Extra-thick coal seam top coal caving working face roadway arrangement method
A technology for extra-thick coal seam and roadway layout, which is applied in tunnels, safety devices, earthwork drilling and mining, etc., can solve the problems of stope roof collapse and stress distribution, affect the advancing speed of the working face, and high cost, and reduce support Maintenance cost and maintenance difficulty, improvement of filling effect, effect of size reduction
Patent Information
- Authority / Receiving Office
- CN · China
- Current Assignee / Owner
- Publication Date
- 2022-04-01
Smart Images

Figure 1 
Figure 2 
Figure 3
Abstract
Description
technical field
[0001] The invention relates to a coal mining technology, in particular to a roadway layout method for a top-coal caving face in an extra-thick coal seam, and is especially related to maintenance of a main road during the final mining period and reduction of the final mining coal pillar. Background technique
[0002] With the increase of the coal seam height, the impact of mining on the working face, especially the top coal caving face, is gradually increasing, which is manifested in the collapse of the roof of the coal wall, the severe deformation of the mining roadway in the advanced working face section, and the remaining protective coal at the end of mining. The large column size not only increases the roadway support and maintenance costs during mining, but also makes a large amount of coal resources remain underground and cannot be mined.
[0003] After the working face is mined, the overlying roof collapses downward, destroying the initial equilibrium ...
Examples
Embodiment 1
[0062] Such as figure 1 , figure 2 , image 3 As shown, the specific steps are as follows:
[0063] A. Firstly, excavate the transport lane 1 and the track lane 2 of the working face along the coal seam floor in the extra-thick coal seam. After the tunneling reaches the design direction length of the working face, the excavation working face cuts through the working face, and installs the coal setting support on the working face 6 and other equipment, start the recovery of the working face.
[0064] B. While mining at the working face, excavate the withdrawal roadway 7 at the position of the designed stop production line, and complete the corresponding roadway support.
[0065] The formula for calculating the width of the final mining pillar 10 between the above-mentioned retraction roadway 7 and the main roadway is:
[0066]
[0067] Among them, L 1 Coal pillar width when managing the roof of the final mining face for the natural caving method; L 2 is the coal pilla...