Dynamic wireless charging facility deployment method for electric bus routes based on chance-constrained programming

By optimizing the layout of wireless charging facilities on bus lines using a method based on chance constrained programming, the problem of high cost of dynamic wireless charging facilities is solved, the battery capacity and body weight of electric buses are reduced, and the operating efficiency is improved.

CN114239201BActive Publication Date: 2024-10-15JILIN UNIVERSITY
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202111534980.X
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2021-12-15
Publication Date
2024-10-15
Estimated Expiration
2041-12-15

AI Technical Summary

Technical Problem

The cost of existing dynamic wireless charging facilities is relatively high, resulting in economic costs and resource waste when deployed on the entire bus line, which limits the development of electric buses.

Method used

A method based on chance constrained programming is used to divide bus lines, describe the operating status of electric buses, estimate power consumption and charging capacity, establish a chance constrained programming model, and optimize the layout location of wireless charging facilities to minimize the total layout cost. As the goal, random simulation technology and particle swarm algorithm are combined to solve the problem to determine the optimal layout plan.

Benefits of technology

It effectively reduces the battery rated capacity of electric buses, reduces the body weight, improves operational efficiency, reduces the operating costs of bus companies, guides the planning of dynamic wireless charging facilities, and solves the problems of short driving range and frequent charging needs of electric buses. question.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114239201B_ABST
    Figure CN114239201B_ABST
Patent Text Reader

Abstract

The present invention relates to a method for laying out dynamic wireless charging facilities for electric bus lines based on chance-constrained programming. The purpose of the present invention is to solve the problem that the cost of existing dynamic wireless charging facilities is high. If wireless charging plates are laid out on the entire line, it will not only generate large economic costs, but also cause waste of resources. The process is: Step 1: Divide the bus lines; Step 2: Describe the operating status of the electric bus lines based on Step 1; Step 3: Estimate the power consumption and charging amount of the electric bus based on Step 2; Step 4: Express the change of the power of the electric bus based on Step 3; Step 5: Establish an opportunity-constrained programming model based on Step 4; Step 6: Solve the opportunity-constrained programming model to obtain the optimal layout plan of the dynamic wireless charging facilities for the basic units of the line and the corresponding minimum total layout cost. The present invention is used in the field of urban transportation planning.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the field of urban traffic planning, and in particular relates to a method for laying out dynamic wireless charging facilities for electric bus lines. Background Art

[0002] In recent years, in order to reduce the operating costs of public transportation companies and reduce public transportation pollution emissions, my country has been vigorously promoting the electrification of urban public transportation vehicles. However, electric buses have problems such as short driving range and frequent charging, which have a great impact on line operation and scheduling. At present, in order to increase the driving range of electric buses, public transportation companies often equip them with batteries with larger rated capacity, which not only increases the purchase cost of the vehicle, but also increases the weight of the bus body and the energy consumption per unit mileage.

[0003] Dynamic wireless charging technology allows electric vehicles to transmit electrical energy to energy storage devices on ground vehicles in the form of high-frequency alternating magnetic fields through power supply rails buried in the ground while driving, enabling the vehicle to charge while driving. This is of great significance for reducing battery rated capacity, reducing vehicle weight, and improving endurance.

[0004] If wireless charging facilities are configured for bus routes, electric buses can charge while driving, without the need or less time to arrange special charging time, which can not only reduce the number of vehicles required for line operation, but also electric buses only need to be equipped with smaller capacity batteries, reducing the body weight and unit energy consumption. However, the cost of dynamic wireless charging facilities is high. If wireless charging boards are laid out on the entire route, it will not only incur a large economic cost, but also cause a waste of resources, thus restricting the further development of electric buses. Summary of the invention

[0005] The purpose of the present invention is to solve the problem that the cost of existing dynamic wireless charging facilities is high. If wireless charging boards are deployed on the entire line, it will not only incur a large economic cost, but also cause a waste of resources. A method for deploying dynamic wireless charging facilities for electric bus lines based on chance constrained programming is proposed.

[0006] The specific process of the dynamic wireless charging facility layout method for electric bus lines based on chance-constrained programming is as follows:

[0007] Step 1: Divide the bus routes;

[0008] Step 2: Describe the operation status of the electric bus line based on step 1;

[0009] Step 3: Estimate the power consumption and charging amount of the electric bus based on step 2;

[0010] Step 4: Express the change of electric bus power based on step 3;

[0011] Step 5: Establish an opportunity-constrained programming model based on step 4;

[0012] Step 6: Solve the chance-constrained programming model to obtain the optimal layout plan of the dynamic wireless charging facilities of the basic line unit and the corresponding minimum total layout cost.

[0013] The beneficial effects of the present invention are:

[0014] This invention takes electric buses as the research object. In order to solve the problems of short driving range of electric buses, frequent charging, the impact on line operation and scheduling, and the high cost of dynamic wireless charging facilities, this invention considers the randomness of electric bus travel time and proposes a dynamic wireless charging facility deployment method based on chance-constrained planning. This is of great significance for improving the operating efficiency of electric bus lines, reducing the operating costs of bus companies, and guiding the planning of dynamic wireless charging facilities.

[0015] The present invention proposes a method for deploying dynamic wireless charging facilities based on chance-constrained programming for bus-only lanes. By optimizing the layout of wireless charging facilities, the contradiction between frequent charging demand, short driving range and vehicle scheduling of electric buses is solved without increasing the number of vehicles running on the line, so as to reduce the cost of deploying dynamic wireless charging facilities on bus lines and improve the reliability of electric bus operation. The implementation steps are as follows: dividing the rapid bus line with dedicated lanes into basic units such as stations, intersections, and sections; considering the random fluctuations of the travel time of buses of different shifts in each basic unit, describing the movement process of the bus, calculating the charging amount and power consumption of each basic unit according to the movement state, and then establishing a battery charge state estimation model; then taking whether each basic unit is equipped with wireless charging facilities as the optimization variable, taking the minimum total layout cost of wireless charging facilities as the optimization target, and taking the remaining power of the electric bus to meet the normal operation of the line as the constraint condition, an optimization model based on chance-constrained programming is established; and a solution process based on random simulation technology and particle swarm algorithm is designed, and finally determining the optimal layout plan of wireless charging facilities on the bus line and the corresponding minimum total layout cost. The present invention can effectively reduce the rated capacity of the battery of the electric bus, reduce the weight of the vehicle body, and alleviate the driver's "range anxiety". BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1 It is a flow chart of the present invention;

[0017] Figure 2 It is a schematic diagram of the division of the basic units of the bus line of the present invention. DETAILED DESCRIPTION

[0018] Specific implementation method 1: The specific process of the method for deploying dynamic wireless charging facilities for electric bus routes based on chance-constrained planning in this implementation method is as follows:

[0019] Step 1: Divide the bus routes;

[0020] Step 2: Describe the operation status of the electric bus line based on step 1;

[0021] Step 3: Estimate the power consumption and charging amount of the electric bus based on step 2;

[0022] Step 4: Express the change of electric bus power based on step 3;

[0023] Step 5: Establish an opportunity-constrained programming model based on step 4;

[0024] Step 6: Solve the chance-constrained programming model to obtain the optimal layout plan of the dynamic wireless charging facilities of the basic line unit and the corresponding minimum total layout cost.

[0025] Specific implementation method 2: This implementation method is different from the specific implementation method 1 in that the bus routes are divided in step 1; the specific process is as follows:

[0026] The bus routes are divided into three parts: intersection area, station area and section area, as shown in the attached figure. Figure 2 As shown;

[0027] Each station area is a basic unit, and the length of each station basic unit is equal to the length of the bus stop;

[0028] Each intersection area is a basic unit, and the length of each intersection basic unit is equal to the distance from the intersection stop line to the farthest point in the queue;

[0029] The remaining part of the bus line except the station area and the intersection area is regarded as the section area, and each section area is divided into several section basic units with Δ as the basic length in m;

[0030] A bus route consists of multiple basic units;

[0031] A route consists of intersections, stations and road sections. Each station is considered as a basic unit, each intersection is considered as a basic unit, and the road section is divided into multiple road section basic units. Therefore, a route consists of multiple basic units.

[0032] The bus line is divided into L basic units in a single direction. The length of the basic unit l is The unit is m,

[0033] u represents the running direction of the electric bus on the bus line, u = 0 represents the upward direction, and u = 1 represents the downward direction; decision variables Indicates direction u basic unit l is arranged with wireless charging facilities; Indicates that no wireless charging facilities are deployed.

[0034] The other steps and parameters are the same as those in the first embodiment.

[0035] Specific implementation method three: This implementation method is different from specific implementation methods one or two in that the electric bus line operation status is described based on step one in step two; the specific process is as follows:

[0036] The present invention refers to the process of a bus running from the departure station to the terminal station as a shift;

[0037] The vehicle returns to the depot after a full day of operation and is recharged at night until the battery reaches its maximum capacity. The vehicle then departs from the depot the next day to start daily operations.

[0038] Since there is a certain correlation between the remaining power of two adjacent shifts of the same bus, that is, the remaining power of the vehicle at the end of the previous shift is equal to the remaining power at the start of the current shift, taking bus k as an example, the I shifts served by bus k throughout the day are numbered according to the departure order, namely 1, 2, 3, ..., I;

[0039] The travel time t of the i-th shift of vehicle k on basic unit l i,k,l The calculation of is divided into two cases:

[0040] When the base unit l belongs to a site area:

[0041]

[0042] In the formula: to p ,t cl is the average opening and closing time of the bus door / s; is the average time for each passenger to get on and off the bus / (s·person -1 ); is the number of passengers boarding the i-th bus k at the station in the basic unit l; is the number of passengers getting off the i-th bus k arriving at the station in basic unit l;

[0043] When the basic unit l belongs to an intersection or a road section area:

[0044]

[0045] Where: v i,k,l is the running speed of bus k i-th shift on basic unit l; is the length of the basic unit l in direction u;

[0046] The speed of buses in different shifts and different basic units follows different probability distributions; f(v i,k,l ) indicates v i,k,l The probability density function of in and They represent the minimum and maximum running speeds of bus k’s i-th shift on basic unit l respectively.

[0047] The other steps and parameters are the same as those in the first or second embodiment.

[0048] Specific implementation method 4: This implementation method is different from one of the specific implementation methods 1 to 3 in that the power consumption and charging amount of the electric bus are estimated based on step 2 in step 3; the specific process is:

[0049] Assuming that the speed of the bus on the basic unit l changes uniformly, the relationship between acceleration and speed is:

[0050]

[0051] Where: is the speed of bus k at the end of basic unit l (m·s -1 ), d is the end point of the basic unit; is the speed of bus k at the starting point of basic unit l / (m·s -1 ), o is the starting point of the basic unit; t i,k,l is the travel time of bus k’s ith shift in basic unit l / s;

[0052] The speed v of bus k i-th shift in unit l at time t i,k,l (t), as shown in formula (4):

[0053]

[0054] When the bus is running on the line, the vehicle has braking energy recovery, that is, when the vehicle brakes, the heat energy generated by friction is converted into kinetic energy and recovered into the energy storage device, thereby reducing the energy consumption of the vehicle. Therefore, the actual power consumption of the i-th bus k in the basic unit l is Affected by the power consumed by wheel rotation and the power recovered when the vehicle brakes. Based on vehicle kinematics data, vehicle characteristics, road grade, rolling friction, etc., the instantaneous wheel power of the bus can be obtained. Instantaneous power of bus wheels The expression is:

[0055]

[0056] Where: m i,k,l is the total mass of bus k on the basic unit l / kg; a i,k,l is the acceleration of bus k on the i-th shift on the basic unit l / (m·s -2 ); g is the acceleration due to gravity / (m·s -2 );θ l is the inclination angle of the basic unit l / rad; C r 、c r1 、c r2 is the rolling resistance parameter; v i,k,l (t) is the running speed of the ith bus k on the basic unit l at time t / (m·s -1 );ρ air is the air density / (kg·m -3 );A f is the frontal projection area of ​​the vehicle / m 2 ; C D is the air resistance coefficient;

[0057] In the above formula, the total mass of the bus is m i,k,l Including the fixed mass of the vehicle (excluding the battery mass), the battery mass, and the mass of the driver and passengers in the vehicle;

[0058] The above is the fixed mass of the vehicle excluding the mass of the battery;

[0059] In the basic unit l, the number of passengers in the i-th bus is p i,k,l It is equal to the cumulative sum of the difference in the number of people getting on and off at all the stops the bus passes from the departure station to the basic unit l;

[0060]

[0061] Where: Z l is the total number of stations from the originating station to the basic unit l; is the number of passengers boarding bus k at station z for the i-th bus; is the number of passengers getting off bus k at station z for the i-th bus;

[0062] m i,k,l It is equal to the sum of the vehicle's fixed mass, battery mass, driver mass, and passenger mass;

[0063]

[0064] Where: m0 is the fixed mass of the vehicle excluding the battery mass / kg; ρ B is the energy density of the battery / (kWh·kg -1); B0 is the battery capacity / kWh; m div is the mass of the driver / kg; m p is the average mass per passenger / kg;

[0065] According to the instantaneous power of bus wheels Calculate the traction power required for vehicle operation and braking energy recovery power

[0066] When the vehicle is in traction mode, energy flows from the motor to the wheels, which is power output, defined as is a non-negative value, calculate

[0067] When the vehicle is in braking mode, energy is recovered from the wheels into the energy storage device, which is power input. For negative values, calculate

[0068]

[0069] Where: η DL , η EM , η BAT , η RB,i,k,l They are the efficiency values ​​of the transmission system, motor system, battery system, and brake energy recovery;

[0070] η RB,i,k,l It is related to the acceleration of the vehicle during braking. Fiori et al. used the least square method to correct the parameters of formula (9) and obtained that ε is 0.0411;

[0071]

[0072] Where: ε is the relevant parameter;

[0073] The actual power consumption of bus k on the basic unit l It is equal to the difference between the amount of electricity consumed during vehicle operation and the amount of electricity recovered during vehicle braking;

[0074]

[0075] The actual power consumption of bus k's ith shift on basic unit l The unit is kWh;

[0076] The amount of charge of bus k on the basic unit l during the i-th shift As shown in formula (11);

[0077]

[0078] Where: η + is the conversion efficiency of the charging plate / %; When a charging board is deployed for the basic unit l, the power of the charging board / W;

[0079] The amount of charge of bus k on the i-th shift on the basic unit l The unit is kWh.

[0080] The other steps and parameters are the same as those in Specific Embodiments 1 to 3.

[0081] Specific implementation method 5: This implementation method is different from any one of the specific implementation methods 1 to 4 in that the electric bus power change expression is performed based on step 3 in step 4; the specific process is:

[0082] The change in the amount of electricity in a vehicle during operation is expressed by the battery's state of charge (SOC), which is expressed by formula (12):

[0083]

[0084] Where: s is the state of charge of the battery / %; B' is the remaining capacity of the battery / kWh; B0 is the rated capacity of the battery / kWh;

[0085] The soc value of bus k at the starting point of basic unit l is When i=l=1, It represents the SOC value of the first bus k at the route departure station (the starting point of basic unit 1), which is equal to the SOC value when the vehicle leaves the depot minus the SOC change during the process of running from the depot to the route departure station. o represents the starting point of the basic unit;

[0086]

[0087] Where: s max is the initial soc value of the bus throughout the day, that is, the maximum soc value / %; is the power consumption of bus k from the depot to the starting station of the route every day / kWh;

[0088] represents the soc value when the i-th bus k arrives at the starting station of the line; when bus k is the first bus k (i=1), Value equal to on the contrary Value equal to

[0089]

[0090] Where: is the soc value of bus k’s i-1th trip at the route terminal (the end of basic unit L), and d is the end of the basic unit;

[0091] The shift i-1 is the shift before shift i; the soc value of bus k arriving at the starting point of basic unit l+1 (the end point of basic unit l) is When wireless charging facilities are installed on the basic unit l When the vehicle consumes and replenishes electricity during the operation of the basic unit l, the soc value of the vehicle may increase or decrease; if the soc value reaches s max , even if the vehicle continues to run on the charging plate, the soc does not change; when there is no wireless charging facility on the basic unit l When the vehicle's soc value continues to decrease;

[0092]

[0093] Where: is the power consumption of bus k on the basic unit l (kWh); is the charging amount of bus k on the basic unit l for the i-th shift / kWh; is the soc value / % of bus k’s ith shift at the starting point of basic unit l.

[0094] The other steps and parameters are the same as those in Specific Embodiments 1 to 4.

[0095] Specific implementation method 6: This implementation method is different from any one of the specific implementation methods 1 to 5 in that the opportunity constraint programming model is established based on step 4 in step 5; the specific process is:

[0096] The optimization goal of this study is to minimize the total deployment cost of wireless charging facilities, which includes fixed costs and variable costs. Fixed costs are mainly the cost of inverters, which are determined by the unit price and quantity of inverters. Variable costs are mainly determined by the deployment length of wireless charging plates.

[0097] If multiple basic units are deployed with wireless charging pads, only one inverter needs to be installed; therefore, the number of inverters required on the line is equal to the difference between the total number of basic units with wireless charging pads deployed on the line and the total number of wireless charging pads deployed on two adjacent basic units;

[0098]

[0099] The chance constrained programming model is as follows:

[0100]

[0101]

[0102]

[0103]

[0104]

[0105] Formula (17) is the optimization objective function, which is to minimize the total deployment cost of wireless charging facilities;

[0106] where c var is the cost of the charging plate per unit length / (yuan·m -1 ), c fix is the cost of a single inverter / (yuan / unit -1 ), Indicates the length of the basic unit l in direction u / m;

[0107] Formula (18) is a constraint on the remaining power of the vehicle after the last shift;

[0108] Formula (19) represents the constraint on the remaining power of the vehicle at the end point of basic unit l;

[0109] α and β are pre-given confidence levels. Respectively represent events Probability of establishment;

[0110] It represents the soc value of bus k at the end of basic unit L after the operation of bus k ends. represents the soc value of bus k operating shift i at the starting point of basic unit l; s min Indicates the lower limit of the soc value of the electric bus battery; It represents the amount of electricity consumed by bus k when returning to the station after the end of operation shift I (kWh); They represent the charging capacity and power consumption of bus k in operating shift i in basic unit l / kWh respectively;

[0111] Formula (20) indicates that the total length of the charging board is less than the total length of the line.

[0112] The other steps and parameters are the same as those in Specific Implementation Methods 1 to 5.

[0113] Specific implementation method 7: This implementation method is different from any one of specific implementation methods 1 to 6 in that the opportunity constraint programming model is solved in step 6 to obtain the optimal layout plan of the line basic unit dynamic wireless charging facilities and the corresponding minimum total layout cost; the specific process is:

[0114] Step 61: Convert the constrained problem into an unconstrained problem; the specific process is:

[0115] By setting the penalty function, the constrained problem is transformed into an unconstrained problem, and then the discrete particle swarm algorithm is used to solve it. As shown in formula (22), formula (23) and formula (24):

[0116]

[0117]

[0118]

[0119] Regarding the constraints, this paper believes that under different confidence levels, when the constraints are not met, the penalty function is set to 1; when the constraints are met, the penalty function is set to 0;

[0120] Therefore, the objective function formula (17) is transformed into formula (25):

[0121]

[0122] Where: c var is the cost of the charging plate per unit length / (yuan·m -1 ), c fix is the cost of a single inverter / (yuan / unit -1 ); Indicates the length of the basic unit l in direction u / m; τ1, τ2, τ3 are penalty coefficients, which are generally large; are the penalty functions corresponding to the constraint conditions (18), (19), and (20) respectively;

[0123] Step 62: Use random simulation (also known as Monte Carlo simulation) and particle swarm algorithm to solve the chance constraint model (the optimization model composed of formulas 17-21, and according to step 61, convert formula 17 to 25 when solving); obtain the optimal layout plan of the line basic unit dynamic wireless charging facilities and the corresponding minimum total layout cost.

[0124] The other steps and parameters are the same as those in Specific Embodiments 1 to 6.

[0125] Specific implementation eight: This implementation is different from specific implementations one to seven in that, in step six two, random simulation (also known as Monte Carlo simulation) and particle swarm algorithm are used to solve the chance-constrained programming model (the optimization model composed of formulas 17-21, and according to step six one, formula 17 is converted into 25 when solving), to obtain the optimal layout plan of the line basic unit dynamic wireless charging facilities and the corresponding minimum total layout cost; the specific process is:

[0126] Step 621:

[0127] Stochastic simulation technology is a typical method for dealing with problems involving random variables. It mainly performs sampling based on probability distribution and obtains statistical estimates of random variables through a large number of experiments.

[0128] The steps of stochastic simulation are as follows:

[0129] (1) Obtain the variance and mean of the vehicle's running speed at each basic unit l under random conditions, as well as the number of passengers getting on and off at the station, the stop time at the station, and the relevant parameters required to calculate the SOC value of the end point of the basic unit l (all parameters involved in formulas (1) to (15));

[0130] (2) Set A′=0, A″=0;

[0131] (3) Set the probability density function f(v i,k,l ), based on the probability density function f(v i,k,l ) Get A random variable samples of speed

[0132] (4) Substitute the random variable sample output from (3) into the constraint condition ( and )middle;

[0133] if If it holds, then A′=A′+1, otherwise A′ remains unchanged;

[0134] if If it holds, then A″=A″+1, otherwise A″ remains unchanged;

[0135] The two constraint formulas involve speed (Formula (1) to Formula (15), obtained in (1));

[0136] (5) Output A′ / A, A″ / A;

[0137] Step 622: Embed the random simulation technology into the particle swarm algorithm to solve the problem and obtain the optimal layout plan of the dynamic wireless charging facilities of the basic line unit and the corresponding minimum total layout cost.

[0138] The other steps and parameters are the same as those in Specific Embodiments 1 to 7.

[0139] Specific implementation method 9: This implementation method is different from specific implementation methods 1 to 8 in that in step 622, random simulation technology is embedded in the particle swarm algorithm to solve the problem, so as to obtain the optimal layout plan of the line basic unit dynamic wireless charging facilities and the corresponding minimum total layout cost; the steps are as follows:

[0140] (1) Set algorithm parameters:

[0141] The number of random simulations is set to 500, the confidence levels α and β are both 0.95 (the confidence levels α and β in formula (18) and formula (19) are both 0.95), the number of particles in the particle swarm algorithm is 200, the maximum number of iterations is 300, the maximum value of the inertia weight ω is 0.94, and the minimum value is 0.4;

[0142] (2) In the solution space, randomly initialize the position and velocity of each particle in the particle population;

[0143] The position of each particle has D dimensions, where D is equal to the number of basic units, and the value of each basic unit is only 0 or 1;

[0144] The velocity of each particle has D dimensions, where D is equal to the number of basic units. The velocity value of each dimension (i.e., each basic unit) is randomly set according to the velocity constraints of each basic unit.

[0145] A route consists of intersections, stations and road sections. Each station is considered as a basic unit, each intersection is considered as a basic unit, and the road section is divided into multiple road section basic units. Therefore, a route consists of multiple basic units.

[0146] (3) According to the random simulation process in step 6, the values ​​of A′ / A and A″ / A are regarded as the actual probabilities of the chance constraints; the actual probability values ​​are substituted into formulas (22)-(24) to calculate the penalty function corresponding to each constraint condition. (A′ / A is The probability of , is substituted into formula 22; The probability is substituted into Formula 23; Formula 24 does not require random simulation. Formula 24 is just a constraint condition, that is, the number of laid charging boards does not exceed the total number of basic units of the line, and there is no need to calculate it);

[0147] Based on the penalty function and the position and velocity of each particle randomly initialized in (2), the objective function value of each particle is calculated, and the calculated objective function value of each particle is regarded as the current optimal objective function value of the particle, and its corresponding position is stored in the Among them represents the optimal position of an individual; compare the optimal objective function values ​​of all particles in the group, and The individual positions corresponding to the minimum values ​​of Among them represents the optimal position of the population;

[0148] (4) Using the iterative formula (26)-(27) of the particle swarm optimization algorithm, update the velocity and position of the particle;

[0149] Formulas (28)-(29) are used to realize the binarization of particle position values, that is, to ensure that the dimension value of each particle position is only 0 or 1;

[0150]

[0151]

[0152] Where: is the velocity of the ath particle at the x+1th iteration / (m·s -1 ); is the velocity of the ath particle at the xth iteration / (m·s -1 ); is the position of the ath particle at the xth iteration; ω is the inertia weight; c1 and c2 are acceleration factors; r1 and r2 are random numbers uniformly distributed between 0 and 1; x is the number of iterations;

[0153] Since the wireless charging facility location optimization model studied in this paper belongs to an integer programming problem, a discrete particle swarm optimization algorithm is used to solve it; the particle speed will be limited to [-V max ,V max ], where V max Represents the maximum velocity of the particle, and the position update formula is as follows:

[0154]

[0155]

[0156] Where: random represents a pseudo-random number uniformly distributed in the interval [0,1];

[0157] (5) According to the random simulation process in step 6, the values ​​of A′ / A and A″ / A are regarded as the actual probabilities of the chance constraints; the actual probability values ​​are substituted into formulas (22)-(24) to calculate the penalty function corresponding to each constraint condition. (A′ / A is The probability of , is substituted into formula 22; The probability is substituted into Formula 23; Formula 24 does not require random simulation. Formula 24 is just a constraint condition, that is, the number of laid charging boards does not exceed the total number of basic units of the line, and there is no need to calculate it);

[0158] Based on the penalty function and the updated particle speed and position in (4), calculate the particle's objective function value (the sum of the total layout cost corresponding to the current line basic unit layout plan and the penalty function value);

[0159] Compare the objective function value of the current particle with its historical optimal objective function value. If the objective function value of the current particle is smaller, replace the individual Otherwise, no replacement is required; the optimal value of the optimal objective function value of all particles in the group is compared with The corresponding objective function values ​​are compared. If the current group optimal value is smaller, the position of the particle corresponding to the current group optimal value is used to replace Otherwise, no replacement is required;

[0160] (6) If the stopping condition is met, that is, the set maximum number of iterations (usually the preset calculation accuracy or number of iterations) is reached, the search is stopped and the best particle is given as the optimal solution (that is, the line basic unit dynamic wireless charging layout plan corresponding to the minimum total layout cost when all constraints are met), otherwise return to (4).

[0161] The other steps and parameters are the same as those in Specific Embodiments 1 to 8.

[0162] Specific implementation method 10: This implementation method is different from the specific implementation methods 1 to 9 in that the process of solving the inertia weight ω is:

[0163] In the particle swarm algorithm, the inertia weight ω affects the algorithm's search ability. A larger ω can enhance the algorithm's global search ability; a smaller ω can improve the algorithm's local search ability. The calculation of the inertia weight in this paper is shown in formula (30):

[0164]

[0165] Where: ω(χ) is the inertia weight factor of the χth iteration; χ is the number of iterations; χ max is the final number of iterations of the algorithm; ω min is the minimum inertia weight factor; ω max is the maximum inertia weight factor;

[0166] The process of solving the acceleration factors c1 and c2 is:

[0167] The acceleration factor affects the optimization process of the particle swarm algorithm. The PSO algorithm performs a global search in the early stage of optimization. At this time, individuals learn from the global world, and c1 should take a larger value; while in the later stage of optimization, local search occurs, and c2 should take a larger value. The sine function is used to simulate the change of the acceleration factor.

[0168]

[0169]

[0170] Where: c1(χ), c2(χ) are acceleration factors, c a , c b , c γ , c0 is the relevant parameter;

[0171] c a =1, c b =1.5, c γ =1, c0=1.5.

[0172] The other steps and parameters are the same as those in Specific Embodiments 1 to 9.

[0173] The present invention may also have many other embodiments. Without departing from the spirit and essence of the present invention, those skilled in the art may make various corresponding changes and modifications based on the present invention, but these corresponding changes and modifications should all fall within the scope of protection of the claims attached to the present invention.

Claims

1. A method for deploying dynamic wireless charging facilities on electric bus routes based on chance-constrained programming, characterized in that: The specific process of the method is: Step 1: Divide the bus routes; Step 2: Describe the operation status of the electric bus line based on step 1; Step 3: Estimate the power consumption and charging amount of the electric bus based on step 2; Step 4: Express the change of electric bus power based on step 3; Step 5: Establish an opportunity-constrained programming model based on step 4; Step 6: Solve the chance-constrained programming model to obtain the optimal layout plan of the line basic unit dynamic wireless charging facilities and the corresponding minimum total layout cost; In the step 1, the bus routes are divided; the specific process is as follows: Divide the bus routes into three parts: intersection area, station area and section area; Each station area is a basic unit, and the length of each station basic unit is equal to the length of the bus stop; Each intersection area is a basic unit, and the length of each intersection basic unit is equal to the distance from the intersection stop line to the farthest point in the queue; The remaining part of the bus line except the station area and the intersection area is regarded as the section area, and each section area is divided into several section basic units with Δ as the basic length in m; A bus route consists of multiple basic units; The bus line is divided into L basic units in a single direction. The length of the basic unit l is The unit is m, u represents the running direction of the electric bus on the bus line, u = 0 represents the upward direction, and u = 1 represents the downward direction; decision variables Indicates direction u basic unit l is arranged with wireless charging facilities; It means that wireless charging facilities will not be deployed; In the step 2, the running status of the electric bus line is described based on the step 1; the specific process is: The process of a bus running from the starting station to the terminal is called a trip; The vehicle returns to the depot after a full day of operation and is recharged at night until the battery reaches its maximum capacity. The vehicle then departs from the depot the next day to start daily operations. The remaining power of the vehicle at the end of the previous shift is equal to the remaining power at the start of the current shift. The I shifts served by bus k throughout the day are numbered in the order of departure, 1, 2, 3, ..., I; The travel time t of the i-th shift of vehicle k on basic unit l i,k,l The calculation of is divided into two cases: When the base unit l belongs to a site area: Where: t op ,t cl is the average opening and closing time of the bus door / s; is the average time for each passenger to get on and off the bus / (s·person -1 ); is the number of passengers boarding the i-th bus k at the station in the basic unit l; is the number of passengers getting off the i-th bus k arriving at the station in the basic unit l; When the basic unit l belongs to an intersection or a road section area: Where: v i,k,l is the running speed of bus k i-th shift on basic unit l; is the length of the basic unit l in direction u; The speed of buses in different shifts and different basic units follows different probability distributions; f(v i,k,l ) indicates v i,k,l The probability density function of in and They represent the minimum and maximum running speeds of bus k’s ith shift on basic unit l respectively; In step 3, the power consumption and charging amount of the electric bus are estimated based on step 2; the specific process is: Assuming that the speed of the bus on the basic unit l changes uniformly, the relationship between acceleration and speed is: Where: is the speed of bus k at the end of basic unit l (m·s -1 ), d is the end point of the basic unit; is the speed of bus k at the starting point of basic unit l / (m·s -1 ), o is the starting point of the basic unit; t i,k,l is the travel time of bus k’s ith shift in basic unit l / s; The speed v of bus k i-th shift in unit l at time t i,k,l (t), as shown in formula (4): Instantaneous power of bus wheels The expression is: Where: m i,k,l is the total mass of bus k on the basic unit l / kg; a i,k,l is the acceleration of bus k on the i-th shift on the basic unit l / (m·s -2 ); g is the acceleration due to gravity / (m·s -2 );θ l is the inclination angle of the basic unit l / rad; C r 、c r1 、c r2 is the rolling resistance parameter; v i,k,l (t) is the running speed of the ith bus k on the basic unit l at time t / (m·s -1 );ρ air is the air density / (kg·m -3 );A f is the frontal projection area of ​​the vehicle / m 2 ; C D is the air resistance coefficient; In the above formula, the total mass of the bus is m i,k,l Including the fixed mass of the vehicle, the mass of the battery, and the mass of the driver and passengers in the vehicle; In the basic unit l, the number of passengers in the i-th bus is p i,k,l It is equal to the cumulative sum of the difference in the number of people getting on and off at all the stops the bus passes from the departure station to the basic unit l; Where: Z l is the total number of stations from the originating station to the basic unit l; is the number of passengers boarding bus k at station z for the i-th bus; is the number of passengers getting off bus k at station z for the i-th bus; m i,k,l It is equal to the sum of the vehicle's fixed mass, battery mass, driver mass, and passenger mass; Where: m0 is the fixed mass of the vehicle excluding the battery mass / kg; ρ B is the energy density of the battery / (kWh·kg -1 ); B0 is the battery capacity / kWh; m div is the mass of the driver / kg; m p is the average mass per passenger / kg; According to the instantaneous power of bus wheels Calculate the traction power required for vehicle operation and braking energy recovery power When the vehicle is in traction mode, energy flows from the motor to the wheels, which is power output, defined as is a non-negative value, calculate When the vehicle is in braking mode, energy is recovered from the wheels into the energy storage device, which is power input. For negative values, calculate Where: η DL , η EM , η BAT , η RB ,i,k,l are the efficiency values ​​of the transmission system, motor system, battery system, and braking energy recovery respectively; Where: ε is the relevant parameter; The actual power consumption of bus k on the basic unit l It is equal to the difference between the amount of electricity consumed during vehicle operation and the amount of electricity recovered during vehicle braking; The actual power consumption of bus k's ith shift on basic unit l The unit is kWh; The amount of charge of bus k on the basic unit l during the i-th shift As shown in formula (11); Where: η + is the conversion efficiency of the charging plate / %; When a charging board is deployed for the basic unit l, the power of the charging board / W; The amount of charge of bus k on the i-th shift on the basic unit l The unit is kWh; In step 4, the electric bus power change expression is performed based on step 3; the specific process is: The change in the amount of electricity in a vehicle during operation is expressed by the battery's state of charge, as expressed by formula (12): Where: s is the state of charge of the battery / %; B' is the remaining capacity of the battery / kWh; B0 is the rated capacity of the battery / kWh; The soc value of bus k at the starting point of basic unit l is When i=l=1, It represents the SOC value of the first bus k at the starting station of the route, which is equal to the SOC value when the vehicle leaves the depot minus the SOC change during the process of running from the depot to the starting station of the route. o represents the starting point of the basic unit; Where: s max is the initial soc value of the bus throughout the day, that is, the maximum soc value / %; is the power consumption of bus k from the depot to the starting station of the route every day / kWh; represents the soc value when the i-th bus k arrives at the starting station of the line; when bus i is the first bus k, Value equal to on the contrary Value equal to Where: is the soc value of bus k’s i-1th trip at the route terminal, and d is the end point of the basic unit; The shift i-1 is the shift before shift i; the soc value of bus k arriving at the starting point of basic unit l+1 is Where: is the power consumption of bus k on the basic unit l (kWh); is the charging amount of bus k on the basic unit l for the i-th shift / kWh; is the soc value / % of bus k at the starting point of basic unit l; In step 5, an opportunity-constrained programming model is established based on step 4; the specific process is as follows: The optimization goal is to minimize the total deployment cost of wireless charging facilities, which includes fixed cost and variable cost. Fixed cost is the cost of the inverter, which is determined by the unit price and quantity of the inverter. Variable cost is determined by the deployment length of the wireless charging board. If multiple basic units are deployed with wireless charging panels, only one inverter needs to be installed; therefore, the calculation formula for the number of inverters φ required on the line is: The chance constrained programming model is as follows: Formula (17) is the optimization objective function, which is to minimize the total deployment cost of wireless charging facilities; where c var is the cost of the charging plate per unit length / (yuan·m -1 ), c fix is the cost of a single inverter / (yuan / unit -1 ), Indicates the length of the basic unit l in direction u / m; Formula (18) is a constraint on the remaining power of the vehicle after the last shift; Formula (19) represents the constraint on the remaining power of the vehicle at the end point of basic unit l; α and β are pre-given confidence levels. Represent events separately Probability of establishment; It represents the soc value of bus k at the end of basic unit L after the operation of bus k ends. represents the soc value of bus k operating shift i at the starting point of basic unit l; s min Indicates the lower limit of the soc value of the electric bus battery; It represents the amount of electricity consumed by bus k when returning to the station after the end of operation shift I (kWh); They represent the charging capacity and power consumption of bus k in operating shift i in basic unit l / kWh respectively; Formula (20) indicates that the total length of the charging board is less than the total length of the line; In step 6, the opportunity constraint programming model is solved to obtain the optimal layout plan of the line basic unit dynamic wireless charging facilities and the corresponding minimum total layout cost; the specific process is: Step 61: Convert the constrained problem into an unconstrained problem; the specific process is: Design penalty function As shown in formula (22), formula (23) and formula (24): At different confidence levels, when the constraint condition does not hold, the penalty function is set to 1; when the constraint condition holds, the penalty function is set to 0; Therefore, the objective function formula (17) is transformed into formula (25): Where: c var is the cost of the charging plate per unit length / (yuan·m -1 ), c fix is the cost of a single inverter / (yuan / unit -1 ); represents the length of the basic unit l in direction u / m; τ1, τ2, τ3 are penalty coefficients; are the penalty functions corresponding to the constraint conditions (18), (19), and (20) respectively; Step 62: Use random simulation and particle swarm algorithm to solve the chance constraint model; obtain the optimal layout plan of the basic unit dynamic wireless charging facilities and the corresponding minimum total layout cost.

2. The method for deploying dynamic wireless charging facilities on electric bus routes based on chance-constrained programming according to claim 1 is characterized in that: In the step 62, random simulation and particle swarm algorithm are used to solve the chance-constrained programming model to obtain the optimal layout plan of the line basic unit dynamic wireless charging facilities and the corresponding minimum total layout cost; the specific process is: Step 621: The steps of stochastic simulation are as follows: (1) Obtain the variance and mean of the vehicle's running speed at each basic unit l under random conditions, as well as the number of passengers getting on and off at the station, the stop time at the station, and the related parameters required to calculate the SOC value of the terminal of the basic unit l; (2) Set A′=0, A″=0; (3) Set the probability density function f(v i,k,l ), based on the probability density function f(v i,k,l ) obtain A random variable samples of speed (4) Substitute the random variable sample outputted by (3) into the constraints; if If it holds, then A′=A′+1, otherwise A′ remains unchanged; if If it holds, then A″=A″+1, otherwise A″ remains unchanged; (5) Output A′ / A, A″ / A; Step 622: Embed the random simulation technology into the particle swarm algorithm to solve the problem and obtain the optimal layout plan of the dynamic wireless charging facilities of the basic line unit and the corresponding minimum total layout cost.

3. The method for deploying dynamic wireless charging facilities on electric bus routes based on chance-constrained programming according to claim 2 is characterized in that: In step 622, random simulation technology is embedded in the particle swarm algorithm to solve the problem, and the optimal layout plan of the line basic unit dynamic wireless charging facilities and the corresponding minimum total layout cost are obtained; the steps are as follows: (1) Set algorithm parameters: The number of random simulations is set to 500, the confidence levels α and β are both 0.95, the number of particles in the particle swarm algorithm is 200, the maximum number of iterations is 300, the maximum value of the inertia weight ω is 0.94, and the minimum value is 0.4; (2) In the solution space, randomly initialize the position and velocity of each particle in the particle population; The position of each particle has D dimensions, where D is equal to the number of basic units, and the value of each basic unit is only 0 or 1; The speed of each particle has D dimensions, where D is equal to the number of basic units. The speed value of each dimension is randomly set according to the speed constraints of each basic unit. (3) The values ​​of A′ / A and A″ / A are regarded as the actual probabilities of the chance constraints; the actual probability values ​​are substituted into formulas (22)-(24) to calculate the penalty functions corresponding to each constraint condition. Based on the penalty function and the position and velocity of each particle randomly initialized in (2), the objective function value of each particle is calculated, and the calculated objective function value of each particle is regarded as the current optimal objective function value of the particle, and its corresponding position is stored in the Among them represents the optimal position of an individual; compare the optimal objective function values ​​of all particles in the group, and The individual positions corresponding to the minimum values ​​of Among them represents the optimal position of the population; (4) Using the iterative formula (26)-(27) of the particle swarm optimization algorithm, update the velocity and position of the particle; Formulas (28)-(29) are used to realize the binarization of particle position values, that is, to ensure that the dimension value of each particle position is only 0 or 1; Where: is the velocity of the ath particle at the x+1th iteration / (m·s -1 ); is the velocity of the ath particle at the xth iteration / (m·s -1 ); is the position of the ath particle at the xth iteration; ω is the inertia weight; c1 and c2 are acceleration factors; r1 and r2 are random numbers uniformly distributed between 0 and 1; x is the number of iterations; The particle speed will be limited to [-V max ,V max ], where V max Represents the maximum velocity of the particle, and the position update formula is as follows: Where: random represents a pseudo-random number uniformly distributed in the interval [0,1]; (5) The values ​​of A′ / A and A″ / A are regarded as the actual probabilities of the chance constraints; the actual probability values ​​are substituted into formulas (22)-(24) to calculate the penalty functions corresponding to each constraint condition. Based on the penalty function and the updated particle velocity and position in (4), calculate the particle's objective function value; Compare the objective function value of the current particle with its historical optimal objective function value. If the objective function value of the current particle is smaller, replace the individual Otherwise, no replacement is required; the optimal value of the optimal objective function value of all particles in the group is compared with The corresponding objective function values ​​are compared. If the current group optimal value is smaller, the position of the particle corresponding to the current group optimal value is used to replace Otherwise, no replacement is required; (6) If the stopping condition is met, that is, the maximum number of iterations is reached, the search is stopped and the best particle is given as the optimal solution. Otherwise, return to (4).

4. The method for deploying dynamic wireless charging facilities on electric bus routes based on chance-constrained programming according to claim 3 is characterized by: The solution process of the inertia weight ω is: The calculation of inertia weight is shown in formula (30): Where: ω(χ) is the inertia weight factor of the χth iteration; χ is the number of iterations; χ max is the final number of iterations of the algorithm; ω min is the minimum inertia weight factor; ω max is the maximum inertia weight factor; The process of solving the acceleration factors c1 and c2 is: The sine function is used to simulate the change of acceleration factor; Where: c1(χ), c2(χ) are acceleration factors, c a , c b , c γ , c0 is the relevant parameter; c a =1,c b =1.5,c γ =1,c0=1.5。