum BACKUP output capacity of 10KW are connected in parallel, and the user's BACKUP load power is 80KW. When only 4 inverters are turned on due to maintenance or other reasons, the output power of the BACKUP output side of the inverter is insufficient and power needs to be taken from the grid. At this time, the output current of the user's BACKUP is twice the maximum output current, and the third switch K3-1, the BACKUP output terminal, and the circuit from the third switch K3-1 to the AC output bus may have overcurrent. Then the first switch K1-1 and its line to the grid are also facing the risk of overcurrent, which is very likely to cause overcurrent damage.

[0045] Figure 1 The grid-connected and off-grid energy storage inverter shown emphasizes the line connection of the AC part, and does not provide a detailed description of the specific structure of the inverter. For example, the energy flow between the PV cell, the energy storage battery and the power grid and the load requires voltage size conversion and voltage property conversion. Therefore, the inverter should also include at least a DC converter, a DC-AC converter and a communication interface for data communication with the outside. The above structure can be connected to the inverter using the existing conventional connection method. The specific structure of the inverter is not the innovation of the present invention. The present invention focuses on the control method applied to the circuit structure, and other necessary structures of the inverter are not described in detail here.

[0046] In order to solve the problem that when an unknown large-capacity critical load is connected to the BACKUP port of the inverter, the number of parallel inverters is too small, and the output current of some inverters is too large, causing damage to components and corresponding lines, it is necessary to determine the capacity of the critical load before the critical load is connected to the grid to ensure that there are enough inverters to start up and connect to the grid to avoid excessive BACKUP output current of the machine.

[0047] As such Figure 2 As shown, the present invention provides a key load grid-connected startup method that can be connected to a parallel off-grid energy storage inverter, comprising the following steps:

[0048] Make the powered-on inverter enter parallel off-grid mode and adopt DC power supply;

[0049] Each inverter outputs a set detection pulse, and within the set detection period T, the current value at the BACKUP port of all powered-on inverters is obtained in real time for n times and voltage value , where n≥2;

[0050] According to the obtained n current values and voltage value , calculate the average apparent power P of the key load at the BACKUP port within the detection period T, the change rate of the average apparent power between two adjacent times, and the effective value of the current And voltage RMS ;

[0051] Compare the change rate of two consecutive average apparent powers with the set change rate threshold to determine whether the critical load is stable;

[0052] If the critical load is stable, the current effective value when the critical load is stable And voltage RMS , calculate the equivalent impedance Z of the key load, and then obtain the estimated value A1 of the current key load capacity;

[0053] According to the estimated value A1 of the critical load capacity, calculate the number of inverters N1 required for parallel operation;

[0054] The critical load is powered by a DC power supply, the corresponding switch group on the N1 parallel inverters is closed, and the N1 inverters are made to output in turn according to the maximum output current of the inverter to try to start the critical load. When the critical load is started normally, the inverter is connected to the grid to connect the critical load to the grid.

[0055] Ensure that before unknown large-capacity critical loads are connected to the grid, there are enough inverters that can be turned on and connected to the grid to avoid insufficient inverters, which may cause excessive inverter output current and damage components or corresponding lines. Ensure safe and reliable power supply to critical loads, reduce the number of non-essential inverters that are turned on, and ensure the service life of the inverter.

[0056] In this embodiment, the DC power source is an energy storage battery or a PV battery, and the energy storage battery is a storage battery.

[0057] Specifically, the calculation steps of the average apparent power value P at the BACKUP port within the detection period T are as follows:

[0058] (1)

[0059] in, is the nth sampling current at the BACKUP port, is the n+1th sampling current at the BACKUP port, is the nth sampling voltage at the BACKUP port, is the n+1th sampling voltage at the BACKUP port, n is the sampling number within a detection cycle T, and N is the total sampling number.

[0060] Specifically, according to the current data and voltage data collected by the sampling unit at the BACKUP port, the current value sampled in real time at the BACKUP port during the detection period can be obtained. and voltage value , including the current and voltage values ​​when the critical load is unstable, and the current value when the critical load is stable , voltage value And the current value at the BACKUP port after grid connection , voltage value , and then get the effective value of the current in each time period within the detection cycle T and voltage RMS .

[0061] Preferably, the data collected by the sampling unit can be restored to the current waveform and voltage waveform through a digital low-pass filter, and the real-time current value of the BACKUP port can be obtained by converting the above waveform information. and voltage value , the conversion formula is as follows:

[0062] (2)

[0063] (3)

[0064] in, is the peak value of the voltage waveform collected by the sampling unit, is the peak value of the current waveform collected by the sampling unit, is the phase corresponding to the voltage peak value collected by the sampling unit, is the phase corresponding to the current peak value collected by the sampling unit. The above data can be directly read through the voltage waveform data and current waveform data collected by the sampling unit.

[0065] Current RMS and voltage RMS The calculation formula is as follows:

[0066] (4)

[0067] (5)

[0068] in, is the nth sampling current at the BACKUP port, is the nth sampling voltage at the BACKUP port, where n is the sampling number within a detection cycle T.

[0069] The calculation formula of the equivalent impedance Z of the critical load is as follows:

[0070] (6)

[0071] The calculation formula for the estimated critical load capacity A1 is as follows:

[0072] (7)

[0073] in, is the grid voltage.

[0074] Specifically, the peak value of the detection pulse is 10~380V, the frequency is the power grid frequency, the detection period T is 0.04~4s, and the sampling frequency is 500HZ. Utilizing the adjustable output property of the inverter, the inverter completes the analysis of the key load capacity by sending out the detection pulse and collecting the corresponding voltage waveform and current waveform. This method is suitable for estimating the immutable load capacity.

[0075] In this embodiment, the inverter circuit is controlled by the inverter to output a voltage detection pulse, each detection period T lasts for 0.4 seconds, and the interval time of the sampling period is manually set, and the default value is 0.5 seconds.

[0076] In this embodiment, the range of the set change rate threshold is 5% to 20%. The change rate threshold is the threshold of the change rate of two data, which is used to measure the change amplitude of the data. If the change rate of the average apparent power calculated twice adjacently exceeds the range of the change rate threshold, it indicates that the critical load is unstable. If the change rate of the average apparent power calculated twice adjacently does not exceed the range of the change rate threshold, it indicates that the critical load is stable.

[0077] In order to avoid the problem that the number of inverters required to be paralleled is inaccurately calculated due to the change of the capacity of the key load, and the key load cannot be started normally, preferably, the following steps are also included:

[0078] When trying to start a critical load, obtain the current value of the BACKUP port , voltage value And real-time detection of whether the inverter is outputting normally to confirm whether the key load is started stably.

[0079] In this embodiment, the judgment of whether the critical load is started stably can be made by human experience or based on whether the voltage value of the BACKUP port reaches the grid voltage value after the load is stabilized, whether the current value of the BACKUP port reaches a constant state, and whether the inverter outputs normally. The main detection parameters for whether the inverter can output normally include: output current and output voltage.

[0080] Specifically, the following steps are also included:

[0081] If the critical load can be started stably, obtain the current value of the critical load when it is stable in real time And voltage value Update and save the average apparent power value calculated at this time , which is the capacity A2 of the critical load. At this time, the number of inverters participating in the output is N2 and the number information is saved;

[0082] After the N2 inverters start normally in the off-grid state, close the corresponding switch group to connect the inverter to the grid and re-obtain the current value at the BACKUP port after the grid connection. , voltage value , calculate the average apparent power value at this time , which is the capacity A3 of the critical load. According to the actual output power of the BACKUP port, the number of inverters N3 required to participate in the grid-connected power supply is calculated, and the corresponding switch group is disconnected to make the redundant parallel inverters disconnected from the grid.

[0083] Specifically, the following steps are also included:

[0084] If the critical load cannot be started normally, reset the output power of the N1 parallel inverters to zero, and gradually increase the number of parallel inverters based on the N1 parallel inverters. After restarting the initial N1 inverters and the corresponding increased inverters, try to start the critical load again. Repeat this operation until the critical load is successfully started.

[0085] If the critical load can start stably after increasing the number of parallel inverters, repeat the above operation and adjust the number of grid-connected inverters according to the actual output power of the BACKUP port.

[0086] Gradually increase the number of inverters at the maximum output current, and determine whether the key load is stably started by analyzing whether the output voltage of the BACKUP port can be stabilized to the grid voltage, whether the output current of the BACKUP port remains constant, and whether the inverter is in a stable output state. Then estimate the capacity of the key load, and obtain the optimal number of parallel inverters N3 by determining the total output power of all inverter BUCKUP ports. This is suitable for estimating the capacity of loads with step-down protection or large inrush current.

[0087] Among them, by updating the saved average apparent power value P of the key load under stable operation in real time, it is ensured that the optimal number of parallel inverters can be quickly calculated.

[0088] The following steps are also included:

[0089] If the calculated number of inverters required to participate in parallel operation N1 is greater than the actual number of inverters connected in parallel, the inverter will issue an overload alarm, and at the same time, the output power of each parallel inverter will be reduced to 0.

[0090] The following steps are also included:

[0091] If the critical load still cannot start normally after increasing the number of parallel inverters to the maximum, the inverter will issue an overload alarm and the output power of each parallel inverter will be reduced to 0.

[0092] Through the alarm reminders for the above different scenarios, we can deal with different situations where the critical load capacity is too large and the critical load cannot be started normally, and standardize its use.

[0093] Among them, the relationship between A1 and N1 and the relationship between A2 and N2 should satisfy that the total output capacity of the BACKUP port corresponding to the number of parallel inverters is greater than the capacity A of the critical load. The total output capacity of the BACKUP port corresponding to N parallel inverters should be the product of the output power of the BACKUP port after each inverter is turned on and N. At this time, the output power of the BACKUP port after each inverter is turned on is calculated according to the maximum power. Since there is overcurrent protection in the inverter circuit of the inverter, when the critical load attempts to start, the output power of the inverter is output according to the maximum current to reduce the overcurrent risk.

[0094] The following steps are also included:

[0095] The inverter feeds back the grid-connected status of key loads to the user through the communication interface, so that the user can know the grid-connected status of key loads in time and perform corresponding operations.

[0096] The above are only preferred embodiments of the present invention. The protection scope of the present invention is not limited to the above embodiments. All technical solutions under the concept of the present invention belong to the protection scope of the present invention. It should be pointed out that for ordinary technicians in this technical field, some improvements and modifications without departing from the principle of the present invention should also be regarded as the protection scope of the present invention.

Claims

1. A method for starting up a critical load connected to the grid and connected to the grid and an off-grid energy storage inverter, characterized in that: The steps include: Make the powered-on inverter enter the parallel off-grid mode and adopt DC power supply; Each inverter outputs a set detection pulse, and within the set detection period T, the current value at the BACKUP port of all powered-on inverters is obtained in real time for n times and voltage value , where n≥2; According to the obtained n current values and voltage value , calculate the average apparent power P of the key load at the BACKUP port within the detection period T, the change rate of the average apparent power between two adjacent times, and the effective value of the current And voltage RMS ; Compare the change rate of two consecutive average apparent powers with the set change rate threshold to determine whether the critical load is stable; If the critical load is stable, the current effective value when the critical load is stable And voltage RMS , calculate the equivalent impedance Z of the key load, and then obtain the estimated value A1 of the current key load capacity; According to the estimated value A1 of the critical load capacity, calculate the number of inverters N1 required for parallel operation; Power the critical load with a DC power supply, close the corresponding switch group on the N1 parallel inverters, and make the N1 inverters output in turn according to the maximum output current of the inverter to try to start the critical load. When the critical load starts normally, connect the inverter to the grid to connect the critical load to the grid; When trying to start a critical load, obtain the current value of the BACKUP port , voltage value And real-time detection of whether the inverter is outputting normally to confirm whether the key load is starting stably; If the critical load can be started stably, obtain the current value of the critical load when it is stable in real time And voltage value Update and save the average apparent power value calculated at this time , which is the capacity A2 of the critical load. At this time, the number of inverters participating in the output is N2 and the number information is saved; After the N2 inverters start normally in the off-grid state, close the corresponding switch group to connect the inverter to the grid and re-obtain the current value at the BACKUP port after the grid connection. , voltage value , calculate the average apparent power value at this time , which is the capacity A3 of the critical load. According to the actual output power of the BACKUP port, the number of inverters N3 required to participate in grid-connected power supply is calculated, and the corresponding switch group is disconnected to disconnect the redundant parallel inverters from the grid; If the critical load cannot be started normally, reset the output power of the N1 parallel inverters to zero, and gradually increase the number of parallel inverters based on the N1 parallel inverters. After restarting the initial N1 inverters and the corresponding increased inverters, try to start the critical load again. Repeat this operation until the critical load is successfully started. If the critical load can start stably after increasing the number of parallel inverters, repeat the above operation and adjust the number of grid-connected inverters according to the actual output power of the BACKUP port.

2. The critical load grid-connected startup method of the grid-connected and off-grid energy storage inverter as claimed in claim 1, characterized in that: The following steps are also included: If the critical load still cannot start normally after increasing the number of parallel inverters to the maximum, the inverter will issue an overload alarm and the output power of each parallel inverter will be reduced to 0.

3. The critical load grid-connected startup method of the grid-connected and off-grid energy storage inverter as claimed in claim 1, characterized in that: The following steps are also included: If the calculated number of inverters required to participate in parallel operation N1 is greater than the actual number of inverters connected in parallel, the inverter will issue an overload alarm, and at the same time, the output power of each parallel inverter will be reduced to 0.

4. The critical load grid-connected startup method of the grid-connected and off-grid energy storage inverter according to any one of claims 1 to 3, characterized in that: The following steps are also included: The inverter feeds back the grid-connected status of key loads to the user through the communication interface.

5. The critical load grid-connected startup method of the grid-connected and off-grid energy storage inverter as claimed in claim 1, characterized in that: The calculation steps of the average apparent power value P at the BACKUP port within the detection period T are as follows: (1) in, is the nth sampling current at the BACKUP port, is the n+1th sampling current at the BACKUP port, is the nth sampling voltage at the BACKUP port, is the n+1th sampling voltage at the BACKUP port, n is the sampling number within a detection cycle T, and N is the total sampling number.

6. The critical load grid-connected startup method of the grid-connected and off-grid energy storage inverter as claimed in claim 1, characterized in that: The peak value of the detection pulse is 10-380V, the frequency is the power frequency of the power grid, the detection period T is 0.04-4s, and the sampling frequency is 500HZ.

7. The critical load grid-connected startup method of the grid-connected and off-grid energy storage inverter as claimed in claim 1, characterized in that: The DC power source is an energy storage battery or a PV battery.