Contract batch production control method, device, equipment and storage medium
By determining production parameters and formulating production plans in the final production process, monitoring the batch production process solves the problem of frequent roller and liquid changes in the production line, improves the proportion of material preparation by node and work efficiency, and reduces economic losses and production cost.
Patent Information
- Application Number
- CN202210533970.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-05-17
- Publication Date
- 2024-10-15
- Estimated Expiration
- 2042-05-17
AI Technical Summary
In the final production process, contract batch production due to high surface grade, special coating passivation fluid lubricant, high strength grade, etc., causes the production line to frequently change rollers and fluids, which increases economic losses and transmits information outside the system. Slow response speed may miss the best production opportunity, causing the batch contract to miss the latest preparation date of the process and the batch production date of the final process, increasing the production cost of subsequent processes or causing the batch contract to be carried forward.
By determining the production parameters within the target month, including contract type, quantity, monthly maintenance plan for the whole process and historical production data, the production plan is formulated, the execution sequence of each process, the production cycle and the material preparation date are determined, and during the batch production process Monitor and determine whether the contract is completed. If it is not completed, analyze the reasons for incomplete completion.
It encourages upstream process planners to use the optimal plan to organize batch contract material preparation, increase the proportion of node-based material preparation, reduce the impact of unreasonable scheduling, avoid information transmission failures, reduce the frequency of follow-up reminders by planners, and improve work efficiency.
Smart Images

Figure CN114926013B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of production and processing technology, and in particular to a contract batch production control method, device, equipment and storage medium. Background Art
[0002] Regarding the final production process, when the contract attributes are the same and production control is difficult (including high surface level, special coating passivation liquid lubricant, high strength level, etc.), in order to reduce the economic losses caused by frequent roller and liquid changes on the production line, the contract will arrange batch production on certain days of the month. This part of the contract will put forward special node requirements for the date when the raw materials of each upstream process are ready, forming a production organization schedule similar to a train timetable.
[0003] Based on the experience of batch production planning for contracts in previous months, the comprehensive planner starts batch production planning for the next month's contracts in the second half of each month. As contracts are passed down one after another, the production organization plan is continuously fine-tuned. The final version of the production organization plan is formed when the contract expires on the 10th of the following month.
[0004] There are many types of contracts that need to be organized in batches. For example, the types of cold rolling contracts mainly include automobile outer panels, DP steel, etc. Before the improvement, the cold rolling comprehensive planner made a production organization plan for batch contracts in an offline Excel spreadsheet, and the latest preparation date was passed to the upstream process planners outside the system. The cold rolling contract has a long production process (five processes in the whole process), and the response speed of information transmission outside the system is slow. It is very likely that the batch contract will miss the best production time and the latest preparation date of the process and the batch production date of the last process, which will increase the production cost of the subsequent process or cause the batch contract to be carried forward. Summary of the invention
[0005] In view of the above problems, the present invention is proposed to provide a contract batch production control method, device, equipment and storage medium that overcome the above problems or at least partially solve the above problems.
[0006] In a first aspect, the present invention provides a contract batch production control method, the method comprising:
[0007] Determine the production parameters for contract batch production in the target month, including the types and quantities of contracts for batch production for the entire plant in the target month, the monthly maintenance plan for each process in the target month, and historical production data in a set time period before the target month;
[0008] Determine the production plan for the contract batch production in the target month according to the production parameters, the production plan including the execution order of each process in the whole process, the production cycle of each process, and the material preparation date of each process;
[0009] Carry out batch production of the contract in the target month according to the production plan, and monitor each process during the batch production process;
[0010] Determine whether the contract requiring batch production within the target month has been completed. If not, analyze the reasons for non-completion based on monitoring data.
[0011] Optionally, determining a production plan for contract batch production in a target month according to the production parameters includes:
[0012] Determine the execution order of each process in the entire process and the production cycle of each process in the target month based on the historical production data, the types and quantities of the contracts;
[0013] Determine the material readiness date for the final process based on the historical production data, the type and quantity of the contract;
[0014] The material readiness dates of the processes other than the final process are determined based on the material readiness date of the final process, the production cycle of each process and the monthly maintenance plan, wherein the monthly maintenance plan includes the maintenance date and maintenance duration of each process.
[0015] Optionally, determining the material readiness date of other processes except the final process according to the material readiness date of the final process, the production cycle of each process and the monthly maintenance plan includes:
[0016] The material preparation date of the final process is encoded according to the set encoding rules to obtain a first code;
[0017] Sending the first code to other processes except the last process respectively;
[0018] The other processes determine the material readiness time of the last process according to the first code, and reversely deduce the material readiness time of each process according to the production cycle, maintenance date and maintenance duration of each process.
[0019] Optionally, the step of encoding the material readiness date of the final process according to a set encoding rule includes:
[0020] Encoding is performed according to the arrangement order of the first field, the second field, the third field and the fourth field;
[0021] Among them, the first field is the code of each process, the second field is the material preparation date of each process, the third field is the batch reason code of the contract, and the fourth field is the quantity of the contract.
[0022] Optionally, the method further includes:
[0023] Determine whether there are multiple production plans for the contract that requires batch production in the target month, in which the contract can be produced in multiple parallel processes;
[0024] Determine whether the material readiness date of each process in the multiple production plans meets the date requirement;
[0025] A production plan in which the material readiness date of each process meets the date requirements is selected as the final production plan.
[0026] Optionally, the determining whether the material readiness date of each process in the multiple production plans meets the date requirement includes:
[0027] Determine whether the material readiness date of the last process in each production plan is between the earliest readiness date and the latest readiness date;
[0028] Among them, the earliest preparation date is the preparation date of the materials after being processed through all the steps of the whole process starting from the current date, and the latest preparation date is the delivery date stipulated in the contract.
[0029] Optionally, the determining whether the contract requiring batch production is completed within the target month includes:
[0030] Determine whether the quantity of each material produced according to the production plan in the target month reaches the quantity requirement specified in the contract before the delivery date specified in the contract.
[0031] In a second aspect, the present invention provides a contract batch production control device, the device comprising:
[0032] The production parameter determination module is used to determine the production parameters of the contract batch production in the target month, which include the types and quantities of contracts that need to be batch produced by the whole factory in the target month, the monthly maintenance plan of each process in the whole process in the target month, and the historical production data in the set time period before the target month;
[0033] A production planning determination module is used to determine the production plan of the contract batch production within the target month according to the production parameters, wherein the production plan includes the execution order of each process in the whole process, the production cycle of each process, and the material preparation date of each process;
[0034] A production monitoring module is used to carry out batch production of the contract in the target month according to the production plan, and monitor each process during the batch production process;
[0035] The cause analysis module is used to determine whether the contract requiring batch production is completed within the target month. If not, the reason for non-completion is analyzed based on the monitoring data.
[0036] In a third aspect, the present invention provides an electronic device comprising: a memory and a processor, wherein the memory and the processor are communicatively connected to each other, the memory stores computer instructions, and the processor executes the contract batch production control method as described in the first aspect by executing the computer instructions.
[0037] In a fourth aspect, the present invention provides a computer-readable storage medium storing computer instructions for causing the computer to execute the contract batch production control method as described in the first aspect.
[0038] The technical solution provided in the embodiments of the present invention has at least the following technical effects or advantages:
[0039] The embodiment of the present invention provides a contract batch production control method, device, equipment and storage medium. After determining the production parameters of the contract batch production in the target month, the production plan of the contract batch production in the target month is determined according to the production parameters, and then the contract batch production is carried out in the target month according to the production plan. In the process of batch production, each process is monitored, and finally it is determined whether the contract that needs batch production in the target month is completed. If not, the reason for the incompleteness is analyzed according to the monitoring data. This method can prompt the upstream process planners to organize the batch contract to prepare materials according to the process nodes with the optimal production plan at the first time, improve the proportion of material preparation according to the nodes, and reduce the impact of unreasonable scheduling. At the same time, it can avoid the failure of batch information transmission caused by information omission during the work handover of planners outside the system, reduce the frequency of follow-up reminders outside the system of planners, and improve work efficiency.
[0040] The above description is only an overview of the technical solution of the present invention. In order to more clearly understand the technical means of the present invention, it can be implemented according to the contents of the specification. In order to make the above and other purposes, features and advantages of the present invention more obvious and easy to understand, the specific implementation methods of the present invention are listed below. BRIEF DESCRIPTION OF THE DRAWINGS
[0041] Various other advantages and benefits will become apparent to those of ordinary skill in the art by reading the detailed description of the preferred embodiments below. The accompanying drawings are only for the purpose of illustrating the preferred embodiments and are not to be considered as limiting the present invention. Moreover, the same reference symbols are used throughout the accompanying drawings to represent the same components. In the accompanying drawings:
[0042] Figure 1 It is a flow chart of a contract batch production control method provided by an embodiment of the present invention;
[0043] Figure 2 It is a structural block diagram of a contract batch production control device provided by an embodiment of the present invention. DETAILED DESCRIPTION
[0044] Exemplary embodiments of the present disclosure will be described in more detail below with reference to the accompanying drawings.
[0045] Various structural schematic diagrams according to embodiments of the present disclosure are shown in the accompanying drawings. These figures are not drawn to scale, and some details are magnified and some details may be omitted for the purpose of clear expression. The shapes of various regions and layers shown in the figures and the relative sizes and positional relationships therebetween are only exemplary, and may deviate in practice due to manufacturing tolerances or technical limitations, and those skilled in the art may further design regions / layers with different shapes, sizes, and relative positions according to actual needs.
[0046] In the context of the present disclosure, when a layer / element is referred to as being "on" another layer / element, the layer / element may be directly on the other layer / element, or there may be an intervening layer / element therebetween. Additionally, if a layer / element is "on" another layer / element in one orientation, the layer / element may be "below" the other layer / element when the orientation is reversed. In the context of the present disclosure, similar or identical components may be denoted by the same or similar reference numerals.
[0047] In order to better understand the above-mentioned technical scheme, the above-mentioned technical scheme will be described in detail below in combination with specific implementation methods. It should be understood that the embodiments of the present disclosure and the specific features in the embodiments are detailed descriptions of the technical scheme of the present application, rather than limitations on the technical scheme of the present application. In the absence of conflict, the embodiments of the present application and the technical features in the embodiments can be combined with each other.
[0048] Figure 1 is a flow chart of a contract batch production control method provided by an embodiment of the present invention, such as Figure 1 As shown, the method includes:
[0049] Step 101: Determine production parameters for contract batch production within the target month.
[0050] In this embodiment, the production parameters include the types and quantities of contracts for batch production of the entire factory within the target month, the monthly maintenance plan for each process in the entire process of the target month, and the historical production data within a set time period before the target month.
[0051] For example, the type of contract is the type of material to be processed. For example, taking a cold rolling contract as an example, the types of cold rolling contracts may include automobile outer panels, high-strength steel (DP steel), low-alloy steel, zinc-aluminum-magnesium layer, aluminum-silicon layer, aluminum-zinc-magnesium layer, etc. The quantity of the contract is the quantity of materials to be processed, such as the number of materials or the weight of the materials.
[0052] Exemplarily, the monthly maintenance plan may include the maintenance date and maintenance duration of each processing step, that is, the maintenance date and maintenance duration of the processing machine corresponding to each step.
[0053] For example, historical production data may include the types and quantities of each material actually processed and produced each month, as well as the execution order and production cycle of each corresponding process. All historical production data within a set time period before the target month will be stored and can be retrieved. The set time period can be freely selected as needed. For example, historical production data for 6 months or 12 months before the target month can be selected.
[0054] In one implementation of this embodiment, a base table for defining special attribute contract classifications can be created, and batch production contracts can be defined in multiple dimensions. The contract quantity and historical production data for the target month can be automatically extracted. The multi-dimensional batch production contract structure and quantity can be compared horizontally and vertically.
[0055] Step 102: Determine the production plan for the contract batch production within the target month based on the production parameters.
[0056] Among them, production planning includes the execution order of each process in the whole process, the production cycle of each process, and the date when materials are ready for each process.
[0057] In this embodiment, step S102 may include:
[0058] The first step is to determine the execution order of each process in the target month and the production cycle of each process based on historical production data, contract types and quantities.
[0059] The second step is to determine the date when materials will be ready for the final process based on historical production data, contract type and quantity.
[0060] Specifically, we can refer to the historical data and find that the types and quantities of materials actually processed and produced are the same or similar to the types and quantities of the contracts to be processed in the target month. In this way, we can determine the execution order of each process in the entire process of the target month, the production cycle of each process, and the date when materials are ready for the last process based on the production plans of the historical months.
[0061] The third step is to determine the material readiness date for processes other than the final process based on the material readiness date for the final process, the production cycle of each process, and the monthly maintenance plan.
[0062] Specifically, the third step may include:
[0063] The material preparation date of the final process is encoded according to the set encoding rules to obtain a first code;
[0064] Sending the first code to other processes except the last process respectively;
[0065] Other processes determine the material readiness time of the last process according to the first code, and reversely deduce the material readiness time of each process according to the production cycle, maintenance date and maintenance duration of each process.
[0066] In this embodiment, the coding can be performed according to the arrangement order of the first field, the second field, the third field and the fourth field. The first field is the code of each process, the second field is the material preparation date of each process, the third field is the batch reason code of the contract, and the fourth field is the quantity of the contract.
[0067] Specifically, the first field may include two bytes, the second field may include four bytes, i.e., 2 digits for month + 2 digits for day, the third field may include three bytes, and the fourth field may include three or four bytes, and the transmission within the system is achieved through coded information.
[0068] For example, in this embodiment, taking the cold rolling contract of galvanized automobile outer panel as an example, the processing includes four processes: steelmaking-hot rolling-acid rolling-hot-dip galvanizing. Among them, when the first field is the steelmaking process, the corresponding code can be A5 / A6 / A7; when the first field is the hot rolling process, the corresponding code can be H5 / H6 / H8; when the first field is the acid rolling process, the corresponding code can be SA / SB / SC; when the first field is the hot-dip galvanizing process, the corresponding code can be DA / DB / DD / DE / DK / DG.
[0069] The reason for batching is the type of contract. For example, the reasons for batching of cold rolling contracts may include: automobile outer panels, zinc-aluminum-magnesium coatings, aluminum-silicon coatings, aluminum-zinc coatings, high-strength steel (DP steel), and low alloys, and the corresponding codes are WB, ZM, AS, AZ, DP, and LA.
[0070] It should be noted that the above encoding method is only an example, and the present invention includes but is not limited to this.
[0071] Optionally, the first code may be transmitted to the production plan preparation, production plan management and inventory management interface of each process step in the entire process.
[0072] Specifically, the batch contract is transmitted in the planning and scheduling interface and planning management interface of each upstream process in the whole process of the system, including the material application process, steelmaking process, hot rolling process, acid continuous rolling process, and cold rolling process, a total of five processes. This ensures that the planners of each process can see the time node of the batch requirement of the last process at the first time of scheduling, avoiding the failure of information transmission caused by information omission during the handover between planners outside the system, missing the latest preparation date of the process and the last batch production date, resulting in increased production costs of the subsequent processes or carryover of batch contracts.
[0073] The above method summarizes the characteristics of historical contract batch planning, combines the structure and quantity of the batch contract of the current month, and refers to the monthly maintenance plan to formulate the batch contract production plan for the last process of the month.
[0074] Optionally, the method may further include:
[0075] The first step is to determine whether there are multiple production plans for the contract that requires batch production within the target month. In multiple production plans, the contract can be produced in multiple parallel processes.
[0076] If yes, calculate the completion date of all processes in the whole process. If no, calculate the completion date of all processes in the current process route.
[0077] The second step is to determine whether the material preparation date of each process in various production plans meets the date requirements.
[0078] In this embodiment, the material preparation date T of the last process in each production plan can be determined. i Is it on the earliest date of readiness T mix and the latest date of readiness T max between.
[0079] Among them, the earliest ready date is T mix The date on which the material is ready after all processes in the entire process from the current date. The latest ready date is T max The delivery date specified in the contract.
[0080] If Ti∈(Tmix, Tmax), that is, the readiness date of the current process is between the earliest readiness date and the latest readiness date, the system can automatically complete the calculation of the readiness date of the entire process and all processes. At the same time, the batch collection date and batch collection reason code of each process can also be synchronously transmitted to each process scheduling interface and inventory management interface.
[0081] like That is, the current process's readiness date is earlier than the earliest readiness date or later than the latest readiness date. At this time, the readiness date of the process cannot be met in the actual production organization, and an error message needs to be prompted, and then the planner needs to reset the batch date of the last process.
[0082] The third step is to select a production plan in which the material preparation date of each process meets the date requirements as the final production plan.
[0083] In this embodiment, the comprehensive planners of each process can review whether the currently determined production plan is feasible.
[0084] If it is feasible, the batch collection date and the batch collection reason will be transmitted to the scheduling interface of each process and the inventory management interface, and the professionals of each process will organize the production according to the determined batch collection contract plan;
[0085] If it is not feasible, it will be difficult to organize production according to this plan and the batch contract production plan needs to be adjusted.
[0086] In the specific implementation, you can also create a batch contract adjustment interface, which can be the same screen as the process control interface, and needs to have the function of conveniently adjusting the preparation date according to the review results.
[0087] Step 103: Carry out batch production of the contract in the target month according to the production plan, and monitor each process during the batch production.
[0088] Specifically, the preparation progress of each process in the whole process and the abnormal status of materials can be monitored.
[0089] Exemplarily, it can support single process monitoring and full process monitoring of each process. It supports single process monitoring, and its monitoring attribute fields may include: batch contract reason code, contract number, contract status, full process code, raw material quantity, number of raw material pieces, difference in weight and number of pieces; it supports abnormal status monitoring of raw materials in each process of the full process, and its monitoring attribute fields may include: batch reason code, full process code, material number, brand (steel grade), material weight, material status, customized material status code, material status duration, responsible disposal room, and contract number.
[0090] In the specific implementation, you can also formulate inter-process compliance management methods, set monthly weight or number reward and penalty lines for processes according to node fulfillment rates. According to the process readiness nodes, statistics are collected on actual performance, and the deviation between plan and actual performance is announced daily. At the same time, the execution rate of each process readiness according to the process batch contract and the gap with the monthly target are released. The visualization of statistical data strengthens the sense of responsibility of professionals.
[0091] In the specific implementation, the planner of the final process can follow up on materials according to the responsible disposal room of abnormal materials, which has accelerated the material circulation speed, reduced the inventory capital occupation and increased the material arrival rate according to the node.
[0092] The batch contract is usually a full-month difficult-to-organize contract, which has high requirements for production line conditions, material availability and public auxiliary facilities. The abnormal material status monitoring information is pushed to the account of the responsible person according to the material handling room, and the abnormal material handling progress is counted according to the responsible account every day to visualize the progress results. Focusing 80% of the professionals' energy on 20% of the key tasks can improve the collaborative efficiency of work between different departments.
[0093] The embodiment of the present invention forms a PDCA management cycle for batch contracts, satisfying a closed-loop process of prior planning, plan implementation, process monitoring, and post-analysis and improvement.
[0094] Step 104: determine whether the contract requiring batch production within the target month is completed. If not, analyze the reasons for non-completion based on monitoring data.
[0095] Optionally, step 104 may include:
[0096] Determine whether the quantity of each material produced according to the production plan within the target month reaches the quantity requirements specified in the contract before the delivery date specified in the contract.
[0097] In specific implementation, a statistical table of reasons for the unfinished batch contract can also be created, and the names of the contract-related attribute columns in the analysis table can include, for example: contract number; contract status; manufacturer; manufacturing product classification; sales variety code; end-user name; full-process path code; order month; delivery date; order weight; through quantity (current process); short quantity (current process); accurate quantity within the delivery period; accurate short quantity within the delivery period; the names of the material-related attribute columns in the analysis table include: abnormal reason; material number; output time; multiple feeding; output process; material weight; major category of products; responsible unit; Jingtang defect name; defect code; residual material reason code, etc. The present invention includes but is not limited to this.
[0098] Based on the unfinished performance of the batch contract plan, analyze historical data, use the Pareto chart and the 80 / 20 rule to concentrate main efforts on solving 20% of the problem points and solve 80% of the problems.
[0099] In order to better understand the present invention, the following takes the 3# hot-dip galvanized automobile outer panel of Shougang Jingtang Iron and Steel Company as an example to illustrate the above-mentioned cold rolling contract batch production control method.
[0100] First, according to specific parameters, the number of 3# hot-dip galvanized automobile outer panels contracts for the month is obtained;
[0101] Then, after analyzing the production quantity and production cycle of 3# hot-dip galvanized automobile outer panels in historical months, it is planned that the production of 3# hot-dip galvanized automobile outer panels will start 1.5 days after the start of maintenance. Combined with the monthly maintenance plan of 3# hot-dip galvanizing in that month, the batch collection date Ti of the hot-dip process (i.e. the final process) of 3# hot-dip galvanized automobile outer panels in that month is formulated, taking the batch collection date of August 12 as an example;
[0102] Then, according to the coding rules, the transfer code of 3# hot-dip galvanized automobile outer panel system is formulated, DG0812WB3000, that is, the 3# hot-dip galvanizing process starts to continuously produce 3,000 tons of automobile outer panels on August 12. At the same time, by retrieving the static base table data, the production cycle data of each process in the whole process and the production execution sequence of each process in the whole process are obtained. Take the production sequence of steelmaking-hot rolling-pickling rolling-hot-dip galvanizing, and the production cycle of steelmaking (1 day), hot rolling (2 days), pickling rolling (3 days), hot-dip galvanizing (3 days) as an example. Reverse the preparation date of each process. If there is no overhaul of each process, the preparation dates are steelmaking (0804, which means August 4, the same below), hot rolling (0806), acid rolling (0809), and hot-dip galvanizing (0812). If the acid rolling is overhauled for 16 hours on August 9, the preparation dates of each process are steelmaking (0803), hot rolling (0805), acid rolling (0808), and hot-dip galvanizing (0812).
[0103] Then, calculate the earliest completion date Tmix and the latest completion date Tmax of this part of the contract;
[0104] Taking the current date of August 1 as an example, the earliest preparation date of this part of the contract Tmix = 0801 + 1 day (production cycle of steelmaking process) + 2 days (production cycle of hot rolling process) + 3 days (production cycle of pickling process) + 3 days (production cycle of hot-dip galvanizing process) = 0810; taking the delivery date of the contract as August 30 as an example, the latest preparation date of the contract Tmax = 0830-1 day (production cycle of steelmaking process) - 2 days (production cycle of hot rolling process) - 3 days (production cycle of pickling process) - 3 days (production cycle of hot-dip galvanizing process) = 0821.
[0105] Determine whether Ti∈(Tmix, Tmax) holds; Ti=0812, Tmix=0810, Tmax=0821, Ti∈(Tmix, Tmax) holds.
[0106] In addition, after the batch contract of each cold rolling process is completed according to the planning of 3# hot-dip galvanized automobile outer plate, the material application planner, steelmaking planner, hot rolling planner, and acid rolling planner will review whether the batch arrangement can be met. The evaluation content is mainly whether the current process resource quantity can meet the needs of the subsequent process. After the review is passed, the final version of the monthly batch contract production plan is formed, thus completing the work of the P stage in the PDCA cycle.
[0107] At the same time, the planning information is synchronously transmitted to the material application, steelmaking, hot rolling and pickling rolling planning and management interface, as well as the inventory management interface of the steelmaking, hot rolling and pickling rolling operation departments. The steelmaking, hot rolling and pickling rolling planners organize production according to the planned 3# hot-dip galvanized automobile outer plate train schedule. This gradually completes the work of stage D in the PDCA cycle.
[0108] Then, in the process monitoring stage of the 3# hot-dip galvanized automobile outer plate train schedule, with the help of the system platform, the contract preparation progress of the 3# hot-dip galvanized automobile outer plate in the material application, steelmaking, hot rolling, acid rolling and hot-dip galvanizing processes is monitored by process, and the compliance rate of the deviation release process is counted; at the same time, the status of raw materials in each process is monitored, and abnormal materials are synchronized to the professional and technical personnel in the product room, and the progress of abnormal material processing is counted according to the responsible person. Through the monitoring of the two main lines of contract and material, the node arrival rate of each process is improved. This process is the work of stage C in the PDCA cycle.
[0109] Then, with the help of the system platform, we obtained the statistical analysis of the reasons for the unfinished contract of 3# hot-dip galvanized automobile outer panels. Based on the unfinished performance of the contract of 3# hot-dip galvanized automobile outer panels, we analyzed the historical data, used the Pareto chart and adopted the 80 / 20 rule to focus on overcoming 20% of the problem points and solve 80% of the problems. This process is the work of phase A in the PDCA cycle.
[0110] The embodiment of the present invention is based on the Deming cycle PDCA management theory, that is, after obtaining the structure and quantity of the batch contracts required by the whole factory in the current month, the production plan of the batch contracts for the last process of the whole month is formulated in combination with the monthly maintenance plan and historical production performance (P); then, the batch planning information is transmitted to the production plan preparation, management and inventory management interface of each process in the whole process, and the planners of each process organize production according to the plan (D); at the same time, the system completes the preparation of nodes and material flow status of each process in the whole process of the batch contract, and performs node-by-node monitoring of the batch contract (C); finally, the system platform is used to complete the analysis of the reasons for the failure of the batch contract, and the 80 / 20 rule is used to concentrate the main efforts on overcoming 20% of the problem points and solving 80% of the problems (A).
[0111] Figure 2 is a structural block diagram of a contract batch production control device provided by an embodiment of the present invention, such as Figure 2 As shown, the device includes a production parameter determination module 201, a production planning determination module 202, a production monitoring module 203 and a cause analysis module 204.
[0112] The production parameter determination module 201 is used to determine the production parameters of the contract batch production in the target month. The production parameters include the types and quantities of contracts that need to be batch produced by the whole factory in the target month, the monthly maintenance plan of each process in the whole process in the target month, and the historical production data in the set time period before the target month;
[0113] The production planning determination module 202 is used to determine the production planning of the contract batch production in the target month according to the production parameters. The production planning includes the execution sequence of each process in the whole process, the production cycle of each process, and the material preparation date of each process;
[0114] The production monitoring module 203 is used to carry out batch production of the contract in the target month according to the production plan and monitor each process during the batch production process;
[0115] The reason analysis module 204 is used to determine whether the contract requiring batch production within the target month is completed. If not completed, the reason for the non-completion is analyzed based on the monitoring data.
[0116] The specific details of the above-mentioned contract batch production control device can be found in Figure 1 The corresponding descriptions and effects in the embodiment of the contract batch production control method shown in the figure can be understood and will not be repeated here.
[0117] The embodiment of the present invention also provides an electronic device, which may include a processor and a memory, wherein the processor and the memory may be connected via a bus or other means. The processor may be a central processing unit (CPU). The processor may also be other general-purpose processors, digital signal processors (DSP), application-specific integrated circuits (ASIC), field-programmable gate arrays (FPGA) or other programmable logic devices, discrete gates or transistor logic devices, discrete hardware components and other chips, or a combination of the above-mentioned various types of chips. The memory, as a non-transient computer-readable storage medium, can be used to store non-transient software programs, non-transient computer executable programs and modules, such as the program instructions / modules corresponding to the contract batch production control device in the embodiment of the present invention. The processor executes various functional applications and data processing of the processor by running the non-transient software programs, instructions and modules stored in the memory, that is, the contract batch production control device in the above method embodiment is realized.
[0118] The memory may include a program storage area and a data storage area, wherein the program storage area may store an operating system and an application required by at least one function; the data storage area may store data created by the processor, etc. In addition, the memory may include a high-speed random access memory, and may also include a non-volatile memory, such as at least one disk storage device, a flash memory device, or other non-volatile solid-state storage device. The one or more modules are stored in the memory, and when executed by the processor, the execution is as follows: Figure 1 The contract batch production control method in the embodiment shown. The specific details of the above electronic equipment can be referred to in Figure 1 The corresponding related descriptions and effects in the embodiments shown are understood and will not be repeated here. Those skilled in the art will understand that all or part of the processes in the above-mentioned embodiment methods can be completed by instructing the relevant hardware through a computer program, and the program can be stored in a computer-readable storage medium. When the program is executed, it may include the processes of the embodiments of the above-mentioned methods. Among them, the storage medium may be a read-only memory (ROM), a random access memory (RAM), a flash memory (FlashMemory), a hard disk (Hard Disk Drive, abbreviated as: HDD) or a solid-state drive (SSD), etc.; the storage medium may also include a combination of the above-mentioned types of memory.
[0119] The technical solutions in the above embodiments of the present application have at least the following technical effects or advantages:
[0120] The embodiment of the present invention provides a contract batch production control method, device, equipment and storage medium. After determining the production parameters of the contract batch production in the target month, the production plan of the contract batch production in the target month is determined according to the production parameters, and then the contract batch production is carried out in the target month according to the production plan. In the process of batch production, each process is monitored, and finally it is determined whether the contract that needs batch production in the target month is completed. If not, the reason for the incompleteness is analyzed according to the monitoring data. This method can prompt the upstream process planners to organize the batch contract to prepare materials according to the process nodes with the optimal production plan at the first time, improve the proportion of material preparation according to the nodes, and reduce the impact of unreasonable scheduling. At the same time, it can avoid the failure of batch information transmission caused by information omission during the work handover of planners outside the system, reduce the frequency of follow-up reminders outside the system of planners, and improve work efficiency.
[0121] In the description provided herein, a large number of specific details are described. However, it is understood that embodiments of the present invention can be practiced without these specific details. In some instances, well-known methods, structures and techniques are not shown in detail so as not to obscure the understanding of this description.
[0122] Similarly, it should be understood that in order to streamline the present disclosure and aid in understanding one or more of the various inventive aspects, in the above description of exemplary embodiments of the present invention, various features of the present invention are sometimes grouped together into a single embodiment, figure, or description thereof. However, this disclosed method should not be interpreted as reflecting the intention that the claimed invention requires more features than those explicitly recited in each claim. More specifically, as reflected in the claims below, inventive aspects lie in less than all the features of the individual embodiments disclosed above. Therefore, the claims that follow the specific embodiment are hereby expressly incorporated into the specific embodiment, with each claim itself serving as a separate embodiment of the present invention.
[0123] It should be noted that the above embodiments illustrate the present invention rather than limit it, and that those skilled in the art may devise alternative embodiments without departing from the scope of the appended claims. In the claims, any reference symbol between brackets shall not be construed as a limitation on the claims. The word "comprising" does not exclude the presence of components or steps not listed in the claims. The word "one" or "an" preceding a component does not exclude the presence of a plurality of such components. The present invention may be implemented by means of hardware comprising a number of different components and by means of a suitably programmed computer. In a unit claim enumerating a number of devices, several of these devices may be embodied by the same hardware item. The use of the words first, second, and third, etc., does not indicate any order. These words may be interpreted as names.
Claims
1. A contract batch production control method, characterized in that: The method comprises: Determine the production parameters for contract batch production in the target month, including the types and quantities of contracts for batch production for the entire plant in the target month, the monthly maintenance plan for each process in the target month, and historical production data in a set time period before the target month; Determine the production plan for the contract batch production in the target month according to the production parameters, the production plan including the execution order of each process in the whole process, the production cycle of each process, and the material preparation date of each process; Carry out batch production of the contract in the target month according to the production plan, and monitor each process during the batch production process; Determine whether the contract requiring batch production is completed within the target month. If not, analyze the reasons for non-completion based on monitoring data; The step of determining the production plan for the contract batch production in the target month according to the production parameters includes: Determine the execution order of each process in the entire process and the production cycle of each process in the target month based on the historical production data, the types and quantities of the contracts; Determine the material readiness date for the final process based on the historical production data, the type and quantity of the contract; The material readiness dates of the processes other than the final process are determined based on the material readiness date of the final process, the production cycle of each process and the monthly maintenance plan, wherein the monthly maintenance plan includes the maintenance date and maintenance duration of each process.
2. The contract batch production control method according to claim 1 is characterized in that: Determining the material readiness date of other processes except the final process according to the material readiness date of the final process, the production cycle of each process and the monthly maintenance plan includes: The material preparation date of the final process is encoded according to the set encoding rules to obtain a first code; Sending the first code to other processes except the last process respectively; The other processes determine the material readiness time of the last process according to the first code, and reversely deduce the material readiness time of each process according to the production cycle, maintenance date and maintenance duration of each process.
3. The contract batch production control method according to claim 2 is characterized in that: The material preparation date of the final process is coded according to the set coding rules, including: Encoding is performed according to the arrangement order of the first field, the second field, the third field and the fourth field; Among them, the first field is the code of each process, the second field is the material preparation date of each process, the third field is the batch reason code of the contract, and the fourth field is the quantity of the contract.
4. The contract batch production control method according to claim 1, characterized in that: The method further comprises: Determine whether there are multiple production plans for the contract that requires batch production in the target month, in which the contract can be produced in multiple parallel processes; Determine whether the material readiness date of each process in the multiple production plans meets the date requirement; A production plan in which the material readiness date of each process meets the date requirements is selected as the final production plan.
5. The contract batch production control method according to claim 4 is characterized in that: The determining whether the material preparation date of each process in the multiple production plans meets the date requirement includes: Determine whether the material readiness date of the last process in each production plan is between the earliest readiness date and the latest readiness date; Among them, the earliest preparation date is the preparation date of the materials after being processed through all the steps of the whole process starting from the current date, and the latest preparation date is the delivery date stipulated in the contract.
6. The contract batch production control method according to claim 1 is characterized in that: The determination of whether the contract requiring batch production is completed within the target month includes: Determine whether the quantity of each material produced according to the production plan in the target month reaches the quantity requirement specified in the contract before the delivery date specified in the contract.
7. A contract batch production control device, characterized in that: The device comprises: The production parameter determination module is used to determine the production parameters of the contract batch production in the target month, which include the types and quantities of contracts that need to be batch produced by the whole factory in the target month, the monthly maintenance plan of each process in the whole process in the target month, and the historical production data in the set time period before the target month; A production planning determination module is used to determine the production plan of the contract batch production within the target month according to the production parameters, wherein the production plan includes the execution order of each process in the whole process, the production cycle of each process, and the material preparation date of each process; A production monitoring module is used to carry out batch production of the contract in the target month according to the production plan, and monitor each process during the batch production process; The reason analysis module is used to determine whether the contract requiring batch production is completed within the target month. If not, the reason for non-completion is analyzed based on the monitoring data. The production planning determination module is also used for: Determine the execution order of each process in the entire process and the production cycle of each process in the target month based on the historical production data, the types and quantities of the contracts; Determine the material readiness date for the final process based on the historical production data, the type and quantity of the contract; The material readiness dates of the processes other than the final process are determined based on the material readiness date of the final process, the production cycle of each process and the monthly maintenance plan, wherein the monthly maintenance plan includes the maintenance date and maintenance duration of each process.
8. An electronic device, characterized in that: include: A memory and a processor, wherein the memory and the processor are communicatively connected to each other, the memory stores computer instructions, and the processor executes the contract batch production control method described in any one of claims 1 to 6 by executing the computer instructions.
9. A computer-readable storage medium, characterized in that: The computer-readable storage medium stores computer instructions, and the computer instructions are used to enable the computer to execute the contract batch production control method described in any one of claims 1-6.