A BIM-based engineering supervision method, device and electronic equipment

Through the BIM-based engineering supervision method, the construction process is simulated to determine whether the finished materials meet the construction requirements, which solves the problem of deviations in manual measurements and improves the accuracy and smoothness of the construction progress.

CN114186830BActive Publication Date: 2025-02-18GUANGDONG FINANCE & TRADE CONSTR ENG CONSULTING CO LTD
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
CN202111460215.8
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2021-12-02
Publication Date
2025-02-18
Estimated Expiration
2041-12-02

AI Technical Summary

Technical Problem

During the construction process, there are deviations in manual measurement of whether the finished materials meet the construction requirements, which will affect the construction progress.

Method used

Using BIM-based engineering supervision methods, by obtaining sub-projects to be constructed, finished material data and BIM models of completed construction stages, a second BIM model is established to simulate the construction process, intuitively judge whether the finished material meets the construction requirements, and analyze the causes of the problem.

Benefits of technology

It improves the accuracy of project supervision, reduces the impact of construction progress caused by manual measurement errors, and ensures the smooth progress of construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114186830B_ABST
    Figure CN114186830B_ABST
Patent Text Reader

Abstract

The present application relates to a method, device and electronic equipment for project supervision based on BIM, which includes: obtaining a first BIM model of a sub-project to be constructed, finished material data and a completed construction stage, wherein the finished material data is the size of the finished material; establishing a second BIM model according to the sub-project to be constructed, the finished material data and the first BIM model to simulate the construction process; judging whether there is a problem according to the second BIM model; if so, determining the cause of the problem according to the second BIM model. The present application can intuitively determine whether the finished material meets the construction requirements.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of building construction, and in particular to a BIM-based engineering supervision method, device and electronic equipment. Background Art

[0002] BIM technology is a digital tool used in engineering design, construction, and management. By integrating the digital and information models of buildings, it is shared and transmitted throughout the entire life cycle of project planning, operation, and maintenance, enabling engineering and technical personnel to correctly understand and efficiently respond to various building information.

[0003] During construction, a complete engineering project is usually divided into several sub-projects. In order to improve efficiency, most staff will use raw materials to produce finished materials that meet the construction requirements in advance according to the sub-projects to be constructed. However, in the process of producing finished materials, some construction materials may not meet the construction requirements due to construction errors. In order to solve this problem, most of the current methods use manual measurement to test the finished materials one by one. However, manual measurement often has deviations, which may lead to the discovery that the finished materials cannot meet the construction requirements during the construction process, which will affect the construction progress to a certain extent. Summary of the invention

[0004] In order to intuitively determine whether finished materials meet construction requirements, the present application provides a BIM-based engineering supervision method, device and electronic equipment.

[0005] In the first aspect, the present application provides a BIM-based engineering supervision method, which adopts the following technical solutions:

[0006] A BIM-based project supervision method, including:

[0007] Obtaining the sub-project to be constructed, the finished material data and the first BIM model of the completed construction stage, wherein the finished material data is the size of the finished material;

[0008] According to the sub-projects to be constructed, the finished material data and the first BIM model, a second BIM model is established to simulate the construction process;

[0009] Based on the second BIM model, determine whether there is a problem;

[0010] If yes, determine the cause of the problem based on the second BIM model.

[0011] By adopting the above technical solution, the first BIM model of the sub-projects to be constructed, the finished material data and the completed construction stage is obtained, and the second BIM model is established according to the sub-projects to be constructed, the finished material data and the first BIM model to simulate the construction process. In the simulated construction process, when the finished material data of the magic clothing does not meet the construction requirements, it can be intuitively discovered according to the established second BIM model. After the existing problems are found, the causes of the problems can be analyzed according to the second BIM model. Compared with judging whether it meets the construction requirements based on experience through manual measurement, the above solution can be intuitively seen through the second BIM model, and to a certain extent, the smooth progress of the construction is guaranteed.

[0012] Optionally, the method further includes:

[0013] Determine the solution to the problem based on the cause and case library;

[0014] Based on the preset determination rules, the target solution is determined.

[0015] By adopting the above technical solution, after determining the cause of the problem, a solution to the cause of the problem is searched in the case library according to the cause of the problem, and a target solution is determined based on a preset determination rule, so that the determined target solution is more in line with the construction requirements.

[0016] Optionally, after the finished material is manufactured, the finished material is placed in a preset placement area, and multiple image acquisition devices are set up at the construction site to collect image information of the finished material and the placement area in real time. The method for obtaining the finished material data specifically includes:

[0017] Acquire image information of the finished material and the image information of the placement area and feature information of the placement area;

[0018] Identify the image information of the finished material and the placement area, and determine the ratio of the finished material to the placement area;

[0019] Determine finished material data according to the size information of the placement area and the ratio of the finished material to the placement area, and store the finished material data in a database;

[0020] The finished product material information is retrieved from a database.

[0021] By adopting the above scheme, a placement area is set up to place finished materials. The ratio of the finished materials to the placement area is determined based on the acquired image information of the finished materials and the placement area, and the finished material data is determined in combination with the actual size of the placement area. Compared with manual measurement, a lot of manpower is saved, and at the same time, the inaccurate finished material data acquired due to manual measurement errors is reduced.

[0022] Optionally, the method for obtaining the first BIM model of the sub-project to be constructed and the completed construction stage specifically includes:

[0023] Obtain the sub-projects to be constructed that are manually input and store them in the database;

[0024] Retrieving the sub-project to be constructed from the database;

[0025] Obtain material data for each completed sub-project;

[0026] Establishing a first BIM model based on the material data of each completed sub-project, and storing the first BIM model in a database;

[0027] The first BIM model is retrieved from the database.

[0028] Optionally, the method of determining a solution to a problem based on the cause of the problem and the case library specifically includes:

[0029] Compare the cause of the problem with each case in the case library;

[0030] Identify each case that addresses the cause of the same problem;

[0031] Based on each case where the cause of solving the same problem is determined, the solution is determined.

[0032] Optionally, the method for determining the target solution based on a preset determination rule specifically includes:

[0033] Obtaining constraint conditions, where the constraint conditions are factors that will affect solving the problem;

[0034] Obtaining a weight corresponding to each constraint condition, and sorting the constraints from high to low according to the weight;

[0035] Calculate the impact of each solution on each constraint;

[0036] According to the ranking of the constraints, firstly, the influence of each solution on the first-ranked constraint is compared, and the number of the first solutions with the least influence on the first-ranked constraint is determined;

[0037] If the number of first solutions is greater than 1, then continue to compare the impact of each first solution on the second-ranked constraint condition, and determine the number of second solutions with the smallest impact on the second-ranked constraint condition;

[0038] If the number of the second solutions is equal to 1, determining the second solution as the target solution;

[0039] If the number of the second solutions is greater than 1, one of the second solutions is arbitrarily determined as the target solution.

[0040] In the second aspect, the present application provides a BIM-based engineering supervision device, which adopts the following technical solution:

[0041] A BIM-based engineering supervision device, comprising:

[0042] An acquisition module is used to acquire the sub-project to be constructed, the finished material data and the first BIM model of the completed construction stage, wherein the finished material data is the size of the finished material;

[0043] The construction simulation module is used to establish a second BIM model based on the sub-projects to be constructed, the finished material data and the first BIM model to simulate the construction process;

[0044] A judgment module, used for judging whether there is a problem according to the second BIM model;

[0045] The problem cause determination module is used to determine the cause of the problem according to the second BIM model.

[0046] Optionally, also include:

[0047] The solution retrieval module determines the solution to the problem based on the cause and the case library;

[0048] The solution determination module is used to determine the target solution based on preset determination rules.

[0049] In a third aspect of the present application, an electronic device is provided, which includes a memory and a processor, wherein a computer program is stored in the memory, and when the processor executes the program, the method described above is implemented.

[0050] In a fourth aspect of the present application, a computer-readable storage medium is provided, on which a computer program is stored, and when the program is executed by a processor, the method according to the first aspect of the present application is implemented.

[0051] It should be understood that the contents described in the Summary of the Invention are not intended to limit the key or important features of the embodiments of the present application, nor are they intended to limit the scope of the present application. Other features of the present application will become easily understood through the following description.

[0052] In summary, the present application includes at least one of the following beneficial technical effects:

[0053] By obtaining the first BIM model of the sub-projects to be constructed, the finished material data and the completed construction stage, and establishing the second BIM model according to the sub-projects to be constructed, the finished material data and the first BIM model, the construction process is simulated. In the simulated construction process, when the finished material data does not meet the construction requirements, it can be intuitively discovered according to the established second BIM model. After the existing problems are found, the causes of the problems can be analyzed according to the second BIM model. Compared with judging whether the construction requirements are met based on experience through manual measurement, the above scheme can be intuitively seen through the second BIM model, which improves the accuracy of project supervision and ensures the smooth progress of construction to a certain extent. BRIEF DESCRIPTION OF THE DRAWINGS

[0054] Figure 1 It is a flow chart of the BIM-based engineering supervision method provided in this application.

[0055] Figure 2 It is a structural block diagram of the BIM-based engineering supervision device provided by this application.

[0056] Figure 3 It is a structural schematic diagram of the electronic device provided by this application.

[0057] Explanation of the accompanying drawings: 200, engineering supervision device based on BIM; 201, acquisition module; 202, construction simulation module; 203, judgment module; 204, problem cause determination module; 205, solution retrieval module; 206, solution determination module; 301, CPU; 302, ROM; 303, RAM; 304, I / O interface; 305, input part; 306, output part; 307, storage part; 308, communication part; 309, drive; 310, removable medium. DETAILED DESCRIPTION

[0058] In order to make the purpose, technical solution and advantages of the embodiments of the present application clearer, the technical solution in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of this application.

[0059] In addition, the term "and / or" in this article is only a description of the association relationship between the associated objects, indicating that there can be three relationships. For example, A and / or B can represent: A exists alone, A and B exist at the same time, and B exists alone. In addition, the character " / " in this article generally indicates that the associated objects before and after are in an "or" relationship.

[0060] All terms (including technical terms or scientific terms) used in this application have the same meaning as those understood by ordinary technicians in the field to which this application belongs, unless otherwise specifically defined. It should also be understood that terms defined in general dictionaries should be interpreted as having a meaning consistent with their meaning in the context of the relevant technology, and should not be interpreted in an idealized or extremely formal sense, unless explicitly defined herein.

[0061] Technologies, methods, and equipment known to ordinary technicians in the relevant art may not be discussed in detail, but where appropriate, the technologies, methods, and equipment should be considered as part of the specification.

[0062] The present application embodiment discloses a BIM-based engineering supervision method. Figure 1 , BIM-based engineering supervision methods include:

[0063] S101: Acquire the sub-projects to be constructed, the finished material data and the first BIM model of the completed construction stage.

[0064] Specifically, during construction, a complete engineering project is usually divided into several sub-projects. The sub-projects to be constructed are sub-projects that are about to be constructed. Before construction, the sub-projects to be constructed are manually input through external devices, and the input sub-projects to be constructed are stored in a database. When the sub-projects to be constructed need to be obtained, the server retrieves the corresponding sub-projects to be constructed from the database. In this embodiment, the external device can be a mobile phone, a computer, or other device that can input information.

[0065] During construction, the material data of each sub-project will be stored in the database. Before the construction of the sub-project to be constructed, the server retrieves the material data of each completed sub-project from the database, and establishes a first BIM model based on the material data of each completed sub-project, and stores the first BIM model in the database. The server retrieves the first BIM model from the database when needed. The establishment of the BIM model is a well-known technical means for those skilled in the art, and will not be described in detail here.

[0066] Before carrying out the sub-item to be constructed, in order to ensure construction efficiency, the finished materials required for the sub-item to be constructed are first manufactured according to the construction requirements, and a placement area is designated at the construction site to hold the finished materials. The placement area is determined according to the type, shape and size of the finished materials. After the placement area is designated, the characteristic information of the placement area is uploaded to the server and stored in the database. The characteristic information includes the size and shape of the placement area.

[0067] A plurality of image acquisition devices are arranged at the construction site to acquire image information of finished materials and placement areas. The image acquisition devices upload the acquired image information to the server. The server identifies the received image information, determines the ratio of each finished material to the placement area, and then calculates each finished material data according to the determined ratio of each finished material to the placement area and the characteristic information of the placement area. The finished material data is the size of the finished material, and the determined finished material data is stored in a database. When necessary, the server retrieves the corresponding finished material data from the database according to actual needs.

[0068] For example: when constructing a building, a large number of floor slabs are needed. Most of the floor slabs are in the shape of a cuboid. In order to facilitate the determination of the size of the floor slabs through image recognition, a rectangular trough-shaped placement area is designed at the construction site. After the finished materials are processed, each finished material is placed in the placement area. The length, width and height of the placement area are A, B and C respectively. The ratio of the length of the floor slab to the length of the placement area is 1:3, the ratio of the width of the floor slab to the width of the placement area is 1:5, and the ratio of the height of the floor slab to the height of the placement area is 3:1. Therefore, it can be determined that the length, width and height of the floor slab are A / 3, B / 5 and 3C respectively.

[0069] S102: Building a second BIM model based on the sub-project to be constructed, the finished material data and the first BIM model to simulate the construction process.

[0070] S103: Determine whether there is a problem based on the second BIM model.

[0071] In step S102 and step S103, specifically, according to the acquired data of the sub-project to be constructed and the finished material, a second BIM model is established on the basis of the first BIM model to simulate the construction process of the sub-project to be constructed. During the construction simulation, when the data of a certain finished material does not meet the construction requirements, the first BIM model cannot be built. At this time, a prompt message is output, and the staff can intuitively find the problematic construction nodes according to the second BIM model.

[0072] S104: If yes, determine the cause of the problem according to the second BIM model.

[0073] Specifically, when it is determined that the server outputs a prompt message, the server simultaneously obtains the construction data of the construction node that causes the prompt message to be generated. The construction data includes the finished material data corresponding to the construction node and other construction data associated with the finished material data. The cause of the problem is determined based on the correlation between the data.

[0074] For example, when a floor slab cannot be placed at the construction location during floor construction, the size of the floor slab is first determined, and then the distance between the supporting materials used to support the floor slab is obtained. For example, if the distance between the supporting materials is E, and the length of the floor slab is F, F=E+e under normal conditions; e is a fixed constant; therefore, when F<E+e, the cause of the problem is determined to be that the floor slab is too short, and when F>E+e, the cause of the problem is determined to be that the floor slab is too long.

[0075] S105: Determine the solution to the problem based on the cause and case library.

[0076] Specifically, a case library is established through the big data of building plans. The case library stores cases in which problems arise in the construction process due to various reasons, as well as corresponding solutions and the time and cost of adopting the solutions. After the cause of the problem is determined, cases that lead to such problems due to the cause and corresponding solutions are retrieved from the case library based on the cause of the problem. The solutions include material adjustment and construction method adjustment.

[0077] S106: Determine a target solution based on a preset determination rule.

[0078] Specifically, the construction personnel determine the constraints according to the current construction process. The constraints are factors that will affect the solution of the problem. For example, in this embodiment, the constraints include cost and construction period. After the constraints are determined, the construction personnel determine the importance of different constraints according to the actual situation and set a weight for each constraint. The higher the weight, the more important the corresponding constraint. For example, in the current state, the construction period should be shortened as much as possible, so the weight corresponding to the construction period is set to 70%, and the weight corresponding to the cost is set to 30%. The constraints are sorted from high to low according to the weights, and the sorting result is construction period and cost; after the sorting is completed, the solutions are sorted from short to long according to the construction period corresponding to each solution, and the solution with the shortest construction period is determined. After the solution with the shortest construction period is determined, the number of solutions is determined. If the number of solutions is equal to 1, the solution with the shortest construction period is determined according to the cost. After the sorting is completed, the solution with the lowest cost among the solutions with the shortest construction period is determined. If the number of solutions with the lowest cost among the solutions with the shortest construction period is equal to 1, then the solution is the target solution. If the number of solutions with the lowest cost among the solutions with the shortest construction period is greater than 1, then any solution with the lowest cost among the solutions with the shortest construction period is selected as the target solution. In this embodiment, the number of constraints and the weight corresponding to each constraint can be set according to the actual working conditions, and there is no restriction here.

[0079] The present application also discloses a BIM-based engineering supervision device. Figure 2 , the BIM-based engineering supervision device 200 includes:

[0080] An acquisition module 201 is used to acquire the sub-project to be constructed, the finished material data and the first BIM model of the completed construction stage, wherein the finished material data is the size of the finished material;

[0081] The construction simulation module 202 is used to establish a second BIM model based on the sub-project to be constructed, the finished material data and the first BIM model to simulate the construction process;

[0082] A judgment module 203 is used to judge whether there is a problem according to the second BIM model;

[0083] A problem cause determination module 204, for determining the problem cause according to the second BIM model if yes;

[0084] The solution retrieval module 205 determines the solution to the problem according to the cause of the problem and based on the case library, and the solution includes material adjustment and construction method adjustment;

[0085] The solution determination module 206 is used to determine the target solution based on a preset determination rule.

[0086] Those skilled in the art can clearly understand that, for the convenience and brevity of description, the specific working process of the described module can refer to the corresponding process in the aforementioned method embodiment, and will not be repeated here.

[0087] The present application embodiment discloses an electronic device. Figure 3 The electronic device includes a central processing unit (CPU) 301, which can perform various appropriate actions and processes according to the program stored in the read-only memory (ROM) 302 or the program loaded from the storage part 307 to the random access memory (RAM) 303. In the RAM 303, various programs and data required for system operation are also stored. The CPU 301, the ROM 302 and the RAM 303 are connected to each other through a bus. The input / output (I / O) interface 304 is also connected to the bus.

[0088] The following components are connected to the I / O interface 304: an input section 305 including a keyboard, a mouse, etc.; an output section 306 including a cathode ray tube (CRT), a liquid crystal display (LCD), etc., and a speaker, etc.; a storage section 307 including a hard disk, etc.; and a communication section 308 including a network interface card such as a LAN card, a modem, etc. The communication section 308 performs communication processing via a network such as the Internet. A drive 309 is also connected to the I / O interface 304 as needed. A removable medium 310, such as a magnetic disk, an optical disk, a magneto-optical disk, a semiconductor memory, etc., is installed on the drive 309 as needed, so that a computer program read therefrom is installed into the storage section 307 as needed.

[0089] In particular, according to an embodiment of the present application, the above reference flow chart Figure 1 The described process can be implemented as a computer software program. For example, an embodiment of the present application includes a computer program product, which includes a computer program carried on a machine-readable medium, and the computer program contains program code for executing the method shown in the flowchart. In such an embodiment, the computer program can be downloaded and installed from a network through a communication part 308, and / or installed from a removable medium 310. When the computer program is executed by a central processing unit (CPU) 301, the above-mentioned functions defined in the device of the present application are executed.

[0090] It should be noted that the computer-readable medium shown in the present application may be a computer-readable signal medium or a computer-readable storage medium or any combination of the above two. The computer-readable storage medium may be, for example, but not limited to, an electrical, magnetic, optical, electromagnetic, infrared, or semiconductor system, device or device, or any combination of the above. More specific examples of computer-readable storage media may include, but are not limited to: an electrical connection with one or more wires, a portable computer disk, a hard disk, a random access memory (RAM), a read-only memory (ROM), an erasable programmable read-only memory (EPROM or flash memory), an optical fiber, a portable compact disk read-only memory (CD-ROM), an optical storage device, a magnetic storage device, or any suitable combination of the above. In the present application, a computer-readable storage medium may be any tangible medium containing or storing a program that can be used by or in combination with an instruction execution system, device or device. In the present application, a computer-readable signal medium may include a data signal propagated in a baseband or as part of a carrier wave, which carries a computer-readable program code. This propagated data signal may take a variety of forms, including but not limited to electromagnetic signals, optical signals, or any suitable combination of the above. Computer-readable signal media may also be any computer-readable medium other than computer-readable storage media, which may send, propagate or transmit a program for use by or in conjunction with an instruction execution system, apparatus or device. The program code contained on the computer-readable medium may be transmitted using any appropriate medium, including but not limited to: wireless, wire, optical cable, RF, etc., or any suitable combination of the above.

[0091] The flow chart and block diagram in the accompanying drawings illustrate the possible architecture, function and operation of the system, method and computer program product according to various embodiments of the present application. In this regard, each box in the flow chart or block diagram can represent a module, a program segment or a part of the code, and the aforementioned module, program segment or a part of the code contains one or more executable instructions for realizing the specified logical function. It should also be noted that in some alternative implementations, the functions marked in the box can also occur in a different order from the order marked in the accompanying drawings. For example, two boxes represented in succession can actually be executed substantially in parallel, and they can sometimes be executed in the opposite order, depending on the functions involved. It should also be noted that each box in the block diagram and / or flow chart, and the combination of the boxes in the block diagram and / or flow chart can be implemented with a dedicated hardware-based system that performs the specified function or operation, or can be implemented with a combination of dedicated hardware and computer instructions.

[0092] The above description is only a preferred embodiment of the present application and an explanation of the technical principles used. Those skilled in the art should understand that the scope of application involved in the present application is not limited to the technical solution formed by a specific combination of the above technical features, but should also cover other technical solutions formed by any combination of the above technical features or their equivalent features without departing from the aforementioned application concept. For example, the above features are replaced with (but not limited to) technical features with similar functions applied in the present application.

[0093] The above are all preferred embodiments of the present application, and are not intended to limit the protection scope of the present application. Any feature disclosed in this specification (including the abstract and drawings), unless otherwise stated, can be replaced by other equivalent or alternative features with similar purposes. That is, unless otherwise stated, each feature is only an example of a series of equivalent or similar features.

Claims

1. A BIM-based engineering supervision method, characterized by: The method includes: Obtaining the sub-project to be constructed, the finished material data and the first BIM model of the completed construction stage, wherein the finished material data is the size of the finished material; According to the sub-projects to be constructed, the finished material data and the first BIM model, a second BIM model is established to simulate the construction process; Based on the second BIM model, determine whether there is a problem; If yes, determine the cause of the problem based on the second BIM model; The method further includes: Determine the solution to the problem based on the cause and case library; Determine the target solution based on the preset determination rules; The solution to the problem is determined based on the cause of the problem and the case library, including: Compare the cause of the problem with each case in the case library; Identify each case that addresses the cause of the same problem; Determine the solution based on each case where the cause of solving the same problem is determined; The method for determining the target solution based on the preset determination rule specifically includes: Obtaining constraint conditions, where the constraint conditions are factors that will affect solving the problem; Obtaining a weight corresponding to each constraint condition, and sorting the constraints from high to low according to the weight; Calculate the impact of each solution on each constraint; According to the ranking of the constraints, firstly, the influence of each solution on the first-ranked constraint is compared, and the number of the first solutions with the least influence on the first-ranked constraint is determined; If the number of first solutions is greater than 1, then continue to compare the impact of each first solution on the second-ranked constraint condition, and determine the number of second solutions with the smallest impact on the second-ranked constraint condition; If the number of the second solutions is equal to 1, determining the second solution as the target solution; If the number of the second solutions is greater than 1, one of the second solutions is arbitrarily determined as the target solution.

2. The BIM-based engineering supervision method according to claim 1, characterized in that: After the finished material is produced, the finished material is placed in a preset placement area. A plurality of image acquisition devices are set up at the construction site to collect image information of the finished material and the placement area in real time. The method for obtaining the finished material data specifically includes: Acquire image information of the finished material and the placement area and characteristic information of the placement area; the characteristic information includes the size and shape of the placement area; Identify the image information of the finished material and the placement area, and determine the ratio of the finished material to the placement area; Determine finished material data according to the size information of the placement area and the ratio of the finished material to the placement area, and store the finished material data in a database; The finished product material information is retrieved from a database.

3. The BIM-based engineering supervision method according to claim 2 is characterized in that: The method for obtaining the first BIM model of the sub-project to be constructed and the completed construction stage specifically includes: Obtain the sub-projects to be constructed that are manually input and store them in the database; Retrieving the sub-project to be constructed from the database; Obtain material data for each completed sub-project; Establishing a first BIM model based on the material data of each completed sub-project, and storing the first BIM model in a database; The first BIM model is retrieved from the database.

4. A BIM-based engineering supervision device, characterized in that: The method for engineering supervision based on BIM according to any one of claims 1 to 3 comprises: An acquisition module (201) is used to acquire a sub-project to be constructed, finished material data and a first BIM model of a completed construction stage, wherein the finished material data is the size of the finished material; A construction simulation module (202) is used to establish a second BIM model based on the sub-project to be constructed, the finished material data and the first BIM model to simulate the construction process; A judgment module (203) is used to judge whether there is a problem according to the second BIM model; A problem cause determination module (204), configured to, if yes, determine the problem cause according to the second BIM model; Also includes: A solution retrieval module (205) determines a solution to the problem based on the cause of the problem and the case library; The solution determination module (206) is used to determine the target solution based on a preset determination rule.

5. An electronic device comprising a memory and a processor, wherein a computer program is stored in the memory, wherein: When the processor executes the program, the method according to any one of claims 1 to 3 is implemented.

6. A computer-readable storage medium having a computer program stored thereon, characterized in that: When the program is executed by a processor, the method according to any one of claims 1 to 3 is implemented.

Citation Information

Patent Citations

  • A schedule scheme evaluation and selection method based on hierarchical optimization

    CN101261702A

  • BIM-based construction progress monitoring method and system, electronic equipment and storage medium

    CN112016908A

  • Fault processing method and device, computer equipment and storage medium

    CN112418453A

  • Three-dimensional modeling method, device, electronic equipment and storage medium

    CN112686988A

  • BIM-based construction method and management system

    CN112990844A