A strengthening measure and construction method for eliminating the yin-yang slope effect of degenerate high-temperature permafrost roadbed
By arranging stone slope protection, EPS insulation boards and fiberglass gratings on the railway subgrade, and using heat pipes to cool down, the problems of permafrost degradation and shady slope effects caused by climate warming have been solved, and the stability and stability of the railway subgrade have been significantly improved. Cooling capability, suitable for long-term operation under climate warming scenarios.
Patent Information
- Application Number
- CN202210015367.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-01-07
- Publication Date
- 2024-10-01
- Estimated Expiration
- 2042-01-07
AI Technical Summary
The existing cooling enhancement measures cannot effectively solve the problems of differential settlement and cracking caused by the degradation of permafrost caused by climate warming and the shady and sunny slope effect of the roadbed, threatening the long-term stability of the railway project.
Composite strengthening measures are adopted, including setting up stone slope protection on the shady slope of the railway subgrade, laying EPS insulation boards and fiberglass grilles on the sunny slope, and inserting heat pipes in the center of the upper platform on the sunny slope, combining the cooling methods of block stone slope protection and inclined heat pipes. , make up for the shortcomings of traditional measures, significantly reduce temperature differences, and enhance roadbed stability.
It can significantly reduce the temperature of degenerative high-temperature permafrost, quickly strengthen the roadbed, reduce differential melt settlement damage, and enhance the long-term stable operation capability of the railway subgrade. It is suitable for degenerative high-temperature permafrost areas under climate warming scenarios.
Smart Images

Figure CN115247388B_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of frozen soil roadbed reinforcement, and in particular relates to a reinforcement measure for eliminating the positive and negative slope effect of a degenerate high-temperature permafrost roadbed and a construction method thereof. Background Art
[0002] Climate warming has become a hot issue of concern at home and abroad, especially in permafrost areas. Climate warming has caused the original permafrost to continue to warm up, causing the degradation of permafrost, and directly threatening the stability of existing projects in permafrost areas. In addition, due to the temperature difference between the positive and negative slopes of the roadbed (the positive slope is about 4°C higher than the negative slope), the non-uniform temperature distribution of the high-temperature permafrost in the lower part of the positive and negative slopes has caused differential settlement and roadbed cracking. This has had a very adverse impact on the smoothness and safe operation of the railway, and directly threatens the long-term safety and stability of railway projects.
[0003] The protection measures for permafrost mainly adopt engineering measures of active cooling of roadbed to protect the permafrost below it. Block stone structure roadbed is widely used for roadbed cooling measures. Although most permafrost sections that adopt block stone structure cooling measures have good stability under the background of climate warming, some high-temperature permafrost sections with weak protection measures have significant deformation under the condition of climate warming. At present, the active cooling measures of block stone structure have a certain effect on permafrost protection. However, the accumulation of wind and sand in the long-term operation process will form local blockages on the pores between the blocks, reduce convective heat exchange, and thus weaken the protection effect of degenerate high-temperature permafrost under the climate warming scenario. At the same time, it does not fully consider the difference in temperature field under the roadbed caused by the yin-yang slope effect of the roadbed, which leads to differential degradation of the lower frozen soil, uneven thawing and settlement of the roadbed, cracking and other problems. The composite roadbed cooling measures using block stone ventilation pipes have a good effect on permafrost protection, but they cannot effectively eliminate the differential settlement under the influence of the yin-yang slope effect of the roadbed. Therefore, the above traditional cooling and strengthening measures have limitations and cannot effectively deal with the degradation problem of degenerate high-temperature permafrost under the climate warming scenario, nor can they effectively solve a series of engineering problems such as differential thawing and settlement of roadbed and roadbed cracking caused by the existence of the yin-yang slope effect of high-temperature permafrost.
[0004] To solve the above problems, it is necessary to target the characteristics of degenerate high-temperature permafrost that is highly sensitive to thermal disturbances and has poor stability, consider the uneven ground temperature distribution on the yin and yang slopes of the roadbed, and adopt a composite strengthening measure and its construction method with a more significant cooling effect, so as to repair the engineering problems caused by climate warming and the yin and yang slope effects of the roadbed and ensure the long-term operation capacity of the Qinghai-Tibet Railway. Summary of the invention
[0005] The present invention aims to solve the problem that the thawing and settlement damage of railway subgrades in degenerate permafrost areas cannot be effectively controlled under the background of climate warming and engineering disturbance. According to the climate characteristics of the Qinghai-Tibet Plateau and the characteristics of the difference between the positive and negative slopes of the degenerate high-temperature permafrost subgrade, combined with the idea of active cooling of the subgrade, a reinforcement measure and a construction method for eliminating the positive and negative slope effect of the high-temperature permafrost subgrade are provided, so as to improve the defects of the existing subgrade cooling measures caused by the temperature difference between the positive and negative slopes during actual operation, and be more conducive to the long-term stable operation of the railway subgrade under the background of climate warming.
[0006] To achieve the above object, the technical solution adopted by the present invention is:
[0007] A strengthening measure for eliminating the yin-yang slope effect of a degenerative high-temperature permafrost roadbed and a construction method thereof, characterized in that: a yin slope of a railway roadbed 1 is provided with a yin slope block stone slope protection 2; the yang slope of the railway roadbed 1 is in a two-step shape, and an EPS insulation board 3 is laid on the upper platform and the slope surface of the yang slope of the railway roadbed 1, respectively, and a glass fiber grid 4 is laid on the XPS insulation board 3, and the glass fiber grid 4 is connected to the EPS insulation board 3 by U-shaped anchor nails 6; soil 7 is filled in the glass fiber grid 4; a heat pipe 5 is inserted at the center of the upper platform of the yang slope of the railway roadbed 1, and the heat pipe 5 passes through the EPS insulation board 3 and the glass fiber grid 4 in sequence and is obliquely inserted into the roadbed; a yang slope block stone layer 8 is laid on the lower step slope surface of the yang slope of the railway roadbed 1.
[0008] Preferably, the railway roadbed 1 is asymmetric, with a shady slope height of 3m and a slope ratio of 1:1.5; the upper step height of the sunny slope of the railway roadbed 1 is 3m, the lower step height is 1.5m, the upper step platform width is 3m, and the slope ratio of the two steps is 1:1.5.
[0009] Preferably, the shady slope block stone slope protection 2 is laid on the shady slope of the roadbed slope, and its top is kept flush with the slope top. The particle size of the block stone used is 25cm-35cm, and the block stone laying thickness is 1m.
[0010] Preferably, the sunny slope block stone layer 8 is laid on the slope of the lower step surface of the railway roadbed, and its top is kept flush with the upper step surface. The particle size of the block stone used is 25cm-35cm, and the block stone laying thickness is 1.5m.
[0011] Preferably, the EPS insulation board 3 is made of anti-oxidation material and has a thickness of 10 cm.
[0012] Preferably, the glass fiber grid 4 has a thickness of 10 cm, and the side length of each grid unit is 1 m.
[0013] Preferably, the surface of the U-shaped anchor nail 6 is galvanized; the two adjacent glass fiber grilles 4 are connected by the U-shaped anchor nail 6, and the U-shaped anchor nail 6 penetrates the EPS insulation board 3 and is inserted into the slope of the railway roadbed 1, and the insertion depth of the slope is not less than 30 cm.
[0014] Preferably, the heat pipe 5 is composed of an evaporation section 501 and a condensation section 502, the outer diameter of the heat pipe 5 is 6.4 cm, the length of the evaporation section 501 of the heat pipe 5 is between 8 m and 12 m, the length of the condensation section 502 is 3 m, an obtuse angle is formed between the evaporation section 501 and the condensation section 502 of the heat pipe, and the included angle is 110° to 130°, and the heat pipe 5 is filled with a low boiling point working medium (such as ammonia, freon, propane, carbon dioxide, etc.); the heat pipe 5 is arranged on a two-step step-shaped protective cover on the sunny slope of the roadbed At the center of the slope step surface, the heat pipe 5 passes through the glass fiber grid 4, penetrates the EPS insulation board 3, and is obliquely inserted into the railway roadbed 1 and the soil at the center of the roadbed, with an angle of 20° to 40° with the horizontal plane; the evaporation section 501 of the heat pipe 5 completely enters the roadbed, and the end enters the soil at the center of the roadbed. The condensation section 502 is vertically arranged at the center of the step surface on the sunny slope of the roadbed and exposed to the air. The condensation section 502 consists of a heat sink 503 and a tube shell 504. The heat pipe 5 is arranged at a spacing of 2 meters on the sunny slope.
[0015] Preferably, the soil 7 filled in the glass fiber grid 4 is the same as the soil of the original roadbed slope. The soil 7 fills the glass fiber grid 4, and after the soil 7 is filled, the slope remains the same as the slope surface.
[0016] A construction method for eliminating the yin-yang slope effect strengthening measures of degenerative high-temperature permafrost roadbed, the construction principle is "construction in cold season, rapid construction", and the steps are:
[0017] (1) Construction preparation: including surveying and setting out, site leveling, equipment delivery, slope loosening and cleaning, and stepping of the sunny and side slopes;
[0018] (2) Construction of the shady slope block stone slope protection 2: The blocks are laid along the shady slope of the roadbed with a thickness of 1m and a height of 3m. The top of the block stone slope protection is flush with the top of the slope. The slope of the shady slope block stone slope protection 2 is consistent with the slope of the roadbed slope.
[0019] (3) Construction of the positive slope block stone slope protection 8: The positive slope block stone layer 8 is laid on the side slope of the lower step surface of the positive slope of the roadbed, with a laying thickness of 1.5m. Its top is kept flush with the upper step surface. The slope of the positive slope block stone slope protection 8 is consistent with the slope of the roadbed side slope. After paving, light-colored paint is sprayed on the surface of the positive slope block stone slope protection 8;
[0020] (4) Construction of EPS insulation board 3: EPS insulation board 3 is laid on the sunny step surface and the upper slope surface of the roadbed slope. The construction should be smooth, the joints should be dense, and the sunny step surface and the upper slope surface should be covered;
[0021] (5) Construction of fiberglass grille 4: fiberglass grille 4 is laid on top of EPS insulation board 3. U-shaped anchor nails 6 are used to connect fiberglass grille 4. U-shaped anchor nails 6 are used to anchor fiberglass grille 4 and EPS insulation board on the sunny slope step surface and its upslope surface. The anchoring section of U-shaped anchor nail 6 should be anchored perpendicular to the paving surface. The depth of U-shaped anchor nail 6 into the soil should not be less than 30 cm.
[0022] (6) Construction of heat pipe 5: Drill holes in the roadbed from the center of the step surface on the sunny slope of the roadbed to the soil layer below the center of the roadbed. The evaporation section 501 of the heat pipe 5 is inserted along the drill hole. The end of the evaporation section 501 enters the soil below the center of the roadbed by no less than 2m. The condensation section 502 of the heat pipe 5 is arranged vertically at the center of the two-step step surface on the sunny slope of the roadbed. The distance between adjacent heat pipes is 2m.
[0023] (7) Construction of fiberglass grid backfill 7: After the construction of the sunny slope block stone slope protection 8, EPS insulation board 3, fiberglass grid 4, and roadbed heat pipe 5 is completed, backfill is carried out. The backfill 7 fills the fiberglass grid 4. The backfill soil has the same soil quality as the original roadbed slope. After the backfill is completed, the slope surface is kept flat, and the original vegetation of the slope is planted in the backfill area of the grid to restore the original ecology of the slope.
[0024] Compared with the shortcomings and deficiencies of the prior art, the strengthening measures and construction method for eliminating the yin-yang slope effect of the degenerate high-temperature permafrost roadbed described in the present invention have the following beneficial effects:
[0025] 1. The present invention can significantly reduce the temperature of degenerate high-temperature permafrost in a short period of time, freeze the degenerate high-temperature permafrost, quickly reinforce the roadbed, and raise the artificial upper limit in a short period of time with high efficiency and large amplitude, and the effect of eliminating the temperature difference between the positive and negative slopes of the roadbed is obvious. The reinforced high-temperature permafrost roadbed can eliminate the impact of strengthening measures on the thermal disturbance of the roadbed and the lower soil engineering in a relatively short period of time. For long-term operating railways, the ability to cope with climate warming is significantly enhanced, and the degradation rate of the high-temperature permafrost under the roadbed is significantly reduced. It is suitable for the long-term stable operation of railway roadbeds in degenerate high-temperature permafrost areas under climate warming scenarios.
[0026] 2. The composite strengthening measures of block stone slope protection, insulation board and inclined heat pipe are used to cool the roadbed, which makes up for the defect of insufficient capacity of traditional block stone slope protection strengthening measures to raise the artificial upper limit of the underlying frozen soil on the sunny slope, limits the degradation of permafrost in the lower part of the roadbed, greatly enhances the stability of the lower part of the railway roadbed in the permafrost area, and reduces the occurrence of differential thawing and settlement damage. The block stone slope protection, EPS insulation board and heat pipe on the sunny slope can give full play to their respective advantages, eliminate the influence of the yin and yang slope effect on the degraded permafrost roadbed, and have a significant reinforcement effect on the degraded high-temperature permafrost.
[0027] 3. The block stone slope protection set at the roadbed slope can significantly reduce the temperature of the roadbed and the lower soil through natural convection. The block stone layer is only laid on the lower step slope of the sunny slope, which reduces the disturbance of the self-weight load of the sunny slope of the roadbed to the degenerate high-temperature permafrost under the roadbed to a certain extent. At the same time, the light-colored material sprayed on the surface of the block stone on the sunny slope can reduce the impact of the temperature increase of the sunny slope soil of the roadbed caused by solar radiation.
[0028] 4. The EPS insulation board laid on the sunny slope of the roadbed can block the interference of external hot air on the roadbed in summer, reduce the conduction of heat from the outside to the sunny slope of the roadbed, limit the increase in temperature on the sunny slope, and protect the degenerate high-temperature frozen soil underneath the sunny slope.
[0029] 5. The heat pipes inserted obliquely into the roadbed at the step surface of the sunny slope freeze the soil in the roadbed and the lower area with higher temperature in the center of the roadbed. This not only makes up for the defect that the EPS insulation board laid on the sunny slope isolates the cold energy from flowing into the roadbed in winter, resulting in a reduction in cold storage capacity, but also solves the problem of reduced cooling effect of the block stone slope protection caused by sand accumulation blocking the gaps in the long-term operation of the block stone slope protection roadbed.
[0030] 6. The fiberglass grille protects the EPS insulation board under the synergistic effect of the U-shaped anchor and the internal fill. At the same time, the U-shaped anchor used is a galvanized anchor, which can reduce the corrosion of the anchor by the outside air and soil. The advantages of the fiberglass grille's resistance to high and low temperatures and weathering combined with the soil body play a good protective role for the EPS insulation board, solving the problem of the EPS insulation board being easily weathered when exposed to the air. In addition, the high tensile strength and no long-term creep characteristics of the fiberglass grille ensure the stability of the overall structure of the composite structure composed of the EPS insulation board, fiberglass grille, and U-shaped anchor in the extreme environment of the Qinghai-Tibet Plateau. BRIEF DESCRIPTION OF THE DRAWINGS
[0031] In order to more clearly understand the present invention, the present disclosure is further described by combining the drawings and exemplary embodiments of the specification. The drawings and embodiments are used for explanation and do not constitute a limitation on the disclosure.
[0032] Figure 1A vertical cross-sectional view of an embodiment of a strengthening measure for eliminating the yin-yang slope effect of a degenerate high-temperature permafrost roadbed according to the present invention;
[0033] Figure 2 For the present invention Figure 1 A partial enlarged view of the middle A;
[0034] Figure 3 This is a large-scale drawing of the glass fiber grid used in the present invention;
[0035] Figure 4 A schematic diagram of a U-shaped anchor nail used in the present invention;
[0036] Figure 5 This is a schematic diagram of the U-shaped galvanized anchor nails used in the present invention to fix the fiberglass grille;
[0037] Figure 6 This is the ground temperature distribution result map of the traditional block stone slope protection roadbed reinforcement measures under the climate warming scenario after 30 years of operation;
[0038] Figure 7 This is the geothermal distribution result diagram of the enhanced measures of the present invention after 30 years of operation under the climate warming scenario. DETAILED DESCRIPTION
[0039] The following will be combined with the accompanying drawings of the present invention to clearly and completely describe a strengthening measure for eliminating the yin-yang slope effect of the degenerate high-temperature permafrost roadbed and its construction method in the embodiment of the present invention. Obviously, the described embodiment is only a part of the embodiment of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0040] The purpose of the present invention is to provide a strengthening measure and a construction method for eliminating the yin-yang slope effect of the degenerative high-temperature permafrost roadbed, so as to eliminate the yin-yang slope effect of the roadbed in the degenerative high-temperature permafrost area and solve the thaw settlement damage problem caused by the differential degradation of the frozen soil at the bottom of the roadbed caused by the yin-yang slope effect under the background of climate warming.
[0041] In order to make the above-mentioned objects, features and advantages of the present invention more obvious and easy to understand, the present invention is further described in detail below with reference to the accompanying drawings and specific embodiments.
[0042] like Figure 1 , 2As shown in Figures 3, 4 and 5, the present invention provides a strengthening measure for eliminating the yin-yang slope effect of a degenerative high-temperature permafrost roadbed and a construction method thereof, which is characterized in that: the yin slope of the railway roadbed 1 is provided with a yin slope block stone slope protection 2; the yang slope of the railway roadbed 1 is in a two-step shape, and the upper platform and the slope surface of the yang slope of the railway roadbed 1 are respectively paved with EPS insulation boards 3, and the glass fiber grille 4 is fitted and connected to the EPS insulation board 3 by U-shaped anchor nails 6; the glass fiber grille 4 is filled with soil 7; the heat pipe 5 passes through the EPS insulation board 3 and the glass fiber grille 4 in sequence and is obliquely inserted into the roadbed; a yang slope block stone layer 8 is laid on the lower step slope surface of the yang slope of the railway roadbed 1.
[0043] like Figure 1 As shown, the railway roadbed 1 of the present invention is asymmetric, with a shady slope height of 3m and a slope ratio of 1:1.5; the upper step height of the yang slope of the railway roadbed 1 is 3m, the lower step height is 1.5m, the upper step platform width is 3m, and the slope ratio of the two steps is 1:1.5.
[0044] like Figure 1 As shown, the shady slope block stone slope protection 2 of the present invention is laid on the shady slope of the roadbed slope, and its top is kept flush with the slope top. The particle size of the block stone used is 25cm-35cm, and the block stone laying thickness is 1m.
[0045] like Figure 1 As shown, the sunny slope block stone layer 8 of the present invention is laid on the slope of the lower step surface of the railway roadbed, and its top is kept flush with the upper step surface. The particle size of the block stone used is 25cm-35cm, and the block stone laying thickness is 1.5m.
[0046] like Figure 1 As shown, the EPS insulation board 3 of the present invention is made of anti-oxidation material and has a thickness of 10 cm.
[0047] like Figure 1 , Figure 3 As shown, the glass fiber grid 4 of the present invention has a thickness of 10 cm, and the side length of each grid unit is 1 m.
[0048] like Figure 1 , Figure 4 , Figure 5 As shown, the surface of the U-shaped anchor nail 6 of the present invention is galvanized; the two adjacent glass fiber grilles 4 are connected by the U-shaped anchor nail 6, and the U-shaped anchor nail 6 penetrates the EPS insulation board 3 and is inserted into the slope of the railway roadbed 1, and the insertion depth of the slope is not less than 30 cm.
[0049] like Figure 1 , Figure 2As shown, the heat pipe 5 of the present invention is composed of an evaporation section 501 and a condensation section 502. The outer diameter of the heat pipe 5 is 6.4 cm. The length of the evaporation section 501 of the heat pipe 5 is between 8 m and 12 m. The length of the condensation section 502 is 3 m. An obtuse angle is formed between the evaporation section 501 and the condensation section 502 of the heat pipe, and the included angle is 110° to 130°. The heat pipe 5 is filled with a low boiling point working medium (ammonia, freon, propane, carbon dioxide, etc.); the heat pipe 5 is arranged on a two-step slope protection slope on the sunny slope of the roadbed At the center of the step surface, the heat pipe 5 passes through the fiberglass grille 4, penetrates the EPS insulation board 3, and is obliquely inserted into the railway roadbed 1 and the soil below the center of the roadbed, with an angle of 20° to 40° with the horizontal plane; the evaporation section 501 of the heat pipe completely enters the roadbed, and the end enters the soil below the center of the roadbed. The condensation section 502 is vertically arranged at the center of the step surface on the sunny slope of the roadbed and exposed to the air. The condensation section 502 consists of a heat sink 503 and a tube shell 504. The heat pipe 5 is arranged at a spacing of 2 meters on the sunny slope.
[0050] like Figure 1 As shown, the soil 7 filled in the glass fiber grid 4 of the present invention is the same as the soil of the original roadbed slope. The soil 7 fills the glass fiber grid 4, and after the soil 7 is filled, the slope is kept the same as the slope surface.
[0051] The present invention discloses a construction method for strengthening measures for eliminating the yin-yang slope effect of degenerative high-temperature permafrost roadbed. The construction principle is "construction in cold season and rapid construction", and the steps are as follows:
[0052] (1) Construction preparation: measurement and layout, site leveling, equipment entry, slope loosening and cleaning, and slope sloping of the sunny side into two steps;
[0053] (2) Construction of the shady slope block stone slope protection 2: The blocks are laid along the shady slope of the roadbed with a thickness of 1m and a height of 3m. The top of the block stone slope protection is flush with the top of the slope. The slope of the shady slope block stone slope protection 2 is consistent with the slope of the roadbed slope.
[0054] (3) Construction of the positive slope block stone slope protection 8: The positive slope block stone layer 8 is laid on the side slope of the lower step surface of the positive slope of the roadbed, with a laying thickness of 1.5m. Its top is kept flush with the upper step surface. The slope of the positive slope block stone slope protection 8 is consistent with the slope of the roadbed side slope. After paving, light-colored paint is sprayed on the surface of the positive slope block stone slope protection 8;
[0055] (4) Construction of EPS insulation board 3: EPS insulation board 3 is laid on the sunny step surface and the upper slope surface of the roadbed slope. The construction should be smooth, the joints should be dense, and the sunny step surface and the upper slope surface should be covered;
[0056] (5) Construction of fiberglass grille 4: fiberglass grille 4 is laid on top of EPS insulation board 3. U-shaped anchor nails 6 are used to connect fiberglass grille 4. U-shaped anchor nails 6 are used to anchor fiberglass grille 4 and EPS insulation board on the sunny slope step surface and its upslope surface. The anchoring section of U-shaped anchor nail 6 should be anchored perpendicular to the paving surface. The depth of U-shaped anchor nail 6 into the soil should not be less than 30 cm.
[0057] (6) Construction of heat pipe 5: Drill holes in the roadbed from the center of the step surface on the sunny slope of the roadbed to the soil layer below the center of the roadbed. The evaporation section 501 of the heat pipe 5 is inserted along the drill hole. The end of the evaporation section 501 enters the soil below the center of the roadbed by no less than 2m. The condensation section 502 of the heat pipe 5 is arranged vertically at the center of the two-step step surface on the sunny slope of the roadbed. The distance between adjacent heat pipes is 2m.
[0058] (7) Construction of fiberglass grid backfill 7: After the construction of the sunny slope block stone slope protection 8, EPS insulation board 3, fiberglass grid 4, and roadbed heat pipe 5 is completed, backfill is carried out. The backfill 7 fills the fiberglass grid 4. The backfill soil has the same soil quality as the original roadbed slope. After the backfill is completed, the slope surface is kept flat, and the original vegetation of the slope is planted in the backfill area of the grid to restore the original ecology of the slope.
[0059] In order to better verify the actual control effect of the present invention, combined with the present invention, considering the environmental conditions of the degenerate high-temperature permafrost zone under the background of climate warming, numerical simulation calculations were performed on the embodiments of the composite strengthening measures of the present invention and the traditional roadbed cooling measures (traditional block stone roadbed). The results are Figure 6 (traditional cooling measures) and Figure 7 (Composite strengthening measures of the present invention) are shown, and the results show that compared with the traditional composite roadbed forms in the past, the present invention can eliminate the temperature difference of the underlying degenerative frozen soil of the roadbed caused by the yin-yang slope effect of the roadbed, more effectively cool the roadbed, and more efficiently raise the artificial upper limit of permafrost. Considering the climate warming of 2.6℃ in the next 50 years, the present invention has the ability to eliminate the yin-yang slope effect of the roadbed and the cooling capacity is still significant, which can better cope with the adverse effects of climate warming on the long-term operation of the railway roadbed.
[0060] The working principle of the present invention is as follows: when the cold season comes, the heat pipe inserted obliquely at the sunny slope step starts to work, and the heat pipe exchanges heat through the convection of low-boiling-point working medium vapor and liquid in the closed vacuum cavity. Since the air temperature in the cold season is lower than the temperature of permafrost, the liquid working medium in the evaporation section absorbs the heat in the surrounding soil and evaporates to form a vapor working medium. Under the action of the pressure difference in the tube, the steam rises to the condensation section, contacts the colder condensation section pipe wall, releases the latent heat of vaporization, and then transfers the heat to the air through the heat sink of the condensation section. At the same time, the steam working medium condenses into liquid when it encounters cold, and under the action of gravity, the liquid flows back to the evaporation section along the pipe wall and evaporates again. This cycle repeats, transferring the heat in the soil to the air. At the same time, the internal convection heat exchange of the block stones laid on the sunny slope increases the cold storage capacity of the soil at the lower part of the sunny slope of the roadbed. When the cold season ends, the air temperature gradually rises, the heat pipe gradually stops working, and the roadbed exchanges heat through the internal convection of the block stone slope protection on both sides. At this time, the insulation board laid on the sunny slope isolates the air with gradually rising outside temperature from flowing to the sunny slope of the roadbed. The light-colored paint on the surface of the block stone on the sunny slope reduces the amount of solar radiation absorbed by the surface of the block stone slope protection. By reducing the temperature rise effect of hot air and solar radiation on the soil under the sunny slope, the cold storage capacity of the soil under the sunny slope in a cycle can completely offset the heat input from the outside at the end of the cold season. By enhancing the cold storage capacity of the sunny slope in the cold season and reducing the heat input from the sunny slope in the hot season, the temperature difference between the soil under the sunny slope and the shady slope gradually tends to a balanced state.
[0061] Finally, it should be noted that the above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art can still modify the technical solutions described in the aforementioned embodiments or replace some of the technical features therein by equivalents. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.
Claims
1. A reinforcement structure for eliminating the yin-yang slope effect of a degenerate high-temperature permafrost roadbed, comprising a railway roadbed (1), characterized in that: The shady slope of the railway embankment (1) is provided with a shady slope block stone slope protection (2); the shady slope of the railway embankment (1) is in the shape of two steps, and the upper platform and the slope surface of the shady slope of the railway embankment (1) are respectively paved with EPS insulation boards (3), and the EPS insulation boards (3) are paved with glass fiber grids (4), and the glass fiber grids (4) are connected to the EPS insulation boards (3) by U-shaped anchor nails (6); the glass fiber grids (4) are filled with soil (7); a heat pipe (5) is inserted at the center of the upper platform of the shady slope of the railway embankment (1), and the heat pipe (5) passes through the EPS insulation board (3) and the glass fiber grid (4) in sequence and is obliquely inserted into the embankment; a shady slope block stone layer (8) is laid on the lower step slope surface of the shady slope of the railway embankment (1); The railway embankment (1) is asymmetrical, with a shady slope height of 3m and a shady slope ratio of 1:1.5; the upper step height of the shady slope of the railway embankment (1) is 3m, the lower step height is 1.5m, the upper step platform width is 3m, and the slope ratio of the two steps is 1:1.5; The heat pipe (5) is composed of an evaporation section (501) and a condensation section (502); the outer diameter of the heat pipe (5) is 6.4 cm; the length of the evaporation section (501) of the heat pipe (5) is between 8 m and 12 m; the length of the condensation section (502) is 3 m; an obtuse angle is formed between the evaporation section (501) and the condensation section (502) of the heat pipe (5); the included angle is between 110° and 130°; the heat pipe (5) is filled with a low-boiling-point working fluid, which is ammonia, freon, propane and carbon dioxide; the heat pipe (5) is arranged on two steps on the sunny slope of the roadbed At the center of the step surface of the slope protection, the heat pipe (5) passes through the glass fiber grid (4), penetrates the EPS insulation board (3), and is obliquely inserted into the railway roadbed (1) and the soil at the center of the roadbed, with an angle of 20° to 40° with the horizontal plane; the evaporation section (501) of the heat pipe (5) completely enters the roadbed, and the end enters the soil at the center of the roadbed; the condensation section (502) is vertically arranged at the center of the step surface of the sunny slope of the roadbed and exposed to the air; the condensation section (502) is composed of a heat sink (503) and a tube shell (504); the heat pipes (5) are arranged at a spacing of 2 meters on the sunny slope; The above-mentioned construction method for eliminating the yin-yang slope effect and strengthening the structure of the degenerate high-temperature permafrost roadbed comprises the following steps: 1) Construction preparation: including surveying and setting out, site leveling, equipment entry, slope loosening and cleaning, and stepping of the sunny and side slopes; 2) Construction of Shade Slope Block Stone Retaining Wall (2): The blocks are laid along the shade slope of the roadbed side slope with a thickness of 1m and a height of 3m. The top of the blocks is flush with the top of the slope. The slope of the shade slope block stone retaining wall (2) is consistent with the slope of the roadbed side slope. 3) Construction of the positive slope block stone slope protection: The positive slope block stone layer (8) is laid on the side slope of the lower step surface of the positive slope of the roadbed, with a laying thickness of 1.5m. Its top is kept flush with the upper step surface. The slope of the positive slope block stone slope protection is consistent with the slope of the roadbed side slope. After laying, light-colored paint is sprayed on the surface of the positive slope block stone slope protection; 4) EPS insulation board (3) construction: EPS insulation board (3) is laid on the sunny step surface and the upper slope surface of the roadbed slope. The construction should be smooth, the joints should be dense, and the whole sunny step surface and the upper slope surface should be covered; 5) Construction of glass fiber grille (4): The glass fiber grille (4) is laid on the EPS insulation board (3). The glass fiber grilles (4) are connected together with U-shaped anchor nails (6). The glass fiber grille (4) and the EPS insulation board are anchored on the sunny slope step surface and the upslope surface of the roadbed with U-shaped anchor nails (6). The anchoring section of the U-shaped anchor nail (6) should be anchored perpendicular to the paving surface. The depth of the U-shaped anchor nail (6) into the soil should not be less than 30 cm. 6) Construction of heat pipe (5): Drill holes in the roadbed, diagonally drill from the center of the step surface of the sunny slope of the roadbed to the soil layer below the center of the roadbed, insert the evaporation section (501) of the heat pipe (5) along the drill hole, and the end of the evaporation section (501) enters the soil below the center of the roadbed by no less than 2m. The condensation section (502) of the heat pipe (5) is vertically arranged at the center of the two-step step surface of the sunny slope of the roadbed, and the distance between adjacent heat pipes is 2m; 7) Construction of glass fiber grid filling soil (7): After the construction of the sunny slope block stone slope protection, EPS insulation board (3), glass fiber grid (4), and roadbed heat pipe (5) is completed, the filling soil (7) is filled with glass fiber grid (4). The filling soil has the same soil quality as the original roadbed slope. After the filling is completed, the slope surface is kept flat, and the original vegetation of the slope is planted in the filling area of the grid to restore the original ecology of the slope.
2. A strengthening structure for eliminating the yin-yang slope effect of degenerative high-temperature permafrost roadbed according to claim 1, characterized in that: The shady slope block stone slope protection (2) is laid on the shady slope of the roadbed side slope, with its top kept flush with the top of the slope. The particle size of the block stone used is 25 cm to 35 cm, and the thickness of the block stone laying is 1 m.
3. The strengthening structure for eliminating the yin-yang slope effect of degenerative high-temperature permafrost roadbed according to claim 1 is characterized in that: The sunny slope block stone layer (8) is laid on the side slope of the lower step surface of the railway roadbed, and its top is kept flush with the upper step surface. The particle size of the block stone used is 25cm to 35cm, and the block stone laying thickness is 1.5m.
4. The strengthening structure for eliminating the yin-yang slope effect of degenerative high-temperature permafrost roadbed according to claim 1, characterized in that: The EPS insulation board (3) is made of an anti-oxidation material and has a thickness of 10 cm.
5. The strengthening structure for eliminating the yin-yang slope effect of degenerative high-temperature permafrost roadbed according to claim 1 is characterized in that: The glass fiber grid (4) has a thickness of 10 cm, and the side length of each grid unit is 1 m.
6. The strengthening structure for eliminating the yin-yang slope effect of degenerative high-temperature permafrost roadbed according to claim 1, characterized in that: The surface of the U-shaped anchor nail (6) is galvanized; two adjacent glass fiber grilles (4) are connected by the U-shaped anchor nail (6); the U-shaped anchor nail (6) penetrates the EPS insulation board (3) and is inserted into the slope of the railway roadbed (1); the insertion depth of the U-shaped anchor nail (6) is not less than 30 cm.
7. The strengthening structure for eliminating the yin-yang slope effect of degenerative high-temperature permafrost roadbed according to claim 1, characterized in that: The soil (7) filled in the glass fiber grid (4) is of the same quality as the soil of the original roadbed slope. The soil (7) fills the glass fiber grid (4). After the soil (7) is filled, the slope is the same as that of the slope surface.