A construction method for increasing the amount of sand released by using a down-the-hole drill in a vertical shaft
The construction method of increasing the amount of sand discharged by a down-the-hole drilling rig, combined with compressed air disturbance and multi-frequency grouting technology, solves the depth and safety problems of the drilling grouting method in vertical shafts, achieves effective management of flowing sand layers of different thicknesses, and reduces costs and risks.
Patent Information
- Application Number
- CN202210619348.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-06-02
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2042-06-02
AI Technical Summary
The existing grouting method for drilling holes in vertical shafts has the problems of high drill pipe consumption, limited drilling depth, poor grouting effect, high construction safety risks and high costs. It is difficult to effectively control the problems of different thicknesses and hydrogeological complexity. A flow-rich sand layer.
The construction method of using a down-the-hole drilling rig to increase the amount of sand release includes wellbore sealing, building a grouting platform, drilling holes, exiting drilling tools, drilling and injection operations, grouting operations, re-injection work and inspection hole construction, through compressed air disturbance For the flowing sand layer, multi-frequency quantitative constant pressure grouting and re-drilling and sweeping processes are used to control the drilling structure and parameters to increase the amount of sand discharged in the drilling and achieve sand fixation and water blocking.
It effectively solves the problems of borehole layout and parameters, and forms a set of treatment methods for water-rich sand layers suitable for different thicknesses and hydrogeological complexities, which reduces construction costs and safety risks and improves the sand-fixing and water-blocking effect of boreholes.
Smart Images

Figure CN114893186B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of down-the-hole drilling machines, in particular to a construction method for increasing the amount of sand released in a vertical shaft by utilizing a down-the-hole drilling machine. Background Art
[0002] The pipe drilling and grouting method is a commonly used treatment method at present. Its principle is to use a special drill rod to realize grouting through the drill rod. After the hole is drilled to the designed hole depth, grouting is injected into the drill rod to fix sand and block water. After grouting, the drill rod remains in the hole. This method consumes a large amount of drill rods and cannot be re-drilled in the original hole after drilling and grouting. If the grouting effect is not ideal and additional grouting is required, the hole must be re-drilled, resulting in large drilling workload and material consumption, long construction period and high cost.
[0003] The principle of the intensive hole arrangement handheld drilling rig drilling and injection method is to use a handheld rock drill to carry out intensive drilling on the working face. The hole diameter is generally less than 40mm, and the drilling depth is generally not more than 3.5m. The orifice pipe is buried through the construction borehole and grouting is carried out. This method has limited drilling depth and the grouting effect cannot be guaranteed. The drilling hole cannot be re-drilled in the original hole. At the same time, once a large amount of water and sand gushing occurs during drilling, it is difficult to effectively control it. The construction safety risk is relatively high, and it is often only suitable for the treatment of thin layers or quicksand layers with small thickness and small water gushing volume.
[0004] The principle of the post-wall grouting method after the short section of well ring back plate support is to adopt the method of advance dewatering and connect the rigid materials into a whole after driving them into the working face to form a common temporary support. The post-wall grouting is carried out after the concrete well wall of the quicksand layer section is poured. This method has high requirements on the connection of various processes and the operation of the well drilling system and the construction difficulty is relatively large. Once a large amount of water and sand gushing occurs during the construction process or the drainage system fails, the working face is likely to be flooded, and the construction safety risk is high. It is only suitable for the management of quicksand layers with small water gushing volume and small thickness and the gravel layer thickness cannot be too large.
[0005] The principle of the grouting support method with rigid support inside the hole drilled by a lightweight drilling rig is to use a lightweight drilling rig to construct a certain number of holes on the working face, grouting through the holes, and then re-drilling and sweeping the holes after a certain period of maintenance. After that, rigid materials are put into the holes and grouting is performed to seal the holes. The curtain formed by the slurry stone body (column) added with the rigid material is used to achieve the purpose of sand consolidation and water blocking. Once the curtain is not formed in some places or the curtain thickness does not meet the standard, water and sand will gush out of the working face again. Therefore, this method generally has special requirements for the spacing between boreholes, and the spacing between boreholes is often not more than 300mm, which leads to a large number of boreholes, a long construction period and high costs. It is more suitable for situations where the wellbore diameter is small, the quicksand layer thickness is small, and the water gushing amount is not large. Summary of the invention
[0006] In order to fill the gap in the market, the present invention provides a construction method for increasing the amount of sand released in a vertical shaft by using a down-the-hole drill.
[0007] The object of the present invention is to provide a construction method for increasing the amount of sand released in a vertical shaft by using a down-the-hole drill, so as to solve the problems raised in the above-mentioned background technology.
[0008] To achieve the above-mentioned purpose, the present invention provides the following technical solutions: a construction method for increasing the amount of sand release in a vertical shaft by using a down-the-hole drill, wherein the production method comprises the following steps: closing the shaft, building a grouting platform, drilling and opening a hole, withdrawing the drilling tool, drilling and grouting operations, grouting operations, re-injection work, and inspection hole construction:
[0009] Step A. Shaft sealing: After the quicksand layer appears in the shaft of the vertical shaft, the working surface is sealed according to the actual water and sand gushing situation on site. The sealing method is to pour concrete stop pads with concrete strength grade C30;
[0010] Step B. Building a grouting platform: After the grouting pad has been cured for a certain period of time, a drilling grouting platform is built. The platform is a removable and removable structure. After the platform is built, the drilling and grouting equipment is lowered and debugged;
[0011] Step C. Drilling: Drill holes using a drilling bit according to the design parameters, i.e. mark the positions of each hole on the working surface. The allowable hole position deviation shall not exceed ±0.1m. The distance between the drilling hole circle and the well wall should be 0.5-0.8m inward, generally 0.6m;
[0012] Step D. withdraw the drilling tool: after the orifice pipe is maintained, the hole is swept, the drill bit diameter is 91 mm, and the hole is drilled to 0.1m to 0.2m beyond the bottom of the orifice pipe, the drilling tool is withdrawn from the hole, and the orifice pipe is subjected to a pressure resistance and anti-seepage test using 1.2 times the final grouting pressure;
[0013] Step E. Drilling and grouting: Drill holes are grouped and sequenced in a clockwise or counterclockwise direction. In the early stage of treatment, each group consists of 3 holes. The height of the drilling and grouting sections in the drilling and grouting holes should not exceed 0.5 meters. In the later stage of treatment, each group can consist of 1 to 3 holes. According to the early sand consolidation and water blocking conditions, the height of the grouting section in the hole is adjusted to 0.5 to 1.5 meters. If the sand consolidation and water blocking effect is very ideal, it can also exceed 1.5 meters;
[0014] Step F. Grouting operation: After all the holes in each group are drilled to the designed grouting depth, grouting operation is carried out. Grouting adopts multi-frequency quantitative and constant pressure grouting. The grouting material can be ordinary cement, ultrafine cement, water glass, calcium chloride, resin chemical slurry and other diversified grouting materials;
[0015] Step G. Re-injection: After all the boreholes on the working face are drilled to the first designed grouting depth, the drilling to the second designed depth is carried out. If water and sand still gush out of some boreholes within the first designed grouting depth during the hole sweeping process, the drilling to the second designed depth is stopped, and the drilling tool is taken out for re-injection. This cycle is repeated until all the boreholes are drilled to the designed hole depth.
[0016] Step H. Inspection hole construction: After all drilling construction is completed, inspection hole construction is carried out according to the drilling and injection conditions, and an inspection hole is arranged in the center of the wellbore.
[0017] Furthermore, in step C, a solid pipe slurry stone body is provided inside the well wall, and a drilling structure is opened inside the solid pipe slurry stone body by a down-the-hole drilling rig, and an orifice pipe is provided inside the drilling structure, and an orifice pipe fixing device is provided on the upper side of the orifice pipe, and an orifice water control device is installed on the upper side of the orifice pipe fixing device, a drilling and injection platform is built on the solid pipe slurry stone body, and a down-the-hole drilling rig is installed on the drilling and injection platform, the lower side of the solid pipe slurry stone body is a water-rich quicksand layer, and a compressed air disturbed quicksand layer area is provided on the water-rich quicksand layer, the compressed air disturbed quicksand layer area and the disturbed area replacement grouting slurry stone body area are layered, and the hole-opening drill bit on the down-the-hole drilling rig is arranged inside the compressed air disturbed quicksand layer area.
[0018] Furthermore, in step C, the diameter of the drilling drill bit is 130 mm, and the drilling depth is stopped when it is at least 0.5 m close to the top of the quicksand layer or the top of the first aquifer. After the drilling tool is withdrawn from the hole, a borehole pipe is lowered into the hole. The pipe is made of a seamless steel pipe with a specification of Ø108 mm×4 mm, and its length is determined according to the drilling depth and the 0.8 m to 1 m exposed grouting pad surface at the hole mouth. The borehole pipe is fixed with single-liquid cement slurry or cement-water glass double-liquid slurry, and an anchor hole is constructed on the grouting pad surface. After a 36 mm round steel anchor is inserted, it is welded and fixed to the borehole pipe.
[0019] Furthermore, in the step E, each group of boreholes is constructed in sequence. After the first borehole is drilled to the designed grouting depth, when the drill tool is pulled out, water carries gravel up along the borehole. At this time, the orifice is kept open to release sand until the amount of sand gushing is significantly reduced and then the orifice valve is closed. Then the second borehole is constructed. When the second borehole is drilled to 0.5m from the designed grouting depth, the orifice valve of the first borehole is opened and the drill tool is repeatedly pulled up in the second borehole, and the air volume control valve is opened and closed at the same time until the drilling reaches the designed depth. The purpose is to use the wind pressure of the drilling rig to disturb the quicksand layer and release sand from the two boreholes. Similarly, the third borehole is constructed in this way, but whether to open the first and second orifice valves at the same time or only open one borehole valve should be determined comprehensively based on the capacity of the drainage system, the amount of sand and gravel deposited on the working face, the amount of drilling water, etc.; this part is one of the core process methods of the present invention.
[0020] Furthermore, in step G, the hole depth is generally more than 1m beyond the bottom plate of the quicksand layer, and the bottom of the hole is more than 1.5m beyond the wellbore excavation section, but should not exceed 2.5m, generally 2m; during the drilling and grouting process, each borehole undergoes multiple drilling, sand release, grouting, re-drilling and sweeping, and cyclic drilling and grouting processes, and in the early stage when the amount of sand released is large, the amount of sand released by a single hole must be controlled as necessary. Blindly pursuing the amount of sand released may cause settlement of surface buildings. At the beginning of the quicksand layer management, a surface building settlement observation system is established, and data are regularly observed and compared and analyzed every day.
[0021] Furthermore, the inspection hole in step H should be arranged about 0.5m from the inner side of the drilling hole to the center of the wellbore. The bottom of the inspection hole should not penetrate the slurry stone curtain formed by cementation. In principle, the inspection hole is not segmented in the hole and is drilled to the designed hole depth at one time. When there is no sand or water or no sand but only a small amount of water gushing out during the drilling of the inspection hole, the current treatment can be ended and the wellbore excavation and masonry operation can be started. Otherwise, the inspection hole will be drilled densely until there is no sand or water or no sand but only a small amount of water gushing out during the drilling of the inspection hole, and the current treatment can be ended and the wellbore excavation and masonry operation can be started.
[0022] Compared with the prior art, the beneficial effects of the present invention are as follows: in the process of treating the water-rich quicksand layer on the vertical shaft working face by the grouting method, the problems of drilling hole arrangement and parameters, drilling hole structure, drilling and grouting method and how to increase the amount of sand released in the drilling are solved, aiming to form a relatively unified working face treatment method for water-rich quicksand layers of different thicknesses and hydrogeological complexities, so as to adapt to the treatment of various quicksand layers encountered in the process of drilling in mine shaft engineering. BRIEF DESCRIPTION OF THE DRAWINGS
[0023] Figure 1 It is a schematic diagram of installation of a down-the-hole drilling rig of the structure of the present invention;
[0024] Figure 2 It is the principle diagram of step C of the structure of the present invention;
[0025] Figure 3 A schematic diagram of the core principle of the construction method of the structure of the present invention;
[0026] Figure 4 The structure of the present invention Figure 3 Schematic diagram of grouting in
[0027] Figure 5 It is a schematic diagram of the effect of slurry stone formation in the water-rich quicksand layer section of the structure of the present invention;
[0028] Figure 6 This is a schematic diagram of drilling three holes in each group on one side of the wellbore structure of the present invention, and drilling of the 1# hole;
[0029] Figure 7 The present invention has a wellbore structure with three holes drilled in each group on one side, and a schematic diagram of the 2# hole drilling;
[0030] Figure 8 The present invention has a wellbore structure with three holes drilled in each group on one side, and a schematic diagram of the drilling of the 3# hole;
[0031] Fig. 9 The wellbore structure of the present invention has three boreholes per group on one side, and the figure shows a schematic diagram of drilling the 1# borehole in the next layer;
[0032] Fig.10 The wellbore structure of the invention has 3 boreholes per group on one side, and the figure shows the schematic diagram of drilling into the next layer of the 2# borehole;
[0033] Fig.11 The wellbore structure of the invention has 3 boreholes per group on one side, and the figure shows the schematic diagram of drilling into the next layer of the 3# borehole;
[0034] Fig.12 Process flow chart of the construction method in the invention.
[0035] In the figure: 1. down-the-hole drilling rig; 2. well wall; 3. drilling and injection platform; 4. orifice pipe fixing device; 5. orifice water control device; 6. orifice pipe; 7. pipe-fixed slurry stone body; 8. water-rich quicksand layer; 9. area of quicksand layer disturbed by compressed air; 10. area of disturbed area displacing grouting slurry stone body; 11. drilling structure; 12. hole-opening drill bit. DETAILED DESCRIPTION
[0036] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0037] Specific implementation method 1: Please refer to Figure 1-12 The present invention provides a technical solution: a construction method for increasing the amount of sand released by using a down-the-hole drill in a vertical shaft, wherein the production method comprises the following steps: closing the shaft, building a grouting platform, drilling and opening a hole, withdrawing the drilling tool, drilling and grouting, grouting, re-injection and inspection hole construction:
[0038] Step A. Shaft sealing: After the quicksand layer appears in the shaft of the vertical shaft, the working surface is sealed according to the actual water and sand gushing situation on site. The sealing method is to pour concrete stop pads with concrete strength grade C30;
[0039] Step B. Building a grouting platform: After the grouting pad has been cured for a certain period of time, a drilling grouting platform is built. The platform is a removable and removable structure. After the platform is built, the drilling and grouting equipment is lowered and debugged;
[0040] Step C. Drilling: Drill holes using the drilling bit 12 according to the design parameters, i.e., mark the positions of each drilling hole on the working surface. The allowable hole position deviation shall not be greater than ±0.1m. The drilling hole circle is preferably 0.5 to 0.8m inward from the well wall 2, and is generally 0.6m.
[0041] Step D. withdrawing the drilling tool: after the orifice pipe 6 is cured, the hole is swept, the drill bit diameter is 91 mm, and the hole is drilled to 0.1m to 0.2m beyond the bottom of the orifice pipe 6, the drilling tool is withdrawn from the hole, and the orifice pipe 6 is subjected to a pressure resistance and anti-seepage test using 1.2 times the final grouting pressure;
[0042] Step E. Drilling and grouting: Drill holes are grouped and sequenced in a clockwise or counterclockwise direction. In the early stage of treatment, each group consists of 3 holes. The height of the drilling and grouting sections in the drilling and grouting holes should not exceed 0.5 meters. In the later stage of treatment, each group can consist of 1 to 3 holes. According to the early sand consolidation and water blocking conditions, the height of the grouting section in the hole is adjusted to 0.5 to 1.5 meters. If the sand consolidation and water blocking effect is very ideal, it can also exceed 1.5 meters;
[0043] Step F. Grouting operation: After all the holes in each group are drilled to the designed grouting depth, grouting operation is carried out. Grouting adopts multi-frequency quantitative and constant pressure grouting. The grouting material can be ordinary cement, ultrafine cement, water glass, calcium chloride, resin chemical slurry and other diversified grouting materials;
[0044] Step G. Re-injection: After all the boreholes on the working face are drilled to the first designed grouting depth, the drilling to the second designed depth is carried out. If water and sand still gush out of some boreholes within the first designed grouting depth during the hole sweeping process, the drilling to the second designed depth is stopped, and the drilling tool is taken out for re-injection. This cycle is repeated until all the boreholes are drilled to the designed hole depth.
[0045] Step H. Inspection hole construction: After all drilling construction is completed, inspection hole construction is carried out according to the drilling and injection conditions, and an inspection hole is arranged in the center of the wellbore.
[0046] Taking advantage of the fact that the down-the-hole drill 1 is driven by compressed air and the pressure can reach 0.8-1.2Mpa, the air volume is controlled by controlling the drilling rig operating valve at a specific layer to achieve artificial disturbance of the water-rich flowing sand layer, thereby achieving the purpose of increasing the amount of sand released in the drilling hole. At the same time, the drilling construction equipment has a strong drilling capacity and can achieve the treatment of water-rich flowing sand layers of different thicknesses, with a maximum treatment thickness of up to 60m.
[0047] The drilling holes are constructed in groups and sequences. The preceding drilling holes in each group are used to explore the position of the quicksand layer and the water and sand gushing conditions, while taking into account the release of water and sand. The subsequent drilling holes start from 0.5 meters above the explored layer. The orifice valve of the preceding drilling hole is opened and the drill tool is repeatedly pulled up and down in the hole of the subsequent drilling hole. At the same time, the air volume control valve is opened and closed until the drilling reaches the set depth. Secondary artificial disturbance of the quicksand layer is implemented to increase the amount of sand released.
[0048] Each borehole can be repeatedly drilled, sanded, grouted, re-drilled and swept, and the drilling and grouting process can be circulated to achieve multiple drills in one hole. The quality of the process can be monitored, weak points can be discovered in time and supplemented and strengthened, thereby effectively ensuring the overall sand consolidation and water blocking effect of the water-rich flowing sand layer.
[0049] The drilling adopts the overall segmented hole short-section forward drilling method, which not only ensures that the grouting consolidation wall is uniform and reaches the designed thickness, but also effectively avoids damage to the upper consolidated sand layer during the treatment process.
[0050] Specific implementation method two: This implementation method is a further limitation of specific implementation method one. In step C, a solid pipe slurry stone body 7 is arranged inside the well wall 2, and a drilling structure 11 is opened inside the solid pipe slurry stone body 7 through a down-the-hole drill 1, and a orifice pipe 6 is arranged inside the drilling structure 11, and an orifice pipe fixing device 4 is arranged on the upper side of the inner part of the orifice pipe 6, and an orifice water control device 5 is installed on the upper side of the orifice pipe fixing device 4, a drilling and injection platform 3 is built on the solid pipe slurry stone body 7, and a down-the-hole drill 1 is installed on the drilling and injection platform 3, the lower side of the solid pipe slurry stone body 7 is a water-rich quicksand layer 8, and a compressed air disturbed quicksand layer area 9 is arranged on the water-rich quicksand layer 8, the compressed air disturbed quicksand layer area 9 and the disturbed area replacement grouting slurry stone body area 10 are layered, and the hole-opening drill bit 12 on the down-the-hole drill 1 is arranged inside the compressed air disturbed quicksand layer area 9.
[0051] like Figure 1-4 As shown: a hole is pre-drilled on the grouting pad to bury and install a fixed orifice pipe 6, a valve water control device is installed on the orifice pipe 6, and drilling is carried out through the valve cavity. Once water and sand gushing out of the hole or the drainage system fails, the drilling tool can be withdrawn in time to close the water control device to achieve rapid water control. Compared with the method of drilling a hole first and then burying a pipe and grouting on the working face, the construction of the present invention is safe and reliable, and can effectively avoid the situation where a large amount of water and sand gushing out of the working face and the working face is flooded when the quicksand layer with complex hydrogeological conditions is managed.
[0052] A detachable drilling and injection platform 3 is built. During drilling, equipment and personnel work on the platform. The space below the platform is used to accumulate water and sand gushing out of the drilling hole, thereby increasing the amount of sand released during drilling, while also ensuring the safety of personnel and equipment during drilling construction.
[0053] Specific implementation method three: This implementation method is a further limitation of specific implementation method one. In step C, the diameter of the drilling drill bit 12 is 130 mm. The drilling is stopped when the drilling depth is close to the top plate of the quicksand layer or the top plate of the first aquifer by at least 0.5 m. After the drilling tool is withdrawn from the hole, a borehole pipe 6 is lowered into the hole. The pipe is made of a seamless steel pipe with a specification of Ø108 mm×4 mm, and its length is determined according to the drilling depth and the 0.8 m to 1 m exposed on the stop grouting pad surface at the hole mouth. The borehole pipe 6 is fixed with single-liquid cement slurry or cement-water glass double-liquid slurry, and an anchor hole is constructed on the stop grouting pad surface. After the 36 mm round steel anchor is inserted, it is welded and fixed to the borehole pipe 6.
[0054] like Figure 1-4 As shown: utilizing the characteristics of the down-the-hole drill 1 driven by compressed air and the pressure reaching 0.8-1.2Mpa, the air volume is controlled by controlling the drilling rig operating valve at a specific layer to achieve artificial disturbance of the water-rich flowing sand layer, thereby achieving the purpose of increasing the amount of sand released in the drilling hole;
[0055] The boreholes are constructed in groups and sequences. The first borehole constructed in each group is used to explore the position of the quicksand layer and the water and sand gushing conditions, while taking into account the function of releasing water and sand. The second borehole starts from 0.5 meters above the explored layer. The orifice valve of the first borehole is opened, and the drill bit is repeatedly pulled up in the second borehole. At the same time, the air volume control valve is opened and closed until the drilling reaches the set depth. Secondary artificial disturbance of the quicksand layer is implemented to increase the amount of sand released. The third borehole also starts from 0.5 meters above the explored layer. The orifice valves of the first two boreholes are opened, and the drill bit is repeatedly pulled up in the third borehole. At the same time, the air volume control valve is opened and closed until the drilling reaches the set depth. Secondary artificial disturbance of the quicksand layer is implemented to increase the amount of sand released.
[0056] Specific implementation method four: This implementation method is a further limitation of specific implementation method one. In step E, each group of boreholes is constructed in sequence. The first borehole is assumed to be numbered 1#. After the hole is drilled to the designed grouting depth, when the drill tool is pulled out, water carries gravel along the borehole. At this time, the orifice is kept open to release sand until the amount of sand gushing is significantly reduced and then the orifice valve is closed. Then the second borehole is constructed, assuming the hole number is 2#. When the second borehole is drilled to 0.5m from the designed grouting depth, the orifice valve of the first borehole is opened and the drill tool is repeatedly pulled up in the second borehole. At the same time, the air volume control valve is opened and closed until the drilling reaches the designed depth. The purpose is to use the wind pressure of the drilling rig to disturb the quicksand layer and release sand from the two boreholes. Similarly, the third borehole is assumed to be numbered 3# and is also constructed in this way, but whether to open the first and second orifice valves at the same time or only open one borehole valve should be determined comprehensively based on the capacity of the drainage system, the amount of sand and gravel deposited on the working face, the amount of drilling water, etc.; this part is one of the core process methods of the present invention.
[0057] Each borehole can be repeatedly drilled, sanded, grouted, and circulated to achieve multiple drillings in one hole, which can greatly reduce the number of management boreholes. At the same time, the quality of the previous drilling and grouting sequence can be checked by re-drilling and scanning the holes, and weak points can be discovered in time for pre-management control, effectively ensuring the overall sand consolidation and water blocking effect of the water-rich quicksand layer, and ensuring that the wellbore can smoothly pass through water-rich quicksand layers of different thicknesses.
[0058] The drilling adopts the overall segmented hole short-section forward drilling and grouting method, that is, the working face drilling is carried out in the same layer for grouting. When the quicksand layer in this layer achieves the effect of sand consolidation and water blocking, the next layer is drilled and grouted. This cycle is repeated until the designed hole depth is reached. This not only ensures that the grouting consolidation wall is uniform and reaches the designed thickness, but also effectively avoids damage to the upper consolidated sand layer during the treatment process.
[0059] Specific implementation method five: This implementation method is a further limitation of specific implementation method one. In step G, the hole depth generally exceeds the bottom plate of the quicksand layer by more than 1m, and the bottom of the hole exceeds the wellbore excavation section by more than 1.5m, but should not exceed 2.5m, and is generally 2m. During the drilling and grouting process, each borehole undergoes multiple drilling, sand release, grouting, re-drilling and sweeping, and cyclic drilling and grouting processes. In the early stage when the amount of sand released is large, the amount of sand released by a single hole must be controlled as necessary. Blindly pursuing the amount of sand released may cause settlement of surface buildings. At the beginning of the quicksand layer management, a surface building settlement observation system is established, and data are regularly observed and compared and analyzed every day.
[0060] like Figure 3 As shown: the vertical shaft exposes the water-rich quicksand layer 8. After the concrete stop pad is poured on the working face, the detachable drilling and injection platform 3 is built, the hole is drilled and the reinforced orifice pipe is buried, two units 1 are arranged to work simultaneously. The drilling depth shown in the figure has entered the water-rich quicksand layer 8. By controlling the valve of the down-the-hole drill rig 1, medium-pressure compressed air is transported from the inside of the drill tool to the drill bit, and the water-rich quicksand layer 8 is artificially disturbed. After a certain amount of gravel is deposited on the working face through the disturbance ejection orifice, due to the special properties of the quicksand layer, flowing gravel will be supplemented to the area, but the total amount of gravel in the quicksand layer will be reduced to a certain extent, providing a certain space for slurry filling and replacement.
[0061] Specific implementation method six: This implementation method is a further limitation of specific implementation method one. The inspection hole in step H should be arranged on the inner side of the drilling hole about 0.5m away from the center of the wellbore. The bottom of the inspection hole should not penetrate the slurry stone curtain formed by cementation. In principle, the inspection hole is not segmented in the hole and is drilled to the designed hole depth at one time. When there is no sand or water or no sand but only a small amount of water gushing out during the drilling of the inspection hole, the current treatment can be ended and the wellbore excavation and masonry operation can be started. Otherwise, the inspection hole will be drilled densely until there is no sand or water or no sand but only a small amount of water gushing out during the drilling of the inspection hole, and the current treatment can be ended and the wellbore excavation and masonry operation can be started.
[0062] like Figure 6As shown: 3 boreholes are drilled in each group on one side of the wellbore, and the figure shows the drilling of 1# borehole to expose the water-rich flowing sand layer 8. By using medium wind pressure, when the drill bit is raised after the compressed air disturbance, the water carries the sand and gravel up along the borehole. At this time, the orifice is kept open to release sand until the sand gushing amount is significantly reduced and then the orifice valve is closed.
[0063] like Figure 7 As shown: 3 holes are drilled in each group on one side of the wellbore. The figure shows the drilling of the 2# hole. When the drilling is 0.5 meters away from the quicksand layer, the valve of the 1# hole is opened, and the drilling tool is repeatedly pulled up through the 2# hole. At the same time, the air volume control valve is opened and closed, and the quicksand layer is disturbed by compressed air with medium wind pressure until the drilling reaches the designed depth. At this time, a certain amount of gravel is ejected from the 1# and 2# holes;
[0064] like Figure 8 As shown: This figure shows that there are 3 boreholes in each group on one side of the wellbore. The figure shows the drilling of the 3# borehole. When drilling to 0.5 meters away from the quicksand layer, the valves at the mouths of the 1# and 2# holes are opened. Whether to open the 1# and 2# valves at the same time should be determined according to the water pump capacity of the working face, the amount of gravel accumulation, etc., and the drilling tool is repeatedly pulled up through the 3# hole. At the same time, the air volume control valve is opened and closed, and the medium wind pressure and compressed air are used to disturb the quicksand layer until the drilling reaches the designed depth. At this time, a certain amount of gravel is ejected from the 1#, 2# and 3# holes and accumulated on the working face;
[0065] like Figure 4 As shown: This figure shows that after all the boreholes in the working face have completed the replacement grouting of one layer, the original hole is drilled again to sweep the hole. During the sweeping process, the effect of the last drilling on sand consolidation and water blocking is checked. If there is still a small amount of water and sand gushing, it is refilled; the figure shows that the next layer has been entered for replacement grouting. The slurry stone body after grouting is actually a mixed stone body of gravel and slurry. The stone body has a certain strength that can support and block the quicksand layer outside the wellbore from entering the wellbore. The compressed air disturbed quicksand layer area 9 in the figure is shown as a second layer disturbance area. In fact, after a certain amount of gravel is accumulated on the working face through the disturbance ejection orifice, due to the special properties of the quicksand layer, flowing gravel will be supplemented to this area, but the total amount of gravel in the quicksand layer will be reduced to a certain extent, providing a certain space for slurry filling and replacement;
[0066] like Fig. 9 As shown: 3 boreholes per group on one side of the wellbore, the 1# borehole is drilled in the next layer to expose the water-rich flowing sand layer. When the drill tool is pulled out after being disturbed by medium-pressure compressed air, the water carries the sand and gravel up along the borehole. At this time, the hole is kept open to release sand until the sand inrush volume is significantly reduced and then closed;
[0067] like Fig.10As shown: This figure shows three boreholes in each group on one side of the wellbore. The figure shows the drilling of the next layer of the 2# borehole. When drilling to 0.5 meters away from the quicksand layer, the valve of the 1# hole is opened, and the drilling tool is repeatedly pulled up and down through the 2# hole. At the same time, the air volume control valve is opened and closed to use medium-pressure compressed air to disturb the quicksand layer until the drilling reaches the designed depth. At this time, a certain amount of gravel is ejected from the 1# and 2# holes and accumulated on the working surface;
[0068] like Fig.11 As shown: This figure shows 3 boreholes in each group on one side of the wellbore. The figure shows the drilling of the next layer of the 3# borehole. When drilling to 0.5 meters away from the quicksand layer, the orifice valves of the 1# and 2# holes are opened. Whether to open the 1# and 2# valves at the same time should be determined according to the water pump capacity of the working face, the amount of gravel accumulation, etc., and repeatedly pull the drill bit through the 3# hole, and open and close the air volume control valve at the same time. Use the medium wind pressure and compressed air to disturb the quicksand layer until drilling to the designed depth. At this time, a certain amount of gravel is ejected from the 1#, 2# and 3# holes and accumulated on the working face. Figure 8 5 and Figure 5 The middle 9 corresponds;
[0069] like Figure 6-11 As shown: According to the above drilling and grouting cycle, in the early stage of treatment, each group consists of 3 boreholes, and the segment height in the drilling and grouting hole should not exceed 0.5 meters. In the later stage of treatment, each group can consist of 1 to 3 boreholes. According to the early sand consolidation and water blocking conditions, the grouting segment height in the hole is adjusted to 0.5 to 1.5 meters. If the sand consolidation and water blocking effect is very ideal, it can also exceed 1.5 meters. This cycle is carried out until all boreholes are drilled and grouted to the designed hole depth. The hole depth generally exceeds the bottom plate of the quicksand layer by more than 1m, and the bottom of the hole exceeds the shaft excavation section by more than 1.5m, but should not exceed 2.5m, and generally 2m is taken; Fig.10 This is a schematic diagram of the effect of slurry stones in the water-rich quicksand layer.
[0070] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A construction method for increasing the amount of sand released by using a down-the-hole drill in a vertical shaft, the production method of which includes the following steps: closing the shaft, building a grouting platform, drilling holes, withdrawing the drilling tool, drilling and grouting operations, grouting operations, re-injection work and inspection hole construction, characterized in that: Step A. Shaft sealing: After the quicksand layer appears in the shaft of the vertical shaft, the working surface is sealed according to the actual water and sand gushing situation on site. The sealing method is to pour concrete stop pads with concrete strength grade C30; Step B. Building a grouting platform: After the grouting pad has been cured for a certain period of time, a drilling grouting platform is built. The platform is a removable and removable structure. After the platform is built, the drilling and grouting equipment is lowered and debugged; Step C. Drilling holes: drilling holes by using a drilling drill bit (12) according to design parameters, i.e. marking the positions of each drilling hole on the working surface, the allowable hole position deviation of the drilling hole shall not be greater than ±0.1m, and the drilling hole circle is 0.5-0.8m inward from the well wall (2); in the step C, a solid pipe slurry stone body (7) is arranged inside the well wall (2), and a drilling structure (11) is opened inside the solid pipe slurry stone body (7) by a down-the-hole drilling rig (1), and a hole mouth pipe (6) is arranged inside the drilling structure (11), and a hole mouth pipe fixing device (4) is arranged on the upper side of the hole mouth pipe (6), and a hole mouth water control device (5) is installed on the upper side of the hole mouth pipe fixing device (4), a drilling and injection platform (3) is built on the solid pipe slurry stone body (7), and a down-the-hole drilling rig (1) is installed on the drilling and injection platform (3), and the lower side of the solid pipe slurry stone body (7) is a water-rich quicksand layer (8), and A compressed air disturbed quicksand layer area (9) is provided on the water-rich quicksand layer (8), and the compressed air disturbed quicksand layer area (9) and the disturbed area replacement grouting slurry stone body area (10) are arranged in layers, and the drilling bit (12) on the down-the-hole drilling rig (1) is arranged inside the compressed air disturbed quicksand layer area (9); in the step C, the drilling bit (12) has a diameter of 130 mm, and the drilling is stopped when the drilling depth exceeds 0.5 m from the quicksand layer top plate or the first aquifer top plate, and after the drilling tool is withdrawn from the hole, a borehole pipe (6) is lowered into the hole, and the specification is Ø108 mm×4 mm seamless steel pipe. The length is determined according to the drilling depth and the hole mouth exposed 0.8 m to 1 m on the grouting pad surface; the borehole pipe (6) is fixed with single-liquid cement slurry or cement-water glass double-liquid slurry, and an anchor hole is constructed on the grouting pad surface, and a 36 mm round steel anchor is inserted and then welded to the borehole pipe (6); Step D. withdrawing the drilling tool: after the orifice pipe (6) is cured, the hole is swept, the drill bit is 91 mm in diameter, and the hole is drilled to a depth of 0.1 m to 0.2 m beyond the bottom of the orifice pipe (6), the drilling tool is withdrawn from the hole, and a pressure resistance and anti-permeability test is performed on the orifice pipe (6) using 1.2 times the final grouting pressure; Step E. Drilling and grouting: Drill holes are grouped and sequenced in a clockwise or counterclockwise direction. In the early stage of treatment, each group consists of 3 holes, and the height of the drilling and grouting sections in the drilling and grouting holes does not exceed 0.5 meters. In the later stage of treatment, each group can consist of 1 to 3 holes, and the height of the grouting section in the hole is adjusted to 0.5 to 1.5 meters according to the early sand consolidation and water blocking conditions; Step F. Grouting operation: After all the boreholes in each group are drilled to the designed grouting depth, grouting operation is carried out. The grouting adopts multi-frequency quantitative constant pressure grouting. The grouting material is at least one of ordinary cement, ultrafine cement, water glass, calcium chloride, and resin chemical slurry; Step G. Re-injection: After all the boreholes on the working face are drilled to the first designed grouting depth, the drilling to the second designed depth is carried out. If water and sand still gush out of some boreholes within the first designed grouting depth during the hole sweeping process, the drilling to the second designed depth is stopped, and the drilling tool is taken out for re-injection. This cycle is repeated until all the boreholes are drilled to the designed hole depth. Step H. Inspection hole construction: After all drilling construction is completed, inspection hole construction is carried out according to the drilling and injection conditions, and an inspection hole is arranged in the center of the wellbore.
2. A vertical shaft construction method for increasing the amount of sand release by using a down-the-hole drill according to claim 1, characterized in that: In the step E, each group of boreholes is constructed in sequence. After the first borehole is drilled to the designed grouting depth, when the drill tool is pulled out, water carries gravel up along the borehole. At this time, the orifice is kept open to release sand until the amount of sand gushing is significantly reduced and then the orifice valve is closed. Then the second borehole is constructed. When the second borehole is drilled to 0.5m from the designed grouting depth, the orifice valve of the first borehole is opened and the drill tool is repeatedly pulled up in the second borehole. At the same time, the air volume control valve is opened and closed until the drilling reaches the designed depth. The purpose is to use the wind pressure of the drilling rig to disturb the quicksand layer and release sand from the two boreholes. Then the third borehole is constructed. However, whether to open the first and second orifice valves at the same time or only open one borehole valve should be determined based on the capacity of the drainage system, the amount of sand and gravel deposited on the working face, and the amount of drilling water.
3. A vertical shaft construction method for increasing the amount of sand release by using a down-the-hole drill according to claim 1, characterized in that: In step G, the hole depth exceeds the bottom plate of the quicksand layer by 1m, and the bottom of the hole exceeds the wellbore excavation section by 1.5m, but does not exceed 2.5m; during the drilling and injection process, each borehole undergoes multiple drilling, sand release, grouting, re-drilling and sweeping, and cyclic drilling and grouting processes, and in the early stage when the amount of sand released is large, the amount of sand released by a single hole must be controlled as necessary. Blindly pursuing the amount of sand released may cause surface building settlement. At the beginning of the quicksand layer management, a surface building settlement observation system is established, and data are regularly observed and compared and analyzed every day.
4. A vertical shaft construction method for increasing the amount of sand release by using a down-the-hole drill according to claim 1, characterized in that: In the step H, the inspection hole is arranged on the inner side of the drilling hole about 0.5m away from the center of the wellbore. The bottom of the inspection hole should not penetrate the slurry stone curtain formed by cementation. In principle, the inspection hole is not segmented in the hole and is drilled to the designed hole depth at one time. When there is no sand or water or no sand but only a small amount of water gushing out during the drilling of the inspection hole, the current treatment can be ended and the wellbore excavation and masonry operation can be started. Otherwise, the inspection hole will be drilled densely until there is no sand or water or no sand but only a small amount of water gushing out during the drilling of the inspection hole, and the current treatment can be ended and the wellbore excavation and masonry operation can be started.
Citation Information
Patent Citations
Fast slip casting technique between composite well wall
CN101105130A
Shaft sinking process for expansion well completion of mine vertical shaft with boring method
CN101858218A