A fireproof and waterproof sealing construction method for structural beam and slab casing

By using a combination of bolt positioning device, fireproof board and water-absorbing rubber plate in the structural beam and plate casing, the problem of leaking and repairing of casing gaps is solved, and efficient fire-proof and water-proof sealing is achieved and repair costs are reduced.

CN115962351BActive Publication Date: 2024-12-03SHAANXI CONSTR ENG HUAXIN DINGYE ENG EQUIP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202111571940.2
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2021-12-21
Publication Date
2024-12-03
Estimated Expiration
2041-12-21

AI Technical Summary

Technical Problem

In the concrete construction of structural beam slabs, the gap between the pipe sleeves causes leakage. The existing waterproof and fire-proof sealing devices are difficult to construct and repair, and are costly.

Method used

The four bolts are positioned and fixed by using a bolt positioning device, and installed with a fireproof board and a water-absorbing rubber board to form a fire-proof and water-proof sealing component, simplifying the installation and disassembly process, and reducing the difficulty and cost of repair.

Benefits of technology

Improve the installation efficiency and sealing quality of fire-proof and waterproof sealing components, prevent leakage, reduce fire risk, and reduce repair difficulty and cost.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN115962351B_ABST
    Figure CN115962351B_ABST
Patent Text Reader

Abstract

The present invention discloses a fireproof and waterproof sealing construction method for a structural beam and slab casing, comprising the following steps: 1. Waterproof sealing inside the pipe casing; 2. Installing a bolt positioning device at one end of the pipe casing; 3. Pre-installing an end fireproof and waterproof sealing component at one end of the pipe casing; 4. Pushing the pre-installed end fireproof and waterproof sealing component into the pipe casing; 5. Fireproof water sealing at one end of the pipe casing. The construction method of the present invention is simple, and the four bolts are positioned and fixed by the bolt positioning device, which can effectively improve the installation efficiency of the end fireproof and waterproof sealing component. By combining the fireproof board and the water-absorbing rubber board together and installing them between the pipe and the pipe casing for fireproof and waterproof sealing, leakage between the pipe and the pipe casing can be effectively prevented, and the occurrence of fire can be effectively reduced. It is easy to install and disassemble, and can effectively reduce the repair difficulty and repair cost of the end fireproof and waterproof sealing component.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of casing sealing construction, and in particular relates to a fireproof and waterproof sealing construction method for a structural beam and slab casing. Background Art

[0002] In the concrete construction of the structural beam slab, it is necessary to pre-embed the pipe sleeve in the structural beam slab for the pipe to pass through. Because there is a gap at the pipe sleeve, it is easy to leak and affect the fire prevention of the entire structural beam slab. Therefore, when installing the pipeline, it is necessary to simultaneously perform waterproof and fireproof sealing between the pipeline and the pipe sleeve. However, the existing waterproof and fireproof sealing device is generally difficult to construct, and when the waterproof and fireproof sealing device is damaged, it is difficult to repair and the repair cost is high. Summary of the invention

[0003] The technical problem to be solved by the present invention is to provide a fireproof and waterproof sealing construction method for structural beam and slab casings in view of the deficiencies in the above-mentioned prior art. The construction method is simple, and four bolts are positioned and fixed by a bolt positioning device, which can effectively improve the installation efficiency of the end fireproof and waterproof sealing components. By combining the fireproof board and the water-absorbing rubber board together and installing them between the pipe and the pipe casing for fireproof and waterproof sealing, leakage between the pipe and the pipe casing can be effectively prevented, and the occurrence of fire can be effectively reduced. It is easy to install and disassemble, and can effectively reduce the repair difficulty and repair cost of the end fireproof and waterproof sealing components.

[0004] In order to solve the above technical problems, the technical solution adopted by the present invention is: a fireproof and waterproof sealing construction method for a structural beam and slab casing, characterized in that the method comprises the following steps:

[0005] Step 1: Waterproof and seal the inside of the pipe casing: fill the gap between the pipe casing and the pipe with a flexible waterproof material from one end of the pipe casing to form a waterproof layer; wherein a gap is provided between the waterproof layer and one end of the pipe casing;

[0006] Step 2, installing a bolt positioning device at one end of the pipe casing: installing a bolt positioning device on the pipe extending out of the pipe casing, and installing four bolts on the bolt positioning device, the four bolts are all located at one end of the pipe casing; wherein the bolt positioning device comprises a clamp sleeved on the outside of the pipe and four bolt positioning members arranged on one side of the clamp, the four bolt positioning members are all located on one side of the clamp close to the pipe casing, and the four bolt positioning members are all arranged on the same circumference; the axis of the bolt is parallel to the axis of the pipe, and the head of the bolt is arranged away from the pipe casing;

[0007] Step 3: Pre-install the end fireproof and waterproof sealing assembly at one end of the pipe casing. The specific process is as follows:

[0008] Step 301, welding four nuts on the side of the inner fireproof plate close to the pipe sleeve;

[0009] Step 302: An outer fireproof plate, two first water-absorbing rubber plates, a middle fireproof plate, two second water-absorbing rubber plates and an inner fireproof plate are sequentially inserted on the screw rod of the bolt extending out of the bolt positioning member; wherein the four bolts are respectively connected with four nuts after passing through the inner fireproof plate;

[0010] Step 4: Push the pre-installed end fireproof and waterproof sealing assembly into the pipe casing;

[0011] Step 5. Fireproof water sealing at one end of the pipe casing: remove the bolt positioning device, tighten all four bolts, so that the first water-absorbing rubber plate and the second water-absorbing rubber plate seal one end of the pipe casing under the extrusion of the inner fireproof plate, the middle fireproof plate and the outer fireproof plate.

[0012] The above-mentioned structural beam and slab casing fireproof and waterproof sealing construction method is characterized in that the outer diameters of the first water-absorbing rubber sheet and the second water-absorbing rubber sheet are both smaller than the inner diameter of the pipeline casing, and the inner diameters of the first water-absorbing rubber sheet and the second water-absorbing rubber sheet are both equal to the outer diameter of the pipeline.

[0013] The above-mentioned structural beam and slab casing fireproof and waterproof sealing construction method is characterized in that: the outer diameters of the inner fireproof board and the middle fireproof board are equal and are both smaller than the outer diameter of the first water-absorbing rubber board, the outer diameter of the outer fireproof board is equal to the inner diameter of the pipe casing, and the inner diameters of the inner fireproof board, the middle fireproof board and the outer fireproof board are equal and are not less than the outer diameter of the pipe.

[0014] The above-mentioned structural beam and slab casing fireproof and waterproof sealing construction method is characterized in that: the inner fireproof plate, the middle fireproof plate, the outer fireproof plate, the first water-absorbing rubber plate and the second water-absorbing rubber plate are all provided with four bolt through holes at equal intervals along their circumferences, the bolt through holes are circular holes and their hole diameters are not less than the thread diameter of the bolts, and the four nuts are respectively coaxially arranged with the four bolt through holes.

[0015] The above-mentioned structural beam and slab casing fireproof and waterproof sealing construction method is characterized in that: the inner fireproof plate, the middle fireproof plate and the outer fireproof plate are all annular fireproof plates spliced ​​together by two semicircular ring plates and having a splicing seam, the first water-absorbing rubber plate and the second water-absorbing rubber plate are both water-absorbing rubber plates spliced ​​together by two semicircular ring plates and having a splicing seam, the inner fireproof plate, the middle fireproof plate, the outer fireproof plate, the first water-absorbing rubber plate and the second water-absorbing rubber plate are coaxially arranged; the two adjacent semicircular ring plates are arranged at 90°.

[0016] The above-mentioned structural beam and slab casing fireproof and waterproof sealing construction method is characterized in that the inner fireproof plate, the middle fireproof plate and the outer fireproof plate are all galvanized steel plates, and the bolts are galvanized hexagonal bolts or chrome-plated hexagonal bolts.

[0017] The above-mentioned fireproof and waterproof sealing construction method for a structural beam and slab casing is characterized in that: the bolt positioning piece is cylindrical and one end of which is fixed on the clamp, the other end of the bolt positioning piece is provided with a hexagonal countersunk hole for the head of the bolt to be installed, and the other end of the bolt positioning piece is provided with a clamping piece for clamping the bolt;

[0018] The axis of the bolt positioning member is parallel to the axis of the pipeline.

[0019] The above-mentioned structural beam and slab casing fireproof and waterproof sealing construction method is characterized in that: the clamp is coaxially arranged with the pipeline, and the clamp includes two interlocking arc-shaped clamp parts, and two bolt positioning parts are arranged on one side of each of the arc-shaped clamp parts.

[0020] The above-mentioned structural beam and slab casing fireproof and waterproof sealing construction method is characterized in that: the inner ring of the arc-shaped clamp is provided with two hydraulic push rods for tightening the pipeline, the hydraulic push rods are arranged along the radial direction of the arc-shaped clamp, one end of the hydraulic push rod is fixed to the inner ring of the arc-shaped clamp, and the other end of the hydraulic push rod is provided with an arc-shaped top plate.

[0021] The above-mentioned structural beam and slab casing fireproof and waterproof sealing construction method is characterized in that: in step four, when the pre-installed end fireproof and waterproof sealing assembly is pushed into the pipe casing, the hydraulic push rod is first contracted to separate the arc-shaped top plate from the outer wall of the pipe, and then the clamp is manually pushed to push the end fireproof and waterproof sealing assembly into the pipe casing, and the inner side of the outer fireproof plate is flush with the end face of one end of the pipe casing.

[0022] Compared with the prior art, the present invention has the following advantages:

[0023] 1. The present invention can effectively position and fix four bolts by installing a bolt positioning device on the pipeline, thereby facilitating the subsequent installation of waterproof panels and fireproof panels, and can effectively improve the installation efficiency and installation effect of the end fireproof and waterproof sealing components, thereby ensuring the sealing quality of the end fireproof and waterproof sealing components.

[0024] 2. The present invention can effectively provide waterproof and fireproof seals between the pipeline and the pipeline casing by arranging two water-absorbing rubber plates between the inner fireproof plate and the middle fireproof plate, and between the middle fireproof plate and the outer fireproof plate, thereby preventing leakage between the pipeline and the pipeline casing and effectively reducing the occurrence of fire.

[0025] 3. The present invention makes the inner fireproof board, the middle fireproof board, the outer fireproof board and the water-absorbing rubber board all spliced ​​by two semicircular ring plates, and fastens the inner fireproof board, the middle fireproof board, the outer fireproof board and the water-absorbing rubber board together by multiple bolts, which is easy to install and disassemble, and can effectively reduce the repair difficulty and repair cost of the end fireproof and waterproof sealing components.

[0026] 4. The present invention can effectively ensure the installation stability and integrity of the end fireproof and waterproof sealing components by making the joints between any two adjacent plates among the inner fireproof plate, the middle fireproof plate, the outer fireproof plate and the water-absorbing rubber plate perpendicular to each other, thereby effectively improving the sealing effect between the pipeline and the pipeline casing.

[0027] To sum up, the construction method of the present invention is simple. The four bolts are positioned and fixed by a bolt positioning device, which can effectively improve the installation efficiency of the end fireproof and waterproof sealing assembly. The fireproof board and the water-absorbing rubber board are combined together and installed between the pipe and the pipe sleeve for fireproof and waterproof sealing. It can effectively prevent leakage between the pipe and the pipe sleeve, and can effectively reduce the occurrence of fire. It is easy to install and disassemble, and can effectively reduce the repair difficulty and repair cost of the end fireproof and waterproof sealing assembly.

[0028] The technical solution of the present invention is further described in detail below through the accompanying drawings and embodiments. BRIEF DESCRIPTION OF THE DRAWINGS

[0029] Figure 1 It is a flowchart of the present invention.

[0030] Figure 2 It is a schematic diagram of the structure when the end fireproof and waterproof sealing component of the present invention is pushed into the pipe casing.

[0031] Figure 3 This is a schematic diagram of the structure of the bolt positioning device of the present invention without the clamping member.

[0032] Figure 4 It is a schematic diagram of the structure after the end fireproof and waterproof sealing assembly of the present invention is installed in place.

[0033] Figure 5 It is a schematic structural diagram of the end fireproof and waterproof sealing assembly of the present invention.

[0034] Figure 6 for Figure 5 Left view of .

[0035] Description of reference numerals:

[0036] 1—Pipeline; 2—Pipeline casing; 3—Inner fireproof board;

[0037] 4—middle fireproof board; 5—outer fireproof board; 6-1—first water-absorbing rubber board;

[0038] 6-2—second water-absorbing rubber sheet; 7—bolt; 8—nut;

[0039] 9—waterproof layer; 10—clamp; 10-1—arc-shaped clamp;

[0040] 11—bolt positioning piece; 12—clamping piece; 13—hydraulic ejector rod;

[0041] 14—Curved top plate. DETAILED DESCRIPTION

[0042] like Figures 1 to 6 The fireproof and waterproof sealing construction method of the structural beam and slab casing comprises the following steps:

[0043] Step 1: Waterproof and seal the inside of the pipe casing: fill the gap between the pipe casing 2 and the pipe 1 with a flexible waterproof material from one end of the pipe casing 2 to form a waterproof layer 9; wherein a gap is provided between the waterproof layer 9 and one end of the pipe casing 2;

[0044] In actual use, one side of the pipeline sleeve 2 is connected to the outer facade of the structural beam and slab, and is directly sealed by concrete or structural soil layer.

[0045] It should be noted that the flexible waterproof material is waterproof hemp. When filling the flexible waterproof material, it is necessary to ensure a gap of at least the length of a bolt 7 between the filled waterproof layer 9 and one end of the pipe sleeve 2 for the installation of the end fireproof and waterproof sealing component.

[0046] Step 2, installing a bolt positioning device at one end of the pipe casing: installing a bolt positioning device on the pipe 1 extending out of the pipe casing 2, and installing four bolts 7 on the bolt positioning device, the four bolts 7 are all located at one end of the pipe casing 2; wherein the bolt positioning device comprises a clamp 10 sleeved on the outside of the pipe 1 and four bolt positioning members 11 arranged on one side of the clamp 10, the four bolt positioning members 11 are all located on one side of the clamp 10 close to the pipe casing 2, and the four bolt positioning members 11 are evenly distributed on the same circumference; the axis of the bolt 7 is parallel to the axis of the pipe 1, and the head of the bolt 7 is arranged away from the pipe casing 2;

[0047] In a specific implementation, the four bolt positioning members 11 are arranged at equal intervals on the same circumference, and the radius of the circle where the four bolt positioning members 11 are located is greater than the outer diameter of the pipeline 1 and smaller than the inner diameter of the pipeline casing 2; the circle where the four bolt positioning members 11 are located is coaxially arranged with the pipeline 1, and the pipeline 1 and the pipeline casing 2 are coaxially arranged;

[0048] In actual use, by installing the bolt positioning device on the pipe 1, the four bolts 7 can be effectively positioned and fixed, thereby facilitating the subsequent installation of waterproof panels and fireproof panels, and effectively improving the installation efficiency and installation effect of the end fireproof and waterproof sealing components, thereby ensuring the sealing quality of the end fireproof and waterproof sealing components.

[0049] It should be noted that the distance between the axis of the bolt 7 and the outer wall of the pipe 1 is equal to the distance between the axis of the bolt 7 and the inner wall of the pipe sleeve 2, which can ensure the stability and reliability of the overall structure of the end fireproof and waterproof sealing assembly.

[0050] During specific implementation, when the bolt positioning device is installed on the pipeline 1, the clamp 10 is sleeved on the outside of the pipeline 1, and the hydraulic push rod 13 is extended to make the arc-shaped top plate 14 press tightly against the outer wall of the pipeline 1, so that the bolt positioning device is fixed to the pipeline 1, and at the same time, the head of the bolt 7 is clamped in the hexagonal countersunk hole of the bolt positioning member 11, and the screw rod of the bolt 7 is clamped by the clamping member 12 to achieve the positioning and fixing of the bolt 7.

[0051] Step 3: Pre-install the end fireproof and waterproof sealing assembly at one end of the pipe casing. The specific process is as follows:

[0052] Step 301, welding four nuts 8 on the side of the inner fireproof plate 3 close to the pipe sleeve;

[0053] Step 302: An outer fireproof board 5, two first water-absorbing rubber boards 6-1, a middle fireproof board 4, two second water-absorbing rubber boards 6-2 and an inner fireproof board 3 are sequentially inserted on the screw rod of the bolt 7 extending out of the bolt positioning member 11; wherein the four bolts 7 are respectively connected with four nuts 8 after passing through the inner fireproof board 3;

[0054] In actual use, when installing the outer fireproof plate 5, a semicircular ring plate is installed from the screw end of the bolt 7 to the first bolt and the second bolt, and a semicircular ring plate is installed from the screw end of the bolt 7 to the third bolt and the fourth bolt to form a circular outer fireproof plate 5, and the outer fireproof plate 5 is sleeved on the outside of the pipeline 1, and the outer fireproof plate 5 and the pipeline 1 are coaxially arranged;

[0055] One of the bolts 7 is recorded as the first bolt, and then the other three bolts 7 are recorded as the second bolt, the third bolt and the fourth bolt in a clockwise direction from the first bolt.

[0056] When installing the first water-absorbing rubber sheet 6-1 that is tightly attached to the outer fireproof plate 5, a semicircular ring plate is installed from the screw end of the bolt 7 to the second bolt and the third bolt, and at the same time, a semicircular ring plate is installed from the screw end of the bolt 7 to the first bolt and the fourth bolt to form a circular first water-absorbing rubber sheet 6-1. The first water-absorbing rubber sheet 6-1 is coaxially arranged with the pipeline 1, and the outer fireproof plate 5 is located between the head of the bolt 7 and the first water-absorbing rubber sheet 6-1, so that the splicing seam of the outer fireproof plate 5 and the splicing seam of the adjacent first water-absorbing rubber sheet 6-1 are perpendicular to each other.

[0057] In specific implementation, by setting two first water-absorbing rubber plates 6-1 between the inner fireproof plate 3 and the middle fireproof plate 4, and setting two second water-absorbing rubber plates 6-2 between the middle fireproof plate 4 and the outer fireproof plate 5, the pipeline 1 and the pipeline sleeve 2 can be effectively waterproofed and fireproofed to prevent leakage between the pipeline 1 and the pipeline sleeve 2, and the occurrence of fire can be effectively reduced.

[0058] It should be noted that the inner fireproof board 3, the middle fireproof board 4, the outer fireproof board 5 and the water-absorbing rubber board 6 are all spliced ​​together by two semicircular ring plates, and the inner fireproof board 3, the middle fireproof board 4, the outer fireproof board 5, the first water-absorbing rubber board 6-1 and the second water-absorbing rubber board 6-2 are fastened together by multiple bolts 7, which is convenient for installation and disassembly, and can effectively reduce the repair difficulty and repair cost of the end fireproof and waterproof sealing components.

[0059] In specific implementation, by making the joint seams between any two adjacent plates among the inner fireproof board 3, the middle fireproof board 4, the outer fireproof board 5, the first water-absorbing rubber board 6-1 and the second water-absorbing rubber board 6-2 perpendicular to each other, the installation stability and integrity of the end fireproof and waterproof sealing assembly can be effectively guaranteed, thereby effectively improving the sealing effect between the pipeline 1 and the pipeline sleeve 2.

[0060] In this embodiment, during actual use, one semicircular ring plate in the middle fireproof plate 4 is installed on the first bolt and the second bolt, and the other semicircular ring plate in the middle fireproof plate 4 is installed on the third bolt and the fourth bolt.

[0061] Step 4: Figure 2 As shown, push the pre-installed end fireproof and waterproof sealing assembly into the pipe sleeve;

[0062] Step 5: Fireproof water seal at one end of the pipe casing: Figure 4 As shown, the bolt positioning device is removed and the four bolts 7 are tightened so that the first water-absorbing rubber sheet 6-1 and the second water-absorbing rubber sheet 6-2 are sealed to one end of the pipe sleeve 2 under the extrusion of the inner fireproof board 3, the middle fireproof board 4 and the outer fireproof board 5.

[0063] In actual use, when removing the bolt positioning device, first loosen the four clamping parts 12, and move the bolt positioning device along the pipeline 1 toward the end away from the end fireproof and waterproof sealing assembly until the bolt positioning part 11 is separated from the bolt 7, and then remove the clamp 10 from the pipeline 1.

[0064] It should be noted that when tightening the four bolts 7 , the four bolts 7 may be tightened simultaneously, or the four bolts 7 may be tightened little by little in a cycle for multiple times.

[0065] In this embodiment, the outer diameters of the first water-absorbing rubber sheet 6-1 and the second water-absorbing rubber sheet 6-2 are both smaller than the inner diameter of the pipeline sleeve 2, and the inner diameters of the first water-absorbing rubber sheet 6-1 and the second water-absorbing rubber sheet 6-2 are both equal to the outer diameter of the pipeline 1.

[0066] In actual use, the outer diameters of the first water-absorbing rubber sheet 6-1 and the second water-absorbing rubber sheet 6-2 are 1 mm smaller than the inner diameter of the pipeline sleeve 2, which facilitates the installation and removal of the first water-absorbing rubber sheet 6-1 and the second water-absorbing rubber sheet 6-2.

[0067] In this embodiment, the outer diameters of the inner fireproof board 3 and the middle fireproof board 4 are equal and are both smaller than the outer diameter of the first water-absorbing rubber board 6-1, the outer diameter of the outer fireproof board 5 is equal to the inner diameter of the pipe sleeve 2, and the inner diameters of the inner fireproof board 3, the middle fireproof board 4 and the outer fireproof board 5 are equal and are both larger than the outer diameter of the pipe 1.

[0068] In actual use, since the inner fireproof board 3 and the middle fireproof board 4 are rigid boards, the outer diameters of the inner fireproof board 3 and the middle fireproof board 4 are 1 mm smaller than the outer diameter of the first water-absorbing rubber board 6-1, which facilitates the installation and disassembly of the inner fireproof board 3 and the middle fireproof board 4, and at the same time can provide a certain expansion space for the outer edge of the first water-absorbing rubber board 6-1, thereby effectively improving the sealing effect.

[0069] like Figure 5 and Figure 6 As shown, in this embodiment, the inner fireproof plate 3, the middle fireproof plate 4, the outer fireproof plate 5, the first water-absorbing rubber plate 6-1 and the second water-absorbing rubber plate 6-2 are all provided with four bolt through holes at equal intervals along their circumferences, the bolt through holes are circular holes and their hole diameters are larger than the thread diameter of the bolt 7, and the four nuts 8 are respectively coaxially arranged with the four bolt through holes.

[0070] In actual use, two bolt through holes are provided on the semicircular ring plate and the semicircular ring plate, and the two bolt through holes are symmetrically arranged, and the hole diameter of the bolt through hole is 1 mm larger than the thread diameter of the bolt 7.

[0071] In actual use, by fixing the nut 8 to the inner fireproof plate 3, it is convenient to tighten the bolt 7 from the outside.

[0072] In specific implementation, the end of the bolt 7 close to the hexagonal head is a smooth rod, and the end of the bolt 7 away from the hexagonal head is provided with an external thread. When the outer fireproof board 5, the two first water-absorbing rubber boards 6-1, the middle fireproof board 4, the two second water-absorbing rubber boards 6-2 and the inner fireproof board 3 are installed tightly on the bolt 7 in sequence, the section of the bolt 7 with the external thread is covered by 5mm.

[0073] In this embodiment, the inner fireproof plate 3, the middle fireproof plate 4 and the outer fireproof plate 5 are all annular fireproof plates spliced ​​together by two semicircular ring plates and having a splicing seam, the first water-absorbing rubber plate 6-1 and the second water-absorbing rubber plate 6-2 are both water-absorbing rubber plates spliced ​​together by two semicircular ring plates and having a splicing seam, the inner fireproof plate 3, the middle fireproof plate 4, the outer fireproof plate 5, the first water-absorbing rubber plate 6-1 and the second water-absorbing rubber plate 6-2 are coaxially arranged; the two adjacent semicircular ring plates are arranged at 90°.

[0074] In actual use, the splicing seams of the inner fireproof board 3, the splicing seams of the outer fireproof board 5, the splicing seams of the first water-absorbing rubber board 6-1 adjacent to the middle fireproof board 4, and the splicing seams of the second water-absorbing rubber board 6-2 adjacent to the middle fireproof board 4 are parallel to each other, the splicing seams of the middle fireproof board 4, the splicing seams of the first water-absorbing rubber board 6-1 adjacent to the outer fireproof board 5, and the splicing seams of the second water-absorbing rubber board 6-2 adjacent to the inner fireproof board 3 are parallel to each other, and the splicing seams of the inner fireproof board 3 and the splicing seams of the middle fireproof board 4 are perpendicular to each other.

[0075] In this embodiment, the inner fireproof plate 3, the middle fireproof plate 4 and the outer fireproof plate 5 are all galvanized steel plates, and the bolts 7 are galvanized hexagonal bolts or chrome-plated hexagonal bolts.

[0076] In actual use, by setting the inner fireproof board 3, the middle fireproof board 4 and the outer fireproof board 5 to galvanized steel plates, and the bolts 7 to galvanized hexagonal bolts or chrome-plated hexagonal bolts, rust can be effectively prevented.

[0077] In this embodiment, the outer annular walls of the first water-absorbing rubber plate 6-1 and the second water-absorbing rubber plate 6-2 are both arc-shaped surfaces, and the cross-sections of the outer annular walls of the first water-absorbing rubber plate 6-1 and the second water-absorbing rubber plate 6-2 are both semicircular.

[0078] like Figure 3 As shown, in this embodiment, the bolt positioning member 11 is cylindrical and one end of it is fixed on the clamp 10, and the other end of the bolt positioning member 11 is provided with a hexagonal countersunk hole for the head of the bolt 7 to be installed, and the other end of the bolt positioning member 11 is provided with a clamping member 12 for clamping the bolt 7;

[0079] The axis of the bolt positioning member 11 is parallel to the axis of the pipeline 1 .

[0080] In actual use, the clamping piece 12 does not affect the head of the bolt 7 being installed in the hexagonal countersunk hole after passing through the clamping piece 12. When the head of the bolt 7 is installed in the hexagonal countersunk hole, the clamping piece 12 can clamp and fix the screw rod of the bolt 7.

[0081] In this embodiment, the clamp 10 is coaxially arranged with the pipe 1, and the clamp 10 includes two interlocking arc-shaped clamp parts 10-1, and two bolt positioning parts 11 are arranged on one side of each of the arc-shaped clamp parts 10-1.

[0082] In actual use, the two ends of the two arc-shaped clamps 10 - 1 are fastened and connected by bolts respectively.

[0083] In this embodiment, the inner ring of the arc-shaped clamp 10-1 is provided with two hydraulic push rods 13 for tightening the pipe 1. The hydraulic push rods 13 are arranged along the radial direction of the arc-shaped clamp 10-1. One end of the hydraulic push rod 13 is fixed to the inner ring of the arc-shaped clamp 10-1, and the other end of the hydraulic push rod 13 is provided with an arc-shaped top plate 14.

[0084] During actual use, the cylinder body of the hydraulic jack 13 is embedded in the arc-shaped clamp 10 - 1 .

[0085] In this embodiment, in step four, when the pre-installed end fireproof and waterproof sealing assembly is pushed into the pipe sleeve 2, the hydraulic push rod 13 is first contracted to separate the arc-shaped top plate 14 from the outer wall of the pipe 1, and then the clamp 10 is manually pushed to push the end fireproof and waterproof sealing assembly into the pipe sleeve 2, and make the inner side of the outer fireproof plate 5 flush with the end face of one end of the pipe sleeve 2.

[0086] The above description is only a preferred embodiment of the present invention and does not limit the present invention in any way. Any simple modification, change and equivalent structural change made to the above embodiment based on the technical essence of the present invention still falls within the protection scope of the technical solution of the present invention.

Claims

1. A fireproof and waterproof sealing construction method for a structural beam and slab casing, characterized in that: The method comprises the following steps: Step 1: Waterproof sealing inside the pipe casing: filling a flexible waterproof material from one end of the pipe casing (2) into the gap between the pipe casing (2) and the pipe (1) to form a waterproof layer (9); wherein a gap is provided between the waterproof layer (9) and one end of the pipe casing (2); Step 2, installing a bolt positioning device at one end of the pipe sleeve: installing a bolt positioning device on the pipe (1) extending out of the pipe sleeve (2), and installing four bolts (7) on the bolt positioning device, wherein the four bolts (7) are all located at one end of the pipe sleeve (2); wherein the bolt positioning device comprises a clamp (10) sleeved on the outside of the pipe (1) and four bolt positioning members (11) arranged on one side of the clamp (10), wherein the four bolt positioning members (11) are all located on one side of the clamp (10) close to the pipe sleeve (2), and the four bolt positioning members (11) are evenly distributed on the same circumference; the axis of the bolt (7) is parallel to the axis of the pipe (1), and the head of the bolt (7) is arranged away from the pipe sleeve (2); Step 3: Pre-install the end fireproof and waterproof sealing assembly at one end of the pipe casing. The specific process is as follows: Step 301, welding four nuts (8) on the side of the inner fireproof plate (3) close to the pipe sleeve; Step 302, an outer fireproof plate (5), two first water-absorbing rubber plates (6-1), an intermediate fireproof plate (4), two second water-absorbing rubber plates (6-2) and an inner fireproof plate (3) are sequentially inserted into the screw rod of the bolt (7) extending out of the bolt positioning member (11); wherein the four bolts (7) are respectively connected to the four nuts (8) after passing through the inner fireproof plate (3); Step 4: Push the pre-installed end fireproof and waterproof sealing assembly into the pipe casing; Step 5: Fireproof water sealing at one end of the pipe casing: remove the bolt positioning device, tighten the four bolts (7), and make the first water-absorbing rubber sheet (6-1) and the second water-absorbing rubber sheet (6-2) seal one end of the pipe casing (2) under the pressure of the inner fireproof board (3), the middle fireproof board (4) and the outer fireproof board (5); The outer diameters of the first water-absorbing rubber sheet (6-1) and the second water-absorbing rubber sheet (6-2) are both smaller than the inner diameter of the pipeline casing (2), and the inner diameters of the first water-absorbing rubber sheet (6-1) and the second water-absorbing rubber sheet (6-2) are both equal to the outer diameter of the pipeline (1); The inner fireproof plate (3), the middle fireproof plate (4), the outer fireproof plate (5), the first water-absorbing rubber plate (6-1) and the second water-absorbing rubber plate (6-2) are all provided with four bolt through holes at equal intervals along the circumference thereof, the bolt through holes being circular holes and having a hole diameter not less than the thread diameter of the bolt (7), and the four nuts (8) are respectively arranged coaxially with the four bolt through holes; The inner fireproof plate (3), the middle fireproof plate (4) and the outer fireproof plate (5) are all annular fireproof plates spliced ​​together by two semicircular ring plates and having a splicing seam, the first water-absorbing rubber plate (6-1) and the second water-absorbing rubber plate (6-2) are all water-absorbing rubber plates spliced ​​together by two semicircular ring plates and having a splicing seam, the inner fireproof plate (3), the middle fireproof plate (4), the outer fireproof plate (5), the first water-absorbing rubber plate (6-1) and the second water-absorbing rubber plate (6-2) are coaxially arranged; two adjacent semicircular ring plates are arranged at 90 degrees; The outer diameters of the inner fireproof plate (3) and the middle fireproof plate (4) are equal and are both smaller than the outer diameter of the first water-absorbing rubber plate (6-1); One side of the pipeline casing (2) is connected to the outer facade of the structural beam slab and is directly sealed by concrete or structural soil layer.

2. A fireproof and waterproof sealing construction method for a structural beam and slab casing according to claim 1, characterized in that: The outer diameter of the outer fireproof plate (5) is equal to the inner diameter of the pipe sleeve (2), and the inner diameters of the inner fireproof plate (3), the middle fireproof plate (4) and the outer fireproof plate (5) are equal and not less than the outer diameter of the pipe (1).

3. A fireproof and waterproof sealing construction method for a structural beam and slab casing according to claim 1, characterized in that: The inner fireproof plate (3), the middle fireproof plate (4) and the outer fireproof plate (5) are all galvanized steel plates, and the bolts (7) are galvanized hexagonal bolts or chrome-plated hexagonal bolts.

4. A fireproof and waterproof sealing construction method for a structural beam and slab casing according to claim 3, characterized in that: The bolt positioning member (11) is cylindrical and one end of which is fixed to the clamp (10); the other end of the bolt positioning member (11) is provided with a hexagonal countersunk hole for mounting the head of the bolt (7); the other end of the bolt positioning member (11) is provided with a clamping member (12) for clamping the bolt (7); The axis of the bolt positioning member (11) and the axis of the pipeline (1) are parallel to each other.

5. A fireproof and waterproof sealing construction method for a structural beam and slab casing according to claim 1, characterized in that: The clamp (10) and the pipeline (1) are arranged coaxially, and the clamp (10) comprises two interlocking arc-shaped clamp parts (10-1), and two bolt positioning parts (11) are arranged on one side of each of the arc-shaped clamp parts (10-1).

6. A fireproof and waterproof sealing construction method for a structural beam and slab casing according to claim 5, characterized in that: The inner ring of the arc-shaped clamp (10-1) is provided with two hydraulic push rods (13) for tightening the pipe (1); the hydraulic push rods (13) are arranged along the radial direction of the arc-shaped clamp (10-1); one end of the hydraulic push rod (13) is fixed to the inner ring of the arc-shaped clamp (10-1); and the other end of the hydraulic push rod (13) is provided with an arc-shaped top plate (14).

7. A fireproof and waterproof sealing construction method for a structural beam and slab casing according to claim 6, characterized in that: In step 4, when the pre-installed end fireproof and waterproof sealing assembly is pushed into the pipe sleeve (2), the hydraulic push rod (13) is first retracted to separate the arc-shaped top plate (14) from the outer wall of the pipe (1), and then the clamp (10) is manually pushed to push the end fireproof and waterproof sealing assembly into the pipe sleeve (2) and make the inner side of the outer fireproof plate (5) flush with the end face of one end of the pipe sleeve (2).