A concrete lining grouting support arch for tunnels
By designing the sliding structure of the inferior curved steel body and curved plate, combined with the deflector and anchoring mechanism, the problem of concrete detachment and installation of the steel body in the tunnel concrete lining grouting is solved, and stable assembly and efficient filling are achieved. Improve construction efficiency and stability.
Patent Information
- Application Number
- CN202210006624.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-01-05
- Publication Date
- 2024-11-15
- Estimated Expiration
- 2042-01-05
AI Technical Summary
In the tunnel concrete lining grouting process, the concrete is prone to detachment during the second round of pouring in the prior art, and the mesh structure causes the concrete layer to be not firm enough, and the advance support steps required during the installation of the steel body are cumbersome, which affects construction efficiency and stability.
A concrete lining grouting support arch frame including inferior curved steel body, curved plate, deflector frame and anchoring mechanism was designed. Through the sliding of the curved plate and the design of the deflector frame, the mesh plate is avoided from moving downward relative to the concrete. The resulting gap simplifies the splicing process of the steel body and achieves stable assembly and filling.
The design is conveniently assembled, which improves the internal filling of concrete, reduces the advance support steps, improves construction efficiency and quality, ensures the stability and firmness of the concrete layer, and avoids the emergence of gaps after pouring.
Smart Images

Figure CN114483098B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a concrete lining grouting support arch frame for a tunnel, in particular to a concrete lining grouting support arch frame for a tunnel. Background Art
[0002] In the concrete lining grouting process of the tunnel, the initial grouting layer is pre-done on the inner wall of the tunnel, and then the arch frame is installed, and then the second round of grouting is carried out to complete the support of the top surface of the tunnel. In the prior art, in order to ensure that the second round of concrete pouring is not easy to fall off, a mesh plate is set between adjacent steel bodies to help the concrete hang and prevent it from falling. Finally, after the grouting is completed, the surface compaction step is carried out. During the compaction process, the concrete layer is pushed upward, that is, it moves upward relative to the mesh plate. The mesh structure of the mesh plate will cause gaps in the upward part of the concrete layer, so that the concrete layer structure is not strong enough, which brings adverse effects. During the installation of the steel body, it is necessary to carry out the advance support step between adjacent steel bodies. The support step is quite inconvenient, and the lateral anchor rods of the support will also cause the problem of gaps in the concrete after squeezing, affecting the stability of the tunnel wall. Summary of the invention
[0003] The object of the present invention is to provide a concrete lining grouting support arch for a tunnel, which is used to solve the problems existing in the background technology.
[0004] The technical solution of the present invention is as follows: a concrete lining grouting support arch frame for tunnels, comprising a steel body, the steel body comprising an upper steel and a lower steel which are in an inferior arc shape and are layered and arranged in parallel, the upper steel and the lower steel are fixedly connected via connecting steel, the front and rear end faces of the connecting steel are respectively connected with an arc plate extending outward along a vertical sliding manner, the upper end face of the arc plate is slidably mounted with a guide frame, the positive cross-section of the guide frame is triangular in shape, comprising an inner bevel and an outer bevel, two adjacent steel bodies are connected to an upper plate via a lower mesh plate, a plug-in mechanism is arranged on the lower end face of the arc plate, the front and rear side edges of the lower mesh plate are respectively connected to the two arc plates of the two steel bodies via the plug-in mechanism, and the front and rear edges of the upper plate are respectively connected to the two upper steels via an anchoring mechanism.
[0005] In the aforementioned concrete lining grouting support arch frame for tunnels, a plurality of fixing blocks are fixedly arranged at intervals on the front and rear end surfaces of the connecting steel, a plurality of fitting grooves corresponding to the positions of the fixing blocks are opened on the edge of the arc plate adjacent to the connecting steel, an L-shaped groove is opened on the front side of the fixing block, an opening is also provided on the outer surface of the fixing block at the L-shaped groove, an insert plate is provided on the edge of the arc plate at the fitting groove, the insert plate is slidably inserted into the L-shaped groove, and the arc plate extends out from the opening of the fixing block.
[0006] In the aforementioned concrete lining grouting support arch frame for tunnels, an elastic pad is fixedly connected to the inner top surface of the L-shaped groove, a deformation cavity is opened on the front side of the elastic pad, and a shovel plate is provided at the upper end of the plug plate.
[0007] In the aforementioned concrete lining grouting support arch frame for tunnels, a plurality of I-shaped blocks are fixedly installed at intervals along the length direction on the upper end surface of the arc plate, and a T-shaped groove is opened on the lower end surface of the guide frame at the position corresponding to the I-shaped block, and the I-shaped block slides into the inner side of the T-shaped groove.
[0008] In the aforementioned concrete lining grouting support arch frame for tunnels, a soft strip is fixedly embedded on the outer side of the upper end surface of the arc plate along its length direction, and a soft pad is fixedly connected to the bottom of the guide frame adjacent to the connecting steel.
[0009] In the aforementioned concrete lining grouting support arch frame for tunnels, the plug-in mechanism includes a connecting block fixedly connected to the lower end face of the arc plate, a threaded opening is provided on the front end face of the connecting block, a connecting rod is fixedly connected to the edge of the lower mesh plate, a threaded hole is provided at the end of the connecting rod, a threaded rod is threadedly connected in the threaded hole, a threaded column is fixedly connected to the other end of the threaded rod, the threaded column is threaded into the threaded opening, and a polygonal block is fixedly sleeved on the outer surface of the threaded column.
[0010] In the aforementioned concrete lining grouting support arch frame for tunnels, the anchoring mechanism includes a limit seat fixedly connected to the outer end of the lower end surface of the upper steel section, an extension rod is fixedly connected to the edge of the mesh plate, an L-shaped plate is fixedly connected to the end of the extension rod, an insertion port is provided on the outer side surface of the limit seat, the L-shaped plate is slidably inserted into the insertion port, a radial anchor rod is vertically penetrated in the limit seat, and the radial anchor rod slides through the upper steel section and the L-shaped plate, and a bolt head is fixedly connected to the lower end of the radial anchor rod located at the bottom of the limit seat.
[0011] In the aforementioned concrete lining grouting support arch frame for tunnels, the number of the steel bodies is set to three groups, and the ends of adjacent steel bodies are fixedly connected. The inner ends of the steel bodies at the end on both sides are respectively fixedly connected to bottom connecting plates, and a number of locking anchor rods are obliquely inserted on the bottom connecting plates.
[0012] In the aforementioned concrete lining grouting support arch frame for tunnels, both ends of each steel body are fixedly connected with splicing plates, and two adjacent splicing plates are fixedly connected by bolts.
[0013] Beneficial effects of the invention: Compared with the prior art, the invention has the following advantages:
[0014] 1. It can be assembled conveniently and firmly, eliminating the need for advance support. During the concrete pouring and compaction process, there will be no gap inside the concrete due to the downward movement of the mesh plate relative to the concrete, which is conducive to ensuring the firmness and fullness of the concrete interior and effectively improving construction efficiency and quality.
[0015] 2. Pour the initial concrete layer on the inner wall of the tunnel in advance, and then install several steel bodies. Adjacent steel bodies are fixedly connected by splicing plates, and the corners are fixed to the ground by radial anchor rods. Then, the adjacent steel bodies are connected by mesh plates. Insert the L-shaped plate into the inner side of the insertion port, and then drive in the radial anchor rods to stabilize the steel and mesh plates. The assembly is convenient, eliminating the step of advanced support, and the stabilization reinforcement step can be carried out while the splicing is fast.
[0016] 3. After completing the connection of the upper mesh plate, assemble the lower mesh plate and insert the plug plate into the inner side of the L-shaped groove in advance. During this process, squeeze the lower end of the elastic pad to ensure that the plug plate can be inserted into the inner side of the L-shaped groove. Rotate the polygonal block so that the threaded column is screwed into the inner side of the threaded mouth to complete the stability of the lower mesh plate. At the same time, the adjacent steel bodies are also stabilized to ensure the stability between the adjacent steel bodies when the advance support is avoided, and the installation is convenient.
[0017] 4. After the lower mesh plate is assembled, the secondary concrete pouring is carried out, and the concrete is sprayed to the bottom of the upper steel. During the pouring process, the slurry flows into the inner slope and the side of the connecting steel under the action of the inner slope. Under the pushing effect of gravity, the edge of the guide frame squeezes the soft strip, and after breaking through the restriction, it moves along the front lower arc track, that is, the relative I-shaped block slides along the inner side of the T-slot. After the pouring is completed, the concrete surface is squeezed. At this time, due to the drainage effect of the lower end surface of the guide frame and the lower end surface of the arc plate, more concrete slurry pushed upward is squeezed into the pushing part, thereby causing the arc plate and the lower mesh plate to move upward. Therefore, a compaction part is formed above the guide frame due to the upward movement. When the compaction part is tight, the guide frame will not move toward the connecting steel. At this time, a gap will be left at the position where the lower mesh plate passes through the concrete. Since the gap is located below the lower mesh plate, it can be directly filled when the concrete surface is squeezed upward, thereby preventing the problem of gaps inside the concrete back-filling layer. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] Figure 1 It is a structural schematic diagram of a concrete lining grouting support arch frame for a tunnel according to the present invention;
[0019] Figure 2 It is a schematic diagram of splicing a group of adjacent steel bodies of a concrete lining grouting support arch frame for a tunnel according to the present invention;
[0020] Figure 3It is a partial cross-sectional view of a steel body of a concrete lining grouting support arch frame for a tunnel according to the present invention;
[0021] Figure 4 The present invention is a concrete lining grouting support arch frame for tunnels Figure 3 Enlarged view of point A in the middle;
[0022] Figure 5 The present invention is a concrete lining grouting support arch frame for tunnels Figure 3 Enlarged view of point B in the middle;
[0023] Figure 6 This is a cross-sectional view of a steel body of a concrete lining grouting support arch frame for a tunnel, close to the fixing blocks on both sides of the steel body;
[0024] Figure 7 It is a cross-sectional view of a guide frame of a concrete lining grouting support arch frame for a tunnel according to the present invention;
[0025] Figure 8 It is a schematic diagram of a lower mesh plate and a guide frame of a concrete lining grouting support arch frame for a tunnel according to the present invention;
[0026] Fig. 9 It is a schematic diagram of a lower mesh plate of a concrete lining grouting support arch frame for a tunnel according to the present invention;
[0027] Fig.10 It is a cross-sectional view of a plug-in mechanism of a concrete lining grouting support arch frame for a tunnel according to the present invention;
[0028] Fig.11 It is a rear view of a steel body of a concrete lining grouting support arch frame for a tunnel according to the present invention;
[0029] Fig.12 It is a front view of a steel body of a concrete lining grouting support arch frame for a tunnel according to the present invention;
[0030] Fig.13 This is a moving directional diagram of an arc-shaped plate of a concrete lining grouting support arch frame for a tunnel according to the present invention;
[0031] Fig.14 It is a partial side cross-sectional view of a concrete lining grouting support arch frame for a tunnel according to the present invention;
[0032] Fig.15 The present invention is a side sectional view of a concrete lining grouting support arch frame used for a tunnel during grouting.
[0033] Reference numerals: 1, upper steel; 2, connecting steel; 3, lower steel; 4, arc plate; 5, fixing block; 6, L-shaped groove; 7, plug plate; 8, shovel plate; 9, elastic pad; 10, deformation cavity; 11, guide frame; 12, inner bevel; 13, outer bevel; 14, T-slot; 15, I-shaped block; 16, soft pad; 17, soft strip; 18, connecting block; 19, threaded column; 20, polygonal block; 21, threaded rod; 22, threaded mouth; 23. Threaded hole; 24. Connecting rod; 25. Lower mesh plate; 26. Upper mesh plate; 27. Extension rod; 28. L-shaped plate; 29. Limit seat; 30. Insertion port; 31. Radial anchor rod; 32. Bolt head; 33. Splicing plate; 34. Bottom plate; 35. Locking anchor rod; 36. Set groove; 37. Rock layer; 38. Initial concrete pouring layer; 39. Post-concrete pouring layer; 40. Compacting part; 41. Pushing part; 42. Concrete surface layer. DETAILED DESCRIPTION
[0034] The present invention is further described below in conjunction with the accompanying drawings and embodiments, but they are not intended to limit the present invention.
[0035] Embodiments of the present invention: A concrete lining grouting support arch for a tunnel, such as Figure 1-Figure 15 As shown, it includes a steel body, which includes an upper steel 1 and a lower steel 3 in an inferior arc shape and arranged in layers and parallel to each other, and a connecting steel 2 fixedly connected between the upper steel 1 and the lower steel 3. The front and rear end faces of the connecting steel 2 are respectively connected to the arc plate 4 in a vertical sliding manner. The upper end face of the arc plate 4 is slidably mounted with a guide frame 11. The positive cross section of the guide frame 11 is triangular and includes an inner bevel 12 and an outer bevel 13. During use, the guide frame 11 slides outward along the surface of the arc plate 4 to move in an arc track so that the plane of the outer bevel 13 is vertical. A lower mesh plate 25 and an upper mesh plate 26 are arranged between the two adjacent steel bodies in front and back. The lower end face of the arc plate 4 is provided with a plug-in mechanism. The front and rear side edges of the lower mesh plate 25 are respectively connected to the two arc plates 4 of the two steel bodies through the plug-in mechanism, and the front and rear edges of the upper mesh plate 26 are respectively connected to the two upper steels 1 through an anchoring mechanism.
[0036] The concrete lining grouting support arch frame used for the tunnel of the present invention can be conveniently assembled and firmly assembled, eliminating the step of advance support. During the concrete pouring and compacting process, no gap will be generated inside the concrete due to the downward movement of the mesh plate relative to the concrete, which is beneficial to ensuring the firmness and fullness of the concrete interior and effectively improving the construction efficiency and construction quality.
[0037] like Figure 3 , Figure 4 , Fig.11 and Fig.14As shown, a plurality of fixing blocks 5 are fixedly arranged at intervals on the front and rear end surfaces of the connecting steel 2, and a plurality of fitting grooves 36 corresponding to the positions of the fixing blocks 5 are provided on the edge of the arc plate 4 adjacent to the connecting steel 2. An L-shaped groove 6 is provided on the front of the fixing block 5, and an opening is also provided on the outer surface of the fixing block 5 at the L-shaped groove 6. An insert plate 7 is provided on the edge of the arc plate 4 at the fitting groove 36, and the insert plate 7 is slidably inserted into the L-shaped groove 6, so that the arc plate 4 extends out from the opening of the fixing block 5. This structure can make the installation of the arc plate 4 very convenient, and can ensure that the arc plate 4 slides up and down along the L-shaped groove 6, and the insert plate 7 will not fall out of the L-shaped groove 6 during the up and down movement. Since the connecting steel 2 is in an arc-shaped state, such as Figure 6 A cross-sectional view of the fixing block 5 at the curved edge is shown, as Fig.12 As shown by the arrows in FIG. 1 , the setting of the fixing blocks 5 at various positions ensures that the arc-shaped plate 4 can move upward.
[0038] An elastic pad 9 is fixedly connected to the inner top surface of the L-shaped groove 6, and a deformation cavity 10 is provided on the front of the elastic pad 9, which ensures that the elastic pad 9 can be deformed after being squeezed. A shovel plate 8 extends from the upper end of the insert plate 7, and the shovel plate 8 ensures that the insert plate 7 will not move upward when there is concrete slurry above.
[0039] like Figure 4 and Figure 7 As shown, a plurality of I-shaped blocks 15 are fixedly provided on the upper end surface of the arc plate 4 along its length direction, and a plurality of T-shaped slots 14 are spaced apart at the positions corresponding to the I-shaped blocks 15 on the lower end surface of the guide frame 11. The I-shaped blocks 15 are slidably inserted into the inner sides of the T-shaped slots 14. The I-shaped blocks 15 and the T-shaped slots 14 are interlocked with each other to ensure that the guide frame 11 can move along the arc track and will not be separated from the arc plate 4.
[0040] A soft strip 17 arranged along its length direction is fixedly embedded at the outer end of the upper end surface of the arc plate 4, and a soft pad 16 is fixedly arranged at the bottom of the rear edge of the guide frame 11. The soft pad 16 is made of memory foam and plays a blocking role to prevent concrete slurry from seeping into the bottom of the arc plate 4. The soft strip 17 is made of rubber and plays a role in blocking the guide frame 11 to prevent the guide frame 11 from directly sliding down during assembly, thereby affecting the secondary grouting and making it difficult for concrete to reach the top of the guide frame 11.
[0041] like Figure 4 and Fig.10As shown, the plug-in mechanism includes a connecting block 18 fixedly connected to the lower end face of the arc plate 4, a threaded opening 22 is provided on the front end face of the connecting block 18, a plurality of connecting rods 24 are fixedly connected to the edge of the lower mesh plate 25, a threaded hole 23 is provided at the end of the connecting rod 24, a threaded rod 21 threadably matched is inserted into the inner side of the threaded hole 23, a threaded column 19 is fixedly connected to the end of the threaded rod 21, the threaded column 19 is inserted into the inner side of the threaded opening 22 and threadably matched, and a polygonal block 20 is fixedly sleeved on the outer surface of the threaded column 19.
[0042] like Figure 5 As shown, the anchoring mechanism includes a limit seat 29 fixedly connected to the lower end surface of the upper steel 1 close to the front and rear edges, an extension rod 27 is fixedly connected to the edge of the upper screen 26, and an L-shaped plate 28 is fixedly connected to the end of the extension rod 27. A plurality of insertion openings 30 are provided on the outer end surface of the limit seat 29, and the L-shaped plate 28 is slidably inserted into the insertion opening 30. A radial anchor rod 31 is penetrated by the limit seat 29, and the radial anchor rod 31 slides through the upper steel 1 and the L-shaped plate 28. A bolt head 32 is fixedly connected to the lower end of the radial anchor rod 31. Since the radial anchor rod 31 is inserted into the rock layer 37 and is relatively stable, if further reinforcement is required, the contact between the bolt head 32 and the upper steel 1 can be welded. This step can be selectively performed according to the situation.
[0043] like Figure 1 As shown, the number of profiled steel bodies is set to three groups, and the ends of adjacent profiled steel bodies are fixedly connected (such as Figure 2 As shown in the figure, two steel bodies form a group). After the three groups of steel bodies are assembled, the inner sides of the steel bodies at the end of both sides are fixedly connected with bottom connecting plates 34, and the end faces of the bottom connecting plates 34 are obliquely inserted with a plurality of locking foot anchor rods 35 to reinforce the corner position of the steel body and the tunnel, as shown in the figure. Fig.13 The arrows in FIG. 1 are the moving directions of each arc plate 4 when the steel body is arranged in three groups.
[0044] Both ends of each steel body are fixedly connected with splicing plates 33 , and two splicing plates 33 on adjacent steel bodies are fixedly connected by bolts, so that the assembly of the steel bodies is more convenient.
[0045] like Figure 8 and Fig. 9 As shown, a schematic diagram of the structure of the lower mesh plate 25 and the connected partial structure is shown.
[0046] like Fig.15 As shown, during grouting in the tunnel, a concrete back-filling layer 39 is formed below the upper steel section 1, a compaction portion 40 is formed in the area between the guide frame 11 and the connecting steel 2, and a pushing portion 41 is formed below the guide frame 11. During extrusion, the lower mesh plate 25 is moved upward under the action of the concrete in the pushing portion 41.
[0047] During the construction process, the initial concrete pouring layer 38 is poured on the inner wall of the tunnel in advance, and then a number of steel bodies are installed. Adjacent steel bodies are fixedly connected by splicing plates 33, and the corners are fixed to the ground by radial anchor rods 31. Then, the upper mesh plate 26 is connected between adjacent steel bodies, and the L-shaped plate 28 is inserted into the insertion port 30. Then, the radial anchor rod 31 is driven in to stabilize the upper steel 1 and the mesh plate 26. The assembly is relatively convenient, and the step of advanced support is eliminated. The stabilization reinforcement step is performed while the splicing is fast. After completing the connection of the upper mesh plate 26, assemble the lower mesh plate 25, insert the plug plate 7 into the inner side of the L-shaped groove 6 in advance, and squeeze the lower end of the elastic pad 9 during this process to ensure that the plug plate 7 can be inserted into the inner side of the L-shaped groove 6, rotate the polygonal block 20 so that the threaded column 19 is screwed into the inner side of the threaded opening 22, and the stability of the lower mesh plate 25 can be completed. At the same time, the adjacent steel bodies are also stabilized to ensure the stability between the adjacent steel bodies when the advance support is avoided, and the installation is more convenient. After the lower mesh plate 25 is assembled, the secondary concrete pouring is carried out, and the concrete is sprayed to the bottom of the upper steel 1. During the pouring process, the slurry flows into the inner bevel 12 and the side of the connecting steel 2 under the action of the inner bevel 12. Under the pushing effect of gravity, the edge of the guide frame 11 squeezes the soft strip 17, and after breaking through the restriction, it moves along the front lower arc track, that is, the relative I-shaped block 15 slides along the inner side of the T-shaped groove 14. After the pouring is completed, the concrete surface 42 is squeezed. At this time, due to the drainage effect of the lower end surface of the guide frame 11 and the lower end surface of the arc plate 4, the concrete is pushed upward. More squeezed concrete slurry is squeezed into the pushing part 41, thereby causing the arc plate 4 and the lower mesh plate 25 to move upward. Therefore, a compaction part 40 is formed above the guide frame 11 due to the upward movement. When the compaction part 40 is relatively tight, the guide frame 11 will not move toward the connecting steel 2. At this time, a gap will be left at the position where the lower part of the lower mesh plate 25 passes through the concrete. Since the gap is located below the lower mesh plate 25, it can be directly filled when the concrete surface layer 42 is squeezed upward, thereby preventing the problem of gaps inside the concrete back-filling layer 39.
Claims
1. A concrete lining grouting support arch for a tunnel, characterized in that: The invention comprises a profiled steel body, wherein the profiled steel body comprises an upper profiled steel (1) and a lower profiled steel (3) which are in an inferior arc shape and are arranged in layers and parallel to each other. The upper profiled steel (1) and the lower profiled steel (3) are fixedly connected via a connecting steel (2). The front and rear end surfaces of the connecting steel (2) are respectively connected to an arc-shaped plate (4) extending outward in a vertical sliding manner. A guide frame (11) is slidably mounted on the upper end surface of the arc-shaped plate (4). The positive cross section of the guide frame (11) is in a triangular shape and comprises an inner inclined surface (12) and an outer inclined surface (13). Two adjacent profiled steel bodies are connected to an upper plate (26) via a lower mesh plate (25). A plug-in mechanism is arranged on the lower end surface of the arc-shaped plate (4). The front and rear side edges of the lower mesh plate (25) are respectively connected to the two arc-shaped plates (4) of the two profiled steel bodies via the plug-in mechanism. The front and rear edges of the upper plate (26) are respectively connected to the two upper profiled steels (1) via an anchoring mechanism.
2. The concrete lining grouting support arch for tunnel according to claim 1, characterized in that: A plurality of fixing blocks (5) are fixedly arranged at intervals on the front and rear end surfaces of the connecting steel (2), and an edge of the arc-shaped plate (4) adjacent to the connecting steel (2) is provided with a plurality of set grooves (36) corresponding to the positions of the fixing blocks (5). An L-shaped groove (6) is provided on the front surface of the fixing block (5), and an opening is further provided on the outer surface of the fixing block (5) at the L-shaped groove (6). An inserting plate (7) is provided on the edge of the arc-shaped plate (4) at the set groove (36), and the inserting plate (7) is slidably inserted into the L-shaped groove (6) so that the arc-shaped plate (4) protrudes from the opening of the fixing block (5).
3. The concrete lining grouting support arch for tunnel according to claim 2, characterized in that: An elastic pad (9) is fixedly connected to the inner top surface of the L-shaped groove (6), a deformation cavity (10) is provided on the front surface of the elastic pad (9), and a shovel plate (8) is provided at the upper end of the insert plate (7).
4. The concrete lining grouting support arch for tunnel according to claim 1, characterized in that: A plurality of I-shaped blocks (15) are fixedly installed at intervals on the upper end surface of the arc-shaped plate (4) along its length direction, and a T-shaped groove (14) is provided on the lower end surface of the flow guide frame (11) at a position corresponding to the I-shaped block (15), and the I-shaped block (15) is slidably inserted into the inner side of the T-shaped groove (14).
5. The concrete lining grouting support arch for tunnel according to claim 4, characterized in that: A soft strip (17) is fixedly embedded in the outer side of the upper end surface of the arc-shaped plate (4) along its length direction, and a soft pad (16) is fixedly connected to the bottom of the guide frame (11) adjacent to the connecting steel (2).
6. The concrete lining grouting support arch for tunnel according to claim 1, characterized in that: The plug-in mechanism comprises a connecting block (18) fixedly connected to the lower end surface of the arc-shaped plate (4), a threaded opening (22) being provided on the front end surface of the connecting block (18), a connecting rod (24) being fixedly connected to the edge of the lower mesh plate (25), a threaded hole (23) being provided at the end of the connecting rod (24), a threaded rod (21) being threadedly connected in the threaded hole (23), a threaded column (19) being fixedly connected at the other end of the threaded rod (21), the threaded column (19) being threadedly screwed into the threaded opening (22), and a polygonal block (20) being fixedly sleeved on the outer surface of the threaded column (19).
7. The concrete lining grouting support arch for tunnel according to claim 1, characterized in that: The anchoring mechanism comprises a limit seat (29) fixedly connected to the outer end of the lower end surface of the upper steel section (1), an extension rod (27) fixedly connected to the edge of the upper plate (26), an L-shaped plate (28) fixedly connected to the end of the extension rod (27), an insertion opening (30) is provided on the outer side surface of the limit seat (29), the L-shaped plate (28) is slidably inserted into the insertion opening (30), a radial anchor rod (31) is vertically penetrated in the limit seat (29), and the radial anchor rod (31) slidably penetrates the upper steel section (1) and the L-shaped plate (28), and a bolt head (32) is fixedly connected to the lower end of the radial anchor rod (31) located at the bottom of the limit seat (29).
8. The concrete lining grouting support arch for tunnel according to claim 1, characterized in that: The number of the steel bodies is set to three groups, and the ends of adjacent steel bodies are fixedly connected. The inner ends of the steel bodies at the end on both sides are respectively fixedly connected to bottom connecting plates (34), and a plurality of locking foot anchor rods (35) are obliquely inserted into the bottom connecting plates (34).
9. The concrete lining grouting support arch for tunnel according to claim 8, characterized in that: Both ends of each steel body are respectively fixedly connected with splicing plates (33), and two adjacent splicing plates (33) are fixedly connected by bolts.