A method, device and medium for controlling power grid frequency
Through the coordinated double-feed wind turbine cutting and load reduction control, combined with the power grid frequency control model, the problem of grid frequency control caused by high-frequency cutter of wind farms is solved, and the control accuracy and emergency power control capabilities of the power system are improved. Overcut phenomenon is avoided and high frequency problems are suppressed.
Patent Information
- Application Number
- CN202310403481.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-04-14
- Publication Date
- 2024-11-05
- Estimated Expiration
- 2043-04-14
AI Technical Summary
Under the high proportion of installation of wind farms, the power grid is prone to overpower when the transmission channel is interrupted, resulting in an increase in generator speed and high-frequency problems in the system. The existing technology cutter control particle size is large, which is prone to overcut or undercutting. , unable to effectively deal with high-frequency states, and the wind turbine lacks inertia response, so it is impossible to automatically adjust the power output.
Through the coordinated double-feed wind turbine cutting and load reduction control, the grid frequency control strategy is determined, based on the grid frequency control model, combined with wind turbine load reduction and synchronous machine cutting control, avoid frequency exceeding the limit, improve control accuracy, and reduce overtime The cutting phenomenon is maintained and some wind turbines are retained for load reduction control to jointly suppress high-frequency problems.
It improves the accuracy of grid frequency control and emergency power control capabilities, avoids over-shut, ensures that the system can recover stably under high-frequency conditions, and enhances the dynamic balance capability of the power system.
Smart Images

Figure CN116436034B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of new energy power systems, and in particular to a power grid frequency control method, device and medium. Background Art
[0002] As the proportion of wind power installed capacity gradually increases, wind farms use ultra-high voltage AC and DC transmission channels for centralized transmission. When the transmission channel is interrupted for some reason, the power grid with a high proportion of wind power at the sending end is prone to power surplus, making the electromagnetic torque of the generator higher than the mechanical torque, which in turn causes the generator speed to increase, resulting in high-frequency problems in the system.
[0003] Generator shedding is the most direct emergency frequency control method for high-frequency system state, but generator shedding is based on generator sets, and the power regulation granularity is large, which is prone to over-cutting or under-cutting, causing the system's low-frequency load shedding to malfunction or fail to recover from high frequency to normal operation. High-frequency generator shedding combined with wind turbine power regulation can maximize the dynamic balance of system power. Wind turbines do not have inertia response and cannot automatically adjust power output according to frequency changes. Load shedding control can better cope with high-frequency system problems by controlling and changing the operating point of wind turbines and reducing the output of active power to a large extent, but it will waste the standby of synchronous units and cause a second high frequency of the system during speed recovery.
[0004] Therefore, how to improve the power grid frequency control capability based on the coordination of load shedding control and machine cutting of wind turbines is an urgent problem to be solved by those skilled in the art. Summary of the invention
[0005] The purpose of the present invention is to provide a power grid frequency control method, device and medium. By coordinating the cutting and load reduction control of doubly-fed wind turbines, some wind turbines are "controlled instead of cut". Compared with the prior art that avoids frequency over-limit by cutting off synchronous generators, the present invention can improve the control accuracy and effectively avoid over-cutting. While cutting the high-frequency machine, some doubly-fed wind turbines are retained for load reduction control, jointly suppressing high-frequency problems and improving the emergency power control capability of the power system.
[0006] In order to solve the above technical problems, the present invention provides a power grid frequency control method, comprising:
[0007] When the current frequency of the power grid system reaches a preset requirement, obtaining power parameters of the double-fed wind turbine of the power grid system;
[0008] Determine the excess power of the power grid according to the current frequency, and determine the critical parameter of the load-shedding power of the doubly-fed wind turbine generator set according to the power parameter;
[0009] Determine a corresponding power grid frequency control strategy according to the relationship between the current frequency and the critical parameter of the load-shedding power, wherein the power grid frequency control strategy is determined based on a power grid frequency control model, including a wind turbine load shedding control strategy and a synchronous machine cutting control strategy;
[0010] The frequency of the power grid system is controlled according to the corresponding power grid frequency control strategy.
[0011] Preferably, the preset requirement is that the duration of the current frequency exceeds the duration of the frequency anomaly, and the process of determining whether the current frequency of the power grid system reaches the preset requirement includes:
[0012] Obtaining the duration of the current frequency and the frequency anomaly duration in the system frequency safety binary table;
[0013] When the duration exceeds the frequency abnormality duration, it is determined that the current frequency meets the preset requirement.
[0014] Preferably, determining the excess power of the power grid according to the current frequency includes:
[0015] Obtaining a single-mass block equivalent inertia time constant of the doubly-fed wind generator and a rated operating power parameter of the power grid system;
[0016] The excess power of the power grid is determined according to the relationship between the current frequency, the single mass block equivalent inertia time constant and the rated operating power parameter.
[0017] Preferably, determining the load-shedding power critical parameter of the doubly-fed wind turbine generator set according to the power parameter includes:
[0018] Obtaining critical power parameters of load shedding and active power parameters of an optimal operating point of the doubly-fed wind turbine generator set;
[0019] Determining the load-shedding power critical parameter according to the relationship between the power critical parameter and the active power parameter of the optimal operating point;
[0020] The process of determining the power critical parameter includes:
[0021] Obtaining a pitch speed and a load reduction time of a wind turbine of the doubly-fed wind turbine generator system;
[0022] Determining a pitch angle adjustment threshold value of the wind turbine according to a relationship between the pitch speed and the load reduction time;
[0023] Acquire a first wind energy utilization coefficient of the doubly-fed wind generator, a blade radius of the wind turbine, and a current wind speed, wherein the first wind energy utilization coefficient is determined by selecting a maximum speed value from speed values corresponding to each rotor of the doubly-fed wind generator set;
[0024] Determining the power critical parameter according to the relationship between the first wind energy utilization coefficient, the blade radius, the current wind speed and the pitch angle adjustment critical value;
[0025] The process of determining the active power parameter of the optimal operating point includes:
[0026] Obtaining a second wind energy utilization coefficient of the doubly-fed wind generator, wherein the second wind energy utilization coefficient is determined by selecting an optimal speed value from speed values corresponding to each rotor of the doubly-fed wind generator set;
[0027] The active power parameter is determined according to the relationship between the second wind energy utilization coefficient, the blade radius and the current wind speed.
[0028] Preferably, the determining of the corresponding grid frequency control strategy according to the relationship between the current frequency and the load-shedding power critical parameter includes:
[0029] Obtaining the number of removed double-fed wind turbines and corresponding operating power parameters, and a response coefficient of the frequency of the power grid system to a frequency change of the double-fed wind turbine group;
[0030] Determine the frequency allowable operating range of the power grid system according to the load shedding power critical parameter, the number of units removed, the corresponding operating power parameter and the response coefficient;
[0031] Determine whether the current frequency is within the frequency allowable operating range;
[0032] If yes, determining that the grid frequency control strategy is the wind turbine load reduction control strategy;
[0033] If not, it is determined that the power grid frequency control strategy is the synchronous machine switching control strategy.
[0034] Preferably, the process of establishing the power grid frequency control model includes:
[0035] Obtaining a transient frequency critical value, a low-frequency load reduction action threshold value, an OPC action threshold value, a frequency deviation critical value, a total active load value of the power grid system, and a wind farm change amplitude limit value;
[0036] The condition that the minimum value of the transient frequency critical value is greater than the low-frequency load reduction action threshold value is used as the first constraint condition;
[0037] The condition that the maximum value of the transient frequency critical value is less than or equal to the OPC action threshold value is used as the second constraint condition;
[0038] The condition that the deviation value of the current frequency is less than or equal to the maximum value of the frequency deviation critical value is used as a third constraint condition;
[0039] The condition that the total active load value of the power grid system is greater than or equal to the frequency regulation confidence level value of the power grid system is used as a fourth constraint condition;
[0040] The condition that the wind farm change amplitude limit value is greater than or equal to the operating power threshold of the power grid system is used as the fifth constraint condition;
[0041] The grid frequency control model is established according to the relationship among the first constraint condition, the second constraint condition, the third constraint condition, the fourth constraint condition and the fifth constraint condition.
[0042] Preferably, the process of determining the wind turbine load reduction control strategy includes:
[0043] Determine the active power of the doubly-fed wind turbine generator set participating in the power shedding control, the power variation range of the doubly-fed wind turbine generator set participating in the load shedding control, and the active power reduction of the synchronous machine in the power grid system according to the constraints of the power grid frequency control model;
[0044] A first grid frequency target function is obtained by minimizing the active power of the doubly-fed wind turbine generator set participating in the machine shedding, the power variation range of the doubly-fed wind turbine generator set participating in the load shedding control, and the reduced active power of the synchronous machine;
[0045] A first system cost objective function is obtained by performing minimization processing according to the active power of the doubly-fed wind turbine generator set participating in the machine shedding and the power variation range of the doubly-fed wind turbine generator set participating in the load shedding control;
[0046] Determine the wind turbine load shedding control strategy according to the result of the first grid frequency objective function and the first system cost objective function;
[0047] Correspondingly, the process of determining the synchronous machine cutting control strategy includes:
[0048] Determining the active power of the doubly-fed wind turbine generator set participating in the power switching, the active power of the synchronous machine participating in the power switching, and the reduced active power of the synchronous machine in the power grid system according to the constraint conditions of the power grid frequency control model;
[0049] A second grid frequency objective function is obtained by minimizing the active power of the doubly-fed wind turbine generator set participating in the power switching, the active power of the synchronous machine participating in the power switching, and the reduced active power of the synchronous machine;
[0050] A second system cost objective function is obtained by minimizing the active power of the doubly-fed wind turbine generator set participating in the power switching and the active power of the synchronous machine participating in the power switching;
[0051] The synchronous machine switching control strategy is determined according to the result of the second power grid frequency objective function and the second system cost objective function.
[0052] Preferably, the optimization of the active power of the doubly-fed wind turbine generator set participating in the machine switching and the power variation range of the doubly-fed wind turbine generator set participating in the load shedding control in the corresponding objective function in the grid frequency control strategy is obtained by an ant colony algorithm.
[0053] In order to solve the above technical problems, the present invention further provides a power grid frequency control device, comprising:
[0054] An acquisition module, used for acquiring power parameters of a double-fed wind turbine of the power grid system when the current frequency of the power grid system reaches a preset requirement;
[0055] A first determination module is used to determine the excess power of the power grid according to the current frequency, and to determine the load-shedding power critical parameter of the doubly-fed wind turbine generator set according to the power parameter;
[0056] A second determination module is used to determine a corresponding power grid frequency control strategy according to the relationship between the current frequency and the critical parameter of the load-shedding power, wherein the power grid frequency control strategy is determined based on a power grid frequency control model, including a wind turbine load shedding control strategy and a synchronous machine cutting control strategy;
[0057] A control module is used to control the frequency of the power grid system according to the corresponding power grid frequency control strategy.
[0058] In order to solve the above technical problems, the present invention further provides a power grid frequency control device, comprising:
[0059] Memory for storing computer programs;
[0060] A processor is used to implement the steps of the power grid frequency control method as described above when executing the computer program.
[0061] In order to solve the above technical problems, the present invention also provides a computer-readable storage medium, on which a computer program is stored. When the computer program is executed by a processor, the steps of the power grid frequency control method as described above are implemented.
[0062] The present invention provides a power grid frequency control method, including: when the current frequency of the power grid system reaches the preset requirements, obtaining the power parameters of the doubly-fed wind turbine of the power grid system; determining the excess power of the power grid according to the current frequency, and determining the load-reducible power critical parameters of the doubly-fed wind turbine according to the power parameters; determining the corresponding power grid frequency control strategy according to the relationship between the current frequency and the load-reducible power critical parameters, wherein the power grid frequency control strategy is determined based on the power grid frequency control model, including the wind turbine load reduction control strategy and the synchronous machine cutting control strategy; and performing frequency control on the power grid system according to the corresponding power grid frequency control strategy. The method performs the power grid frequency control strategy when the preset requirements are met, determines the corresponding power grid frequency control strategy according to the relationship between the current frequency and the load-reducible power critical parameters, and "controls instead of cuts" some wind turbines by coordinating the cutting and load reduction control of the doubly-fed wind turbine. Compared with the prior art that avoids frequency over-limit by cutting the synchronous generator, the present invention can improve the accuracy of control and effectively avoid the over-cut phenomenon. While cutting the high-frequency machine, some doubly-fed wind turbines are retained for load reduction control, and the high-frequency problem is jointly suppressed, thereby improving the emergency power control capability of the power system.
[0063] In addition, the present invention also provides a power grid frequency control device and medium, which have the same beneficial effects as the above-mentioned power grid frequency control method. BRIEF DESCRIPTION OF THE DRAWINGS
[0064] In order to more clearly illustrate the embodiments of the present invention, the following briefly introduces the drawings required for use in the embodiments. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0065] Figure 1 A flow chart of a power grid frequency control method provided by an embodiment of the present invention;
[0066] Figure 2 A structural diagram of a power grid frequency control device provided by an embodiment of the present invention;
[0067] Figure 3 A structural diagram of another power grid frequency control device provided by an embodiment of the present invention;
[0068] Figure 4 A schematic diagram of a calculation example system provided by an embodiment of the present invention;
[0069] Figure 5 A schematic diagram of system frequency during a 280MW disturbance provided by an embodiment of the present invention;
[0070] Figure 6A schematic diagram of a system frequency when the rotation speed recovery constraint is not considered provided by an embodiment of the present invention;
[0071] Figure 7 A schematic diagram of system frequency during a 600MW disturbance provided by an embodiment of the present invention;
[0072] Figure 8 A flow chart of another power grid frequency control method provided by an embodiment of the present invention. DETAILED DESCRIPTION
[0073] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0074] The core of the present invention is to provide a grid frequency control method, device and medium. By coordinating the cutting and load reduction control of the doubly-fed wind turbine, some wind turbines are "controlled instead of cut". Compared with the prior art that avoids frequency over-limit by cutting off the synchronous generator, the present invention can improve the control accuracy and effectively avoid over-cutting. While cutting the high-frequency machine, some doubly-fed wind turbines are retained for load reduction control, jointly suppressing high-frequency problems and improving the emergency power control capability of the power system.
[0075] In order to enable those skilled in the art to better understand the solution of the present invention, the present invention is further described in detail below in conjunction with the accompanying drawings and specific implementation methods.
[0076] It should be noted that, under emergency conditions of a high-proportion wind power system, how to use wind turbines to maintain the dynamic stability of system power has become a key issue for the further development and utilization of wind power. Removing generators can alleviate the system's excess power, suppress the rapid rise in frequency, and maintain the frequency stability of the sending-end system. Removing conventional units according to the above-mentioned machine-cutting scheme will reduce the system inertia level, resulting in a further decline in the system's frequency support capacity. However, the prior art ignores the mutual influence between the load-shedding control and machine-cutting of wind turbines, which not only affects the frequency control effect, but may also limit the subsequent frequency response capability of the system. The grid frequency control method provided by the present invention can take into account the coordination of the load-shedding control and machine-cutting of wind turbines.
[0077] Figure 1 A flow chart of a power grid frequency control method provided by an embodiment of the present invention, such as Figure 1 As shown, the method includes:
[0078] S11: When the current frequency of the power grid system reaches a preset requirement, obtaining power parameters of the double-fed wind turbine of the power grid system;
[0079] S12: determining the excess power of the power grid according to the current frequency, and determining the critical parameter of the load-shedding power of the doubly-fed wind turbine generator according to the power parameter;
[0080] S13: Determine a corresponding grid frequency control strategy according to the relationship between the current frequency and the critical parameter of the load-shedding power;
[0081] Among them, the grid frequency control strategy is determined based on the grid frequency control model, including wind turbine load reduction control strategy and synchronous machine cutting control strategy;
[0082] S14: Controlling the frequency of the power grid system according to the corresponding power grid frequency control strategy.
[0083] It is understandable that when the current frequency of the power grid system reaches the preset requirement, the power grid frequency control mechanism is started, that is, the subsequent steps S12-S14. There is no limitation on what preset requirement is met, as long as it is a condition that triggers the power grid frequency control mechanism. As an embodiment, the preset requirement is that the duration of the current frequency exceeds the duration of the frequency abnormality. The process of determining whether the current frequency of the power grid system reaches the preset requirement includes:
[0084] Obtain the duration of the current frequency and the duration of frequency anomaly in the system frequency safety binary table;
[0085] When the duration exceeds the frequency abnormality duration, it is determined that the current frequency meets the preset requirement.
[0086] Specifically, the power grid frequency safety binary table information is obtained, and when the duration of the real-time frequency of the power grid exceeds the abnormal duration corresponding to the threshold value in the frequency safety binary table, it is determined that the current frequency meets the preset requirements. In addition, the setting of the preset requirements can correspond to multiple requirements, which are not limited here. The more preset requirements, the higher the accuracy of starting the power grid frequency control mechanism.
[0087] The frequency safety binary table is used to describe the system's acceptability to frequency deviation, including (frequency drop threshold value f cr.1 , allowable frequency abnormality duration T1), (f cr.2 , T2) etc.
[0088] When the current frequency reaches the preset requirement, the power parameters of the double-fed wind turbine in the power grid system are obtained. The power parameters include not only one parameter, but also a general term for various parameters related to power, including power critical parameters and active power parameters.
[0089] Obtaining the current excess power of the power grid. As an embodiment, determining the excess power of the power grid according to the current frequency includes:
[0090] Obtain the single-mass equivalent inertia time constant of the doubly-fed wind turbine and the rated operating power parameters of the power grid system;
[0091] The excess power of the power grid is determined based on the relationship between the current frequency, the equivalent inertia time constant of the single mass block and the rated operating power parameters.
[0092] Specifically, the formula for determining the grid process power is as follows:
[0093]
[0094] Among them, f is the real-time operating frequency of the doubly-fed wind turbine, that is, the current frequency, H w is the equivalent inertia time constant of the single mass block of the doubly fed wind turbine, f N It is the rated operating power parameter of the power grid system.
[0095] The load shedding power critical parameter of the doubly-fed wind turbine generator set is determined according to the power parameter. The critical parameter in this embodiment is the maximum load shedding power critical parameter, which is the maximum active output that can be reduced by the doubly-fed wind turbine generator set through pitch angle control and overspeed control. As an embodiment, the load shedding power critical parameter of the doubly-fed wind turbine generator set is determined according to the power parameter, including:
[0096] Obtain the power critical parameters of load shedding of the doubly-fed wind turbine generator and the active power parameters of the optimal operating point;
[0097] Determine the load shedding power critical parameter according to the relationship between the power critical parameter and the active power parameter of the optimal operating point;
[0098] The process of determining the power critical parameters includes:
[0099] Obtain the pitch speed and load reduction time of the wind turbine of the doubly-fed wind turbine generator system;
[0100] Determine a critical value for adjusting the pitch angle of the wind turbine according to the relationship between the pitch speed and the load reduction time;
[0101] Obtaining a first wind energy utilization coefficient of a doubly-fed wind generator, a blade radius of the wind turbine, and a current wind speed, wherein the first wind energy utilization coefficient is determined by selecting a maximum speed value from speed values corresponding to each rotor of the doubly-fed wind generator set;
[0102] Determine a power critical parameter according to a relationship between a first wind energy utilization coefficient, a blade radius, a current wind speed, and a pitch angle adjustment critical value;
[0103] The process of determining the active power parameters of the optimal operating point includes:
[0104] Obtaining a second wind energy utilization coefficient of the doubly-fed wind turbine, wherein the second wind energy utilization coefficient is determined by selecting an optimal speed value from speed values corresponding to each rotor of the doubly-fed wind turbine set;
[0105] The active power parameter is determined according to the relationship between the second wind energy utilization coefficient, the blade radius and the current wind speed.
[0106] Specifically, the function for determining the critical parameter of the load-shedding power is as follows:
[0107] ΔP W.c.max =P g.opt -P de.max
[0108] Among them, P de.max is the power critical parameter, P g.opt is the active power parameter of the optimal operating point.
[0109] Correspondingly, the function of determining the power critical parameters is as follows:
[0110]
[0111] Wherein, R is the blade radius of the wind turbine, ρ is the air density, vw is the current wind speed, and Cp() is the first wind energy utilization coefficient, which is determined by selecting the maximum speed from the speed values corresponding to each rotor. ω max is the maximum speed value, β max The maximum adjustment amount for the pitch angle adjustment threshold.
[0112] The determination function of the maximum adjustment amount corresponding to the critical value of pitch angle adjustment is:
[0113] β max =v β ·t ref
[0114] Among them, v β is the pitch speed, t ref The load shedding time of the doubly-fed wind turbine generator set is determined by the grid operation requirements.
[0115] Correspondingly, the function corresponding to the determination process of the active power parameters of the optimal operating point is as follows:
[0116]
[0117] Among them, ω g.opt is the optimal speed value among the speed values corresponding to each rotor. Cp() in this embodiment is the second wind energy utilization coefficient.
[0118] There is no limitation on determining the optimal speed value, and the optimal speed value may be found based on a certain algorithm or model.
[0119] The corresponding grid frequency control strategy is determined based on the relationship between the current frequency and the critical parameters of the load-shedding power, that is, it is determined whether the grid frequency can be restored to the normal allowable operating range by cutting off the wind turbine and reducing the load. The grid emergency frequency optimization control model is established for the two situations respectively, and the emergency frequency optimization control scheme is determined and implemented by solving the grid emergency frequency optimization control model.
[0120] As an embodiment, determining a corresponding power grid frequency control strategy according to a relationship between a current frequency and a critical parameter of load-shedding power includes:
[0121] Obtain the number of doubly-fed wind turbines removed and the corresponding operating power parameters, and the response coefficient of the frequency of the power grid system to the frequency change of the doubly-fed wind turbines;
[0122] Determine the frequency allowable operating range of the power grid system based on the critical parameters of load shedding power, the number of units removed, and the corresponding operating power parameters and response factors;
[0123] Determine whether the current frequency is within the allowable operating range;
[0124] If yes, then the grid frequency control strategy is determined to be a wind turbine load reduction control strategy;
[0125] If not, the grid frequency control strategy is determined to be the synchronous machine switching control strategy.
[0126] Specifically, the function of the frequency allowed operating range is as follows:
[0127]
[0128] Among them, ΔP W.c.max.j is the critical parameter of load shedding power, i.e., the maximum load shedding power parameter of the jth doubly-fed wind turbine generator system participating in load shedding operation, n w is the number of double-fed wind turbines removed, P W.trip.i is the operating power parameter of the i-th double-fed wind turbine generator set removed, K W is the response coefficient of system frequency to the power change of doubly-fed wind turbine generator set.
[0129] By judging whether the current frequency is within the allowable operating range, the corresponding control strategy can be determined for the two situations. If it is within the range, the synchronous machine cutting is avoided, which is the wind turbine load reduction control strategy. Otherwise, the synchronous machine cutting control strategy is used.
[0130] In addition, the grid frequency control strategy is determined based on the grid frequency control model, which requires constraints and optimized parameters to facilitate subsequent control strategies to perform frequency control.
[0131] A power grid frequency control method provided by an embodiment of the present invention includes: when the current frequency of the power grid system reaches a preset requirement, obtaining the power parameters of the doubly-fed wind turbine of the power grid system; determining the excess power of the power grid according to the current frequency, and determining the critical parameters of the load-reducible power of the doubly-fed wind turbine according to the power parameters; determining the corresponding power grid frequency control strategy according to the relationship between the current frequency and the critical parameters of the load-reducible power, wherein the power grid frequency control strategy is determined based on the power grid frequency control model, including the wind turbine load reduction control strategy and the synchronous machine cutting control strategy; and performing frequency control on the power grid system according to the corresponding power grid frequency control strategy. The method performs the power grid frequency control strategy when the preset requirements are met, determines the corresponding power grid frequency control strategy according to the relationship between the current frequency and the critical parameters of the load-reducible power, and "controls instead of cuts" some wind turbines by coordinating the cutting and load reduction control of the doubly-fed wind turbine. Compared with the prior art of avoiding frequency over-limit by cutting the synchronous generator, the present invention can improve the accuracy of control and effectively avoid the over-cut phenomenon. While cutting the high-frequency machine, some doubly-fed wind turbines are retained for load reduction control, and the high-frequency problem is jointly suppressed, thereby improving the emergency power control capability of the power system.
[0132] Based on the above embodiment, the process of establishing the power grid frequency control model includes:
[0133] Obtain the transient frequency critical value of the power grid system, the low-frequency load reduction action threshold value, the OPC action threshold value, the frequency deviation critical value, the total active load value of the power grid system and the wind farm change amplitude limit value;
[0134] The condition that the minimum value of the transient frequency critical value is greater than the low-frequency load reduction action threshold value is used as the first constraint condition;
[0135] The condition that the maximum value of the transient frequency critical value is less than or equal to the OPC action threshold value is used as the second constraint condition;
[0136] The condition that the current frequency deviation value is less than or equal to the maximum value of the frequency deviation critical value is used as the third constraint condition;
[0137] The condition that the total active load value of the power grid system is greater than or equal to the frequency regulation confidence level value of the power grid system is used as the fourth constraint condition;
[0138] The condition that the wind farm change amplitude limit value is greater than or equal to the operating power threshold of the power grid system is used as the fifth constraint condition;
[0139] A power grid frequency control model is established according to the relationship among the first constraint condition, the second constraint condition, the third constraint condition, the fourth constraint condition and the fifth constraint condition.
[0140] It can be understood that the model is established through constraints, and the objective function is obtained in the constraint parameters of the constraints.
[0141] The first constraint condition (the minimum transient frequency of the system does not cause low-frequency load reduction action) is as follows:
[0142] f min >f UFLS
[0143] Among them, f min is the minimum transient frequency of the system, f UFLS It is the system low-frequency load reduction action threshold.
[0144] The second constraint condition (the maximum transient frequency of the system does not cause the overspeed protection control unit (OPC) to operate) is as follows:
[0145] f max ≤f OPC
[0146] Among them, f max is the maximum transient frequency of the system, f OPC It is the system OPC action threshold.
[0147] The third constraint condition (during the recovery of wind turbine speed and synchronous machine output, the grid system frequency deviation should not exceed the maximum frequency deviation), the formula is as follows:
[0148]
[0149] Among them, n w is the number of double-fed wind turbines removed, KW is the response coefficient of system frequency to the power change of double-fed wind turbines, P W.g.j is the active power output of the jth wind turbine after the speed is restored, which is P de.max , that is, the power critical parameter, K S.k is the frequency response coefficient of the kth synchronization station,
[0150]
[0151] The fourth constraint (system active power balance) formula is as follows:
[0152] P{P L =P W +P S}≥α
[0153] Among them, P L is the total active load value of the system, P W is the power of wind turbines running during frequency modulation, P S is the power of the synchronous units operating during the frequency regulation process, α is the confidence level during the system frequency regulation process, and P is the probability that the load power in the system is balanced with the active output of the generator.
[0154] The fifth constraint condition (the wind farm power variation range limit should not be less than the threshold operating power), for example, the threshold is 10%, and its formula is as follows:
[0155] ΔP W.c.j ≥0.1P g.opt
[0156] Among them, ΔP W.c.j is the wind farm change range limit value, P g.opt is the operating power of the power grid system.
[0157] The grid frequency control model is constructed based on the above five constraints.
[0158] Based on the above embodiment, the process of determining the wind turbine load reduction control strategy includes:
[0159] According to the constraints of the grid frequency control model, the active power of the doubly-fed wind turbines participating in the power shedding, the power variation range of the doubly-fed wind turbines participating in the load shedding control, and the reduced active power of the synchronous machine are determined in the grid system;
[0160] A first grid frequency objective function is obtained by minimizing the active power of the doubly-fed wind turbine generator sets participating in the machine shedding, the power variation range of the doubly-fed wind turbine generator sets participating in the load shedding control, and the reduced active power of the synchronous machine;
[0161] A first system cost objective function is obtained by minimizing the active power of the doubly-fed wind turbine generator sets participating in the machine shedding and the power variation range of the doubly-fed wind turbine generator sets participating in the load shedding control;
[0162] Determine a wind turbine load reduction control strategy according to the results of the first grid frequency objective function and the first system cost objective function;
[0163] Correspondingly, the process of determining the synchronous machine cutting control strategy includes:
[0164] According to the constraints of the power grid frequency control model, the active power of the doubly-fed wind turbine units participating in the power cut, the active power of the synchronous machines participating in the power cut and the reduced active power of the synchronous machines in the power grid system are determined;
[0165] The second grid frequency objective function is obtained by minimizing the active power of the doubly-fed wind turbines involved in the power switching, the active power of the synchronous machines involved in the power switching, and the reduced active power of the synchronous machines;
[0166] The second system cost objective function is obtained by minimizing the active power of the doubly-fed wind turbine generator set and the active power of the synchronous machine involved in the cutting of the machine.
[0167] The synchronous machine switching control strategy is determined according to the results of the second grid frequency objective function and the second system cost objective function.
[0168] Specifically, the first grid frequency objective function is as follows:
[0169]
[0170] Among them, K W is the response coefficient of system frequency to the power change of doubly-fed wind turbine generator set, P W.trip.i is the active power of the doubly-fed wind turbine generator set participating in the power cut, that is, the active power of the i-th doubly-fed wind turbine generator set that is cut, n w is the number of double-fed wind turbines removed, n is the number of synchronous machines participating in frequency control, ΔP W.c.j is the power variation range of the doubly-fed wind turbines participating in load shedding control, that is, the power variation range of the j-th wind turbine participating in load shedding control, K S.k is the frequency response coefficient of the kth synchronization station, ΔP S.k is the kth synchronous machine participating in the control, K L is the frequency characteristic coefficient of compliance, ΔP L is the load power change.
[0171] The first system cost objective function is as follows:
[0172]
[0173] Among them, n w is the number of double-fed wind turbines removed, d W.trip.i represents the penalty coefficient for the i-th wind turbine to be removed, d W.c.j is the load reduction penalty coefficient of the jth wind turbine participating in load reduction control, P W.trip.i is the active power of the doubly-fed wind turbines participating in the power cut, that is, the active power of the i-th doubly-fed wind turbine that is cut, ΔP W.c.j is the power variation range of the doubly-fed wind turbine generator set participating in load shedding control, that is, the power variation range of the j-th wind turbine generator set participating in load shedding control.
[0174] Correspondingly, the second grid frequency objective function is as follows:
[0175]
[0176] Among them, K W is the response coefficient of system frequency to the power change of doubly-fed wind turbine generator set, P W.trip.i is the active power of the doubly-fed wind turbine generator set participating in the power cut, that is, the active power of the i-th doubly-fed wind turbine generator set that is cut, n s is the number of synchronous machines removed, K S.m is the frequency response coefficient of the mth synchronous machine, P S.m is the rated operating power of the mth synchronous machine, K S.k is the frequency response coefficient of the kth synchronization station, ΔP S.k is the kth synchronous machine participating in the control, K L is the frequency characteristic coefficient of compliance, ΔP L is the load power change.
[0177] The second system cost objective function is as follows:
[0178]
[0179] Among them, n S is the number of synchronous machines removed, d W.trip.i represents the penalty coefficient for the i-th wind turbine to be removed, d S.m is the penalty coefficient for the mth synchronous machine removed, P S.m is the rated operating power of the mth synchronous machine.
[0180] On the basis of the above embodiments, the optimization of the active power of the doubly-fed wind turbines participating in the machine switching and the power variation range of the doubly-fed wind turbines participating in the load shedding control in the corresponding objective function in the grid frequency control strategy is obtained by an ant colony algorithm.
[0181] Specifically, the parameters of the optimization model are obtained based on the ant colony algorithm, and the specific steps are as follows:
[0182] 1. Initialize various parameters, set the number of ants m, pheromone concentration τ, pheromone volatility factor ρ, maximum number of iterations t, etc. in the ant colony algorithm;
[0183] 2. Construct the solution space, place ants at different starting nodes, and use the roulette method to select the target node to be reached;
[0184] 3. After the ant reaches the target node, it obtains the optimal path for the iteration and updates the pheromone;
[0185] 4. Repeat steps 2 and 3 until the number of iterations reaches the preset maximum number of iterations to obtain the optimal path.
[0186] In step 2, the solution space is constructed as follows:
[0187] Place each ant at a different starting point, and for each ant k, calculate the next node to be visited until each ant has visited all nodes. In each step of building a path, the ant uses the roulette method to select the next node to reach. The probability of selecting each path is expressed as:
[0188]
[0189] Among them, p and q represent the starting point and end point of each path respectively. In this method, each path corresponds to each unit. pq (t) represents the pheromone concentration from p to q, η pq The value of (t) is equal to the inverse of the path length, which corresponds to the effect of frequency control of each path segment when solving the optimization of the first grid frequency objective function and the second grid frequency objective function. When solving the optimization of the first system cost objective function and the second system cost objective function, allowed k is the set of nodes that have not been visited. From this formula, we can see that the greater the pheromone concentration, the greater the probability that the path with a shorter distance between two places will be selected. The better the control effect of the unit on the system frequency and the smaller the control cost, the greater the probability of being selected.
[0190] In step 3, the expression of pheromone update is:
[0191] τ pq (t+1)=τ pq (t)*(1-ρ)+Δτ pq ,0<ρ<1
[0192] Among them, Δτ pq is the sum of pheromones left by all ants on the path from node p to node q. The solution is:
[0193]
[0194] Where m is the type of pheromone.
[0195] The optimization parameters and the objective function of the model provided in this embodiment establish a multi-objective optimization model with the goal of minimizing the system frequency change and minimizing the system comprehensive plan cost, taking into account the system frequency security while further reducing the emergency frequency control cost. Considering the speed constraint of the doubly-fed wind turbine generator set during the recovery process, the problem of secondary frequency increase due to increased wind farm output in the speed recovery mode is prevented while improving the emergency frequency control effect.
[0196] The above describes in detail various embodiments corresponding to the power grid frequency control method. On this basis, the present invention also discloses a power grid frequency control device corresponding to the above method. Figure 2 The structure diagram of a power grid frequency control device provided by an embodiment of the present invention is shown in FIG. Figure 2 As shown, the power grid frequency control device includes:
[0197] An acquisition module 11 is used to acquire power parameters of a double-fed wind turbine of a power grid system when the current frequency of the power grid system reaches a preset requirement;
[0198] A first determination module 12 is used to determine the excess power of the power grid according to the current frequency, and to determine the load-shedding power critical parameter of the doubly-fed wind turbine generator according to the power parameter;
[0199] A second determination module 13 is used to determine a corresponding power grid frequency control strategy according to the relationship between the current frequency and the critical parameter of the load-shedding power, wherein the power grid frequency control strategy is determined based on the power grid frequency control model, including a wind turbine load shedding control strategy and a synchronous machine cutting control strategy;
[0200] The control module 14 is used to perform frequency control on the power grid system according to the corresponding power grid frequency control strategy.
[0201] Since the embodiments of the device part correspond to the above embodiments, please refer to the description of the embodiments of the method part for the embodiments of the device part, and will not be repeated here.
[0202] For an introduction to a power grid frequency control device provided by the present invention, please refer to the above method embodiment, and the present invention will not be repeated here. It has the same beneficial effects as the above power grid frequency control method.
[0203] Figure 3 A structural diagram of another power grid frequency control device provided by an embodiment of the present invention, such as Figure 3 As shown, the device comprises:
[0204] A memory 21, used for storing computer programs;
[0205] The processor 22 is used to implement the steps of the power grid frequency control method when executing the computer program.
[0206] The power grid frequency control device provided in this embodiment may include but is not limited to a tablet computer, a laptop computer, or a desktop computer.
[0207] Among them, the processor 22 may include one or more processing cores, such as a 4-core processor, an 8-core processor, etc. The processor 22 can be implemented in at least one hardware form of a digital signal processor (DSP), a field-programmable gate array (FPGA), and a programmable logic array (PLA). The processor 22 may also include a main processor and a coprocessor. The main processor is a processor for processing data in the awake state, also known as a central processing unit (CPU); the coprocessor is a low-power processor for processing data in the standby state. In some embodiments, the processor 22 may be integrated with a graphics processing unit (GPU), which is responsible for rendering and drawing the content to be displayed on the display screen. In some embodiments, the processor 22 may also include an artificial intelligence (AI) processor, which is used to process computing operations related to machine learning.
[0208] The memory 21 may include one or more computer-readable storage media, which may be non-transitory. The memory 21 may also include a high-speed random access memory, and a non-volatile memory, such as one or more disk storage devices, flash memory storage devices. In this embodiment, the memory 21 is at least used to store the following computer program 211, wherein, after the computer program is loaded and executed by the processor 22, it can implement the relevant steps of the power grid frequency control method disclosed in any of the aforementioned embodiments. In addition, the resources stored in the memory 21 may also include an operating system 212 and data 213, etc., and the storage method may be temporary storage or permanent storage. Among them, the operating system 212 may include Windows, Unix, Linux, etc. The data 213 may include but is not limited to data related to the power grid frequency control method, etc.
[0209] In some embodiments, the grid frequency control device may further include a display screen 23 , an input / output interface 24 , a communication interface 25 , a power supply 26 , and a communication bus 27 .
[0210] Those skilled in the art can understand that Figure 3 The structure shown in the figure does not constitute a limitation on the grid frequency control device, and may include more or fewer components than those shown in the figure.
[0211] The processor 22 implements the grid frequency control method provided by any of the above embodiments by calling the instructions stored in the memory 21 .
[0212] For an introduction to a power grid frequency control device provided by the present invention, please refer to the above method embodiment, and the present invention will not be repeated here. It has the same beneficial effects as the above power grid frequency control method.
[0213] Furthermore, the present invention also provides a computer-readable storage medium, on which a computer program is stored, and when the computer program is executed by the processor 22, the steps of the above-mentioned power grid frequency control method are implemented.
[0214] It is understandable that if the method in the above embodiment is implemented in the form of a software functional unit and sold or used as an independent product, it can be stored in a computer-readable storage medium. Based on this understanding, the technical solution of the present invention is essentially or the part that contributes to the prior art or all or part of the technical solution can be embodied in the form of a software product, and the computer software product is stored in a storage medium to perform all or part of the steps of the method described in each embodiment of the present invention. The aforementioned storage medium includes: U disk, mobile hard disk, read-only memory (ROM), random access memory (RAM), disk or optical disk and other media that can store program code.
[0215] For an introduction to a computer-readable storage medium provided by the present invention, please refer to the above method embodiment, and the present invention will not be repeated here. It has the same beneficial effects as the above grid frequency control method.
[0216] The Institute of Electrical and Electronics Engineers (IEEE)-30 system is used to verify the correctness and effectiveness of theoretical research. Figure 4 A schematic diagram of a calculation example system provided by an embodiment of the present invention is shown in FIG. Figure 4 As shown. Among them, nodes 1, 2, 3, 5, 8, and 13 are wind farm nodes, Table 1 is the wind farm parameter table, and the operating parameters are shown in Table 1. Nodes 14, 22, 23, and 27 are SG nodes, Table 2 is the SG parameters, and the servo motor encoder (Screen Grid, SG) operating parameters are shown in Table 2. Nodes 10, 21, 24, 26, 29, and 30 are load nodes.
[0217] Table 1 Wind farm parameters
[0218]
[0219] Table 2SG parameters
[0220]
[0221] Therefore, the ant colony algorithm is used to compare the following two control methods: Scheme 1 is the control scheme of the embodiment of the present invention. Scheme 2 removes the wind turbines according to the minimum undercut principle, and the remaining unbalanced power is preferentially controlled by the double-fed wind turbines. Combined with Example 1 and Example 2, the emergency frequency control performance of each control scheme is studied when the system power disturbance is 280MW and 600MW respectively.
[0222] Example 1: The line BUS7-BUS10 fails, so that the active power cannot be delivered to the load node 10, and the system power surplus is 280MW. At this time, the synchronous machine does not need to be removed. The emergency frequency control scheme 1 is optimized, and Table 3 is the control scheme 1 for the 280MW disturbance, as shown in Table 3. The wind farm WF2 is removed, which increases the maximum controllable power of the system, effectively suppresses the system power disturbance, reduces the load reduction of the remaining wind farms, and reduces the system control cost.
[0223] Table 3 Control scheme 1 for 280MW disturbance
[0224]
[0225] Figure 5 A schematic diagram of system frequency during a 280MW disturbance provided by an embodiment of the present invention is shown in FIG. Figure 5 As shown in the figure, after the system was subjected to a power disturbance of 280MW at 32s, the system frequency rose rapidly and a high-frequency problem occurred. When Scheme 2 was adopted, the highest point of the system frequency rose to 50.651Hz, and the frequency exceeded the limit but failed to be prevented. The reason was that the power disturbance could not be suppressed in the first time according to the principle of minimum undercut. Under Scheme 1, the highest point of the system frequency was 50.467Hz. This scheme effectively prevented the frequency from exceeding the limit and avoided the high-frequency protection action. In addition, the steady-state frequency of Scheme 1 is closer to the rated operating power than Scheme 1. This is because Scheme 1 has a larger adjustable power expansion and can effectively smooth out the system power disturbance.
[0226] If the speed recovery constraint is not considered during the optimization solution process, Figure 6 A schematic diagram of a system frequency without considering the rotation speed recovery constraint is provided in an embodiment of the present invention, such as Figure 6 As shown in the figure, when the speed recovery constraint is not considered, the doubly-fed wind turbines recover their speeds at the same time, the active power output increases at the same time, the system has a power surplus, and the system frequency increases and fluctuates for the second time after 48 seconds. This shows that considering the speed recovery constraint can enable the doubly-fed wind turbines to smoothly and effectively participate in the system emergency frequency control and improve the control effect.
[0227] Example 2: Line BUS10-BUS21 fails, so that active power cannot be delivered to the load side. At this time, the system has a power surplus of 600MW. At this time, removing all wind turbines still cannot completely smooth the system power disturbance. Therefore, some synchronous units need to be removed, and the emergency frequency control scheme is optimized. Table 4 is the emergency frequency control scheme 1 for 600MW disturbance, as shown in Table 4. This scheme removes all wind farms and synchronous unit SG27 to cope with large-power system disturbances. The remaining synchronous units reduce active output to provide frequency modulation capacity for subsequent system power control.
[0228] Table 4 Emergency frequency control scheme 1 for 600MW disturbance
[0229]
[0230] Figure 7 A schematic diagram of system frequency during a 600MW disturbance provided by an embodiment of the present invention is shown in FIG. Figure 7 As shown in the figure, the system was subjected to a 600MW power disturbance at 32s. Scheme 1 was used for control, and the highest point of the system frequency was 50.493Hz. When faced with large power disturbances, Scheme 1 can still quickly smooth out the unbalanced power by cutting off the wind turbines and coordinating the load reduction control of some synchronous machines and wind turbines. When Scheme 2 was used, the highest point of the system frequency was 50.692Hz. The reason is that the cutting of the machine according to the minimum undercut principle cannot provide enough active output change to balance the system power.
[0231] As an example, Figure 8 A flowchart of another power grid frequency control method provided by an embodiment of the present invention, such as Figure 8 As shown, the method includes:
[0232] S21: Collect the real-time frequency of the power grid and obtain the information of the power grid frequency safety binary table. When the duration of the real-time frequency of the power grid is higher than the abnormal duration corresponding to the threshold value in the frequency safety binary table, start the emergency frequency control of the power grid;
[0233] S22: Calculate excess power of the power grid according to the power grid frequency;
[0234] S23: Detect the number and power of wind turbines and synchronous machines in operation in the power grid, and calculate the maximum load-shedding power of the wind turbines;
[0235] S24: Determine whether the grid frequency can be restored to a normal allowable operating range by cutting off the wind turbine and reducing the load. If yes, proceed to step S25; if no, proceed to step S26;
[0236] S25: Taking the wind turbine load reduction control amount and the wind turbine shutdown amount as variables, establish a power grid emergency frequency optimization control model, and proceed to step S27;
[0237] S26: Taking the wind turbine generator set off-line quantity and the synchronous machine off-line quantity as variables, establish a power grid emergency frequency optimization control model, and proceed to step S27;
[0238] S27: Solve the power grid emergency frequency optimization control model, determine the emergency frequency optimization control plan, and implement control.
[0239] For an introduction to another grid frequency control method provided by the present invention, please refer to the above method embodiment, and the present invention will not go into details here. It has the same beneficial effects as the above grid frequency control method.
[0240] The above is a detailed introduction to a grid frequency control method, a grid frequency control device and a medium provided by the present invention. The various embodiments in the specification are described in a progressive manner, and each embodiment focuses on the differences from other embodiments. The same and similar parts between the various embodiments can be referenced to each other. For the device disclosed in the embodiment, since it corresponds to the method disclosed in the embodiment, the description is relatively simple, and the relevant parts can be referred to the method part description. It should be pointed out that for ordinary technicians in this technical field, without departing from the principle of the present invention, several improvements and modifications can be made to the present invention, and these improvements and modifications also fall within the scope of protection of the claims of the present invention.
[0241] It should also be noted that, in this specification, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "comprises", "comprising" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of further restrictions, an element defined by the sentence "comprising a ..." does not exclude the presence of other identical elements in the process, method, article or device including the element.
Claims
1. A method for controlling power grid frequency, characterized in that: include: When the current frequency of the power grid system reaches a preset requirement, obtaining power parameters of the double-fed wind turbine of the power grid system; Determine the excess power of the power grid according to the current frequency, and determine the critical parameter of the load-shedding power of the doubly-fed wind turbine generator according to the power parameter; Determine a corresponding power grid frequency control strategy according to the relationship between the current frequency and the critical parameter of the load-shedding power, wherein the power grid frequency control strategy is determined based on a power grid frequency control model, including a wind turbine load shedding control strategy and a synchronous machine cutting control strategy; Performing frequency control on the power grid system according to the corresponding power grid frequency control strategy; The process of establishing the power grid frequency control model includes: Obtaining a transient frequency critical value, a low-frequency load reduction action threshold value, an OPC action threshold value, a frequency deviation critical value, a total active load value of the power grid system, and a wind farm change amplitude limit value; The condition that the minimum value of the transient frequency critical value is greater than the low-frequency load reduction action threshold value is used as the first constraint condition; The condition that the maximum value of the transient frequency critical value is less than or equal to the OPC action threshold value is used as the second constraint condition; The condition that the deviation value of the current frequency is less than or equal to the maximum value of the frequency deviation critical value is used as a third constraint condition; The condition that the total active load value of the power grid system is greater than or equal to the frequency regulation confidence level value of the power grid system is used as a fourth constraint condition; The condition that the wind farm change amplitude limit value is greater than or equal to the operating power threshold of the power grid system is used as the fifth constraint condition; Establishing the grid frequency control model according to the relationship among the first constraint condition, the second constraint condition, the third constraint condition, the fourth constraint condition and the fifth constraint condition; Correspondingly, the process of determining the wind turbine load reduction control strategy includes: Determine the active power of the doubly-fed wind turbine generator set participating in the power shedding control, the power variation range of the doubly-fed wind turbine generator set participating in the load shedding control, and the active power reduction of the synchronous machine in the power grid system according to the constraints of the power grid frequency control model; A first grid frequency target function is obtained by minimizing the active power of the doubly-fed wind turbine generator set participating in the machine shedding, the power variation range of the doubly-fed wind turbine generator set participating in the load shedding control, and the reduced active power of the synchronous machine; A first system cost objective function is obtained by performing minimization processing according to the active power of the doubly-fed wind turbine generator set participating in the machine shedding and the power variation range of the doubly-fed wind turbine generator set participating in the load shedding control; Determine the wind turbine load shedding control strategy according to the result of the first grid frequency objective function and the first system cost objective function; Correspondingly, the process of determining the synchronous machine cutting control strategy includes: Determining the active power of the doubly-fed wind turbine generator set participating in the power switching, the active power of the synchronous machine participating in the power switching, and the reduced active power of the synchronous machine in the power grid system according to the constraint conditions of the power grid frequency control model; A second grid frequency objective function is obtained by minimizing the active power of the doubly-fed wind turbine generator set participating in the power switching, the active power of the synchronous machine participating in the power switching, and the reduced active power of the synchronous machine; A second system cost objective function is obtained by minimizing the active power of the doubly-fed wind turbine generator set participating in the power switching and the active power of the synchronous machine participating in the power switching; The synchronous machine switching control strategy is determined according to the result of the second power grid frequency objective function and the second system cost objective function.
2. The power grid frequency control method according to claim 1, characterized in that: The preset requirement is that the duration of the current frequency exceeds the duration of the frequency anomaly, and the process of determining whether the current frequency of the power grid system reaches the preset requirement includes: Obtaining the duration of the current frequency and the frequency anomaly duration in the system frequency safety binary table; When the duration exceeds the frequency abnormality duration, it is determined that the current frequency meets the preset requirement.
3. The grid frequency control method according to claim 2, characterized in that: The determining of excess power of the power grid according to the current frequency includes: Obtaining a single-mass block equivalent inertia time constant of the doubly-fed wind generator and a rated operating power parameter of the power grid system; The excess power of the power grid is determined according to the relationship between the current frequency, the single mass block equivalent inertia time constant and the rated operating power parameter.
4. The power grid frequency control method according to claim 1, characterized in that: The step of determining the load-shedding power critical parameter of the doubly-fed wind turbine generator set according to the power parameter comprises: Obtaining critical power parameters of load shedding and active power parameters of an optimal operating point of the doubly-fed wind turbine generator set; Determining the load-shedding power critical parameter according to the relationship between the power critical parameter and the active power parameter of the optimal operating point; The process of determining the power critical parameter includes: Obtaining a pitch speed and a load reduction time of a wind turbine of the doubly-fed wind turbine generator system; Determining a pitch angle adjustment threshold value of the wind turbine according to a relationship between the pitch speed and the load reduction time; Acquire a first wind energy utilization coefficient of the doubly-fed wind generator, a blade radius of the wind turbine, and a current wind speed, wherein the first wind energy utilization coefficient is determined by selecting a maximum speed value from speed values corresponding to each rotor of the doubly-fed wind generator set; Determining the power critical parameter according to the relationship between the first wind energy utilization coefficient, the blade radius, the current wind speed and the pitch angle adjustment critical value; The process of determining the active power parameter of the optimal operating point includes: Obtaining a second wind energy utilization coefficient of the doubly-fed wind generator, wherein the second wind energy utilization coefficient is determined by selecting an optimal speed value from speed values corresponding to each rotor of the doubly-fed wind generator set; The active power parameter is determined according to the relationship between the second wind energy utilization coefficient, the blade radius and the current wind speed.
5. The power grid frequency control method according to claim 3 or 4, characterized in that: The determining of the corresponding grid frequency control strategy according to the relationship between the current frequency and the load-shedding power critical parameter includes: Obtaining the number of removed double-fed wind turbines and the corresponding operating power parameters, and the response coefficient of the frequency of the power grid system to the frequency change of the double-fed wind turbine group; Determine the frequency allowable operating range of the power grid system according to the load shedding power critical parameter, the number of units removed, the corresponding operating power parameter and the response coefficient; Determine whether the current frequency is within the frequency allowable operating range; If yes, determining that the grid frequency control strategy is the wind turbine load reduction control strategy; If not, it is determined that the power grid frequency control strategy is the synchronous machine switching control strategy.
6. The grid frequency control method according to claim 1, characterized in that: The optimization of the active power of the doubly-fed wind turbine generator set participating in the machine switching and the power variation range of the doubly-fed wind turbine generator set participating in the load shedding control in the objective function corresponding to the grid frequency control strategy is obtained by an ant colony algorithm.
7. A power grid frequency control device, characterized in that: include: An acquisition module, used for acquiring power parameters of a double-fed wind turbine of the power grid system when the current frequency of the power grid system reaches a preset requirement; A first determination module is used to determine the excess power of the power grid according to the current frequency, and to determine the load-shedding power critical parameter of the doubly-fed wind turbine generator according to the power parameter; A second determination module is used to determine a corresponding power grid frequency control strategy according to the relationship between the current frequency and the critical parameter of the load-shedding power, wherein the power grid frequency control strategy is determined based on a power grid frequency control model, including a wind turbine load shedding control strategy and a synchronous machine cutting control strategy; A control module, used for performing frequency control on the power grid system according to the corresponding power grid frequency control strategy; The process of establishing the power grid frequency control model includes: Obtaining a transient frequency critical value, a low-frequency load reduction action threshold value, an OPC action threshold value, a frequency deviation critical value, a total active load value of the power grid system, and a wind farm change amplitude limit value; The condition that the minimum value of the transient frequency critical value is greater than the low-frequency load reduction action threshold value is used as the first constraint condition; The condition that the maximum value of the transient frequency critical value is less than or equal to the OPC action threshold value is used as the second constraint condition; The condition that the deviation value of the current frequency is less than or equal to the maximum value of the frequency deviation critical value is used as a third constraint condition; The condition that the total active load value of the power grid system is greater than or equal to the frequency regulation confidence level value of the power grid system is used as a fourth constraint condition; The condition that the wind farm change amplitude limit value is greater than or equal to the operating power threshold of the power grid system is used as the fifth constraint condition; Establishing the grid frequency control model according to the relationship among the first constraint condition, the second constraint condition, the third constraint condition, the fourth constraint condition and the fifth constraint condition; Correspondingly, the process of determining the wind turbine load reduction control strategy includes: Determine the active power of the doubly-fed wind turbine generator set participating in the power shedding control, the power variation range of the doubly-fed wind turbine generator set participating in the load shedding control, and the active power reduction of the synchronous machine in the power grid system according to the constraints of the power grid frequency control model; A first grid frequency target function is obtained by minimizing the active power of the doubly-fed wind turbine generator set participating in the machine shedding, the power variation range of the doubly-fed wind turbine generator set participating in the load shedding control, and the reduced active power of the synchronous machine; A first system cost objective function is obtained by performing minimization processing according to the active power of the doubly-fed wind turbine generator set participating in the machine shedding and the power variation range of the doubly-fed wind turbine generator set participating in the load shedding control; Determine the wind turbine load shedding control strategy according to the result of the first grid frequency objective function and the first system cost objective function; Correspondingly, the process of determining the synchronous machine cutting control strategy includes: Determining the active power of the doubly-fed wind turbine generator set participating in the power switching, the active power of the synchronous machine participating in the power switching, and the reduced active power of the synchronous machine in the power grid system according to the constraint conditions of the power grid frequency control model; A second grid frequency objective function is obtained by minimizing the active power of the doubly-fed wind turbine generator set participating in the power switching, the active power of the synchronous machine participating in the power switching, and the reduced active power of the synchronous machine; A second system cost objective function is obtained by minimizing the active power of the doubly-fed wind turbine generator set participating in the power switching and the active power of the synchronous machine participating in the power switching; The synchronous machine switching control strategy is determined according to the result of the second power grid frequency objective function and the second system cost objective function.
8. A power grid frequency control device, characterized in that: include: Memory for storing computer programs; A processor, configured to implement the steps of the power grid frequency control method as claimed in any one of claims 1 to 6 when executing the computer program.
9. A computer-readable storage medium, characterized in that: The computer-readable storage medium stores a computer program, and when the computer program is executed by a processor, the steps of the power grid frequency control method according to any one of claims 1 to 6 are implemented.