A water-stopping structure for inlet and outlet of a guided micro-jacking pipe
Through the water-stopping structure of the entrance and exit holes of the guided micro-pipe jacking, and the use of annular plates, water-stopping plates and water leakage detection devices, the problems of water leakage and sand leakage during pipe jacking construction are solved, and the sealing and safety alarm of the construction area are achieved to ensure Construction was smooth and safe.
Patent Information
- Application Number
- CN202210435902.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-04-24
- Publication Date
- 2024-10-15
- Estimated Expiration
- 2042-04-24
AI Technical Summary
During pipe jacking construction, when the tunnel boring machine penetrates the wall and exits the hole, it is easy for groundwater and mud to flow into the working well, causing surface collapse and potential safety hazards for underground pipelines.
The entrance and exit hole water-stopping structure using guided micro-jacking pipes includes a cylindrical casing, annular plate, water-stopping plate, pressure ring and water leakage detection device. It automatically identifies water leakage and sends out an alarm signal to ensure the airtightness of the construction area.
Effectively prevent water leakage and sand leakage to ensure the smooth progress of construction, and promptly warn construction personnel of water leakage to ensure construction safety and the safety of surrounding facilities.
Smart Images

Figure CN114753870B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of pipe jacking engineering, and in particular to a water-stopping structure for an inlet and outlet hole of a guided micro-pipe jacking. Background Art
[0002] Pipe jacking is a trenchless construction method that has developed into a mature technology, which has the advantages of high precision, low cost and low pollution. It is widely used in urban water supply and drainage construction and urban power pipeline construction. Pipe jacking in and out of the hole is a construction stage with high technical difficulty and complex procedures in pipe jacking construction.
[0003] In the jacking tunnel project, if the tunnel boring machine directly passes through the wall to exit the hole, it is very likely that groundwater and mud and sand will flow into the working well from the gap, and it will also cause the collapse of the surface above the embedded hole, and even cause accidents, endangering the safety of surrounding buildings and underground pipelines. Summary of the invention
[0004] In view of the above technical problems, the present invention aims to provide a water-stopping structure for the entry and exit of a guided micro-jacking pipe. To solve the above technical problems, the present invention adopts the following technical solutions:
[0005] A water-stopping structure for entering and exiting a guided micro-jacking pipe comprises a cylindrical casing, an annular plate, a water-stopping plate, a pressure ring, a first bolt and a pile body, wherein the first bolt sequentially connects the annular plate, the water-stopping plate and the pressure ring, the cylindrical casing and the pile body are respectively inserted into a soil layer, the pile body is arranged outside the cylindrical casing, the annular plate is fixedly connected to the cylindrical casing by a second bolt, a pre-buried hole is opened on the cylindrical casing, and the water-stopping plate covers the pre-buried hole;
[0006] A water leakage detection device is placed on the bottom wall of the working well surrounded by the cylindrical casing and the soil layer.
[0007] Advantageously, a partition is provided inside the water leakage detection device, which divides the inner cavity of the water leakage detection device into a water cavity and a transmission cavity, and a thin plate portion is provided on the partition, a floating block is slidably connected to the rear wall of the water cavity, and a first permanent magnet is fixed to the floating block;
[0008] A second permanent magnet, a sliding rod, a supporting rod, a barrel body, a turntable, a third permanent magnet, a fourth permanent magnet and a bell are arranged in the transmission cavity. The sliding rod is slidably connected to the rear wall of the transmission cavity. The supporting rod and the second permanent magnet are respectively fixed to the supporting rod. The barrel body and the third permanent magnet are both fixed to the rear wall of the transmission cavity. The fourth permanent magnet is fixed to the front wall of the barrel body. A gas channel is opened on the bottom wall of the barrel body. An elastic sheet is fixed to the bottom wall of the barrel body. A pull ring is fixed to the bottom wall of the elastic sheet. The sliding rod passes through the pull ring. The elastic sheet is in a stretched state. The turntable is rotatably connected to the side wall of the transmission cavity. A light iron plate is fixed to the turntable. The bell is connected to the right wall of the transmission cavity through an elastic member. An alarm light is fixed to the top wall of the water leakage detection device. The left wall of the light iron plate is connected to the alarm light through an electric wire, and the right wall of the light iron plate is connected to the alarm light through an electric wire.
[0009] Advantageously, the water stop plate is provided with a first opening slot, a second opening slot is provided in the first opening slot, a third opening slot is provided in the second opening slot, and the water stop plate is provided with a pre-opening marking line.
[0010] Advantageously, the water stop plate is made of rubber.
[0011] Advantageously, the annular plate is made of steel.
[0012] Advantageously, the pressure ring is made of steel.
[0013] Advantageously, the cylindrical casing is made of steel.
[0014] Advantageously, the pile body is a steel sheet pile.
[0015] Advantageously, the pile body is a jet grouting pile.
[0016] The present invention has the following beneficial effects:
[0017] The present invention can effectively stop water from the hole of the cylindrical casing through the annular plate, the water stop plate and the pressure ring, so that the construction can be carried out more smoothly; the floating block can automatically identify whether a water leakage occurs, and automatically control the barrel body to emit an air cannon, so that the bell and the alarm light can send an alarm signal to the user at the same time, so that the user can be notified of the water leakage in time and take measures. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] The present invention is further described using the accompanying drawings, but the embodiments in the accompanying drawings do not constitute any limitation to the present invention. A person skilled in the art can obtain other drawings based on the following drawings without creative work.
[0019] Figure 1 It is a structural schematic diagram of a water-stopping structure for an inlet and outlet hole of a guided micro-jacking pipe according to the present invention;
[0020] Figure 2 The present invention Figure 1A top view of the left wall of the middle cylindrical casing;
[0021] Figure 3 The present invention Figure 1 Right view of the water stop plate;
[0022] Figure 4 The present invention Figure 1 The right side view of the water leakage detection device;
[0023] Figure 5 The present invention Figure 4 Top view of the middle transmission cavity.
[0024] Figure numerals: cylindrical casing 1, embedded hole 2, annular plate 3, second bolt 31, water stop plate 4, first opening groove 41, pressure ring 5, first bolt 6, soil layer 7, working well 8, main top equipment 9, pile body 10, corbel 11, water leakage detection device 12, water chamber 13, transmission chamber 14, partition 15, thin plate part 16, floating block 17, first permanent magnet 18, second permanent magnet 19, sliding rod 20, support rod 201, barrel body 21, gas channel 22, elastic sheet 23, pull ring 24, turntable 25, lightweight iron plate 26, bell 27, elastic part 271, third permanent magnet 28, fourth permanent magnet 29, alarm light 30. DETAILED DESCRIPTION
[0025] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0026] In the description of the present invention, it should be noted that the terms "vertical", "upper", "lower", "horizontal", etc., indicating the orientation or positional relationship, are based on the orientation or positional relationship shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as limiting the present invention. In addition, "first", "second", "third", and "fourth" are only used for descriptive purposes and cannot be understood as indicating or implying relative importance.
[0027] In the description of the present invention, it is also necessary to explain that, unless otherwise clearly specified and limited, the terms "set", "install", "connect", and "connect" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection, it can be a mechanical connection, it can be an electrical connection, it can be a direct connection, it can be connected through an intermediate medium, and it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0028] like Figure 1-Figure 5 As shown, a water-stopping structure for entering and exiting a guided micro-jacking pipe comprises a cylindrical casing 1, an annular plate 3, a water-stopping plate 4, a pressure ring 5, a first bolt 6 and a pile body 10. The first bolt 6 sequentially connects the annular plate 3, the water-stopping plate 4 and the pressure ring 5. The cylindrical casing 1 and the pile body 10 are respectively inserted into a soil layer 7. The pile body 10 is arranged outside the cylindrical casing 1. The annular plate 3 is fixedly connected to the cylindrical casing 1 by a second bolt 31. A pre-buried hole 2 is opened on the cylindrical casing 1, and the water-stopping plate 4 covers the pre-buried hole 2.
[0029] A water leakage detection device 12 is placed on the bottom wall of the working well 8 surrounded by the cylindrical casing 1 and the soil layer 7.
[0030] According to an optional embodiment of the present invention, a partition 15 is provided in the water leakage detection device 12, and the partition 15 divides the inner cavity of the water leakage detection device 12 into a water cavity 13 and a transmission cavity 14. A thin plate portion 16 is provided on the partition 15, and a floating block 17 is slidably connected to the rear wall of the water cavity 13, and a first permanent magnet 18 is fixed to the floating block 17;
[0031] The transmission cavity 14 is provided with a second permanent magnet 19, a sliding rod 20, a support rod 201, a barrel body 21, a turntable 25, a third permanent magnet 28, a fourth permanent magnet 29 and a bell 27. The sliding rod 20 is slidably connected to the rear wall of the transmission cavity 14. The support rod 201 and the second permanent magnet 19 are respectively fixed to the support rod 201. The barrel body 21 and the third permanent magnet 28 are both fixed to the rear wall of the transmission cavity 14. The fourth permanent magnet 29 is fixed to the front wall of the barrel body 21. The bottom wall of the barrel body 21 is provided with a gas channel 22. The barrel body 21 An elastic sheet 23 is fixedly connected to the bottom wall, a pull ring 24 is fixedly connected to the bottom wall of the elastic sheet 23, the sliding rod 20 passes through the pull ring 24, the elastic sheet 23 is in a stretched state, the turntable 25 is rotatably connected to the side wall of the transmission chamber 14, a lightweight iron plate 26 is fixedly connected to the turntable 25, a bell 27 is connected to the right wall of the transmission chamber 14 through an elastic member 271, an alarm light 30 is fixedly connected to the top wall of the water leakage detection device 12, the left wall of the lightweight iron plate 26 is connected to the alarm light 30 through electric wires, and the right wall of the lightweight iron plate 26 is connected to the alarm light 30 through electric wires.
[0032] According to an optional embodiment of the present invention, a first opening slot 41 is provided on the water stop plate 4, a second opening slot is provided in the first opening slot 41, a third opening slot is provided in the second opening slot, and the water stop plate 4 is provided with a pre-opening marking line.
[0033] According to an optional implementation of the present invention, the water stop plate 4 is made of rubber.
[0034] According to an optional embodiment of the present invention, the annular plate 3 is made of steel.
[0035] According to an optional implementation of the present invention, the pressure ring 5 is made of steel.
[0036] According to an optional embodiment of the present invention, the cylindrical casing 1 is made of steel.
[0037] According to an optional embodiment of the present invention, the pile body 10 is a steel sheet pile.
[0038] According to an optional embodiment of the present invention, the pile body 10 is a jet-jet pile.
[0039] Implementation process: The specific steps include:
[0040] S1. The working well 8 of the jacking pipe is surrounded by a cylindrical casing 1 made of steel. The cylindrical casing 1 is in the shape of a cylinder. A corbel 11 for anti-floating is provided on the cylindrical casing 1 to make the cylindrical casing 1 more stable in the soil layer 7. Before the cylindrical casing 1 cuts a hole reserved for the jacking pipe to enter and exit, a pile body 10 can be driven around the cylindrical casing 1 to prevent water and sand leakage from the hole.
[0041] S2. Fix the annular plate 3 to the cylindrical casing 1 of the cylinder through the second bolts 311.
[0042] S3. Before installing the rubber water stop plate 4, set a pre-drilling mark line on the water stop plate 4. After the water stop plate 4 is installed, use the guide drill bit of the main top equipment 9 to enter the third drilling groove to drill a hole in the water stop plate 4, the mud discharge casing enters the second drilling groove to drill a hole in the water stop plate 4, and the tunneling head enters the first drilling groove 41 to drill a hole in the water stop plate 4. In this way, the water stop plate after the hole is drilled can tightly embrace the guide drill bit, the mud discharge casing head and the tunneling head shell, so as to play a double-effect water-stopping role.
[0043] S4. Then use the customized pressure ring 5 to press the water stop plate 4. The customized pressure ring 5 can achieve a close fit with the cylindrical casing 1. Finally, use the first bolt 6 to connect the annular plate 3, the water stop plate 4 and the pressure ring 5 in sequence. The annular plate 3 and the pressure ring 5 are specially customized according to the shape of the cylindrical casing 1 to ensure that the annular plate 3 and the pressure ring adapt to the shape of the cylindrical casing 1, thereby achieving the purpose of fixing the water stop plate 4.
[0044] S6. After the installation of the water stop plate 4 is completed, the pre-installed pile body 10 can be removed, and then the main jacking equipment 9 arranged on the bottom wall of the working well 8 is used to carry out the jacking guide drill bit, mud discharge casing and tunneling machine head into the hole construction.
[0045] The thickness of the water stop plate should not be less than 20mm.
[0046] In S1, the pile body 10 may be a steel sheet pile, which is placed 1 m below the relatively impermeable layer, and the pile body 10 needs to be removed later;
[0047] The pile body 10 may also be a high-pressure jet-jet pile, and the soil layer is reinforced within 1 m of the entrance and exit of the cave, so there is no need to remove the pre-installed pile body 10 later.
[0048] The water stop plate 4 will tightly embrace the guide drill rod head, the mud discharge casing head and the tunneling machine head shell, play a double-effect water stop role, and ensure that there will be no water leakage or sand leakage at the hole entrance.
[0049] When water leaks from the hole, water falls into the water cavity 13, and the water level of the water cavity 13 gradually rises, causing the floating block 17 to move upward. When the first permanent magnet 18 moves to the same horizontal line as the thin plate portion 16, the first permanent magnet 18 attracts the second permanent magnet 19 to move leftward. The thin plate portion 16 reduces the obstruction of the partition 15 to the magnetic force, making it easier for the second permanent magnet 19 to be attracted by the first permanent magnet 18. When the second permanent magnet 19 moves leftward, it drives the sliding rod 20 and the support rod 201 to move leftward. The pull ring 24 loses the support of the support rod 201, and the elastic sheet 23 moves quickly. The air in the elastic sheet 23 is compressed and ejected from the barrel body 21 through the gas passage 22. The ejected air gives an upward thrust to the light iron plate 26, causing the turntable 25 to rotate. The light iron plate 26 continuously hits the bell 27, causing the bell 27 to make a sound to remind the user of water leakage. The light iron plate 26 continuously cuts the magnetic flux lines of the third permanent magnet 28 and the fourth permanent magnet 29, thereby generating an induced current in the light iron plate 26, causing the alarm light 30 to flash, giving a visual reminder to the user of water leakage.
[0050] The present invention can effectively stop water from the opening of the cylindrical casing 1 through the annular plate 3, the water stop plate 4, and the pressure ring 5, so that the construction can proceed more smoothly; the floating block 17 automatically identifies whether a water leak occurs, and automatically controls the barrel 21 to emit an air cannon, so that the bell 27 and the alarm light 30 simultaneously send an alarm signal to the user, so that the user can be notified of the water leak in time and take measures.
[0051] The components, modules, mechanisms and devices not described in detail in the present invention are all universal standard parts or components known to those skilled in the art, and their structures and principles can be known to those skilled in the art through technical manuals or conventional experimental methods.
[0052] Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the present invention, rather than to limit the scope of protection of the present invention. Although the present invention has been described in detail with reference to the preferred embodiments, those skilled in the art should understand that the technical solution of the present invention can be modified or replaced by equivalents without departing from the essence and scope of the technical solution of the present invention.
Claims
1. A water-stopping structure for the entry and exit of a guided micro-jacking pipe, characterized in that: The invention comprises a cylindrical casing (1), an annular plate (3), a water stop plate (4), a pressure ring (5), a first bolt (6) and a pile body (10), wherein the first bolt (6) sequentially connects the annular plate (3), the water stop plate (4) and the pressure ring (5), the cylindrical casing (1) and the pile body (10) are respectively inserted into a soil layer (7), the pile body (10) is arranged outside the cylindrical casing (1), the annular plate (3) is fixedly connected to the cylindrical casing (1) by a second bolt (31), a pre-buried hole (2) is opened on the cylindrical casing (1), and the water stop plate (4) covers the pre-buried hole (2); A water leakage detection device (12) is placed on the bottom wall of a working well (8) surrounded by a cylindrical casing (1) and a soil layer (7); The water leakage detection device (12) is provided with a partition (15), the partition (15) divides the inner cavity of the water leakage detection device (12) into a water cavity (13) and a transmission cavity (14), a thin plate portion (16) is provided on the partition (15), a floating block (17) is slidably connected to the rear wall of the water cavity (13), and a first permanent magnet (18) is fixedly connected to the floating block (17); A second permanent magnet (19), a sliding rod (20), a support rod (201), a barrel (21), a turntable (25), a third permanent magnet (28), a fourth permanent magnet (29) and a bell (27) are arranged in the transmission chamber (14); the sliding rod (20) is slidably connected to the rear wall of the transmission chamber (14); the support rod (201) and the second permanent magnet (19) are respectively fixed to the support rod (201); the barrel (21) and the third permanent magnet (28) are both fixed to the rear wall of the transmission chamber (14); the fourth permanent magnet (29) is fixed to the front wall of the barrel (21); a gas passage (22) is provided on the bottom wall of the barrel (21); and the barrel (21) is provided with a gas passage (22). 21) The bottom wall is fixedly connected with an elastic sheet (23), the bottom wall of the elastic sheet (23) is fixedly connected with a pull ring (24), the sliding rod (20) passes through the pull ring (24), the elastic sheet (23) is in a stretched state, the turntable (25) is rotatably connected to the side wall of the transmission chamber (14), the turntable (25) is fixedly connected with a light iron plate (26), the bell (27) is connected to the right wall of the transmission chamber (14) through an elastic member (271), the top wall of the water leakage detection device (12) is fixedly connected with an alarm light (30), the left wall of the light iron plate (26) is connected to the alarm light (30) through an electric wire, and the right wall of the light iron plate (26) is connected to the alarm light (30) through an electric wire; When water leaks from the hole, water falls into the water cavity (13), and the water level of the water cavity (13) gradually rises, causing the float (17) to move upward. When the first permanent magnet (18) moves to the same horizontal line as the thin plate portion (16), the first permanent magnet (18) attracts the second permanent magnet (19) to move leftward. The thin plate portion (16) reduces the obstruction of the partition (15) to the magnetic force, making it easier for the second permanent magnet (19) to be attracted by the first permanent magnet (18). When the second permanent magnet (19) moves leftward, it drives the sliding rod (20) and the support rod (201) to move leftward. The pull ring (24) loses the support of the support rod (201), and the elastic sheet (23 ) bounces upward quickly, thereby compressing the air in the elastic sheet (23) and ejecting it from the barrel (21) through the gas passage (22). The ejected air gives the light iron plate (26) an upward thrust, causing the turntable (25) to rotate. The light iron plate (26) continuously strikes the bell (27), causing the bell (27) to make a sound to remind the user of a water leak. The light iron plate (26) continuously cuts the magnetic flux lines of the third permanent magnet (28) and the fourth permanent magnet (29), thereby causing the light iron plate (26) to generate an induced current, causing the alarm light (30) to flash, thereby visually reminding the user of a water leak.
2. The water-stopping structure for entering and exiting a guided micro-jacking pipe according to claim 1 is characterized in that: The water stop plate (4) is provided with a first hole opening groove (41), a second hole opening groove is provided in the first hole opening groove (41), a third hole opening groove is provided in the second hole opening groove, and the water stop plate (4) is provided with a pre-hole opening marking line.
3. The water-stopping structure for entering and exiting a guided micro-jacking pipe according to claim 2 is characterized in that: The water stop plate (4) is made of rubber.
4. The water-stopping structure for entering and exiting a guided micro-jacking pipe according to claim 3 is characterized in that: The annular plate (3) is made of steel.
5. The water-stopping structure for entering and exiting a guided micro-jacking pipe according to claim 4 is characterized in that: The pressure ring (5) is made of steel.
6. A water-stopping structure for entering and exiting a guided micro-jacking pipe according to claim 5, characterized in that: The cylindrical casing (1) is made of steel.
7. A water-stopping structure for entering and exiting a guided micro-jacking pipe according to any one of claims 1 to 6, characterized in that: The pile body (10) is a steel sheet pile.
8. A water-stopping structure for entering and exiting a guided micro-jacking pipe according to any one of claims 1 to 6, characterized in that: The pile body (10) is a jet-jet pile.