A method and system for judging the safe distance of near-electricity operation in substation engineering
By dismantling the construction process and judging the live state of the power grid equipment, and combining with the three-dimensional model to determine the safe distance, the problem of low accuracy in power outage planning decision-making in ultra-high voltage projects is solved, and construction safety is improved.
Patent Information
- Application Number
- CN202210680210.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-06-16
- Publication Date
- 2024-11-22
- Estimated Expiration
- 2042-06-16
AI Technical Summary
In ultra-high voltage engineering construction, the accuracy of power outage planning decisions is low, resulting in an increase in construction safety risks. The existing technology fails to effectively consider the measurement of the live state and safety distance of the power equipment, especially during live operations.
By dismantling the construction process, forming a construction process sequence information table, establishing a safety distance table for power outage operations in the ultra-high voltage station, and determining the live status of power grid equipment based on real-time data of the substation, combining with a three-dimensional model to determine the safe distance during construction, and achieving safety in near-power operations Risk identification.
The safety of ultra-high voltage station construction has been improved, and the construction safety risks have been reduced through quantitative analysis, ensuring the safety of personnel and equipment during live operations.
Smart Images

Figure CN115018336B_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of electric power systems, and in particular relates to a method and system for judging the safe distance of near-electricity operations in a substation project. Background Art
[0002] The decision-making of power outage plan is a core component of UHV project construction. The accuracy of its decision directly determines the construction quality and engineering safety of the power grid, and is the basis for the high-quality development of power grid projects. The accuracy of power outage plan decision-making is affected by the site and construction process of the UHV station. Before construction, it is necessary to accurately determine the scope of power outage, ensure the safety of construction operations, avoid construction accidents beyond the safety distance, and ensure the high-quality construction of the power grid.
[0003] Traditional power outage plan submissions must be applied for in advance in accordance with the dispatching requirements at all levels. Many projects do not have construction units or supervision units when submitting annual power outage plans. They only rely on power outages submitted by design, which has low accuracy and is prone to subsequent additions and modifications to power outage plans. Filling out power outage plans requires professional operation and maintenance personnel who are familiar with system operations. The contradiction between the shortage of professional operation and maintenance personnel and the ever-expanding scale of projects has gradually become prominent. During live construction operations, construction units need to dispatch personnel with many years of construction experience and the ability to perform primary installation and protection to conduct on-site surveys and visually inspect whether live operations exceed the safety distance. There is a lack of quantitative analysis, and there are large errors, which increases the safety risk of construction. Some technical solutions disclosed in the prior art do not consider the measurement of safety distances in the power industry, or only consider the safety of robots during operation, but do not consider the calculation of safety distances of live equipment around the robots. Summary of the invention
[0004] In order to solve the above technical problems, the present invention proposes a method and system for judging the safe distance of near-electrical operations in substation projects. By implementing the process and judging the energized state of power equipment, the safety risk identification of near-electrical operations is achieved, thereby ensuring the safety of personnel and equipment during energized operations.
[0005] To achieve the above object, the present invention adopts the following technical solutions:
[0006] A method for determining the safe distance for near-electricity operation in a substation project comprises the following steps:
[0007] Dismantle the UHV station base station operation process to form a construction process sequence information table, select the voltage level of live equipment in the power outage area to establish a UHV station power outage operation safety distance table, and judge the live status of power grid equipment based on the real-time data of the substation to form a live equipment status table of power equipment;
[0008] Establishing a three-dimensional model of a substation, and importing the construction process sequence information table into the three-dimensional model of the substation;
[0009] Select the voltage level and live state of the energized equipment, and determine the safe distance during the construction process based on the three-dimensional model of the construction process as the construction process proceeds.
[0010] Furthermore, the method for establishing the three-dimensional model of the substation is: obtaining the physical space positions of the equipment and buildings in the substation, the sizes of the equipment and the sizes of the buildings in the substation, and using three-dimensional laser scanning technology to establish the three-dimensional model of the substation.
[0011] Furthermore, the construction process sequence information table includes process names and process sequence codes.
[0012] Furthermore, the UHV station power outage operation safety distance table includes voltage levels and safety distances.
[0013] Furthermore, the table of powered equipment status of electric equipment includes equipment name and powered status.
[0014] Furthermore, the process of selecting the voltage level of live equipment is: according to the operating area of the substation, the voltage level of live equipment in the operating area indicated by the UHV station power outage operation safety distance table is selected.
[0015] Furthermore, the process of selecting the voltage state of the energized equipment is: according to the substation operation area, a table of energized equipment states of the electric equipment is selected to distinguish the energized states of the equipment in the substation operation area.
[0016] Furthermore, the process of selecting the voltage level and energized state of live equipment and judging the safe distance during the construction process based on the three-dimensional model of the construction process during the construction process is as follows: identifying the safety risks of near-electrical operations and converting the distance between equipment in the three-dimensional model into a safe distance in the actual construction process.
[0017] The present invention also proposes a substation engineering near-electricity operation safety distance judgment system, including a table forming module, an importing module and a judgment module;
[0018] The table formation module is used to disassemble the UHV station base station operation process to form a construction process sequence information table, select the voltage level of live equipment in the power outage area to establish a UHV station power outage operation safety distance table, and judge the live state of power grid equipment based on the real-time data of the substation to form a live equipment state table of power equipment;
[0019] The import module is used to establish a three-dimensional model of the substation and import the construction process sequence information table into the three-dimensional model of the substation;
[0020] The judgment module is used to select the voltage level and the energized state of the energized equipment, and judge the safe distance during the construction process according to the three-dimensional model of the imported process sequence information table.
[0021] Further, the table forming module includes a first forming module, a second forming module and a third forming module;
[0022] The first forming module is used to disassemble the UHV station base station operation process to form a construction process sequence information table;
[0023] The second forming module is used to select the voltage level of live equipment in the power outage area to establish a safe distance table for power outage operations in the UHV station;
[0024] The third forming module is used to determine the energized state of power grid equipment based on the real-time data of the substation to form a energized equipment state table of the power equipment.
[0025] The effects provided in the content of the invention are only the effects of the embodiments, not all the effects of the invention. One of the above technical solutions has the following advantages or beneficial effects:
[0026] The present invention proposes a method and system for judging the safe distance of near-electrical operation of a substation project. The method includes disassembling the operation process of the UHV station base station to form a construction process sequence information table, selecting the voltage level of live equipment in the power outage area to establish a safe distance table for power outage operation of the UHV station, judging the live state of the power grid equipment based on the real-time data of the substation to form a live equipment state table of the power equipment; establishing a three-dimensional model of the substation, and importing the construction process sequence information table into the three-dimensional model of the substation; selecting the voltage level and live state of the live equipment, and judging the safe distance in the construction process according to the three-dimensional model in the construction process when the construction process is in progress. Based on a method for judging the safe distance of near-electrical operation of a substation project, a system for judging the safe distance of near-electrical operation of a substation project is also proposed. Based on the precise physical space position and size of the equipment and structures in the entire substation, the present invention focuses on the power outage decision-making work, starts from the three-dimensional design model, and establishes a construction process library, which provides a data basis for the simulation calculation and decision-making research of the whole process of near-electrical construction operations, realizes the intelligent decision-making of the power outage plan, and essentially improves the construction safety of the UHV station project. By implementing the process and judging the live status of the power equipment, the safety risks of working near electricity can be identified, thus ensuring the safety of personnel and equipment during live working. BRIEF DESCRIPTION OF THE DRAWINGS
[0027] like Figure 1 This is a flowchart of a substation engineering near-electricity operation process implementation in Example 1 of the present invention;
[0028] like Figure 2 This is a flow chart of a method for determining the safe distance for near-electricity operations in a substation project according to Embodiment 1 of the present invention;
[0029] like Figure 3 This is a schematic diagram of a system for determining the safe distance for near-electrical operations in a substation project according to Embodiment 2 of the present invention. DETAILED DESCRIPTION
[0030] In order to clearly illustrate the technical features of the present solution, the present invention is described in detail below through specific implementation methods and in conjunction with the accompanying drawings. The disclosure below provides many different embodiments or examples for realizing different structures of the present invention. In order to simplify the disclosure of the present invention, the components and settings of specific examples are described below. In addition, the present invention may repeat reference numbers and / or letters in different examples. This repetition is for the purpose of simplification and clarity, and does not itself indicate the relationship between the various embodiments and / or settings discussed. It should be noted that the components illustrated in the accompanying drawings are not necessarily drawn to scale. The present invention omits the description of known components and processing techniques and processes to avoid unnecessary limitations on the present invention.
[0031] Example 1
[0032] Embodiment 1 of the present invention proposes a method for judging the safe distance of near-electrical operations in a substation project, and first designs the near-electrical operation process. According to the precise physical spatial position and size of the equipment and structures in the entire substation, a construction operation process library is established based on the three-dimensional design model and centered around the power outage decision-making work. Specifically, it includes: disassembling the UHV station base station operation process to form a construction process sequence information table, selecting the voltage level of live equipment in the power outage area to establish a UHV station power outage operation safety distance table, judging the live status of power grid equipment based on real-time data from the substation to form a live equipment status table for power equipment; establishing a three-dimensional model of the substation, and importing the construction process sequence information table into the three-dimensional model of the substation; selecting the voltage level and live status of live equipment, and judging the safe distance during the construction process based on the three-dimensional model of the construction process when the construction process is in progress.
[0033] like Figure 1 This is a flowchart of a substation engineering near-electricity operation process implementation in Example 1 of the present invention;
[0034] In step S100, a typical construction process standardization process is established, and the UHV station infrastructure operation process such as crane hoisting and scaffolding disassembly and assembly is disassembled to form a construction process sequence information table. The following table 1 is a process information table template:
[0035]
[0036]
[0037] In step S110, based on the power outage operation rules and specifications, the voltage level of live equipment in the power outage area is selected to establish a safety distance table for power outage operations in the UHV station. The following table 1 is a safety distance table:
[0038] Voltage level (kV) Safety distance (m) Voltage level (kV) Safety distance (m) 10 and below (13.8) 0.70 750 7.20 20、35 1.00 1000 8.70 63(66)、110 1.50 ±50 and below 1.50 220 3.00 ±500 6.00 330 4.00 ±660 8.40 500 5.00 ±800 9.30
[0039] In step S120, the live state of the power equipment in the substation is judged by obtaining the topology file, monitoring signals and operation data in the substation through the dispatching background, and the live state of the power grid equipment can be judged based on the real-time data to form a live equipment state table of the power equipment, such as Figure 3 The table of the power equipment's energized status:
[0040] serial number Device Name Powered state 1. transformer run 2. breaker run 3. Capacitors Deactivate
[0041] In step S130, the power status of the electric equipment is determined.
[0042] like Figure 2 This is a flow chart of a method for determining the safe distance for near-electricity operations in a substation project according to Embodiment 1 of the present invention;
[0043] In step S200, three-dimensional laser scanning technology is used to obtain the precise physical spatial position and size of the equipment and structures in the entire substation to form a three-dimensional model of the substation.
[0044] In step S210, a construction type is selected.
[0045] In step S220, according to the substation operation area, the voltage level of the live equipment in the operation area indicated by the UHV station power outage operation safety distance table is selected.
[0046] In step S230, according to the substation operation area, the energized equipment status table of the electric equipment is selected to distinguish the energized status of the equipment in the substation operation area.
[0047] In step S240, the voltage level and live state of the energized equipment are selected, and the safe distance during the construction process is determined according to the three-dimensional model of the construction process during the construction process. Specifically, it includes: identifying the safety risks of near-electrical operations, and converting the distance between the equipment in the three-dimensional model into the actual safe distance during the construction process.
[0048] A method for judging the safe distance of near-electrical operations in a substation project proposed in Example 1 of the present invention is based on the precise physical spatial position and size of the equipment and structures in the entire substation, and focuses on power outage decision-making work. Starting from a three-dimensional design model, a construction operation process library is established to provide a data basis for simulation calculation and decision-making research of the entire process of near-electrical construction operations, realize intelligent decision-making of power outage plans, and essentially improve the safety of UHV station construction. Through process implementation and judgment of the live state of power equipment, the safety risk identification of near-electrical operations is realized, ensuring the safety of personnel and equipment during live-electrical operations.
[0049] Example 2
[0050] Based on the method for determining the safe distance for close-to-electrical operations in a substation project proposed in Example 1 of the present invention, Example 2 of the present invention further proposes a system for determining the safe distance for close-to-electrical operations in a substation project. Figure 3 This is a schematic diagram of a system for determining safe distances for near-electrical operations in a substation project according to Embodiment 2 of the present invention. The system includes a table forming module, an importing module, and a determining module;
[0051] The table formation module is used to disassemble the UHV station base station operation process to form a construction process sequence information table, select the voltage level of live equipment in the power outage area to establish a UHV station power outage operation safety distance table, and judge the live status of power grid equipment based on the real-time data of the substation to form a live equipment status table of power equipment;
[0052] The import module is used to establish a three-dimensional model of the substation and import the construction process sequence information table into the three-dimensional model of the substation;
[0053] The judgment module is used to select the voltage level and energized state of the energized equipment, and to judge the safe distance during the construction process based on the three-dimensional model of the imported process sequence information table.
[0054] The form forming module includes a first forming module, a second forming module and a third forming module;
[0055] The first forming module is used to dismantle the UHV station base station operation process to form a construction process sequence information table;
[0056] The second forming module is used to select the voltage level of live equipment in the power outage area to establish a safe distance table for power outage operations in the UHV station;
[0057] The third forming module is used to determine the energized state of power grid equipment based on the real-time data of the substation to form a energized equipment state table of the power equipment.
[0058] The process of the judgment module is as follows: according to the substation operation area, select the voltage level of the live equipment in the operation area indicated by the UHV station power outage operation safety distance table. According to the substation operation area, select the live equipment status table of power equipment to distinguish the live status of the equipment in the substation operation area. Identify the safety risks of near-electricity operations and convert the distance between equipment in the three-dimensional model into the safety distance in the actual construction process.
[0059] A system for determining the safe distance for near-electrical operations in a substation project proposed in Example 2 of the present invention modularizes the process of implementing a method for determining the safe distance for near-electrical operations in a substation project. The specific implementation process refers to the method proposed in Example 1.
[0060] The second embodiment of the present invention proposes a system for judging the safe distance of near-electrical operations in substation projects. Based on the precise physical spatial position and size of the equipment and structures in the entire substation, the system starts with a three-dimensional design model and establishes a construction operation process library around the power outage decision-making work, providing a data basis for the simulation calculation and decision-making research of the entire process of near-electrical construction operations, realizing intelligent decision-making of power outage plans, and essentially improving the safety of UHV station construction projects. Through the implementation of the process and the judgment of the live state of the power equipment, the safety risk identification of near-electrical operations is realized, ensuring the safety of personnel and equipment during live-electrical operations.
[0061] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply that there is any such actual relationship or order between these entities or operations. Moreover, the term "include", "comprise" or any other variant thereof is intended to cover non-exclusive inclusion, so that the process, method, article or equipment that includes a series of elements are inherent to the elements. In the absence of more restrictions, the elements limited by the sentence "comprise one..." do not exclude the presence of other identical elements in the process, method, article or equipment that includes the elements. In addition, the above-mentioned technical solution provided in the embodiment of the present application is consistent with the corresponding technical solution in the prior art in principle, and the part is not described in detail, so as not to repeat too much.
[0062] Although the above describes the specific implementation of the present invention in conjunction with the accompanying drawings, it is not intended to limit the scope of protection of the present invention. For those skilled in the art, other different forms of modifications or deformations can be made on the basis of the above description. It is not necessary and impossible to list all the implementation methods here. On the basis of the technical solution of the present invention, various modifications or deformations that can be made by those skilled in the art without creative work are still within the scope of protection of the present invention.
Claims
1. A method for determining the safe distance for near-electricity operations in a substation project, characterized in that: The following steps are involved: Dismantle the UHV station base station operation process to form a construction process sequence information table, select the voltage level of live equipment in the power outage area to establish a UHV station power outage operation safety distance table, and judge the live status of power grid equipment based on the real-time data of the substation to form a live equipment status table of power equipment; Establishing a three-dimensional model of a substation, and importing the construction process sequence information table into the three-dimensional model of the substation; The voltage level and live state of live equipment are selected, and the safe distance during the construction process is judged according to the three-dimensional model of the construction process during the construction process; the process of selecting the voltage level of live equipment is: according to the substation operation area, the voltage level of live equipment in the operation area indicated by the UHV station power outage operation safety distance table is selected; the process of selecting the voltage state of live equipment is: according to the substation operation area, the live equipment state table of electric equipment is selected to distinguish the live state of equipment in the substation operation area; the process of selecting the voltage level and live state of live equipment and judging the safe distance during the construction process according to the three-dimensional model of the construction process during the construction process is: identifying the safety risks of near-electricity operations, and converting the distance between equipment in the three-dimensional model into the actual safety distance during the construction process.
2. A method for determining the safe distance for near-electricity work in a substation project according to claim 1, characterized in that: The method for establishing the three-dimensional model of the substation is: obtaining the physical space positions of the equipment and buildings in the substation, the sizes of the equipment and the sizes of the buildings in the substation, and using three-dimensional laser scanning technology to establish the three-dimensional model of the substation.
3. A method for determining the safe distance for near-electricity work in a substation project according to claim 1, characterized in that: The construction process sequence information table includes process names and process sequence codes.
4. A method for determining the safe distance for near-electricity work in a substation project according to claim 1, characterized in that: The UHV station power outage operation safety distance table includes voltage levels and safety distances.
5. A method for determining the safe distance for near-electricity work in a substation project according to claim 1, characterized in that: The electric equipment live equipment status table includes equipment name and live status.
6. A system for determining the safe distance for close-to-electrical work in a substation project, used to execute a method for determining the safe distance for close-to-electrical work in a substation project as claimed in any one of claims 1 to 5, characterized in that: It includes a table forming module, an importing module and a judging module; The table formation module is used to disassemble the UHV station base station operation process to form a construction process sequence information table, select the voltage level of live equipment in the power outage area to establish a UHV station power outage operation safety distance table, and judge the live status of power grid equipment based on the real-time data of the substation to form a live equipment status table of power equipment; The import module is used to establish a three-dimensional model of the substation and import the construction process sequence information table into the three-dimensional model of the substation; The judgment module is used to select the voltage level and the energized state of the energized equipment, and judge the safe distance during the construction process according to the three-dimensional model of the imported process sequence information table.
7. A substation engineering near-electricity operation safety distance judgment system according to claim 6, characterized in that: The table forming module includes a first forming module, a second forming module and a third forming module; The first forming module is used to disassemble the UHV station base station operation process to form a construction process sequence information table; The second forming module is used to select the voltage level of live equipment in the power outage area to establish a safe distance table for power outage operations in the UHV station; The third forming module is used to determine the energized state of power grid equipment based on the real-time data of the substation to form a energized equipment state table of the power equipment.