A tunnel roof fall grouting repair system and use method
By designing a tunnel top grouting repair system including load columns, load-bearing mesh plates, grouting load-bearing pipes, grouting sealing pipes and grouting sealing trucks, high-pressure grouting material can be used to achieve sealing and bonding of the top of the tunnel. , solve the problems of low construction efficiency and poor safety in the prior art, and improve the building stability and safety of the tunnel tops.
Patent Information
- Application Number
- CN202410258462.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-07
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2044-03-07
AI Technical Summary
The existing tunnel top grouting and repair technology and equipment are inefficient in construction, and cannot provide timely safety protection. The equipment is easily restricted by the environment, and the construction difficulty and cost are high, resulting in increased damage and increased risk of secondary disasters.
A tunnel top grouting repair system including load columns, load-bearing mesh plates, grouting load-bearing pipes, grouting sealing pipes, guide pipes and grouting sealing trucks was designed to seal the top of the tunnel through high-pressure grouting material. and bond to improve structural strength and stability.
It has achieved rapid and safe roof repair of tunnels, reduced construction labor intensity and cost, improved building stability and safety at the top of tunnels, and reduced secondary disaster risks.
Smart Images

Figure CN118148668B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a tunnel roof fall grouting repair system and a use method, belonging to the technical field of grouting and plugging construction equipment. Background Art
[0002] In the process of mining mineral resources, tunnel construction and other operations, due to factors such as geological structure deformation, tunnel roof falls often occur, posing a great hidden danger to production safety. To address this issue, a variety of tunnel roof fall repair technologies or equipment have been developed. However, the traditional grouting technology and equipment currently used in grouting repair can meet the needs of actual construction operations, but the grouting operation efficiency is low, and it is impossible to provide timely and effective safety protection for the roof fall structure. At the same time, during the grouting repair operation, the grouting equipment is also susceptible to working environment restrictions, construction difficulty, construction labor intensity and cost are relatively high. As a result, during the current tunnel roof fall repair operation, it is often easy to increase damage due to the failure to carry out stop-loss protection in time, and the risk of secondary disasters also increases.
[0003] Therefore, in response to this situation, it is necessary to develop a plugging and repair equipment and corresponding plugging and repair process that can be applied to various types of tunnel structures, has a simple construction process, and has good equipment operation flexibility and safety. Summary of the invention
[0004] In view of the deficiencies in the prior art, the present invention provides a tunnel roof fall repair system and method to overcome the above defects and meet the needs of actual equipment operation.
[0005] In order to achieve the above object, the present invention is implemented through the following technical solutions:
[0006] A tunnel roof grouting repair system comprises a bearing column, a bearing mesh plate, a grouting bearing pipe, a grouting plugging pipe, a guide pipe, and a grouting plugging vehicle, wherein the bearing mesh plate is a grating plate structure with a rectangular cross section, the bearing mesh plate is coated on the outside of the tunnel top and is distributed parallel to the tunnel top, and the bearing mesh plate is connected to the tunnel top through a plurality of grouting bearing pipes, and each grouting bearing pipe surrounds the center of the bearing mesh plate and is evenly distributed at the edge of the bearing mesh plate, at least 80% of the effective length of the upper half of each grouting bearing pipe is embedded in the rock wall at the top of the tunnel, the axis of each grouting bearing pipe forms an angle of 30°-90° with the surface of the bearing mesh plate, and each grouting bearing pipe is connected to the grouting plugging vehicle through a guide pipe, and there are a plurality of guide pipes, and the surrounding They are evenly distributed around the axis of the bearing mesh plate, and each guide pipe is embedded in the bearing mesh plate respectively. At the same time, the upper half of the guide pipe is embedded in the rock wall at the top of the tunnel through the bearing mesh plate, and the lower half is located below the lower end surface of the bearing mesh plate. At the same time, each guide pipe is provided with a grouting plugging pipe coaxially distributed therewith, and at least 80% of the effective length of the grouting plugging pipe is embedded in the rock wall at the top of the tunnel. The axis of each grouting plugging pipe is at an angle of 40°-90° to the top of the tunnel. At the same time, each grouting plugging pipe is connected to the grouting plugging vehicle through a guide pipe. In addition, the lower end surface of the grouting bearing pipe is connected to a bearing column respectively, and is connected to the bottom of the tunnel through the bearing column. At the same time, the axis of the bearing column is at an angle of 0°-60° to the axis of the grouting bearing pipe.
[0007] Furthermore, the bearing column includes a bearing base, a flipping mechanism, a hydraulic support, a bearing column, and a clamp, wherein the bearing base is connected to the bottom of the tunnel and is distributed in parallel, the upper end surface of the bearing base is provided with a flipping mechanism, and is hinged to the lower half of the hydraulic support through the flipping mechanism, and the axis of the hydraulic support forms an angle of 0°-90° with the upper end surface of the bearing base, the upper end surface of the hydraulic support is connected to a bearing column and is coaxially distributed, the outer side surface of the bearing column is provided with a guide groove, and is slidably connected to at least two clamps through the guide groove, the axis of the clamp is distributed in parallel with the axis of the bearing column, and each clamp is evenly distributed along the axis direction of the bearing column, the bearing column is connected to the grouting bearing tube through the clamp, and the clamp is covered outside the grouting bearing tube and is coaxially distributed with the grouting bearing tube.
[0008] Furthermore, the grouting bearing pipe includes a connecting pipe head, a grouting anchor, a reinforcement plate, a bursting membrane, an anchor, and a slider, wherein the upper and lower end faces of the grouting anchor are connected to the connecting pipe head, and are connected to the guide pipe through the connecting pipe head, and the outer side of the grouting anchor is connected to the clamp of the bearing column, and a plurality of grouting ports evenly distributed around its axis are evenly distributed on the side wall of the upper half of the grouting anchor, and a bursting membrane coaxially distributed therewith is arranged in the grouting port and in the front end face of the grouting anchor, and a slider coaxially distributed therewith is arranged in the grouting anchor, the slider is slidably connected to the inner side face of the grouting anchor, and the spacing between the slider and the bursting membrane at the front end face of the grouting anchor is 0 to the length of the grouting anchor. The degree is 20%, and an anchor is arranged in the grouting anchor between the slider and the blasting membrane at the front end face of the grouting anchor, and no grouting port is arranged on the side wall of the grouting anchor between the slider and the blasting membrane at the front end face of the grouting anchor, and there are a plurality of reinforcing plates, each of which is coated on the outer side face of the grouting anchor corresponding to a grouting port, and the reinforcing plate is an arc-shaped plate structure coaxially distributed with the grouting anchor, and the projection of the reinforcing plate on the horizontal plane is any one of an isosceles trapezoid and an isosceles triangle, and at the same time, the width of the rear end face of the reinforcing plate is at least 3 times the width of the front end face, and the rear end face of the reinforcing plate is hinged to the outer side face of the grouting anchor by an elastic hinge, and the axis of the reinforcing plate is at an angle of 0°-90° with the axis of the grouting anchor.
[0009] Furthermore, at least one wedge is provided on the upper surface of the reinforcing plate, and the axis of the wedge is perpendicular to the upper surface of the reinforcing plate.
[0010] Furthermore, the grouting plugging pipe includes a three-way valve, a grouting pipe, a grouting bag, a grouting anchor, an overflow port, a bursting membrane, a control valve, a retaining ring, and a connecting pipe head, wherein the rear end face of the grouting anchor is connected to the grouting plugging workshop through the connecting pipe head, and the outer side of the grouting anchor is provided with a connecting thread, and is connected to a plurality of retaining rings through the connecting thread, each retaining ring is covered on the outside of the grouting anchor and is evenly distributed along the axial direction of the grouting anchor, and the spacing between two adjacent retaining rings is 1.1-1.5 times the length of the grouting bag, and at least one overflow port is provided on the side wall of the grouting anchor corresponding to the two adjacent retaining rings, and the overflow port and the grouting anchor are A bursting membrane is arranged in the front end, and the bursting membrane is used for sealing. There are two grouting bags in total, and the two grouting bags are respectively wrapped outside the grouting anchor and coaxially distributed with the grouting anchor. At the same time, the two grouting bags are respectively distributed in front of the front end baffle ring and behind the rear end baffle ring. At the same time, the two grouting bags are respectively connected with the grouting pipe through the control valve. The grouting pipe is embedded in the grouting anchor and distributed parallel to the axis of the grouting anchor. The three-way valve is located outside the rear end face of the grouting anchor, and one end of the three-way valve is connected with the grouting sealing vehicle through the guide pipe, one end is connected with the grouting anchor, and the remaining end is connected with the grouting pipe through the connecting pipe head.
[0011] Furthermore, the retaining rings are all of trumpet-shaped structures, the rear end face of the retaining ring is connected to the grouting anchor rod, and the diameter of the rear end face is 30%-80% of the diameter of the front end face, and the front half of the retaining ring is provided with at least three deformation grooves evenly distributed around its axis, the length of the deformation groove is 30%-80% of the length of the retaining ring side wall, and the width is 3-10 mm.
[0012] Furthermore, the grouting and plugging vehicle includes a load-bearing vehicle, a load-bearing keel, a grouting liquid storage tank, a main boost pump, an auxiliary boost pump, a pressure sensor, a flow sensor, a multi-way valve, a diverter bar and a driving circuit. The load-bearing vehicle is a vehicle driven by any one of electricity, fuel and a winch. The load-bearing vehicle is connected to the load-bearing keel. There is at least one grouting liquid storage tank, and each grouting liquid storage tank is embedded in the load-bearing keel and is connected to the main boost pump and the auxiliary boost pump through a guide pipe, respectively. The main boost pump and the auxiliary boost pump are respectively connected to at least two diverter bars through a multi-way valve, wherein the main boost pump is connected to each grouting load-bearing pipe through the diverter bar, and the auxiliary boost pump is connected to each grouting and plugging pipe through the diverter bar. At the same time, a pressure sensor and a flow sensor are provided at the connection position between the diverter bar and each guide pipe. The driving circuit is connected to the load-bearing vehicle, and is respectively electrically connected to the load-bearing vehicle, the main boost pump, the auxiliary boost pump, the pressure sensor, the flow sensor and the multi-way valve.
[0013] A method for repairing and reinforcing a tunnel roof fall grouting repair system, comprising the following steps:
[0014] S1, initial bearing, first set the bearing mesh plate according to the tunnel roof fall structure and area, and make the bearing mesh plate area at least 1.5 times the tunnel roof fall structure area, and make the bearing mesh plate covered outside the tunnel roof fall structure under the support of the bearing column, and at the same time, transfer the grouting plugging vehicle to the working position, and when the grouting plugging vehicle is transferred, the grouting bearing pipe and the grouting plugging pipe are transferred at the same time; then, preliminarily connect the grouting bearing pipe with the bearing column, and make the grouting bearing pipe and the clamp of the bearing column slidingly connected, and at the same time, insert the upper half of the grouting bearing pipe through the bearing mesh plate into the rock wall outside the tunnel top roof fall area, so that the bearing mesh plate is positioned by the grouting bearing pipe, and after the grouting bearing pipe completes the positioning of the bearing mesh plate, the bearing mesh plate is connected with the bearing column, and the bearing column is separated from the bearing mesh plate, so as to realize the bearing protection of the tunnel top roof fall area by the bearing mesh plate;
[0015] S2, strengthening the bearing capacity of the roof fall area; after completing step S1, the upper half of each grouting plugging pipe is inserted through the bearing mesh plate into the rock layer in the roof fall area at the top of the tunnel, and the grouting plugging pipe is used to strengthen the positioning of the bearing mesh plate on the one hand, and to preliminarily strengthen and fix the rock layer in the roof fall area on the other hand;
[0016] S3, plugging positioning, after completing step S2, drive the grouting plugging vehicle to run, firstly, the main booster pump pressurizes the grouting liquid cached in the grouting liquid storage tank of the grouting plugging vehicle and pours it into each grouting bearing pipe for grouting operation, and uses high-pressure grouting material to, on the one hand, discharge the anchoring agent in the grouting bearing pipe from the front end face of the grouting bearing pipe, and connect the front end face of the grouting bearing pipe with the rock wall at the top of the tunnel by the anchoring agent; on the other hand, the high-pressure grouting amount overflows through the grouting port of the grouting bearing pipe and seeps into the cracks of the rock wall and the gap between the rock wall and the grouting anchor rod of the grouting bearing pipe, and after the anchoring agent and the grouting material solidify, the grouting bearing pipe can be used to seal and bond the rock layers, thereby improving the grouting efficiency. The structural strength of the connection between the grout-bearing pipe and the rock wall; then the auxiliary booster pump pressurizes the grouting liquid buffered in the grouting liquid storage tank of the grouting sealing vehicle and pours it into each grouting sealing pipe for grouting operation. On the one hand, the grouting bag provided in the grouting sealing pipe expands in volume driven by the pressure of the grouting material, thereby sealing the tunnel roof fall area and improving the positioning stability between the grouting sealing pipe and the rock wall; on the other hand, the grouting material penetrates into the cracks of the rock wall in the tunnel roof fall area through the overflow port provided in the grouting sealing pipe, thereby strengthening the connection of the rock wall, thereby achieving the effect of sealing and strengthening the tunnel roof fall area; finally, each bearing column is dismantled and recycled to complete the tunnel roof fall repair operation.
[0017] The system of the present invention has a simple structure, strong environmental adaptability, good versatility and construction flexibility, and compared with traditional grouting and plugging equipment and processes, it can quickly strengthen and reinforce the tunnel roof collapse, promptly carry out damage prevention and repair operations, prevent the risk of aggravated roof collapse hazards and secondary disasters, and improve the stability and safety of the building construction on the top of the tunnel. At the same time, during construction, it can effectively improve the mechanization and automation level of construction operations, thereby effectively reducing the labor intensity and cost of construction operations. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] The present invention will be described in detail below with reference to the accompanying drawings and specific embodiments.
[0019] Figure 1 It is a schematic diagram of the system structure of the present invention;
[0020] Figure 2 It is a schematic diagram of the structure of the load-bearing column;
[0021] Figure 3 It is a schematic diagram of the local structure of the grouting bearing pipe;
[0022] Figure 4 This is a schematic diagram of the local structure of the grouting plugging pipe;
[0023] Figure 5 It is a schematic diagram of the partial structure of the cutaway view of the guide tube;
[0024] Figure 6This is a schematic diagram of the local structure of the grouting and plugging vehicle from above;
[0025] Figure 7 The figure is a flow chart of the method for using the present invention. DETAILED DESCRIPTION
[0026] In order to make the technical means, creative features, objectives and effects achieved by the present invention easy to understand, the present invention is further explained below in conjunction with specific implementation methods.
[0027] like Figure 1-6 As shown, a tunnel roof grouting repair system includes a bearing column 1, a bearing mesh plate 2, a grouting bearing pipe 3, a grouting sealing pipe 4, a guide pipe 5, and a grouting sealing vehicle 6, wherein the bearing mesh plate 2 is a grating plate structure with a rectangular cross section, the bearing mesh plate 2 is coated on the outside of the tunnel top and is distributed parallel to the tunnel top, and the bearing mesh plate 2 is connected to the tunnel top through a plurality of grouting bearing pipes 3, and each grouting bearing pipe 3 is evenly distributed at the edge of the bearing mesh plate 2 around the center of the bearing mesh plate 2, at least 80% of the effective length of the upper half of each grouting bearing pipe 3 is embedded in the rock wall at the top of the tunnel, and the axis of each grouting bearing pipe 3 is at an angle of 30°-90° with the plate surface of the bearing mesh plate 2, and each grouting bearing pipe 3 is connected to the grouting sealing vehicle 6 through a guide pipe, and the guide pipe 5 is connected to the grouting sealing vehicle 6 through a guide pipe. The guide tubes 5 are evenly distributed around the axis of the bearing mesh plate 2, and each guide tube 5 is respectively embedded in the bearing mesh plate 2. At the same time, the upper half of the guide tube 5 is embedded in the rock wall at the top of the tunnel through the bearing mesh plate 2, and the lower half is located below the lower end surface of the bearing mesh plate 2. At the same time, each guide tube 5 is provided with a grouting plugging tube 4 coaxially distributed therewith, and at least 80% of the effective length of the grouting plugging tube 4 is embedded in the rock wall at the top of the tunnel. The axis of each grouting plugging tube 4 is at an angle of 40°-90° to the top of the tunnel. At the same time, each grouting plugging tube 4 is connected to the grouting plugging vehicle 6 through a guide pipe. In addition, the lower end surface of the grouting bearing tube 3 is respectively connected to a bearing column 1, and is connected to the bottom of the tunnel through the bearing column 1. At the same time, the axis of the bearing column 1 is at an angle of 0°-60° to the axis of the grouting bearing tube 3.
[0028] In this embodiment, the bearing column 1 includes a bearing base 11, a flipping mechanism 12, a hydraulic support 13, a bearing column 14, and a hoop 15, wherein the bearing base 11 is connected to the bottom of the tunnel and is distributed in parallel, the upper end surface of the bearing base 11 is provided with a flipping mechanism 12, and is hinged to the lower half of the hydraulic support 13 through the flipping mechanism 12, and the axis of the hydraulic support 13 is at an angle of 0°-90° with the upper end surface of the bearing base 11, the upper end surface of the hydraulic support 13 is connected to a bearing column 14 and is coaxially distributed, the outer side surface of the bearing column 14 is provided with a guide groove 16, and is slidably connected to at least two hoops 15 through the guide groove 16, the axis of the hoop 15 is distributed in parallel with the axis of the bearing column 14, and each hoops 15 is evenly distributed along the axis direction of the bearing column 14, the bearing column 14 is connected to the grouting bearing pipe 3 through the hoop 15, and the hoop 15 is covered outside the grouting bearing pipe 3 and is coaxially distributed with the grouting bearing pipe 3.
[0029] It should be noted that the grouting bearing pipe 3 includes a connecting pipe head 31, a grouting anchor rod 32, a reinforcing plate 33, a bursting membrane 34, an anchor 35, and a slider 36, wherein the upper and lower end faces of the grouting anchor rod 32 are connected to the connecting pipe head 31, and are connected to the guide pipe through the connecting pipe head 31, and the outer side surface of the grouting anchor rod 32 is connected to the clamp 15 of the bearing column 1, and a plurality of grouting ports 37 uniformly distributed around the axis of the grouting anchor rod 32 are evenly distributed on the side wall of the upper half of the grouting anchor rod 32, and a bursting membrane 34 coaxially distributed therewith is provided in the grouting port 37 and in the front end surface of the grouting anchor rod 32, and a slider 36 coaxially distributed therewith is provided in the grouting anchor rod 32, and the slider 36 is slidably connected to the inner side surface of the grouting anchor rod 32, and the distance between the slider 36 and the bursting membrane 34 at the front end surface of the grouting anchor rod 32 is 0 to the grouting anchor rod. 32, and an anchor 35 is arranged in the grouting anchor 32 between the slider 36 and the bursting membrane 34 at the front end face of the grouting anchor 32, and no grouting port 37 is arranged on the side wall of the grouting anchor 32 between the slider 36 and the bursting membrane 34 at the front end face of the grouting anchor 32, and a plurality of reinforcing plates 33 are provided, each reinforcing plate 33 is covered with an outer side face of the grouting anchor 32 corresponding to a grouting port 37, and the reinforcing plate 33 is an arc-shaped plate structure coaxially distributed with the grouting anchor 32, and the reinforcing plate 33 is projected on the horizontal plane as any one of an isosceles trapezoid and an isosceles triangle, and at the same time, the rear end face width of the reinforcing plate 33 is at least 3 times the width of the front end face, and the rear end face of the reinforcing plate 33 is hinged to the outer side face of the grouting anchor 32 through an elastic hinge, and the axis of the reinforcing plate 33 is at an angle of 0°-90° with the axis of the grouting anchor 32.
[0030] For further optimization, at least one wedge 38 is disposed on the upper end surface of the reinforcing plate 33 , and the axis of the wedge 38 is perpendicular to the upper end surface of the reinforcing plate 33 .
[0031] The set blasting membrane can be fractured only after the grouting material pressure in the grouting anchor reaches the set value during grouting plugging. On the one hand, the grouting material pressure is used to drive the anchoring agent to be discharged out of the grouting anchor, so that the anchoring agent can bond and position the grouting anchor and the rock wall; on the other hand, the grouting material can be driven by high pressure to quickly seep into the cracks in the rock wall, so as to strengthen the bonding of the rock structure.
[0032] The reinforcing plate and the sharp wedges arranged on the reinforcing plate are turned over by the driving of the grouting material when the high-pressure grouting material breaks through the blasting membrane and jets to the rock formation. During the turning process, the reinforcing plate and the sharp wedges arranged on the reinforcing plate penetrate into the rock formation, thereby further improving the positioning stability and bearing capacity of the grouting bearing tube.
[0033] At the same time, the grouting plugging pipe 4 includes a three-way valve 46, a grouting pipe 41, a grouting bag 42, a grouting anchor rod 32, an overflow port 43, a bursting membrane 34, a control valve 44, a retaining ring 45, and a connecting pipe head 31, wherein the rear end face of the grouting anchor rod 31 is connected to the grouting plugging vehicle 6 through the connecting pipe head 31, and the outer side of the grouting anchor rod 32 is provided with a connecting thread, and is connected to a plurality of retaining rings 45 through the connecting thread, each retaining ring 45 is covered on the outside of the grouting anchor rod 32 and is evenly distributed along the axial direction of the grouting anchor rod 32, and the spacing between two adjacent retaining rings 45 is 1.1-1.5 times the length of the grouting bag 42, and at least one overflow port 43 is provided on the side wall of the grouting anchor rod 32 corresponding to the two adjacent retaining rings 45, and the overflow port 43 and the grouting anchor rod A bursting membrane 34 is provided in the front end of each grouting anchor rod 32, and the bursting membrane 34 is used for blocking. There are two grouting bags 42 in total, and the two grouting bags 42 are respectively wrapped around the outside of the grouting anchor rod 32 and coaxially distributed with the grouting anchor rod 32. At the same time, the two grouting bags 42 are respectively distributed in front of the front end retaining ring 45 and behind the rear end retaining ring 45. At the same time, the two grouting bags 42 are respectively connected with the grouting pipe 41 through the control valve 44. The grouting pipe 41 is embedded in the grouting anchor rod 32 and distributed parallel to the axis of the grouting anchor rod 32. The three-way valve 46 is located outside the rear end surface of the grouting anchor rod 32, and one end of the three-way valve 46 is connected to the grouting sealing vehicle 6 through the guide pipe, one end is connected to the grouting anchor rod 32, and the remaining end is connected to the grouting pipe 41 through the connecting pipe head 31.
[0034] The blasting membrane can be set to fracture the grouting material in the grouting anchor rod only after the pressure reaches the set value during grouting plugging, so that the grouting material can quickly seep into the cracks in the rock wall under high pressure, thus strengthening the bonding of the rock structure.
[0035] At the same time, the retaining rings 45 are all of a trumpet-shaped structure, the rear end face of the retaining ring 45 is connected to the grouting anchor rod 32, and the diameter of the rear end face is 30%-80% of the diameter of the front end face, and the front half of the retaining ring 45 is provided with at least three deformation grooves 47 evenly distributed around its axis, and the length of the deformation groove 47 is 30%-80% of the length of the side wall of the retaining ring 45, and the width is 3-10 mm.
[0036] The retaining ring passes through the deformation groove, and when driven by the grouting pressure or when the rock formation is deformed, the retaining ring undergoes elastic deformation through the deformation groove, thereby improving the positioning stability of the grouting plugging pipe.
[0037] In this embodiment, the grouting plugging vehicle 6 includes a carrier 61, a carrier keel 62, a grouting liquid storage tank 63, a main boost pump 64, an auxiliary boost pump 65, a pressure sensor 66, a flow sensor 67, a multi-way valve 68, a diversion row 69 and a drive circuit 60. The carrier 61 is a vehicle driven by any one of electricity, fuel and a winch. The carrier 61 is connected to the carrier keel 62. There is at least one grouting liquid storage tank 63, and each grouting liquid storage tank 63 is embedded in the carrier keel 62, and is respectively connected to the main boost pump 64 and the auxiliary boost pump 65 through a guide pipe, wherein the main boost pump 64 and the auxiliary boost pump 65 are respectively connected to the main boost pump 64 and the auxiliary boost pump 65 through a multi-way valve 68. At least two diversion rows 69 are connected, wherein the main boost pump 64 is connected to each grouting bearing pipe 3 through the diversion row 69, and the auxiliary boost pump 65 is connected to each grouting plugging pipe 4 through the diversion row 69. At the same time, a pressure sensor 66 and a flow sensor 67 are provided at the connection position between the diversion row 69 and each guide pipe. The driving circuit 60 is connected to the bearing carrier 61, and is electrically connected to the bearing carrier 61, the main boost pump 64, the auxiliary boost pump 65, the pressure sensor 66, the flow sensor 67, and the multi-way valve 68 respectively. At the same time, the multi-way valve 68, the diversion row 69, the main boost pump 64, and the auxiliary boost pump 65 are all connected to the bearing keel 62 and are located inside the bearing keel 62.
[0038] The driving circuit 60 is a circuit system based on a programmable controller, and a serial communication circuit is also provided in the driving circuit.
[0039] In addition, the guide tube 5 is a hollow tubular structure of any one of a cylindrical and drum-shaped structure. At least one sealing ring 51 coaxially distributed therewith is arranged in the guide tube 5, and the sealing ring 51 is covered on the outside of the grouting sealing tube 4 and distributed along the axial direction of the grouting sealing tube 4.
[0040] like Figure 7 As shown, a method for repairing and reinforcing a tunnel roof fall grouting repair system comprises the following steps:
[0041] S1, initial bearing, first set the bearing mesh plate according to the tunnel roof fall structure and area, and make the bearing mesh plate area at least 1.5 times the tunnel roof fall structure area, and make the bearing mesh plate covered outside the tunnel roof fall structure under the support of the bearing column, and at the same time, transfer the grouting plugging vehicle to the working position, and when the grouting plugging vehicle is transferred, the grouting bearing pipe and the grouting plugging pipe are transferred at the same time; then, preliminarily connect the grouting bearing pipe with the bearing column, and make the grouting bearing pipe and the clamp of the bearing column slidingly connected, and at the same time, insert the upper half of the grouting bearing pipe through the bearing mesh plate into the rock wall outside the tunnel top roof fall area, so that the bearing mesh plate is positioned by the grouting bearing pipe, and after the grouting bearing pipe completes the positioning of the bearing mesh plate, the bearing mesh plate is connected with the bearing column, and the bearing column is separated from the bearing mesh plate, so as to realize the bearing protection of the tunnel top roof fall area by the bearing mesh plate;
[0042] S2, strengthening the bearing capacity of the roof fall area; after completing step S1, the upper half of each grouting plugging pipe is inserted through the bearing mesh plate into the rock layer in the roof fall area at the top of the tunnel, and the grouting plugging pipe is used to strengthen the positioning of the bearing mesh plate on the one hand, and to preliminarily strengthen and fix the rock layer in the roof fall area on the other hand;
[0043] S3, plugging positioning, after completing step S2, drive the grouting plugging vehicle to run, firstly, the main booster pump pressurizes the grouting liquid cached in the grouting liquid storage tank of the grouting plugging vehicle and pours it into each grouting bearing pipe for grouting operation, and uses high-pressure grouting material to, on the one hand, discharge the anchoring agent in the grouting bearing pipe from the front end face of the grouting bearing pipe, and connect the front end face of the grouting bearing pipe with the rock wall at the top of the tunnel by the anchoring agent; on the other hand, the high-pressure grouting amount overflows through the grouting port of the grouting bearing pipe and seeps into the cracks of the rock wall and the gap between the rock wall and the grouting anchor rod of the grouting bearing pipe, and after the anchoring agent and the grouting material solidify, the grouting bearing pipe can be used to seal and bond the rock layers, thereby improving the grouting efficiency. The structural strength of the connection between the grout-bearing pipe and the rock wall; then the auxiliary booster pump pressurizes the grouting liquid buffered in the grouting liquid storage tank of the grouting sealing vehicle and pours it into each grouting sealing pipe for grouting operation. On the one hand, the grouting bag provided in the grouting sealing pipe expands in volume driven by the pressure of the grouting material, thereby sealing the tunnel roof fall area and improving the positioning stability between the grouting sealing pipe and the rock wall; on the other hand, the grouting material penetrates into the cracks of the rock wall in the tunnel roof fall area through the overflow port provided in the grouting sealing pipe, thereby strengthening the connection of the rock wall, thereby achieving the effect of sealing and strengthening the tunnel roof fall area; finally, each bearing column is dismantled and recycled to complete the tunnel roof fall repair operation.
[0044] The system of the present invention has a simple structure, strong environmental adaptability, good versatility and construction flexibility, and compared with traditional grouting and plugging equipment and processes, it can quickly strengthen and reinforce the tunnel roof collapse, promptly carry out damage prevention and repair operations, prevent the risk of aggravated roof collapse hazards and secondary disasters, and improve the stability and safety of the building construction on the top of the tunnel. At the same time, during construction, it can effectively improve the mechanization and automation level of construction operations, thereby effectively reducing the labor intensity and cost of construction operations.
[0045] It should be understood by those skilled in the art that the present invention is not limited by the above-described embodiments. The above-described embodiments and descriptions are merely illustrative of the principles of the present invention. Various changes and improvements may be made to the present invention without departing from the spirit and scope of the present invention. These changes and improvements fall within the scope of the present invention to be protected. The scope of protection of the present invention is defined by the appended claims and their equivalents.
Claims
1. A tunnel roof fall grouting repair system, characterized in that: The tunnel roof grouting repair system includes a bearing column, a bearing mesh, a grouting bearing pipe, a grouting sealing pipe, a guide pipe, and a grouting sealing vehicle, wherein the bearing mesh is a grating plate structure with a rectangular cross section, the bearing mesh is coated on the outside of the tunnel top and is distributed parallel to the tunnel top, and the bearing mesh is connected to the tunnel top through a plurality of grouting bearing pipes, and each grouting bearing pipe is evenly distributed at the edge of the bearing mesh around the center of the bearing mesh, at least 80% of the effective length of the upper half of each grouting bearing pipe is embedded in the rock wall at the top of the tunnel, the axis of each grouting bearing pipe is at an angle of 30°-90° with the surface of the bearing mesh, and each grouting bearing pipe is connected to the grouting sealing vehicle through a guide pipe, and the guide pipes are several, They are evenly distributed around the axis of the bearing mesh plate, and each guide pipe is embedded in the bearing mesh plate respectively. At the same time, the upper half of the guide pipe is embedded in the rock wall at the top of the tunnel through the bearing mesh plate, and the lower half is located below the lower end surface of the bearing mesh plate. At the same time, each guide pipe is provided with a grouting plugging pipe coaxially distributed therewith, and at least 80% of the effective length of the grouting plugging pipe is embedded in the rock wall at the top of the tunnel. The axis of each grouting plugging pipe is at an angle of 40°-90° to the top of the tunnel. At the same time, each grouting plugging pipe is connected to a grouting plugging vehicle through a guide pipe. In addition, the lower end surface of the grouting bearing pipe is connected to a bearing column respectively, and is connected to the bottom of the tunnel through the bearing column. At the same time, the axis of the bearing column is at an angle of 0°-60° to the axis of the grouting bearing pipe.
2. A tunnel roof fall grouting repair system according to claim 1, characterized in that: The bearing column includes a bearing base, a flipping mechanism, a hydraulic support, a bearing column, and a hoop, wherein the bearing base is connected to the bottom of the tunnel and is distributed in parallel, the upper end surface of the bearing base is provided with a flipping mechanism, and is hinged to the lower half of the hydraulic support through the flipping mechanism, and the axis of the hydraulic support forms an angle of 0°-90° with the upper end surface of the bearing base, the upper end surface of the hydraulic support is connected to a bearing column and is coaxially distributed, the outer side surface of the bearing column is provided with a guide groove, and is slidably connected to at least two hoops through the guide groove, the axis of the hoop is distributed in parallel with the axis of the bearing column, and each hoops is evenly distributed along the axis direction of the bearing column, the bearing column is connected to the grouting bearing tube through the hoop, and the hoop is covered outside the grouting bearing tube and is coaxially distributed with the grouting bearing tube.
3. A tunnel roof fall grouting repair system according to claim 1 or 2, characterized in that: The grouting bearing pipe comprises a connecting pipe head, a grouting anchor, a reinforcing plate, a bursting membrane, an anchoring agent, and a slider, wherein the rear end face of the grouting anchor is connected to the connecting pipe head and communicated with the guide pipe through the connecting pipe head, and the outer side face of the grouting anchor is connected to the clamp of the bearing column, and the side wall of the upper half of the grouting anchor is provided with a plurality of grouting ports evenly distributed around its axis, a bursting membrane coaxially distributed therewith is provided in the grouting port and in the front end face of the grouting anchor, a slider coaxially distributed therewith is provided in the grouting anchor, the slider is slidably connected to the inner side face of the grouting anchor, and the spacing between the slider and the bursting membrane at the front end face of the grouting anchor is 0 to 20 of the length of the grouting anchor. %, and an anchor is arranged in the grouting anchor between the slider and the blasting membrane at the front end face of the grouting anchor, and no grouting port is arranged on the side wall of the grouting anchor between the slider and the blasting membrane at the front end face of the grouting anchor, and there are a number of reinforcing plates, each of which is coated on the outer side face of the grouting anchor corresponding to a grouting port, and the reinforcing plate is an arc-shaped plate structure coaxially distributed with the grouting anchor, and the projection of the reinforcing plate on the horizontal plane is any one of an isosceles trapezoid and an isosceles triangle, and at the same time, the width of the rear end face of the reinforcing plate is at least 3 times the width of the front end face, and the rear end face of the reinforcing plate is hinged to the outer side face of the grouting anchor by an elastic hinge, and the axis of the reinforcing plate is at an angle of 0°-90° with the axis of the grouting anchor.
4. A tunnel roof fall grouting repair system according to claim 3, characterized in that: The upper surface of the reinforcing plate is provided with at least one wedge, and the axis of the wedge is vertically distributed to the upper surface of the reinforcing plate.
5. A tunnel roof fall grouting repair system according to claim 1, characterized in that: The grouting plugging pipe comprises a three-way valve, a grouting pipe, a grouting bag, a grouting anchor, an overflow port, a bursting membrane, a control valve, a retaining ring, and a connecting pipe head, wherein the rear end face of the grouting anchor is connected to the grouting plugging workshop through the connecting pipe head, the outer side face of the grouting anchor is provided with a connecting thread, and is connected to a plurality of retaining rings through the connecting thread, each retaining ring is covered on the outside of the grouting anchor and is evenly distributed along the axial direction of the grouting anchor, and the spacing between two adjacent retaining rings is 1.1-1.5 times the length of the grouting bag, and at least one overflow port is provided on the corresponding grouting anchor side wall between two adjacent retaining rings, and the overflow port and the front end of the grouting anchor are A bursting membrane is arranged inside each grouting anchor rod, and the bursting membrane is used for sealing. There are two grouting bags in total, and the two grouting bags are respectively wrapped around the outside of the grouting anchor rod and coaxially distributed with the grouting anchor rod. At the same time, the two grouting bags are respectively distributed in front of the front end baffle ring and behind the rear end baffle ring. At the same time, the two grouting bags are respectively connected with the grouting pipe through the control valve. The grouting pipe is embedded in the grouting anchor rod and distributed parallel to the axis of the grouting anchor rod. The three-way valve is located outside the rear end face of the grouting anchor rod, and one end of the three-way valve is connected with the grouting sealing vehicle through the guide pipe, one end is connected with the grouting anchor rod, and the remaining end is connected with the grouting pipe through the connecting pipe head.
6. A tunnel roof fall grouting repair system according to claim 5, characterized in that: The retaining rings are all of trumpet-shaped structures, the rear end face of the retaining ring is connected to the grouting anchor rod, and the diameter of the rear end face is 30%-80% of the diameter of the front end face. The front half of the retaining ring is provided with at least three deformation grooves evenly distributed around its axis, the length of the deformation groove is 30%-80% of the length of the retaining ring side wall, and the width is 3-10 mm.
7. A tunnel roof fall grouting repair system according to claim 1, characterized in that: The grouting and plugging vehicle comprises a load-bearing vehicle, a load-bearing keel, a grouting liquid storage tank, a main boosting pump, an auxiliary boosting pump, a pressure sensor, a flow sensor, a multi-way valve, a diverter bar and a driving circuit. The load-bearing vehicle is a vehicle driven by any one of electricity, fuel and a winch. The load-bearing vehicle is connected to the load-bearing keel. There is at least one grouting liquid storage tank, and each grouting liquid storage tank is embedded in the load-bearing keel and is connected to the main boosting pump and the auxiliary boosting pump through a guide pipe, respectively. The main boosting pump and the auxiliary boosting pump are respectively connected to at least two diverter bars through a multi-way valve, wherein the main boosting pump is connected to each grouting load-bearing pipe through the diverter bar, and the auxiliary boosting pump is connected to each grouting and plugging pipe through the diverter bar. At the same time, a pressure sensor and a flow sensor are arranged at the connection position between the diverter bar and each guide pipe. The driving circuit is connected to the load-bearing vehicle, and is respectively electrically connected to the load-bearing vehicle, the main boosting pump, the auxiliary boosting pump, the pressure sensor, the flow sensor and the multi-way valve.
8. The repair and reinforcement method of a tunnel roof fall grouting repair system according to claim 1, characterized in that: The repair and reinforcement method of the tunnel roof grouting repair system comprises the following steps: S1, preliminary bearing, firstly, a bearing mesh is set according to the tunnel roof structure and area, and the area of the bearing mesh is at least 1.5 times the area of the tunnel roof structure, and the bearing mesh is covered on the outside of the tunnel roof structure under the support of the bearing column, and at the same time, the grouting and plugging vehicle is transported to the working position, and when the grouting and plugging vehicle is transported, the grouting bearing pipe and the grouting and plugging pipe are transported at the same time; then, the grouting bearing pipe is preliminarily connected to the bearing column, and the grouting bearing pipe and the clamp of the bearing column are slidably connected, and at the same time, the upper half of the grouting bearing pipe is inserted through the bearing mesh Enter into the outer rock wall of the roof fall area at the top of the tunnel, realize the positioning of the bearing mesh plate by the grouting bearing pipe, and after the grouting bearing pipe completes the positioning of the bearing mesh plate, connect the bearing mesh plate with the bearing column, so as to realize the bearing protection of the roof fall area at the top of the tunnel by the bearing mesh plate; S2, strengthen the bearing of the roof fall area; after completing step S1, insert the upper half of each grouting plugging pipe through the bearing mesh plate into the rock layer of the roof fall area at the top of the tunnel, and the grouting plugging pipe strengthens the positioning of the bearing mesh plate on the one hand; on the other hand, the rock layer in the roof fall area is preliminarily strengthened and fixed; S3, plugging positioning, after completing step S2, drive the grouting plugging vehicle During operation, the main booster pump first pressurizes the grouting liquid buffered in the grouting liquid storage tank of the grouting and sealing vehicle and then pours it into each grouting bearing pipe for grouting operation. The high-pressure grouting material is used to, on the one hand, discharge the anchoring agent in the grouting bearing pipe from the front end face of the grouting bearing pipe, and the anchoring agent connects the front end face of the grouting bearing pipe with the rock wall at the top of the tunnel; on the other hand, the high-pressure grouting material overflows through the grouting port of the grouting bearing pipe and seeps into the cracks in the rock wall and the gap between the rock wall and the grouting anchor rods of the grouting bearing pipe. After the anchoring agent and the grouting material solidify, the grouting bearing pipe can seal and bond the rock layers, thereby improving the connection strength between the grouting bearing pipe and the rock wall. Structural strength; then the auxiliary booster pump pressurizes the grouting liquid cached in the grouting liquid storage tank of the grouting sealing vehicle and pours it into each grouting sealing pipe for grouting operation. On the one hand, the grouting bag provided in the grouting sealing pipe expands in volume driven by the pressure of the grouting material, thereby sealing the tunnel roof fall area and improving the positioning stability between the grouting sealing pipe and the rock wall; on the other hand, the grouting material penetrates into the cracks of the rock wall in the tunnel roof fall area through the overflow port provided in the grouting sealing pipe, thereby connecting and strengthening the rock wall, thereby achieving the effect of sealing and strengthening the tunnel roof fall area; finally, the bearing columns are dismantled and recycled to complete the tunnel roof fall repair operation.