An optimization method for intelligent ventilation control in ultra-long highway tunnels
By arranging traffic volume detection equipment in ultra-long highway tunnels, real-time calculation of required air volume and control of the number of fans solve the problems of high energy consumption and low operating efficiency of the ventilation system, realize intelligent ventilation control, and reduce the energy consumption of tunnel ventilation operations. Consumption and expenses.
Patent Information
- Application Number
- CN202311773808.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-21
- Publication Date
- 2024-09-24
- Estimated Expiration
- 2043-12-21
AI Technical Summary
The existing ventilation system of ultra-long highway tunnels has problems such as lag in ventilation control, low operating efficiency, and high energy consumption, resulting in operating expenses accounting for 50% to 70% of the tunnel operating expenses.
Using intelligent ventilation control method, by arranging traffic volume data detection equipment in front of the tunnel entrance, exit and entrance, real-time detection and sending traffic volume data to the ventilation controller, dividing ventilation sections, and calculating each section based on real-time traffic volume data According to the required air volume and number of fans, real-time control of the opening of jet fans, exhaust and supply fans can be performed to optimize the ventilation system.
It effectively reduces the energy consumption of tunnel fans, realizes on-demand ventilation and intelligent management, reduces the energy consumption of ventilation operations in ultra-long tunnels, and achieves the purpose of energy conservation and emission reduction.
Smart Images

Figure CN117722382B
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of tunnel ventilation control, and in particular relates to an intelligent ventilation control optimization method for an ultra-long highway tunnel. Background Art
[0002] In highway tunnel ventilation, fan equipment is used to deliver fresh air into the tunnel and exhaust polluted air in the tunnel. Currently, there are more and more extra-long tunnels and super-long tunnels in operation, and tunnel ventilation systems account for a high proportion of electricity consumption. According to previous engineering experience, the ventilation system of super-long tunnels has a large number of ventilation equipment, including jet fans, axial exhaust fans and axial supply fans, and its operation, maintenance and management costs account for 50% to 70% of the entire tunnel operation costs. Therefore, under the premise of ensuring the performance of the tunnel ventilation system, how to effectively reduce its electricity consumption and thus reduce operating costs is a key issue that needs to be solved in tunnel ventilation operations. The existing tunnel ventilation system has problems such as ventilation control lag, low operating efficiency, and high energy consumption. Summary of the invention
[0003] In view of the defects of the prior art, the present invention provides an intelligent ventilation control optimization method for a super-long highway tunnel, which can effectively solve the above problems.
[0004] The technical solution adopted by the present invention is as follows:
[0005] The present invention provides an intelligent ventilation control optimization method for an ultra-long highway tunnel, comprising the following steps:
[0006] Step 1: Arrange an entrance traffic volume data detection device at the tunnel entrance, arrange an exit traffic volume data detection device at the tunnel exit, and arrange a pre-entrance traffic volume data detection device in front of the tunnel entrance at a distance of L0 from the tunnel entrance;
[0007] The entrance traffic volume data detection device, the exit traffic volume data detection device and the pre-entrance traffic volume data detection device are all connected to the ventilation controller;
[0008] Step 2, presetting the ventilation control period ΔT;
[0009] In each ventilation control cycle ΔT, the entrance traffic volume data detected by the entrance traffic volume data detection device, the exit traffic volume data detected by the exit traffic volume data detection device, and the pre-entrance traffic volume data detected by the pre-entrance traffic volume data detection device are all sent to the ventilation controller in real time;
[0010] The ventilation controller divides the tunnel into n ventilation sections along the length direction, and performs intelligent ventilation optimization calculation according to the entrance traffic volume data, the exit traffic volume data and the pre-entrance traffic volume data received in real time, obtains the optimal number of jet fans currently turned on in each ventilation section, and controls the corresponding number of jet fans to be turned on in real time according to the calculated optimal number;
[0011] For the i-th ventilation section, i = 1, 2, ..., n, the following method is used to determine the optimal number k of jet fans currently turned on: i :
[0012] Step 2.1, in the current ventilation control period ΔT, the ventilation controller calculates the traffic volume of each vehicle type in the current ventilation control period ΔT according to the real-time received entrance traffic volume data, exit traffic volume data and pre-entrance traffic volume data; and then obtains the required air volume Q for tunnel smoke dilution in the i-th ventilation section according to the obtained traffic volume of each vehicle type. req(VI)_i , the required air volume Q for tunnel CO dilution in the i-th ventilation section req(CO)_i and the tunnel ventilation air volume Q of the i-th ventilation section req(ac)_i ;
[0013] Step 2.2: Use the following formula to obtain the required air volume Q of the tunnel in the i-th ventilation section: i :
[0014] Q i =max(Q req(VI)_i ,Q req(CO)_i ,Q req(ac)_i ) (1)
[0015] Step 2.3, use the following formula to obtain the exhaust outlet pressure rise Δp of the i-th ventilation section: e and the air outlet pressure rise Δp of the i-th ventilation section b The expression is:
[0016]
[0017]
[0018] Where: Q ei is the exhaust volume of the ventilation shaft in the ith ventilation section; Q ri is the target air volume of the ith ventilation section; v e is the exhaust volume Q of the ventilation shaft in the i-th ventilation section ei The corresponding ventilation shaft exhaust wind speed; v ri is the target wind speed of the ith ventilation section, v ri =Q ri / A r ,A ris the clear cross-sectional area of the tunnel; α is the angle between the exhaust outlet of the ventilation shaft and the axial direction of the tunnel; ρ is the air density in the tunnel area; Q bi is the air supply volume of the ventilation shaft in the ith ventilation section; Q r(i+1) is the target air volume of the i+1th ventilation section; v b The air volume Q of the ventilation shaft bi The corresponding ventilation shaft air supply speed; v r(i+1) is the target wind speed of the i+1th ventilation section, v r(i+1) =Q r(i+1) / A r ; β is the angle between the ventilation shaft air outlet direction and the tunnel axis;
[0019] Step 2.4: Use the following formula to obtain the tunnel ventilation resistance Δp of the i-th ventilation section: r The expression is:
[0020]
[0021] Among them: i is the local resistance coefficient of the tunnel in the ith ventilation section; r is the tunnel resistance coefficient along the i-th ventilation section; L is the tunnel length; D r is the equivalent diameter of the tunnel section;
[0022] Step 2.5, use the following formula to obtain the traffic ventilation force Δp of the i-th ventilation section: t The expression is:
[0023]
[0024] Among them: A m A is the equivalent impedance area of the vehicle in the i-th ventilation section; r is the clear cross-sectional area of the tunnel; n c is the number of vehicles in the tunnel; v t is the average speed of vehicles in the tunnel;
[0025] Step 2.6: Use the following formula to obtain the natural ventilation force Δp in the tunnel of the i-th ventilation section: m The expression is:
[0026]
[0027] Where: v e is the wind speed in the ith ventilation section caused by natural wind; e is the local resistance coefficient at the inlet of the i-th ventilation section;
[0028] Step 2.7, the pressure balance equation of the longitudinal ventilation mode of the i-th ventilation section is established as follows:
[0029] Δpb +Δp e +k i Δp j =Δp r -Δp t +Δp m (7)
[0030] Where: k i is the number of jet fans required to be arranged in the i-th ventilation section, and is the value to be evaluated; Δp j The pressure rise for a single jet fan;
[0031] Step 2.8, solve the pressure balance equation of the longitudinal ventilation mode of the i-th ventilation section established in step 2.7, and obtain the optimal number of jet fans currently turned on in the i-th ventilation section, that is, the determined k i value.
[0032] Preferably, the traffic volume of each vehicle type in the current ventilation control period ΔT is calculated as follows:
[0033] The current ventilation control cycle ΔT is expressed as the bt-th ventilation control cycle; the traffic volume N of each vehicle type is obtained according to the following formula:
[0034] If bt = 1, then N = N Em1 +C m
[0035] If bt ≥ 2, then N = N Em_bt +N Em_(bt-1) -N Jm_bt
[0036] Where: N Em1 The traffic volume of each type of vehicle detected and counted by the traffic volume data detection equipment before the entrance during the first ventilation control cycle; C m Indicates the traffic volume of each type of vehicle counted from the traffic volume data detection device before the entrance to the tunnel exit during the 0th ventilation control cycle;
[0037] N Em_bt The traffic volume of each type of vehicle passing through the pre-entrance traffic volume data detection device in the bt ventilation control cycle, which is obtained by statistics of the pre-entrance traffic volume data detection device;
[0038] N Em_(bt-1) The traffic volume of each type of vehicle passing through the pre-entrance traffic volume data detection device in the bt-1 ventilation control cycle, which is obtained by statistics of the pre-entrance traffic volume data detection device;
[0039] N Jm_bt It is the traffic volume of each type of vehicle leaving the tunnel exit during the bt ventilation control cycle, obtained by statistics of the exit traffic volume data detection equipment.
[0040] Preferably, the minimum distance L between the location of the traffic volume data detection equipment before the entrance and the tunnel exit is min Determine using the following formula:
[0041]
[0042] in: is the maximum average vehicle speed, which is determined by: Among them, n a is the proportion of small cars during the statistical period; v a The maximum speed limit for small cars; n b is the proportion of large vehicles during the statistical period; v b The maximum speed limit for large vehicles.
[0043] Preferably, the air volume Q required for tunnel smoke dilution in the i-th ventilation section is req(VI)_i , determined using the following formula:
[0044]
[0045] Where: q VI is the smoke benchmark emission; K VI f is the designed concentration of smoke; a(VI) is the vehicle condition factor considering smoke; f d is the vehicle density coefficient; f h(VI) f is the altitude coefficient for considering smoke; iv(VI) is the longitudinal slope-vehicle speed coefficient considering smoke; n D is the number of diesel vehicle types calculated in the current ventilation control cycle ΔT; m is n D One of the number of diesel vehicle types, m = 1, 2, ..., n D ; N m is the traffic volume of the mth diesel vehicle type; f m(VI) is the model coefficient of the mth diesel vehicle model taking smoke into consideration.
[0046] Preferably, the tunnel dilution CO required air volume Q of the i-th ventilation section is req(CO)_i , determined using the following formula:
[0047]
[0048] Where: q CO is the CO benchmark emission; δ is the CO design concentration; f a is the vehicle condition factor considering CO; f h is the vehicle condition factor considering CO; f iv is the longitudinal slope-vehicle speed coefficient considering CO; P0 is the standard atmospheric pressure; P is the atmospheric pressure at the tunnel site; T is the atmospheric pressure at the tunnel site; T0 is the standard temperature; nco is the number of vehicle types calculated in the current ventilation control cycle ΔT; w is n co One of the number of vehicle types, w=1,2,...,n co ; N w is the traffic volume of the wth vehicle type; f m is the vehicle type coefficient of the wth vehicle type category considering CO.
[0049] Preferably, the tunnel ventilation air volume Q of the i-th ventilation section is req(ac)_i , determined using the following formula:
[0050] Q req(ac)_i =v ac ·A r (1-3)
[0051] Where: v ac The wind speed for tunnel ventilation.
[0052] Preferably, the vehicle equivalent impedance area A in the i-th ventilation section m , using the following formula:
[0053] A m =(1-r1)·A c2 ·ζ c2 +r1·A cl ·ζ c1 (5-1)
[0054] Among them: r1 is the proportion of large vehicles; A c2 is the front projection area of a small vehicle; c2 A is the air resistance coefficient of a small vehicle; cl is the front projection area of large vehicles; c1 is the air resistance coefficient of large vehicles.
[0055] Preferably, the exhaust volume Q of the ventilation shaft in the i-th ventilation section is ei and the ventilation shaft air volume Q of the i-th ventilation section bi , solved by the following method:
[0056] Step 2.3.1, establish the equation system:
[0057]
[0058]
[0059]
[0060]
[0061] Where: C2 is the concentration at the ventilation shaft outlet; C3 is the concentration inside the tunnel exit; Q sf is the equivalent fresh air volume in the airflow at the bottom of the ventilation shaft; Q i is the required air volume of the tunnel in the ith ventilation section; Q (i+1) is the required air volume of the tunnel in the i+1th ventilation section; Q ri is the target air volume of the ith ventilation section; Q r(i+1) is the required air volume of the tunnel in the i+1th ventilation section;
[0062] The constraints are established as follows:
[0063]
[0064]
[0065] 0.9≤C2≤1.0 (2-7)
[0066] 0.9≤C3≤1.0 (2-8)
[0067] Step 2.3.2, under the constraints, solve the equations established in step 2.3.1 to obtain the exhaust volume Q of the ventilation shaft in the i-th ventilation section ei and the ventilation shaft air volume Q of the i-th ventilation section bi .
[0068] Preferably, in step 2.7, Δp j The calculation is done using the following formula:
[0069]
[0070] Where: v j is the outlet wind speed of the jet fan; η is the friction loss reduction coefficient at the jet fan position.
[0071] Preferably, when the tunnel is divided into n ventilation sections, a ventilation shaft is arranged between every two adjacent ventilation sections, that is, the zth ventilation shaft is arranged between the i-th ventilation section and the i+1-th ventilation section, and y ventilation shafts are opened in the zth ventilation shaft. ez The exhaust volume of a single exhaust axial flow fan is Q ef , used to exhaust the polluted air in the i-th ventilation section, and at the same time open y bz The air supply volume of a single axial flow fan is Q. bf , used to deliver fresh air to the i+1th ventilation section; when the kth ventilation section is opened i When there are jet fans, the following formula is used to determine the number of exhaust axial fans to be opened y ez and the number of axial flow fans opened ybz :
[0072]
[0073]
[0074] Among them: int() represents rounding up to an integer; Q ei represents the exhaust volume of the ventilation shaft in the i-th ventilation section; Q b(i+1) Represents the air supply volume of the ventilation shaft in the i+1th ventilation section.
[0075] The invention provides an optimization method for intelligent ventilation control in ultra-long highway tunnels, which has the following advantages:
[0076] The present invention calculates the traffic volume of each type of vehicle in each ventilation control cycle in real time through traffic data detection equipment arranged at the front end of the tunnel entrance and the tunnel entrance and exit. Then, the ventilation controller controls the number of fans turned on in the tunnel in real time according to the real-time traffic volume. Therefore, the number of fans turned on in the tunnel is related to the real-time traffic volume, which can ensure that the minimum number of jet fans, exhaust axial flow fans and supply axial flow fans that meet the traffic load and the ventilation requirements in the tunnel are turned on, thereby effectively reducing the energy consumption of tunnel fans and reducing the energy consumption of ventilation operations in super-long tunnels, thereby achieving the goals of energy saving and emission reduction, ventilation on demand and intelligent management under the operating conditions of super-long highway tunnels. BRIEF DESCRIPTION OF THE DRAWINGS
[0077] Figure 1 A schematic diagram of a flow chart of an ultra-long highway tunnel intelligent ventilation control optimization method provided by the present invention;
[0078] Figure 2 This is a layout diagram of each traffic volume data detection device provided by the present invention. DETAILED DESCRIPTION
[0079] In order to make the technical problems, technical solutions and beneficial effects solved by the present invention more clearly understood, the present invention is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not used to limit the present invention.
[0080] The method of the present invention for providing an intelligent ventilation control strategy for a super-long highway tunnel based on accurate calculation of traffic volume has the following advantages:
[0081] The present invention calculates the traffic volume of each type of vehicle in each ventilation control cycle in real time through traffic data detection equipment arranged at the front end of the tunnel entrance and the tunnel entrance and exit. Then, the ventilation controller controls the number of fans turned on in the tunnel in real time according to the real-time traffic volume. Therefore, the number of fans turned on in the tunnel is related to the real-time traffic volume, which can ensure that the minimum number of jet fans, exhaust axial flow fans and supply axial flow fans that meet the traffic load and the ventilation requirements in the tunnel are turned on, thereby effectively reducing the energy consumption of tunnel fans and reducing the energy consumption of ventilation operations in super-long tunnels, thereby achieving the goals of energy saving and emission reduction, ventilation on demand and intelligent management under the operating conditions of super-long highway tunnels.
[0082] See also Figure 1 and Figure 2 The present invention provides an optimization method for intelligent ventilation control of a super-long highway tunnel, comprising the following steps:
[0083] Step 1: Arrange the entrance traffic volume data detection equipment at the tunnel entrance, arrange the exit traffic volume data detection equipment at the tunnel exit, and arrange the pre-entrance traffic volume data detection equipment in front of the tunnel entrance, at a distance of L0 from the tunnel entrance; wherein each traffic volume data detection equipment is used to detect the traffic volume of each type of vehicle passing through, including: the number of vehicles, driving speed, and vehicle type and other traffic quantities. Among them, the vehicle type can be divided into large vehicles and small vehicles, and also divided into diesel vehicles and non-diesel vehicles. Each traffic volume data detection equipment can specifically include an ETC gantry system, a microwave vehicle detector, a toroidal coil vehicle detector, and a video vehicle detector, etc.
[0084] The entrance traffic volume data detection device, the exit traffic volume data detection device and the pre-entrance traffic volume data detection device are all connected to the ventilation controller;
[0085] In this step, when the tunnel length is L, the distance between the traffic volume data detection device before the entrance and the tunnel exit is L0+L. The minimum value of this distance, that is, the minimum distance L between the layout position of the traffic volume data detection device before the entrance and the tunnel exit min Determine using the following formula:
[0086]
[0087] in: is the maximum average vehicle speed, which is determined by: Among them, n a is the proportion of small cars during the statistical period; v a The maximum speed limit for small cars; n b is the proportion of large vehicles during the statistical period; v b The maximum speed limit for large vehicles.
[0088] Step 2, presetting the ventilation control period ΔT;
[0089] In each ventilation control cycle ΔT, generally, the ventilation control cycle ΔT is set to be at least 10 minutes; the entrance traffic volume data detected by the entrance traffic volume data detection device, the exit traffic volume data detected by the exit traffic volume data detection device, and the pre-entrance traffic volume data detected by the pre-entrance traffic volume data detection device are all sent to the ventilation controller in real time;
[0090] The ventilation controller divides the tunnel into n ventilation sections along the length direction, and performs intelligent ventilation optimization calculation according to the entrance traffic volume data, the exit traffic volume data and the pre-entrance traffic volume data received in real time, obtains the optimal number of jet fans currently turned on in each ventilation section, and controls the corresponding number of jet fans to be turned on in real time according to the calculated optimal number;
[0091] In this step, the ventilation controller calculates the traffic volume of each vehicle type in the current ventilation control period ΔT, specifically:
[0092] The current ventilation control cycle ΔT is expressed as the bt-th ventilation control cycle; the traffic volume N of each vehicle type is obtained according to the following formula:
[0093] If bt = 1, then N = N Em1 +C m
[0094] If bt ≥ 2, then N = N Em_bt +N Em_(bt-1) -N Jm_bt
[0095] Where: N Em1 The traffic volume of each type of vehicle detected and counted by the traffic volume data detection equipment before the entrance during the first ventilation control cycle; C m Indicates the traffic volume of each type of vehicle counted from the traffic volume data detection device before the entrance to the tunnel exit during the 0th ventilation control cycle;
[0096] N Em_bt The traffic volume of each type of vehicle passing through the pre-entrance traffic volume data detection device in the bt ventilation control cycle, which is obtained by statistics of the pre-entrance traffic volume data detection device;
[0097] N Em_(bt-1) The traffic volume of each type of vehicle passing through the pre-entrance traffic volume data detection device in the bt-1 ventilation control cycle, which is obtained by statistics of the pre-entrance traffic volume data detection device;
[0098] N Jm_bt It is the traffic volume of each type of vehicle leaving the tunnel exit during the bt ventilation control cycle, obtained by statistics of the exit traffic volume data detection equipment.
[0099] For the i-th ventilation section, i = 1, 2, ..., n, the following method is used to determine the optimal number k of jet fans currently turned on: i :
[0100] Step 2.1, in the current ventilation control period ΔT, the ventilation controller calculates the traffic volume of each vehicle type in the current ventilation control period ΔT according to the real-time received entrance traffic volume data, exit traffic volume data and pre-entrance traffic volume data; and then obtains the required air volume Q for tunnel smoke dilution in the i-th ventilation section according to the obtained traffic volume of each vehicle type. req(VI)_i , the required air volume Q for tunnel CO dilution in the i-th ventilation section req(CO)_i and the tunnel ventilation air volume Q of the i-th ventilation section req(ac)_i ;
[0101] Step 2.2: Use the following formula to obtain the required air volume Q of the tunnel in the i-th ventilation section: i :
[0102] Q i =max(Q req(VI)_i ,Q req(CO)_i ,Q req(ac)_i ) (1)
[0103] Therefore, under normal operating conditions, each ventilation section of the tunnel obtains the required air volume under the three conditions of smoke dilution, CO and ventilation, and the maximum value is taken as the final required air volume of the ventilation section in each fan control cycle.
[0104] The required air volume Q for diluting smoke in the tunnel of the i-th ventilation section req(VI)_i , the required air volume Q for tunnel CO dilution in the i-th ventilation section req(CO)_i and the tunnel ventilation air volume Q of the i-th ventilation section req(ac)_i The determination methods are:
[0105] (1) The required air volume Q for diluting smoke in the tunnel of the i-th ventilation section req(VI)_i , determined using the following formula:
[0106]
[0107] Where: q VI is the smoke benchmark emission; K VI f is the designed concentration of smoke; a(VI) is the vehicle condition factor considering smoke; f d is the vehicle density coefficient, which is calculated based on the traffic volume detected by the traffic volume data detection equipment; f h(VI) f is the altitude coefficient for considering smoke; iv(VI) is the longitudinal slope-vehicle speed coefficient considering smoke; nD is the number of diesel vehicle types calculated in the current ventilation control cycle ΔT; m is n D One of the number of diesel vehicle types, m = 1, 2, ..., n D ; N m is the traffic volume of the mth diesel vehicle type; f m(VI) is the model coefficient of the mth diesel vehicle model that takes smoke into consideration. Therefore, when calculating the air volume required for tunnel smoke dilution, the present invention mainly considers the influence of diesel vehicles.
[0108] (2) The required air volume Q for tunnel CO dilution in the i-th ventilation section req(CO)_i , determined using the following formula:
[0109]
[0110] Where: q CO is the CO benchmark emission; δ is the CO design concentration; f a is the vehicle condition factor considering CO; f h is the vehicle condition factor considering CO; f iv is the longitudinal slope-vehicle speed coefficient considering CO; P0 is the standard atmospheric pressure; P is the atmospheric pressure at the tunnel site; T is the atmospheric pressure at the tunnel site; T0 is the standard temperature; n co is the number of vehicle types calculated in the current ventilation control cycle ΔT; w is n co One of the number of vehicle types, w=1,2,...,n co ; N w is the traffic volume of the wth vehicle type; f m is the vehicle type coefficient of the wth vehicle type category considering CO. Therefore, when calculating the required air volume for diluting CO in the tunnel, the present invention needs to fully consider the impact of diesel vehicles and non-diesel vehicles.
[0111] (3) Tunnel ventilation required air volume Q in the i-th ventilation section req(ac)_i , determined using the following formula:
[0112] Q req(ac)_i =v ac ·A r (1-3)
[0113] Where: v ac The wind speed for tunnel ventilation.
[0114] Step 2.3, use the following formula to obtain the exhaust outlet pressure rise Δp of the i-th ventilation section: e and the air outlet pressure rise Δp of the i-th ventilation section b The expression is:
[0115]
[0116]
[0117] Where: Q ei is the exhaust volume of the ventilation shaft in the ith ventilation section; Q ri is the target air volume of the ith ventilation section; v e is the exhaust volume Q of the ventilation shaft in the i-th ventilation section ei The corresponding ventilation shaft exhaust wind speed; v ri is the target wind speed of the ith ventilation section, v ri =Q ri / A r ,A r is the clear cross-sectional area of the tunnel; α is the angle between the exhaust outlet of the ventilation shaft and the axial direction of the tunnel; ρ is the air density in the tunnel area; Q bi is the air supply volume of the ventilation shaft in the ith ventilation section; Q r(i+1) is the target air volume of the i+1th ventilation section; v b The air volume Q of the ventilation shaft bi The corresponding ventilation shaft air supply speed; v r(i+1) is the target wind speed of the i+1th ventilation section, v r(i+1) =Q r(i+1) / A r ; β is the angle between the ventilation shaft air outlet direction and the tunnel axis;
[0118] In this step, the exhaust volume Q of the ventilation shaft in the i-th ventilation section is ei and the ventilation shaft air volume Q of the i-th ventilation section bi , solved by the following method:
[0119] Step 2.3.1, establish the equation system:
[0120]
[0121]
[0122]
[0123]
[0124] Where: C2 is the concentration at the ventilation shaft outlet; C3 is the concentration inside the tunnel exit; Q sf is the equivalent fresh air volume in the airflow at the bottom of the ventilation shaft; Q i is the required air volume of the tunnel in the ith ventilation section; Q (i+1) is the required air volume of the tunnel in the i+1th ventilation section; Q ri is the target air volume of the ith ventilation section; Q r(i+1) is the required air volume of the tunnel in the i+1th ventilation section;
[0125] The constraints are established as follows:
[0126]
[0127]
[0128] 0.9≤C2≤1.0 (2-7)
[0129] 0.9≤C3≤1.0 (2-8)
[0130] Among them: Formula 2-5 and Formula 2-6 are the constraints that the short passage between the exhaust port and the supply port does not produce backflow; Formula 2-7 and Formula 2-8 are the constraints that the concentration should meet.
[0131] Step 2.3.2, under the constraints, solve the equations established in step 2.3.1 to obtain the exhaust volume Q of the ventilation shaft in the i-th ventilation section ei and the ventilation shaft air volume Q of the i-th ventilation section bi .
[0132] Step 2.4: Use the following formula to obtain the tunnel ventilation resistance Δp of the i-th ventilation section: r The expression is:
[0133]
[0134] Among them: i is the local resistance coefficient of the tunnel in the ith ventilation section; r is the tunnel resistance coefficient along the i-th ventilation section; L is the tunnel length; D r is the equivalent diameter of the tunnel section;
[0135] Step 2.5, use the following formula to obtain the traffic ventilation force Δp of the i-th ventilation section: t The expression is:
[0136]
[0137] Among them: A m A is the equivalent impedance area of the vehicle in the i-th ventilation section; r is the clear cross-sectional area of the tunnel; n c is the number of vehicles in the tunnel; v t is the average speed of vehicles in the tunnel;
[0138] The equivalent impedance area of the vehicle in the i-th ventilation section A m , using the following formula:
[0139] A m =(1-r1)·A c2 ·ζ c2+r1·A cl ·ζ c1 (5-1)
[0140] Where: r1 is the proportion of large vehicles, which is calculated based on the traffic volume detected by the traffic volume data detection equipment; A c2 The front projection area of a small vehicle, for example, is set to 2.13m 2 ;ζ c2 A is the air resistance coefficient of a small vehicle; cl For large vehicles, the front projection area is set to 5.37m 2 ;ζ c1 is the air resistance coefficient of large vehicles.
[0141] Step 2.6: Use the following formula to obtain the natural ventilation force Δp in the tunnel of the i-th ventilation section: m The expression is:
[0142]
[0143] Where: v e is the wind speed in the ith ventilation section caused by natural wind; e is the local resistance coefficient at the inlet of the i-th ventilation section;
[0144] Step 2.7, the pressure balance equation of the longitudinal ventilation mode of the i-th ventilation section is established as follows:
[0145] Δp b +Δp e +k i Δp j =Δp r -Δp t +Δp m (7)
[0146] Where: k i is the number of jet fans required to be arranged in the i-th ventilation section, and is the value to be evaluated; Δp j is the pressure rise of a single jet fan; Δp j The calculation is done using the following formula:
[0147]
[0148] Where: v j is the outlet wind speed of the jet fan; η is the friction loss reduction coefficient at the jet fan position.
[0149] Step 2.8, solve the pressure balance equation of the longitudinal ventilation mode of the i-th ventilation section established in step 2.7, and obtain the optimal number of jet fans currently turned on in the i-th ventilation section, that is, the determined k i value.
[0150] In addition, in the present invention, in step 2.4, the exhaust volume Q of the ventilation shaft of the i-th ventilation section is calculated. ei and the ventilation shaft air volume Q of the i-th ventilation section bi , in order to obtain the exhaust volume Q of the ventilation shaft of the i-th ventilation section that meets this requirement ei and the ventilation shaft air volume Q of the i-th ventilation section bi , a certain number of exhaust axial flow fans and supply axial flow fans of the corresponding ventilation shaft need to be turned on. The number of exhaust axial flow fans and supply axial flow fans turned on is determined by the following method:
[0151] When the tunnel is divided into n ventilation sections, a ventilation shaft is arranged between every two adjacent ventilation sections, that is, the zth ventilation shaft is arranged between the i-th ventilation section and the i+1-th ventilation section, and y ventilation shafts are opened in the zth ventilation shaft. ez The exhaust volume of a single exhaust axial flow fan is Q ef , used to exhaust the polluted air in the i-th ventilation section, and at the same time open y bz The air supply volume of a single axial flow fan is Q. bf , used to deliver fresh air to the i+1th ventilation section; when the kth ventilation section is opened i When there are jet fans, the following formula is used to determine the number of exhaust axial fans to be opened y ez and the number of axial flow fans opened y bz :
[0152]
[0153]
[0154] Among them: int() represents rounding up to an integer; Q ei represents the exhaust volume of the ventilation shaft in the i-th ventilation section; Q b(i+1) Represents the air supply volume of the ventilation shaft in the i+1th ventilation section.
[0155] The invention provides an optimization method for intelligent ventilation control in ultra-long highway tunnels, which has the following advantages:
[0156] The present invention calculates the traffic volume of each type of vehicle in each ventilation control cycle in real time through traffic data detection equipment arranged at the front end of the tunnel entrance and the tunnel entrance and exit. Then, the ventilation controller controls the number of fans turned on in the tunnel in real time according to the real-time traffic volume. Therefore, the number of fans turned on in the tunnel is related to the real-time traffic volume, which can ensure that the minimum number of jet fans, exhaust axial flow fans and supply axial flow fans that meet the traffic load and the ventilation requirements in the tunnel are turned on, thereby effectively reducing the energy consumption of tunnel fans and reducing the energy consumption of ventilation operations in super-long tunnels, thereby achieving the goals of energy saving and emission reduction, ventilation on demand and intelligent management under the operating conditions of super-long highway tunnels.
[0157] The above is only a preferred embodiment of the present invention. It should be pointed out that for ordinary technicians in this technical field, several improvements and modifications can be made without departing from the principle of the present invention. These improvements and modifications should also be considered as the scope of protection of the present invention.
Claims
1. A super-long highway tunnel intelligent ventilation control optimization method, characterized in that: The following steps are involved: Step 1: Arrange an entrance traffic volume data detection device at the tunnel entrance, arrange an exit traffic volume data detection device at the tunnel exit, and arrange a pre-entrance traffic volume data detection device in front of the tunnel entrance at a distance of L0 from the tunnel entrance; The entrance traffic volume data detection device, the exit traffic volume data detection device and the pre-entrance traffic volume data detection device are all connected to the ventilation controller; Step 2, presetting the ventilation control period ΔT; In each ventilation control cycle ΔT, the entrance traffic volume data detected by the entrance traffic volume data detection device, the exit traffic volume data detected by the exit traffic volume data detection device, and the pre-entrance traffic volume data detected by the pre-entrance traffic volume data detection device are all sent to the ventilation controller in real time; The ventilation controller divides the tunnel into n ventilation sections along the length direction, and performs intelligent ventilation optimization calculation according to the entrance traffic volume data, the exit traffic volume data and the pre-entrance traffic volume data received in real time, obtains the optimal number of jet fans currently turned on in each ventilation section, and controls the corresponding number of jet fans to be turned on in real time according to the calculated optimal number; For the i-th ventilation section, i = 1, 2, ..., n, the following method is used to determine the optimal number k of jet fans currently turned on: i : Step 2.1, in the current ventilation control period ΔT, the ventilation controller calculates the traffic volume of each vehicle type in the current ventilation control period ΔT according to the real-time received entrance traffic volume data, exit traffic volume data and pre-entrance traffic volume data; and then obtains the required air volume Q for tunnel smoke dilution in the i-th ventilation section according to the obtained traffic volume of each vehicle type. req(VI)-i , the required air volume Q for tunnel CO dilution in the i-th ventilation section req(CO)_i and the tunnel ventilation air volume Q of the i-th ventilation section req(ac)_i ; Step 2.2: Use the following formula to obtain the required air volume Q of the tunnel in the i-th ventilation section: i : Q i =max(Q req(VI)-i ,Q req(CO)_i ,Q req(ac)_i ) (1) Step 2.3, use the following formula to obtain the exhaust outlet pressure rise Δp of the i-th ventilation section: e and the air outlet pressure rise Δp of the i-th ventilation section b The expression is: Where: Q ei is the exhaust volume of the ventilation shaft in the ith ventilation section; Q ri is the target air volume of the ith ventilation section; v e is the exhaust volume Q of the ventilation shaft in the i-th ventilation section ei The corresponding ventilation shaft exhaust wind speed; v ri is the target wind speed of the ith ventilation section, v ri =Q ri / A r ,A r is the clear cross-sectional area of the tunnel; α is the angle between the exhaust outlet of the ventilation shaft and the axial direction of the tunnel; ρ is the air density in the tunnel area; Q bi is the air supply volume of the ventilation shaft in the ith ventilation section; Q r(i+1) is the target air volume of the i+1th ventilation section; v b The air volume Q of the ventilation shaft bi The corresponding ventilation shaft air supply speed; v r(i+1) is the target wind speed of the i+1th ventilation section, v r(i+1) =Q r(i+1) / A r ; β is the angle between the ventilation shaft air outlet direction and the tunnel axis; Step 2.4: Use the following formula to obtain the tunnel ventilation resistance Δp of the i-th ventilation section: r The expression is: Among them: i is the local resistance coefficient of the tunnel in the ith ventilation section; r is the tunnel resistance coefficient along the i-th ventilation section; L is the tunnel length; D r is the equivalent diameter of the tunnel section; Step 2.5: Use the following formula to obtain the traffic ventilation force Δp of the i-th ventilation section: t The expression is: Among them: A m A is the equivalent impedance area of the vehicle in the i-th ventilation section; r is the clear cross-sectional area of the tunnel; n c is the number of vehicles in the tunnel; v t is the average speed of vehicles in the tunnel; Step 2.6: Use the following formula to obtain the natural ventilation force Δp in the tunnel of the i-th ventilation section: m The expression is: Where: v e is the wind speed in the ith ventilation section caused by natural wind; e is the local resistance coefficient at the inlet of the i-th ventilation section; Step 2.7, the pressure balance equation of the longitudinal ventilation mode of the i-th ventilation section is established as follows: Δp b +Δp e +k i Δp j =Δp r -Δp t +Δp m (7) Where: k i is the number of jet fans required to be arranged in the i-th ventilation section, and is the value to be evaluated; Δp j The pressure rise for a single jet fan; Step 2.8, solve the pressure balance equation of the longitudinal ventilation mode of the i-th ventilation section established in step 2.7, and obtain the optimal number of jet fans currently turned on in the i-th ventilation section, that is, the determined k i value; Among them, the traffic volume of each type of vehicle in the current ventilation control period ΔT is calculated as follows: The current ventilation control cycle ΔT is expressed as the bt-th ventilation control cycle; the traffic volume N of each vehicle type is obtained according to the following formula: If bt = 1, then N = N Em1 +C m If bt ≥ 2, then N = N Em_bt +N Em_(bt-1) -N Jm_bt Where: N Em1 The traffic volume of each type of vehicle detected and counted by the traffic volume data detection equipment before the entrance during the first ventilation control cycle; C m Indicates the traffic volume of each type of vehicle counted from the traffic volume data detection device before the entrance to the tunnel exit during the 0th ventilation control cycle; N Em_bt The traffic volume of each type of vehicle passing through the pre-entrance traffic volume data detection device in the bt ventilation control cycle, which is obtained by statistics of the pre-entrance traffic volume data detection device; N Em_(bt-1) The traffic volume of each type of vehicle passing through the pre-entrance traffic volume data detection device in the bt-1 ventilation control cycle, which is obtained by statistics of the pre-entrance traffic volume data detection device; N Jm_bt is the traffic volume of each type of vehicle exiting the tunnel exit during the bt ventilation control cycle, obtained by statistics from the exit traffic volume data detection equipment; The minimum distance between the traffic volume data detection equipment layout before the entrance and the tunnel exit is L min Determine using the following formula: in: is the maximum average vehicle speed, which is determined by: Among them, n a is the proportion of small cars during the statistical period; v a The maximum speed limit for small cars; n b is the proportion of large vehicles during the statistical period; v b The maximum speed limit for large vehicles.
2. According to claim 1, a super-long highway tunnel intelligent ventilation control optimization method is characterized in that: The required air volume Q for diluting smoke in the tunnel of the i-th ventilation section req(VI)-i , determined using the following formula: Where: q VI is the smoke benchmark emission; K VI f is the designed concentration of smoke; a(VI) is the vehicle condition factor considering smoke; f d is the vehicle density coefficient; f h(VI) f is the altitude coefficient for considering smoke; iv(VI) is the longitudinal slope-vehicle speed coefficient considering smoke; n D is the number of diesel vehicle types calculated in the current ventilation control cycle ΔT; m is n D One of the number of diesel vehicle types, m = 1, 2, ..., n D ; N m is the traffic volume of the mth diesel vehicle type; f m(VI) is the model coefficient of the mth diesel vehicle model taking smoke into consideration.
3. The method for optimizing intelligent ventilation control in a super-long highway tunnel according to claim 1 is characterized in that: The required air volume Q for tunnel CO dilution in the i-th ventilation section req(CO)_i , determined using the following formula: Where: q CO is the CO benchmark emission; δ is the CO design concentration; f a is the vehicle condition factor considering CO; h is the vehicle condition factor considering CO; iv is the longitudinal slope-vehicle speed coefficient considering CO; P0 is the standard atmospheric pressure; P is the atmospheric pressure at the tunnel site; T is the atmospheric pressure at the tunnel site; T0 is the standard temperature; n co is the number of vehicle types calculated in the current ventilation control cycle ΔT; w is n co One of the number of vehicle types, w=1,2,...,n co ; N w is the traffic volume of the wth vehicle type; f m is the vehicle type coefficient of the wth vehicle type category considering CO.
4. The method for optimizing intelligent ventilation control in a super-long highway tunnel according to claim 1 is characterized in that: The required air volume Q for tunnel ventilation in the i-th ventilation section req(ac)_i , determined using the following formula: Q req(ac)_i =v ac ·A r (1-3) Where: v ac The wind speed for tunnel ventilation.
5. The method for optimizing intelligent ventilation control in a super-long highway tunnel according to claim 1 is characterized in that: The equivalent impedance area of the vehicle in the i-th ventilation section A m , using the following formula: AM m M(1-r1)·A c2 ·ζ c2 +r1·A cl ·ζ c1 (5-1) Among them: r1 is the proportion of large vehicles; A c2 is the front projection area of a small vehicle; c2 A is the air resistance coefficient of a small vehicle; cl is the front projection area of large vehicles; c1 is the air resistance coefficient of large vehicles.
6. The method for optimizing intelligent ventilation control in a super-long highway tunnel according to claim 1 is characterized in that: The exhaust volume Q of the ventilation shaft in the i-th ventilation section ei and the ventilation shaft air volume Q of the i-th ventilation section bi , solved by the following method: Step 2.3.1, establish the equation system: Where: C2 is the concentration at the ventilation shaft outlet; C3 is the concentration inside the tunnel exit; Q sf is the equivalent fresh air volume in the airflow at the bottom of the ventilation shaft; Q i is the required air volume of the tunnel in the ith ventilation section; Q (i+1) is the required air volume of the tunnel in the i+1th ventilation section; Q ri is the target air volume of the ith ventilation section; Q r(i+1) is the required air volume of the tunnel in the i+1th ventilation section; The constraints are established as follows: 0.9≤C2≤1.0 (2-7) 0.9≤C3≤1.0 (2-8) Step 2.3.2, under the constraints, solve the equations established in step 2.3.1 to obtain the exhaust volume Q of the ventilation shaft in the i-th ventilation section ei and the ventilation shaft air volume Q of the i-th ventilation section bi .
7. The method for optimizing intelligent ventilation control in a super-long highway tunnel according to claim 1 is characterized in that: In step 2.7, Δp j The calculation is done using the following formula: Where: v j is the outlet wind speed of the jet fan; η is the friction loss reduction coefficient at the jet fan position.
8. The method for optimizing intelligent ventilation control in a super-long highway tunnel according to claim 1 is characterized in that: When the tunnel is divided into n ventilation sections, a ventilation shaft is arranged between every two adjacent ventilation sections, that is, the zth ventilation shaft is arranged between the i-th ventilation section and the i+1-th ventilation section, and y ventilation shafts are opened in the zth ventilation shaft. ez The exhaust volume of a single exhaust axial flow fan is Q ef , used to exhaust the polluted air in the i-th ventilation section, and at the same time open y bz The air supply volume of a single axial flow fan is Q. bf , used to deliver fresh air to the i+1th ventilation section; when the kth ventilation section is opened i When there are jet fans, the following formula is used to determine the number of exhaust axial fans to be opened y ez and the number of axial flow fans opened y bz : Among them: int() represents rounding up; Q ei represents the exhaust volume of the ventilation shaft in the i-th ventilation section; Q b(i+1) Represents the air supply volume of the ventilation shaft in the i+1th ventilation section.