A pipe beam static load test device and use method

By designing a static load test device for pipe beams, using fixed anti-pull-out piles and hydraulic jacks on the ground to apply load, combined with the reel and guide wheel to achieve rapid movement, the problem of low static load data detection efficiency of pipe beams is solved, and efficient detection and simplification is achieved operate.

CN116026671BActive Publication Date: 2024-12-03CHINA RAILWAY SIXTH GROUP CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202211552321.3
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-12-05
Publication Date
2024-12-03
Estimated Expiration
2042-12-05

AI Technical Summary

Technical Problem

In the prior art, the static load data detection efficiency of pipe beams is low and inconvenient to use. It is mainly due to the difficulty of efficient transportation of the test device to the inside of the pipe beams, resulting in a long time of manpower and equipment.

Method used

A pipe beam static load test device is designed, including a loading frame, anti-pile pile, pull rod and displacement detection unit. By fixing the anti-pile pile on the ground and hinged the pull rod, load is applied using a hydraulic jack, and it is realized through a reel and guide wheel. The rapid movement and removal of the load rack avoids the use of large lifting equipment.

Benefits of technology

It realizes the rapid and effective completion of static load data detection of pipe beams, improves detection efficiency, simplifies operating procedures, and reduces test costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN116026671B_ABST
    Figure CN116026671B_ABST
Patent Text Reader

Abstract

The present invention provides a static load test device for a pipe beam and a method for using the same. The static load test device for a pipe beam includes a loading frame, an anti-pulling pile, a first pull rod, a second pull rod and a displacement detection unit. When the present invention is in use, the pipe beam can be placed between two anti-pulling piles. The mouth of the pipe beam is directed toward the anti-pulling pile. In the present application, an independently movable loading frame is provided. When the pipe beam is subjected to a static load test, the loading frame can be passed through the inside of the pipe beam through a hoisting device. The loading frame is driven upward by a first power member and the two ends of the loading frame are respectively connected to the first pull rod and the second pull rod. When the first power member continues to apply a force, the force is applied to the inner wall of the pipe beam, thereby deforming the pipe beam. The static load-bearing capacity and working performance of the pipe beam can be detected based on the force of the first power member and the deformation of the pipe beam detected by the displacement detection unit, thereby providing a basis for the use of the pipe beam in transportation construction.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of vacuum pipeline construction, and in particular relates to a pipe beam static load test device and a use method thereof. Background Art

[0002] At present, the pipe beam structure commonly used in the construction of ultra-high-speed low-vacuum pipeline transportation is a pipe structure, similar to a tunnel structure. It is a structure of a beam and shell combination. In order to ensure that the bearing capacity and working state of the pipe beam in the later transportation construction can meet the design requirements, it is necessary to test and study the static load data on the pipe beam. The vertical and lateral static loads of the pipe beam need to be moved to the middle of the span inside the pipe beam, and the lateral force is applied by the hydraulic cylinder arranged horizontally on the movable support frame on the test equipment. The displacement change of the pipe beam is detected by the displacement meter to obtain data. Due to the limited space inside the pipe beam and the arrangement of many steel bars inside the pipe beam, some transportation equipment is affected to transport the test device to the inside of the pipe beam. At present, the test device is transported to the inside of the pipe beam manually or by conveyor belt. In addition, a large amount of manpower and auxiliary transportation equipment are required to be occupied for a long time during the detection process, resulting in low detection efficiency and inconvenience in the use of the static load data detection equipment of the pipe beam. Summary of the invention

[0003] The embodiment of the present invention provides a static load test device for a tubular beam and a method for using the same, aiming to solve the problems of low detection efficiency and inconvenience in use of static load data detection equipment for tubular beams in the prior art.

[0004] To achieve the above object, the technical solution adopted by the present invention is: to provide a tubular beam static load test device, comprising:

[0005] A loading frame, wherein a first power member arranged in a vertical direction and a second power member arranged in a horizontal direction are arranged below the loading frame, and a walking wheel moving along the length direction of the loading frame is arranged at the bottom of the loading frame;

[0006] Two anti-pulling piles are fixedly disposed below the loading frame and spaced apart along the length direction of the loading frame;

[0007] A first pull rod, one end of which is hingedly connected to one of the two anti-pulling piles, and the other end of which is detachably arranged on the loading frame;

[0008] A second pull rod, hingedly connected with the first pull rod and respectively arranged on the two anti-pulling piles, and the other end of the second pull rod is detachably arranged on the loading frame;

[0009] The displacement detection unit is used to detect the deformation of the pipe beam.

[0010] In a possible implementation, two connecting rollers are slidably provided on the loading frame along the length direction of the loading frame, and the first pull rod and the second pull rod are respectively hingedly connected to the two connecting rollers.

[0011] In a possible implementation, a placement platform for placing the loading frame and a pulling unit for pulling the loading frame are arranged at intervals along the length direction of the loading frame, and the two pull-out piles are located between the placement platform and the pulling unit.

[0012] In a possible implementation, the pulling unit includes:

[0013] A winding drum, on which a fastening rope for pulling the loading frame to move is wound;

[0014] A guide frame, arranged on the side of the winding drum close to the placing table, and a first guide wheel is rotatably arranged on the guide frame;

[0015] The driving member is connected to the rotating shaft on the winding drum and is used to drive the rotating shaft on the winding drum to rotate and tighten the tightening rope.

[0016] In a possible implementation, a second guide wheel is rotatably provided on a side of the placement platform away from the pulling unit.

[0017] In a possible implementation manner, a hook body for connecting with the connecting roller is fixedly connected to the end of the second pull rod, and an opening of the hook body is arranged toward the first pull rod.

[0018] In a possible implementation, when the second pull rod is arranged in a vertical direction, the hook body is arranged to be inclined gradually from top to bottom in a direction away from the inner wall of the second pull rod toward the first pull rod.

[0019] In a possible implementation, a bent wing plate for preventing the anti-pullout pile from moving upward is fixedly connected to the bottom of the anti-pullout pile, and the bent wing plate is gradually extended from top to bottom toward the outside of the anti-pullout pile.

[0020] In a possible implementation, two guide rods are arranged on the loading frame at intervals in the vertical direction, the outer diameter of the connecting roller gradually increases from the middle of the connecting roller to both ends, and the middle of the connecting roller is located between the two guide rods.

[0021] Compared with the prior art, the scheme shown in the embodiment of the present application is that two pull-out piles arranged at intervals are fixedly installed on the ground. The pipe beam can be placed between the two pull-out piles, and the first pull rod and the second pull rod are respectively hingedly arranged on the pull-out piles. The displacement detection unit includes a plurality of displacement meters and a signal collector connected to the signal output end of the displacement meter. When in use, the pipe beam to be subjected to the static load test is placed between the two pull-out piles, and the two ends of the pipe beam are respectively facing the two pull-out piles. A plurality of detection points are evenly arranged on the pipe beam, and a displacement meter is installed at each detection point. The loading frame is pushed through the inside of the pipe beam and the first pull rod and the second pull rod are connected to the loading frame. According to the test data, the first power member is controlled to apply a corresponding force to the pipe beam, and the corresponding deformation of the pipe beam is collected according to the displacement meter. At the same time, the second power member can also apply a force to the pipe beam according to the test data, and a lateral and vertical force can be applied to the pipe beam at the same time. The operation process is simple, and the detection of the pipe beam can be completed quickly and effectively, which can effectively improve the detection efficiency of the static load data detection of the pipe beam.

[0022] In combination with the first aspect, in a possible implementation manner, a method for using the tubular beam static load test device is also included, and the steps are as follows:

[0023] Step 1: Arrange multiple displacement detection units at the lower part of the mid-span of the pipe beam to detect the deformation of the pipe beam and collect data;

[0024] Step 2: Pull the loading frame into the pipe beam through the pulling unit, connect the first pull rod and the second pull rod to the loading frame respectively, and start the first power member so that the driving force of the first power member acts on the pipe beam; observe the detection data of the detection unit;

[0025] Step 3: start the second power member, so that the driving force of the second power member acts on the side walls of the pipe beam and observes the detection data of the detection unit, wherein step 3 is started simultaneously with step 2 or started separately;

[0026] Step 4: After the inspection is completed, retract the first power member and the second power member, and remove the second pull rod from the loading frame. Pass the rope on the winding drum around the second guide wheel and then connect it to the loading frame. Start the driving member to retract the loading frame to the placement table, and retract the rope to conduct the next pipe beam inspection.

[0027] Compared with the prior art, the solution shown in the embodiment of the present application can remove the loading frame from the inside of the pipe beam in the horizontal direction through the combination of the rope on the winding drum and the second guide wheel. Before the inspection, the loading frame can be pulled to the inside of the pipe beam by the winding drum, and after the use is completed, the loading frame can be removed from the inside of the pipe beam by the winding drum. During use, the use of large-scale lifting equipment to lift and move the loading frame is avoided. At the same time, this method is suitable for the inspection of tubular beams. It can effectively reduce the cumbersome steps of moving the loading frame to or from the inside of the pipe beam, and effectively improve the inspection efficiency of the pipe beam. BRIEF DESCRIPTION OF THE DRAWINGS

[0028] Figure 1 A schematic diagram of the structure of a static load test device for a tubular beam provided in an embodiment of the present invention;

[0029] Figure 2 A schematic diagram of the structure of the loading frame conveying state provided by an embodiment of the present invention;

[0030] Figure 3 for Figure 2 A partial enlarged view of the middle A part;

[0031] Figure 4 A side view of a static load test device for a tubular beam provided by an embodiment of the present invention;

[0032] Figure 5 A schematic diagram of the connecting roller installation structure provided in an embodiment of the present invention.

[0033] Description of reference numerals:

[0034] 1. Loading frame; 11. First power member; 12. Second power member; 13. Traveling wheel; 14. Guide rod; 2. Pull-out pile; 21. Bending wing plate; 3. First pull rod; 4. Second pull rod; 41. Hook body; 5. Detection point; 6. Connecting roller; 7. Placement table; 71. Second guide wheel; 8. Pulling unit; 81. Reel; 82. Guide frame; 821. First guide wheel; 83. Driving member; 9. Pipe beam. DETAILED DESCRIPTION

[0035] In order to make the technical problems, technical solutions and beneficial effects to be solved by the present invention more clearly understood, the present invention is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not intended to limit the present invention.

[0036] Please also read Figure 1 , Figure 2 and Figure 4, the static load test device for the tubular beam provided by the present invention is now described. The static load test device for the tubular beam comprises a loading frame 1, an anti-pulling pile 2, a first tie rod 3, a second tie rod 4 and a displacement detection unit. A first power member 11 arranged in the vertical direction and a second power member 12 arranged in the horizontal direction are arranged below the loading frame 1; there are two anti-pulling piles 2, which are fixedly arranged below the loading frame 1 and spaced apart along the length direction of the loading frame 1; one end of the first tie rod 3 is hingedly connected to one of the two anti-pulling piles 2, and the other end is detachably arranged on the loading frame 1; the second tie rod 4 is hingedly arranged on the two anti-pulling piles 2 with the first tie rod 3, respectively, and the other end of the second tie rod 4 is detachably arranged on the loading frame 1; the displacement detection unit is used to detect the deformation of the tubular beam 9.

[0037] Compared with the prior art, the static load test device for the pipe beam provided in this embodiment has two pull-out piles 2 fixedly installed on the ground at intervals. The pipe beam 9 can be placed between the two pull-out piles 2, and the first pull rod 3 and the second pull rod 4 are respectively hingedly arranged on the pull-out piles 2. The displacement detection unit includes a plurality of displacement meters and a signal collector connected to the signal output end of the displacement meter. When in use, the pipe beam 9 to be subjected to the static load test is placed between the two pull-out piles 2, and the two ends of the pipe beam 9 are respectively facing the two pull-out piles 2. A plurality of detection points 5 are evenly arranged on the pipe beam 9, and a displacement meter is installed on each detection point 5. The loading frame 1 is pushed to penetrate the interior of the pipe beam 9 and the first pull rod 3 and the second pull rod 4 are connected to the loading frame 1. According to the test data, the first power member 11 is controlled to apply a corresponding force to the pipe beam 9, and the corresponding deformation of the pipe beam 9 is collected according to the displacement meter. At the same time, a force can be applied to the pipe beam 9 through the second power member 12 according to the test data, and a lateral and vertical force can be applied to the pipe beam 9 at the same time. The operation process is simple, and the detection of the pipe beam 9 can be completed quickly and effectively, and the detection efficiency of the static load data detection of the pipe beam 9 can be effectively improved.

[0038] Specifically, in this embodiment, the connection positions between the first tie rod 3 and the second tie rod 4 on the loading frame 1 are respectively located directly above the hinge axis between the first tie rod 3 and the anti-pulling pile 2 and the hinge axis between the second tie rod 4 and the anti-pulling pile 2. When the first power member 11 applies a loading force to the pipe beam 9, the first tie rod 3 and the second tie rod 4 remain in a vertical state.

[0039] Specifically, in this embodiment, the first power member 11 and the second power member 12 are both hydraulic jacks. The tubular beam static load test device further includes a hydraulic pump station for connecting the first power member 11 and the second power member 12 .

[0040] Specifically, in this embodiment, sleepers are provided at the pushing ends of the first power member 11 and the second power member 12 .

[0041] Specifically, in this embodiment, the bottom of the loading frame 1 is provided with running wheels 13 that move along the length direction of the loading frame 1. The running wheels 13 are installed at the bottom of the loading frame 1 to facilitate the adjustment of the position of the loading frame 1 inside the pipe beam 9. When in use, the first power member 11 first lifts the loading frame 1, and then applies the load force to the pipe beam 9 through the first tie rod 3 and the second tie rod 4, and when the first tie rod 3 and the second tie rod 4 are in a vertical state, the running wheels 13 are separated from the pipe beam 9 and are located above the force application surface of the pipe beam 9. After the test is completed, the driving end of the first power member 11 is retracted so that the running wheels 13 are attached to the force application surface of the pipe beam 9, so as to facilitate the removal of the loading frame 1 from the inside of the pipe beam 9.

[0042] In some embodiments, the loading frame 1 can be used as follows Figure 2 , Figure 3 See also Figure 2 , Figure 3 , two connecting rollers 6 are slidably arranged on the loading frame 1 along the length direction of the loading frame 1, and the first tie rod 3 and the second tie rod 4 are respectively hingedly connected to the two connecting rollers 6. Two support ribs arranged in parallel at intervals are arranged on the ends of the first tie rod 3 and the second tie rod 4 away from the pull-out pile 2. The two support ribs are respectively hingedly arranged at the two ends of the connecting roller 6. When in use, the loading frame 1 can be moved to the inside of the pipe beam 9 first. Then, by rotating the first tie rod 3 and the second tie rod 4 and adjusting the position of the connecting roller 6 on the loading frame 1. First, the first tie rod 3 and the second tie rod 4 are connected to the connecting roller 6. Then, the driving end of the first power member 11 contacts the pipe beam 9 to drive the loading frame 1 to move upward, and the first tie rod 3 and the second tie rod 4 gradually rotate in the vertical direction, so that the first tie rod 3 and the second tie rod 4 drive the connecting roller 6 to slide on the loading frame 1 until the first tie rod 3 and the second tie rod 4 remain in a vertical state. The adjustment of the position of the loading frame 1 can be reduced. When placing the loading frame 1, it is only necessary to make the projections of the two pull-out piles 2 in the vertical direction be located within the projection of the sliding range of the connecting roller 6 on the loading frame 1. This improves the test efficiency.

[0043] In some embodiments, the above-mentioned pipe beam static load test device can be used as follows: Figure 1 , Figure 2 See also Figure 1 , Figure 2 A placing table 7 for placing the loading frame 1 and a pulling unit 8 for pulling the loading frame 1 are arranged at intervals along the length direction of the loading frame 1, and two pull-out piles 2 are located between the placing table 7 and the pulling unit 8. The placing table 7 and the pulling unit 8 are located outside the two pull-out piles 2. When placing the pipe beam 9, the loading frame 1 is located on the placing table 7. After the pipe beam 9 is placed, the loading frame 1 is pulled into the pipe beam 9 by the pulling unit 8, which can reduce the use of hoisting equipment and reduce the test cost.

[0044] In this embodiment, the height of the placement platform 7 is higher than the height of the ground inside the pipe beam 9. In addition, multiple sets of running wheels 13 are arranged at intervals at the bottom of the loading frame 1 along the length direction of the loading frame 1. When the loading frame 1 is transported to the inside of the pipe beam 9, it can slide into the inside of the pipe beam 9 through the running wheels 13.

[0045] In some embodiments, the pulling unit 8 may be configured as follows: Figure 1 , Figure 2 See also Figure 1 , Figure 2 The pulling unit 8 includes a winding drum 81, a guide frame 82 and a driving member 83. A fastening rope for pulling the loading frame 1 to move is wound on the winding drum 81; the guide frame 82 is arranged on the side of the winding drum 81 close to the placement platform 7, and a first guide wheel 821 is rotatably arranged on the guide frame 82; the driving member 83 is connected to the rotating shaft on the winding drum 81, and is used to drive the rotating shaft on the winding drum 81 to rotate and retract the fastening rope. The height of the first guide wheel 821 is higher than the top surface of the placement platform 7. When in use, the fastening rope on the winding drum 81 is wound around the first guide wheel 821 and passed through the inside of the pipe beam 9, and is passed out from the end of the pipe beam 9 close to the placement platform 7 and connected to the loading frame 1, and the rotating shaft of the winding drum 81 is driven by the driving member 83 to rotate, and the fastening rope is wound on the winding drum 81, so as to pull the loading frame 1 to move in the direction of the pipe beam 9, and move the loading frame 1 to the pipe beam 9.

[0046] Optionally, in this embodiment, a plurality of first guide wheels 821 are arranged in the vertical direction on the guide frame 82, and a suitable first guide wheel 821 can be selected according to the pipe beams 9 of different heights to prevent the fastening rope from fitting onto the pipe beams 9 and damaging them.

[0047] In some embodiments, the placement table 7 may be Figure 1 , Figure 2 See also Figure 1 , Figure 2 , a second guide wheel 71 is rotatably provided on one side of the placement table 7 away from the pulling unit 8. The second guide wheel 71 is provided so that when the loading frame 1 needs to be retracted onto the placement table 7, the fastening rope can be passed through the pipe beam 9 and the placement table 7 and then wound around the second guide wheel 71 to connect with the loading frame 1, and then the driving member 83 drives the rotating shaft of the winding drum 81 to rotate, thereby driving the fastening rope to be stored on the winding drum 81, so that the loading frame 1 can be pulled to move onto the placement table 7. Through the cooperation of the first guide wheel 821 and the second guide wheel 71, the loading frame 1 can be moved from the placement table 7 to the inside of the pipe beam 9 through the winding drum 81, and after the test is completed, the loading frame 1 can be moved from the inside of the pipe beam 9 to the placement table 7. The entire operation process does not require the use of lifting equipment for auxiliary operations, which saves steps and effectively improves the test efficiency.

[0048] Specifically, in this embodiment, a guide frame 82 is provided on one side of the placement table 7 close to the pulling unit 8. The guide frame 82 is tilted at the end of the placement table 7, and the guide frame 82 gradually tilts from top to bottom toward the direction close to the pulling unit 8. The top surface of the guide frame 82 and the top surface of the placement table 7 are arranged in a circular arc transition.

[0049] In some embodiments, the second pull rod 4 may be Figure 2 , Figure 3 and Figure 5 See also Figure 2 , Figure 3 and Figure 5 , the end of the second tie rod 4 is fixedly connected with a hook body 41 for connecting with the connecting roller 6, and the opening of the hook body 41 is arranged toward the first tie rod 3. The end of the second tie rod 4 is provided with a hook body 41, and when in use, the loading frame 1 can be moved to the inside of the pipe beam 9, and one end of the loading frame 1 extends out of the pipe beam 9 and is located above the second tie rod 4. By adjusting the position of the connecting roller 6 above the second tie rod 4, the connecting roller 6 is located on the side of the second tie rod 4 close to the first tie rod 3. And the second tie rod 4 is rotated so that the second tie rod 4 overlaps the connecting roller 6. In the later stage, when the first power member 11 drives the loading frame 1 to move upward, the end of the connecting roller 6 will gradually move toward the direction of the hook body 41 until it moves to the inside of the hook body 41. When the loading frame 1 continues to move upward, the second tie rod 4 drives the connecting roller 6 to move in the direction close to the second tie rod 4 until the second tie rod 4 remains in a vertical state. When the second tie rod 4 is connected to the connecting roller 6, the operation is convenient and quick.

[0050] Specifically, in this embodiment, the first tie rod 3 can be connected to the loading frame 1 through the connecting roller 6. When the loading frame 1 moves in the vertical direction, the connecting roller 6 can drive the first tie rod 3 to swing to adjust the state of the first tie rod 3. When the loading frame 1 moves in the horizontal direction, the connecting roller 6 can slide in the connecting frame to change the relative position of the first tie rod 3 and the loading frame 1.

[0051] Optionally, in this embodiment, a slide groove for sliding the connecting roller 6 is provided on the loading frame 1, and the slide groove is provided along the length direction of the loading frame 1. A limit block is provided at the end of the slide groove close to the first pull rod 3, and when the connecting roller 6 connected to the first pull rod 3 hits the limit block, the first pull rod 3 is in a vertical state.

[0052] In some embodiments, the hook body 41 may be Figure 2 , Figure 3 and Figure 5 See also Figure 2 , Figure 3 and Figure 5When the second pull rod 4 is arranged in the vertical direction, the hook body 41 is arranged to be inclined from top to bottom away from the inner wall of the second pull rod 4 and gradually approaching the first pull rod 3. The opening of the hook body 41 faces the first pull rod 3, and the inner wall of the hook body 41 is arranged to be inclined. When the hook body 41 needs to be separated from the connecting roller 6, the second pull rod 4 can be fixed in a vertical state, and the driving end of the second power member 12 is moved toward the fixed end, so that the loading frame 1 moves downward, and the connecting roller 6 is automatically separated from the hook body 41 through the guidance of the inner wall of the hook body 41, thereby realizing the separation of the connecting roller 6 from the second pull rod 4. The operation process is simple and convenient.

[0053] Optionally, in this embodiment, a connection portion for connecting a fastening rope is provided on the second pull rod 4. When the second pull rod 4 needs to be separated from the connecting roller 6, the fastening rope can be connected to the connection portion to prevent the connecting roller 6 from driving the second pull rod 4 to swing toward the first pull rod 3 when the loading frame 1 moves downward, so that the connecting roller 6 is guided by the inclined surface inside the hook body 41 and detached from the second pull rod 4.

[0054] In some embodiments, the pull-out pile 2 may be Figure 2 , Figure 3 See also Figure 2 , Figure 3 , a bent wing plate 21 for preventing the pull-out pile 2 from moving upward is fixedly connected to the bottom of the pull-out pile 2, and the bent wing plate 21 is gradually extended from top to bottom to the outside of the pull-out pile 2. There are multiple bent wing plates 21, and one end of the multiple bent wing plates 21 is fixedly installed at the bottom of the pull-out pile 2. The other end is located on the outside of the projection of the pull-out pile 2 in the vertical direction. And the bent wing plate 21 is gradually inclined from top to bottom to the outside of the pull-out pile 2. In this embodiment, a foundation pit for placing the pull-out pile 2 is processed on the ground, and the pull-out pile 2 is fixed to the inside of the foundation pit by pouring cement into the inside of the foundation pit. The setting of the bent wing plate 21 can strengthen the stability of the pull-out pile 2, and at the same time prevent the pull-out pile 2 from detaching from the ground or having a relative displacement with the ground during the test, which affects the test accuracy.

[0055] Optionally, in this embodiment, a bending portion that is gradually inclined from bottom to top away from the anti-pulling pile 2 is fixedly connected to one end of the bending wing plate 21 away from the anti-pulling pile 2. The bending portion and the bending wing plate 21 are an integral bending structure.

[0056] In some embodiments, the loading frame 1 can be used as follows Figure 5 See the structure shown. Figure 5Two guide rods 14 are arranged on the loading frame 1 at intervals in the vertical direction. The outer diameter of the connecting roller 6 gradually increases from the middle of the connecting roller 6 to both ends, and the middle of the connecting roller 6 is located between the two guide rods 14. The cross section of the guide rod 14 is a circular structure. The connecting roller 6 is rollingly arranged between the two guide rods 14. On the one hand, the connecting roller 6 can be guided, and on the other hand, the connecting roller 6 can be limited to move along the axis direction of the connecting roller 6.

[0057] Optionally, in this embodiment, two hook bodies 41 are provided at the end of the second pull rod 4 and are arranged at intervals along the axial direction of the connecting roller 6. When the second pull rod 4 is connected to the connecting roller 6, the two hook bodies 41 are respectively connected to the two ends of the connecting roller 6, thereby improving the stability of the connection between the second pull rod 4 and the connecting roller 6.

[0058] Specifically, the present application also includes a static load test method for a pipe beam, firstly, the loading frame 1 is pulled onto the placement table 7 by the pulling unit 8, the pipe beam 9 is hoisted and placed between the two pull-out piles 2, and the two ends of the pipeline are respectively oriented between the two pull-out piles 2. A plurality of detection points 5 are evenly arranged on the pipeline, and a displacement meter is installed at the detection point 5, and the signal output end of the displacement meter is connected to the signal input end of the signal collector. After the loading frame 1 is moved to the inside of the pipe beam 9 by the pulling unit 8, the loading frame 1 is first driven to move upward by the first power member 11. The walking wheel 13 at the bottom of the loading frame 1 is separated from the pipe beam 9. According to the test data, the first power member 11 is controlled to apply a corresponding load to the bottom of the U-shaped beam. And the data is collected by the signal collector. Then, the second power member 12 is supported on the inner wall on both sides of the pipe beam 9, and the second power member 12 is controlled to apply a corresponding load to both sides of the U-shaped beam according to the test data. And the data is collected by the signal collector. The first power member 11 and the second power member 12 can also apply corresponding loads to the inside of the pipe beam 9 at the same time, and collect the deformation data of the pipe beam 9 through the signal collector. After the test of the pipe beam 9 is completed, the driving end of the first power member 11 is retracted, so that the walking wheel 13 on the loading frame 1 falls on the pipe beam 9, and the loading frame 1 is moved out of the pipe beam 9 through the pulling unit 8. The pipe beam 9 is also moved out from between the two pull-out piles 2. The next pipe beam 9 is replaced for the cycle test, which effectively improves the work efficiency of the static load test of the pipe beam 9.

[0059] Based on the same inventive concept, the embodiment of the present application also provides a method for using a static load test device for a tubular beam, the steps of which are as follows:

[0060] Step 1: Arrange multiple displacement detection units at the lower part of the mid-span of the pipe beam 9 to detect the deformation of the pipe beam 9 and collect data;

[0061] Step 2: Pull the loading frame 1 into the pipe beam 9 through the pulling unit 8, connect the first pull rod 3 and the second pull rod 4 to the loading frame 1 respectively, and start the first power member 11 so that the driving force of the first power member 11 acts on the pipe beam 9; observe the detection data of the detection unit;

[0062] Step 3: Start the second power member 12, so that the driving force of the second power member 12 acts on the side walls of the pipe beam 9 and observes the detection data of the detection unit, wherein step 3 is started simultaneously with step 2 or started separately;

[0063] Step 4: After the inspection is completed, retract the first power member 11 and the second power member 12, and remove the second pull rod 4 from the loading frame 1. By wrapping the rope on the winding drum 81 around the second guide wheel 71 and then connecting it to the loading frame 1, start the driving member 83 to retract the loading frame 1 onto the placement table 7, and retract the rope to carry out the inspection of the next pipe beam 9.

[0064] Compared with the prior art, the solution shown in the embodiment of the present application can remove the loading frame 1 from the inside of the pipe beam 9 in the horizontal direction through the combination of the rope on the winding drum 81 and the second guide wheel 71. Before the inspection, the loading frame 1 can be pulled to the inside of the pipe beam 9 by the winding drum 81. After the use is completed, the loading frame 1 can be removed from the inside of the pipe beam 9 by the winding drum 81. During use, the use of large-scale lifting equipment to lift and move the loading frame 1 is avoided. At the same time, this method is suitable for the inspection of tubular beams. It can effectively reduce the cumbersome steps of moving the loading frame 1 to or from the inside of the pipe beam 9, and effectively improve the inspection efficiency of the pipe beam 9.

[0065] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. A static load test device for a tubular beam, characterized in that: include: A loading frame, wherein a first power member arranged in a vertical direction and a second power member arranged in a horizontal direction are arranged below the loading frame, and a walking wheel moving along the length direction of the loading frame is arranged at the bottom of the loading frame; Anti-pulling piles are fixedly disposed below the loading frame and arranged at intervals along the length direction of the loading frame; A first pull rod, one end of which is hingedly connected to one of the two anti-pulling piles, and the other end of which is detachably arranged on the loading frame; A second pull rod, hingedly connected with the first pull rod and respectively arranged on the two anti-pulling piles, and the other end of the second pull rod is detachably arranged on the loading frame; Displacement detection unit, used to detect the deformation of the pipe beam; Two connecting rollers are slidably provided on the loading frame along the length direction of the loading frame, and the first pull rod and the second pull rod are respectively hingedly connected to the two connecting rollers; A placing platform for placing the loading frame and a pulling unit for pulling the loading frame are respectively arranged at intervals along the length direction of the loading frame, and the two anti-pulling piles are located between the placing platform and the pulling unit; Two support ribs arranged in parallel at intervals are arranged at one end of the first pull rod and the second pull rod away from the pull-out pile. The two support ribs are hinged at both ends of the connecting roller. When in use, the loading frame is first moved to the inside of the pipe beam, and then the first pull rod and the second pull rod are connected to the connecting roller by rotating the first pull rod and the second pull rod and adjusting the position of the connecting roller on the loading frame. Then, the driving end of the first power member is abutted against the pipe beam to drive the loading frame to move upward. The first pull rod and the second pull rod are gradually rotated in the vertical direction, so that the first pull rod and the second pull rod drive the connecting roller to slide on the loading frame until the first pull rod and the second pull rod remain in a vertical state, thereby reducing the adjustment of the position of the loading frame.

2. The static load test device for tubular beams according to claim 1, characterized in that: The pulling unit comprises: A winding drum, on which a fastening rope for pulling the loading frame to move is wound; A guide frame, arranged on the side of the winding drum close to the placing table, and a first guide wheel is rotatably arranged on the guide frame; The driving member is connected to the rotating shaft on the winding drum and is used to drive the rotating shaft on the winding drum to rotate and tighten the tightening rope.

3. The static load test device for tubular beams according to claim 2, characterized in that: A second guide wheel is rotatably arranged on one side of the placement platform away from the pulling unit.

4. The static load test device for tubular beams according to claim 1, characterized in that: A hook body for connecting with the connecting roller is fixedly connected to the end of the second pull rod, and an opening of the hook body is arranged toward the first pull rod.

5. The static load test device for tubular beams according to claim 4, characterized in that: When the second pull rod is arranged in a vertical direction, the hook body is arranged to be inclined from top to bottom in a direction away from the inner wall of the second pull rod and gradually approaching the first pull rod.

6. The static load test device for tubular beams according to claim 1, characterized in that: A bent wing plate for preventing the anti-pullout pile from moving upward is fixedly connected to the bottom of the anti-pullout pile, and the bent wing plate is gradually extended from top to bottom toward the outside of the anti-pullout pile.

7. The static load test device for tubular beams according to claim 1, characterized in that: Two guide rods are arranged on the loading frame at intervals in the vertical direction. The outer diameter of the connecting roller gradually increases from the middle part of the connecting roller to both ends, and the middle part of the connecting roller is located between the two guide rods.

8. A method for using the static load test device for tubular beams according to any one of claims 1 to 7, characterized in that: Includes steps: Step 1: Arrange multiple displacement detection units at the lower part of the mid-span of the pipe beam to detect the deformation of the pipe beam and collect data; Step 2: Pull the loading frame into the pipe beam through the pulling unit, connect the first pull rod and the second pull rod to the loading frame respectively, and start the first power member so that the driving force of the first power member acts on the pipe beam; observe the detection data of the detection unit; Step 3: Start the second power member, so that the driving force of the second power member acts on the side walls of the pipe beam and observes the detection data of the detection unit, wherein step 3 is started simultaneously with step 2 or started separately; Step 4: After the inspection is completed, retract the first power member and the second power member, and remove the second pull rod from the loading frame. Pass the rope on the winding drum around the second guide wheel and then connect it to the loading frame. Start the driving member to retract the loading frame to the placement table, and retract the rope to conduct the next pipe beam inspection.