A reinforced flooded roadbed and construction method thereof
By setting up a combined structure such as steel mesh, hydrophobic mechanism, permeable geotextile and grille mesh in the immersed roadbed, the problems of freezing and moisture retention are solved, the stability and service life of the roadbed are improved, and the safety and operation of the roadbed are ensured. Continuity.
Patent Information
- Application Number
- CN202310020217.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-01-06
- Publication Date
- 2024-12-06
- Estimated Expiration
- 2043-01-06
AI Technical Summary
The water-soaked roadbed is frozen and swelled due to the frozen water in the seasonal frozen soil area, causing damage to the roadbed. The high groundwater level and frequent water flow lead to the wet roadbed, hollowing out the slope, and making it instable, seriously threatening highway safety and production operations.
The reinforcement and immersion roadbed technology is adopted, including the installation of reinforced steel mesh and hydrophobic mechanisms on the outside of the roadbed layer, permeable geotextile and grille mesh, permeable material and hydrophobic pipes and other combined structures, the moisture in the roadbed is discharged through the hydrophobic mechanism, reducing the impact of freezing and swelling, and reinforcing The layer provides reinforcement, permeable geotextile and grille net to reduce moisture loss and extend the service life of the roadbed.
It effectively reduces the damage to the roadbed by freezing, improves the stability and service life of the roadbed, reduces the risks of moisture retention and freezing, and enhances the roadbed's freezing resistance and loss prevention effect.
Smart Images

Figure CN116122092B_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of roadbed reinforcement and slope protection, and in particular to a reinforced submerged roadbed and a construction method thereof. Background Art
[0002] At present, the roadbed is an important part of the road infrastructure, the main body that bears the traffic load, and the key to the quality assurance of road projects; some geographical locations are mainly farmland and nurseries, with high groundwater levels, scattered water systems, many natural ditches, large floods during the flood season, dense surface runoff, and many sections of roadbeds are perennially submerged. Under the scouring, erosion, and softening of water flow, the submerged roadbed will become wet and the slope foot will be hollowed out; under the influence of water level rise and fall, the submerged roadbed soil is difficult to compact, and the fine particles in the filler are easy to lose, resulting in roadbed instability and slope collapse, causing huge engineering problems and serious threats to highway safety and production operations.
[0003] In the process of implementing this application, the inventors found that there are at least the following problems in this technology: in seasonally frozen soil areas, the water that penetrates into the submerged roadbed is enriched within the base bed, freezes under the action of negative temperature, increases in volume, produces frost heave, and causes damage to the submerged roadbed. Summary of the invention
[0004] In order to reduce damage to the submerged roadbed, the present application provides a reinforced submerged roadbed and a construction method thereof.
[0005] In the first aspect, the present application provides a reinforced submerged roadbed, which adopts the following technical solution:
[0006] A reinforced waterlogged roadbed comprises a cushion layer, a reinforcement layer, a roadbed and a drainage mechanism. The roadbed is laid on the cushion layer, a steel mesh is added on the outer side of the roadbed to form the reinforcement layer to protect the roadbed, and a plurality of drainage mechanisms are arranged in the roadbed to transport moisture at the cushion layer to the outer side of the roadbed.
[0007] By adopting the above technical scheme, when constructing the roadbed in the frequently flooded area, the construction area is first cleaned, and then the cushion layer is laid layer by layer, and then a drainage mechanism is installed on the cushion layer, and then the roadbed is cast in a mold, and a reinforcement layer is cast on the outside of the roadbed; the drainage mechanism is set up to facilitate the discharge of water that has penetrated into the roadbed, thereby reducing the retention of water in the roadbed, and the water is discharged in time. When the seasons change, the impact of frost heave on the roadbed is reduced, thereby reducing the damage to the roadbed; at the same time, the reinforcement layer is set up to reinforce the roadbed, reduce the cracking caused by frost heave, and thus reduce the damage to the roadbed.
[0008] Optionally, multiple layers of permeable geotextiles are provided in the road base layer, and impermeable geotextiles are laid in the cushion layer.
[0009] By adopting the above technical solution, when water seeps into the roadbed, the water passes through the permeable geotextile and approaches the drainage mechanism. The permeable geotextile can reduce the loss of other substances carried by the water, thereby reducing the probability of hollowing out the inside of the reinforced submerged roadbed, and further reducing the damage to the reinforced submerged roadbed; at the same time, the anti-seepage geotextile set up can reduce the permeability of the bottom layer and reduce damage to the roadbed.
[0010] Optionally, grid nets are provided on both sides of each layer of the permeable geotextile, and the grid nets are connected to the permeable geotextile via binding wires, and a plurality of anchor hooks are provided on the sides of the grid nets on both sides that are away from each other.
[0011] By adopting the above technical scheme, when constructing the roadbed, a layered pouring method can be adopted. After each layer is poured, the permeable geotextile can be fixed to the grid net and then embedded on the outside of each layer of the roadbed. The grid net can reduce the concrete solidification and the expansion or contraction of the roadbed in summer and winter, and the tearing of the permeable geotextile, so that the effect of the permeable geotextile can be maintained, and the service life of the roadbed can be increased. At the same time, the tearing of the permeable geotextile caused by slight frost heave can be reduced, so that the anti-loss effect of the permeable geotextile on the roadbed can be maintained; at the same time, the grid net is arranged to facilitate the fixation of the permeable geotextile, making the construction convenient.
[0012] Optionally, the contact surface between the permeable geotextile and the road base layer forms a concave and convex end surface through the grid mesh.
[0013] By adopting the above technical scheme, when pouring the road base layer in layers, the grid mesh is bent and connected to the permeable geotextile with binding wires, and then the permeable geotextile is fixed at the joints of each layer and then poured into the concrete; the shape of the permeable geotextile is modified by the grid mesh, so that when each layer of the road base layer is poured, the contact area between the layers is increased, which makes it easier to increase the stability of the reinforced submerged roadbed and further extend the service life of the submerged roadbed.
[0014] Optionally, the reinforcement layer is provided with two layers, and quick-closing molds are provided on the sides of the two reinforcement layers facing away from each other, and a water-permeable material is filled between the two reinforcement layers.
[0015] By adopting the above technical solution, permeable material is added between the two layers of steel mesh, so that the water that penetrates into the submerged roadbed can flow quickly to the drainage mechanism, and at the same time can reduce the damage to the external surface in contact with water during frost heave, thereby reducing the damage to the roadbed; the quick and easy closing mold set up can increase the adhesion of adjacent concrete, form a rough surface, and make the concrete joints more stable.
[0016] Optionally, the drainage mechanism includes a drainage pipe, which is arranged in the road base layer and located on the inner side of the innermost permeable geotextile. The drainage pipe is connected to the outside of the road base layer for drainage, and a plurality of drainage holes are opened on the outer wall of the drainage pipe.
[0017] By adopting the above technical scheme, the drain pipe is arranged on the inner side of the multi-layer permeable geotextile, which is convenient for multi-layer filtration and blocking of moisture, thereby reducing the outflow of substances in the roadbed carried by moisture; the moisture that penetrates into the roadbed approaches the cushion layer due to the influence of gravity, and is filtered by the multi-layer permeable geotextile, enters the drain hole, and is then discharged to the outside of the submerged roadbed through the drain pipe; the set drain mechanism is simple, and the multiple drain holes are convenient for drainage at multiple locations inside the roadbed, thereby reducing the damage of the submerged roadbed caused by frost heave.
[0018] Optionally, the hydrophobic mechanism also includes a hydrophobic baffle, which is arranged in the road base layer, the hydrophobic baffle is bent and partially embedded in the cushion layer, a hydrophobic cavity is formed between the hydrophobic baffle and the cushion layer, the hydrophobic pipe is located in the hydrophobic cavity, and the hydrophobic baffle is provided with a plurality of water inlet holes connected to the hydrophobic cavity.
[0019] By adopting the above technical solution, after water penetrates into the roadbed, it approaches the cushion layer due to the influence of gravity, then enters the drain cavity through the water inlet hole, and then is discharged from the roadbed through the drain pipe; the set drain baffle facilitates the temporary storage of water, and at the same time, there is a gap between the formed drain cavity and the drain pipe, so that the water that does not have time to be discharged from the drain pipe can have a little relief space when frost heave occurs, thereby reducing the chance of damage to the roadbed.
[0020] Optionally, the drainage mechanism further includes a seepage pipe, a plurality of the seepage pipes are arranged on the drainage partition, a plurality of seepage holes are opened on the seepage pipe, and the plurality of seepage pipes are staggered and located on one side of the cushion layer close to the roadbed layer.
[0021] By adopting the above technical solution, when pouring the roadbed, the seepage pipe is first buried in the cushion layer, and then the cushion layer is compacted. When pouring the subsequent roadbed layer, the set seepage pipe is convenient for collecting most of the water that penetrates into the bottom layer, further reducing the retention of water in the roadbed and further reducing the damage to the roadbed caused by frost heave.
[0022] Optionally, a stabilizing component is provided on the hydrophobic partition, and the stabilizing component includes a transverse protrusion and a longitudinal protrusion. A plurality of the transverse protrusions and a plurality of the longitudinal protrusions are provided on the hydrophobic partition, and the transverse protrusions are cross-arranged with the longitudinal protrusions.
[0023] By adopting the above technical scheme, when pouring the road base, the hydrophobic baffle is first placed on the cushion layer, and then the hydrophobic baffle is connected to the seepage pipe. Then, when pouring the concrete, the horizontal protrusions and vertical protrusions are set, so that a plurality of block grooves are formed on the base surface of the hydrophobic baffle and the concrete, which facilitates the contact between the concrete and the hydrophobic baffle, thereby increasing the stability of the road base, further reducing the influence of the external environment on the reinforced submerged roadbed, and making the reinforced submerged roadbed not easily damaged.
[0024] In the second aspect, the present application provides a construction method for reinforcing a submerged roadbed, which adopts the following technical solution:
[0025] A construction method for reinforcing a flooded roadbed comprises the following steps: S1, construction preparation, excavation of a construction foundation pit, and checking the flatness of the bottom foundation pit before construction;
[0026] S2. Paving the cushion layer, grade and screen the materials, and lay the coarse stone layer, industrial solid waste solidified soil, anti-seepage geotextile and fine stone layer in the bottom layer of the foundation pit in sequence, and compact them layer by layer;
[0027] S3, drainage installation, installing the drainage mechanism on the fine stone layer and compacting the fine stone layer;
[0028] S4. Pave the road base. Set up a formwork above the fine stone layer and pour the road base. The road base is poured in layers and a permeable geotextile is laid on each layer.
[0029] S5, paving the reinforced layer, set up the steel mesh on the outside of the road base, and then pave the reinforced layer. After the reinforcement layer is paved, apply the surface to form a protective layer;
[0030] S6. Curing and testing: lay felt on the outside of the reinforcement layer and sprinkle water for curing. The curing period is generally not less than 3 days, during which the surface of the felt must be kept moist. After 3 days, test the concrete strength and remove the curing felt.
[0031] By adopting the above technical scheme, when constructing the submerged roadbed, first a foundation pit is dug at the location to be constructed, then the soil layer is compacted with a tamping machine, and then coarse stones are laid in the foundation pit and compacted to form a coarse stone layer, and then industrial solid waste solidified soil, anti-seepage geotextile and fine stone layer are laid in sequence, and each layer is compacted after laying, and then the drainage mechanism is installed in the fine stone layer, and the fine stone layer is compacted again, and then a mold is erected above the fine stone layer, and the roadbed is poured in layers, and a permeable geotextile is laid at the joints of each layer until the roadbed is poured, and then the reinforcement layer is laid, and finally the surface is plastered to make the surface of the reinforced submerged roadbed smooth, reduce the probability of water infiltration, and further reduce the damage to the submerged roadbed; then after the pouring is completed, a curing felt is laid on the surface of the submerged roadbed, and water is sprinkled for curing for 3 days, and the surface of the curing felt is kept moist. When the curing period expires, the concrete strength is tested with testing equipment, and the curing felt is removed after the strength is qualified.
[0032] In summary, this application includes the following beneficial technical effects:
[0033] 1. When constructing the roadbed in a frequently flooded area, first clean the construction area, then lay the cushion layer layer by layer, then install a drainage mechanism on the cushion layer, then cast the roadbed in a mold, and cast the reinforcement layer on the outside of the roadbed; the drainage mechanism is set up to facilitate the drainage of water that has infiltrated the roadbed, thereby reducing the retention of water in the roadbed, and the water is discharged in time. When the seasons change, the impact of frost heave on the roadbed is reduced, thereby reducing damage to the roadbed;
[0034] 2. Add permeable material between the two layers of steel bars to facilitate the rapid flow of water that penetrates into the submerged roadbed to the drainage mechanism. At the same time, it can reduce the damage to the external surface in contact with water during frost heave, thereby reducing damage to the roadbed;
[0035] 3. When pouring the roadbed, first bury the seepage pipe in the cushion layer, then compact the cushion layer, and then pour the subsequent roadbed. The set seepage pipe is convenient for collecting most of the water that penetrates into the bottom layer, further reducing the retention of water in the roadbed and further reducing the damage to the roadbed caused by frost heave;
[0036] 4. When constructing a submerged roadbed, first dig a foundation pit at the location to be constructed, then use a rammer to compact the soil layer, then lay coarse stones in the foundation pit and compact them, then lay industrial solid waste solidified soil, anti-seepage geotextile and fine stone layer in sequence, and compact each layer after laying, then install the drain mechanism in the fine stone layer, compact the fine stone layer again, then erect a mold above the fine stone layer, pour the roadbed layer in layers, and lay a permeable geotextile at the joints of each layer until the roadbed is poured, then lay the reinforcement layer, and finally plaster the surface to make the surface of the reinforced submerged roadbed smooth, reduce the chance of water infiltration, and further reduce damage to the submerged roadbed; then after pouring, lay a curing felt on the surface of the submerged roadbed, sprinkle water for maintenance for 3 days, and keep the surface of the curing felt moist. When the curing period expires, use testing equipment to test the strength of the concrete, and remove the curing felt after the strength is qualified. BRIEF DESCRIPTION OF THE DRAWINGS
[0037] Figure 1 This is a schematic diagram of the cross-sectional structure of the reinforced submerged roadbed in an embodiment of the present application;
[0038] Figure 2 This is a schematic diagram of the structure of the hydrophobic mechanism in the embodiment of the present application;
[0039] Figure 3 This is a schematic diagram of the connection between the permeable geotextile and the grid net in the embodiment of the present application;
[0040] Figure 4 This is a schematic diagram of the structure of the reinforcement layer in the embodiment of the present application;
[0041] Figure 5 This is a flowchart of the construction method for reinforcing a flooded roadbed in an embodiment of the present application.
[0042] : 100, cushion layer; 110, coarse stone layer; 120, industrial solid waste solidified soil; 130, impermeable geotextile; 140, fine stone layer; 200, reinforcement layer; 210, steel mesh; 220, quick and easy closing mold; 300, road base layer; 310, permeable geotextile; 320, grid mesh; 330, anchor hook; 400, drainage mechanism; 410, drainage pipe; 411, drainage hole; 420, drainage partition; 421, water inlet hole; 422, drainage cavity; 430, seepage pipe; 431, seepage hole; 440, stabilizing component; 441, horizontal protrusion; 442, longitudinal protrusion; 450, embedded component; 451, first embedded rod; 452, second embedded rod. DETAILED DESCRIPTION
[0043] The following is combined with Figure 1-5 This application is described in further detail.
[0044] The embodiment of the present application discloses a reinforced submerged roadbed.
[0045] refer to Figure 1 , a reinforced submerged roadbed includes a cushion layer 100, a roadbed layer 300 arranged above the cushion layer 100, a reinforcement layer 200 arranged outside the roadbed layer 300, and a drainage mechanism 400 arranged in the roadbed layer 300 and located at the cushion layer 100. When water penetrates into the reinforced submerged roadbed, it penetrates into the drainage mechanism 400 through multiple layers, and then is discharged from the reinforced submerged roadbed through the drainage mechanism 400, thereby reducing the retention of water in the roadbed and reducing the probability of frost heave of the roadbed.
[0046] refer to Figure 1 A foundation pit is opened at the construction location, and the soil layer in the foundation pit is compacted by a rammer. The cushion layer 100 is a multi-layer structure. Each layer laid in the foundation pit is graded and screened so that the particle size of each layer is similar. The first layer laid in the foundation pit is coarse stone with a laying thickness of 20 cm, and is compacted to form a coarse stone layer 110. Industrial solid waste solidified soil 120 is laid on the upper layer of the coarse stone and is compacted to a thickness of 20 cm. An impermeable geotextile 130 is laid on top of the industrial solid waste solidified soil 120, and then a fine stone layer 140 is laid on top of the impermeable geotextile 130. The thickness of the fine stone layer 140 gradually decreases along the edge of the foundation pit toward the middle, and the thickness at the thickest position is 30 cm, and the thickness at the thinnest position is 20 cm.
[0047] refer to Figure 1 and Figure 2 The hydrophobic mechanism 400 includes a hydrophobic partition 420 fixedly connected to the middle position of the fine stone layer 140, the hydrophobic partition 420 is bent and the vertical cross-section of the hydrophobic partition 420 is semicircular, and the hydrophobic partition 420 is inverted on the fine stone layer 140; a hydrophobic cavity 422 is formed between the hydrophobic partition 420 and the fine stone layer 140, and a plurality of water inlet holes 421 are opened on the outer wall of the hydrophobic partition 420, and the plurality of water inlet holes 421 are arranged at equal intervals along the peripheral side wall of the hydrophobic partition 420 and are evenly distributed along the length direction of the hydrophobic partition 420, and the water inlet holes 421 are connected to the hydrophobic cavity 422; a stable The fixing component 440 includes a plurality of transverse protrusions 441 fixedly connected to the outer wall of the hydrophobic partition 420, the transverse protrusions 441 are arranged at equal intervals along the circumference of the hydrophobic partition 420, and a plurality of longitudinal protrusions 442 are fixedly connected to the hydrophobic partition 420, the longitudinal protrusions 442 are fitted with the hydrophobic partition 420, and are arranged at equal intervals along the length direction of the hydrophobic partition 420, and the transverse protrusions 441 and the longitudinal protrusions 442 are cross-intersected, and the transverse protrusions 441 and the longitudinal protrusions 442 form a plurality of grooves for easy embedding of concrete; at the same time, a permeable geotextile 310 can be laid on the hydrophobic partition 420, and the permeable geotextile 310 is fitted with the grooves.
[0048] refer to Figure 1 and Figure 2 A drain pipe 410 is placed in the middle of the fine stone layer 140. The drain pipe 410 can be fixedly connected to the drain baffle 420. The axis of the drain pipe 410 is parallel to the axis of the drain baffle 420, and the distance from the outer wall of the drain pipe 410 to the inner wall of the drain baffle 420 is the same. The drain pipe 410 is provided with a plurality of drain holes 411 connected to the drain cavity 422. The plurality of drain holes 411 are evenly distributed along the peripheral side wall of the drain pipe 410 and are evenly spaced along the length direction of the drain pipe 410. Both sides of the drain baffle 420 in the width direction are fixedly connected with a plurality of seepage pipes 430. The multiple seepage pipes 430 are staggered and connected with the hydrophobic cavity 422. The end of the seepage pipe 430 away from the hydrophobic partition plate 420 is tilted in the direction away from the coarse stone layer 110, and the axis of the seepage pipe 430 is parallel to the plane where the end surface of the fine stone layer 140 away from the anti-seepage geotextile 130 is located; the seepage pipe 430 is provided with a plurality of seepage holes 431, and the plurality of seepage holes 431 are evenly spaced along the circumference of the seepage pipe 430 and are evenly arranged along the length direction of the seepage pipe 430. The seepage pipe 430 is used to collect moisture that seeps into the cushion layer 100 under the influence of gravity.
[0049] refer to Figure 1 and Figure 2 In order to reduce the position change of the seepage pipe 430 during the compaction process, an embedded component 450 is provided on the seepage pipe 430, and the embedded component 450 includes a plurality of first embedded rods 451 fixedly connected to the seepage pipe 430, and the plurality of first embedded rods 451 are arranged at equal intervals along the length direction of the seepage pipe 430, and the end of the first embedded rod 451 away from the seepage pipe 430 is pointed; a plurality of second embedded rods 452 are fixedly connected to the seepage pipe 430, and the plurality of second embedded rods 452 are arranged at equal intervals along the length direction of the seepage pipe 430, and the end of the second embedded rod 452 away from the seepage pipe 430 is pointed, and the second embedded rods 452 are staggered with the first embedded rods 451, and the first embedded rods 451 and the second embedded rods 452 are both inserted into the fine stone layer 140, and the axis of the first embedded rod 451 and the axis of the second embedded rod 452 are arranged at an acute angle.
[0050] refer to Figure 1 and Figure 3 A road base layer 300 is cast on the fine stone layer 140. The road base layer 300 is cast for multiple times, and a permeable geotextile 310 is laid between the casting joints of each layer. Grid nets 320 are arranged on both sides of the permeable geotextile 310. The grid nets 320 on both sides are connected to the permeable geotextile 310 by binding wires, and the grid nets 320 are alternately arranged in concave and convex directions along the width direction, so that the casting area of the casting joints is increased, which is convenient for the connection between each layer, and makes the road base layer 300 cast in layers more stable.
[0051] refer to Figure 1 and Figure 3 In order to facilitate the connection between the grille net 320 and the road base layer 300, a plurality of anchor hooks 330 are fixedly connected to the side walls of the two grille nets 320 that are away from each other. The anchor hooks 330 can be embedded in the road base layer 300 to play an anchoring role.
[0052] refer to Figure 1 and Figure 4 After the last layer of the roadbed 300 is poured, a plurality of steel bar heads are inserted on the outer side of the roadbed 300, and the steel bar heads extend out of the outermost layer of the roadbed 300. The reinforced layer 200 includes two layers of steel meshes 210 fixedly connected to the side of the plurality of steel bar heads away from the roadbed 300, and a quick and easy closing mold 220 is fixedly connected to the sides of the two layers of steel meshes 210 that are away from each other, wherein the quick and easy closing mold 220 close to the roadbed 300 is embedded in the roadbed 300 or directly used as a template for pouring the last layer of the roadbed 300; the quick and easy closing mold 220 is connected to the steel mesh 210 by binding wire, and a water-permeable material is filled between the two layers of the quick and easy closing mold 220, and the water-permeable material is graded crushed stone. After the water-permeable material is added between the two layers of the steel meshes 210, the steel meshes 210 are struck and vibrated so that the water-permeable material fills the two layers of the quick and easy closing molds 220, and then a wooden board is pressed on the water-permeable material and the wooden board is struck with a heavy object to make the water-permeable material compact.
[0053] The implementation principle of a reinforced submerged roadbed in the embodiment of the present application is as follows: when pouring the reinforced submerged roadbed, first dig a foundation pit at the location to be constructed, then lay the cushion layer 100 in sequence, and when laying the fine stone layer 140, install the seepage pipe 430 and the hydrophobic partition 420 on the fine stone layer 140, and then continue to lay the fine stone layer 140, and compact it so that the first embedded rod 451 and the second embedded rod 452 are completely embedded in the fine stone layer 140, and then pour the roadbed 300 in layers, and then install the permeable geotextile 310 and the grid net 320 at the pouring joint of each layer, and use the grid net 320 to control the permeability. The geotextile 310 forms a concave and convex surface, and is roughened when the lower layer is poured; when the last layer of the roadbed 300 is poured, the quick-and-easy closing mold 220 is used as a template for support, and the steel bar head is inserted into the quick-and-easy closing mold 220. After the pouring is completed, two layers of steel mesh 210 are installed on the steel bar head, and then the permeable material is filled, and the permeable material is compacted by vibration and template compaction. As the permeable material is filled, the outer layer of quick-and-easy closing mold 220 is installed from low to high, and then concrete is poured to complete the construction of the reinforcement layer 200, and then the surface operation is performed to reduce the penetration of moisture into the reinforced submerged roadbed.
[0054] When water penetrates into the reinforced submerged roadbed, the water first passes through the permeable material, then is filtered by the two layers of permeable geotextile 310, enters the fine stone layer 140 of the cushion layer 100 under the influence of gravity, then enters the hydrophobic cavity 422 through the infiltration pipe and the water inlet hole 421, and then is discharged from the reinforced submerged roadbed through the hydrophobic pipe 410.
[0055] When the cold season arrives, there is less moisture in the reinforced submerged roadbed and the chance of frost heave is lower. At the same time, the permeable material installed can allow a small amount of frost heave space.
[0056] The embodiment of the present application also discloses a construction method for reinforcing a submerged roadbed.
[0057] refer to Figure 5 The construction method for reinforcing the flooded roadbed includes the following steps: S1, construction preparation, construction foundation pit excavation, before construction, check the flatness of the bottom foundation pit, and compact it with a compactor, and sprinkle a small amount of water; S2, laying the cushion layer 100, grade and screen the materials, first lay coarse stones on the bottom of the foundation pit to form a coarse stone layer 110 with a thickness of 20 cm, and then compact it; then pour the industrial solid waste solidified soil 120 on the coarse stones, flatten it with a flattening device, and then compact it and lay the anti-seepage geotechnical engineering. The geotextile 130 is then laid on the anti-seepage geotextile 130 and compacted to form a fine stone layer 140, and the particle size of the fine stone is between 5mm and 10mm; S3, hydrophobic installation, the hydrophobic mechanism 400 is installed on the fine stone layer 140, the seepage pipe 430 is first installed, and then the hydrophobic pipe 410 and the hydrophobic partition 420 are first connected into a whole, and then fixedly connected to the seepage pipe 430, and then the fine stone layer 140 is laid, and the middle thickness of the fine stone layer 140 is ensured to be 20c m, the edge thickness of the West Lake layer is 30cm, and gradually changes from the edge to the middle, and the fine stone layer 140 is compacted; S4, the road base layer 300 is paved, a mold is erected above the fine stone layer 140, and the road base layer 300 is cast. The road base layer 300 is cast in layers, and a permeable geotextile 310 is laid on each layer, and fixed with a grid mesh 320 to form a concave and convex bonding surface; S5, the reinforcement layer 200 is paved, two layers of steel mesh 210 are erected on the outside of the road base layer 300, and a quick-recovery The mouth mold 220 forms a receiving cavity, and the receiving cavity is filled with permeable material, and then the permeable material is compacted. After the concrete is poured and the reinforcement layer 200 is paved, the surface is plastered to form protection; S6, curing and testing, laying felt on the outside of the reinforcement layer 200 and sprinkling water for curing. The curing period is generally not less than 3 days, during which the surface of the felt must be kept moist; after 3 days, the concrete strength is tested with concrete strength testing equipment. After the concrete strength meets the design requirements and no cracks occur, the curing felt is removed.
[0058] The implementation principle of a construction method for reinforcing a submerged roadbed in an embodiment of the present application is as follows: first, a foundation pit is excavated, and then after the foundation pit is excavated, a tamping and leveling treatment is performed, and then the cushion layer 100 is laid in sequence and compacted, and then the infiltration pipe, the drain pipe 410 and the drain baffle 420 are installed, and the road base layer 300 is poured, and a part of the reinforcement layer 200 is installed when the last layer of the road base layer 300 is poured, and the steel bar heads of the steel mesh 210 are pre-embedded and fixed. After the pouring is completed, the steel mesh 210 is supported, and then the permeable material is filled, and then the reinforcement layer 200 is poured as a whole, and then the surface is plastered, and after reaching the strength for removing the formwork, maintenance is performed.
[0059] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.
Claims
1. A reinforced submerged roadbed, characterized in that: The invention comprises a cushion layer (100), a reinforcement layer (200), a roadbed (300) and a drainage mechanism (400), wherein the roadbed (300) is laid on the cushion layer (100), a steel mesh (210) is added on the outer side of the roadbed (300) to form the reinforcement layer (200) to protect the roadbed, and a plurality of drainage mechanisms (400) are arranged in the roadbed (300), and the drainage mechanisms (400) are used to transport moisture at the cushion layer (100) to the outer side of the roadbed (300); The road base layer (300) is provided with multiple layers of permeable geotextile (310), and the cushion layer (100) is provided with an impermeable geotextile (130); The drainage mechanism (400) comprises a drainage pipe (410), the drainage pipe (410) being arranged in the roadbed layer (300) and being located inside the innermost permeable geotextile (310), the drainage pipe (410) being connected to the outside of the roadbed layer (300) for drainage, and a plurality of drainage holes (411) being provided on the outer wall of the drainage pipe (410); The hydrophobic mechanism (400) further comprises a hydrophobic baffle (420), the hydrophobic baffle (420) being arranged in the roadbed layer (300), the hydrophobic baffle (420) being arranged in a curved manner and partially embedded in the cushion layer (100), a hydrophobic cavity (422) being formed between the hydrophobic baffle (420) and the cushion layer (100), the hydrophobic pipe (410) being located in the hydrophobic cavity (422), and a plurality of water inlet holes (421) being provided on the hydrophobic baffle (420) and being in communication with the hydrophobic cavity (422).
2. A reinforced submerged roadbed according to claim 1, characterized in that: Grid nets (320) are provided on both sides of each layer of the permeable geotextile (310); the grid nets (320) are connected to the permeable geotextile (310) via binding wires; and a plurality of anchor hooks (330) are provided on the sides of the grid nets (320) facing away from each other.
3. A reinforced submerged roadbed according to claim 2, characterized in that: The contact surface between the permeable geotextile (310) and the roadbed (300) forms a concave and convex end surface through the grid mesh (320).
4. A reinforced submerged roadbed according to claim 1, characterized in that: The reinforcement layer (200) is provided with two layers, and a quick closing mold (220) is provided on the sides of the two reinforcement layers (200) facing away from each other, and a water-permeable material is filled between the two reinforcement layers (200).
5. The reinforced submerged roadbed according to claim 1, characterized in that: The hydrophobic mechanism (400) further comprises a seepage pipe (430), a plurality of the seepage pipes (430) being arranged on the hydrophobic partition plate (420), a plurality of seepage holes (431) being opened on the seepage pipe (430), and the plurality of seepage pipes (430) being arranged in a staggered manner and located on a side of the cushion layer (100) close to the roadbed layer (300).
6. The reinforced submerged roadbed according to claim 1, characterized in that: The hydrophobic partition (420) is provided with a stabilizing component (440), the stabilizing component (440) comprising a transverse protrusion (441) and a longitudinal protrusion (442), a plurality of the transverse protrusions (441) and a plurality of the longitudinal protrusions (442) are provided on the hydrophobic partition (420), and the transverse protrusions (441) and the longitudinal protrusions (442) are arranged crosswise.
7. A construction method for reinforcing a submerged roadbed as claimed in any one of claims 2 to 6, characterized in that: The following steps are involved: S1. Construction preparation, excavation of the construction pit, and checking the flatness of the bottom foundation pit before construction; S2, laying the cushion layer (100), screening the materials by grade, laying a coarse stone layer (110), industrial solid waste solidified soil (120), an anti-seepage geotextile (130) and a fine stone layer (140) in sequence on the bottom layer of the foundation pit, and compacting them layer by layer; S3, drainage installation, installing the drainage mechanism (400) on the fine stone layer (140), and compacting the fine stone layer (140); S4, laying the road base layer (300), erecting a mold above the fine stone layer (140), pouring the road base layer (300), pouring the road base layer (300) in layers, and laying a permeable geotextile (310) on each layer; S5, paving the reinforcement layer (200), setting up a steel mesh (210) on the outside of the road base (300), and then paving the reinforcement layer (200), and after the reinforcement layer (200) is paved, plastering is performed to form a protective surface; S6. Curing and testing: lay felt on the outside of the reinforcement layer (200) and sprinkle water for curing. The curing period is generally not less than 3 days, during which the surface of the felt must be kept moist. After 3 days, test the concrete strength and remove the curing felt.