A new method for deep coalbed methane process intervention timing for the entire life cycle

By combining jet pumps and tubing with the Hagedon-Brown model, the timing of process intervention in deep coalbed methane wells was optimized, solving the problem of poor process adaptability in deep coalbed methane wells and achieving efficient production and reservoir protection throughout the entire life cycle.

CN118208188BActive Publication Date: 2024-11-08SOUTHWEST PETROLEUM UNIV
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410383254.X
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-04-01
Publication Date
2024-11-08
Estimated Expiration
2044-04-01

AI Technical Summary

Technical Problem

Deep coalbed methane wells suffer from poor process adaptability, frequent shutdowns and well repairs, which affect the production cycle and damage the reservoir, resulting in discontinuous production release.

Method used

By combining jet pumps and tubing, and using the Hagedon-Brown model, the appropriate timing for the process can be determined. The jet pump is run into the tubing before cavitation occurs, optimizing wellbore energy utilization and achieving full life-cycle production.

Benefits of technology

Effectively determine the timing of technological intervention in deep coalbed methane wells, optimize production plans, reduce the frequency of shutdowns and well workovers, and improve production continuity and reservoir protection.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118208188B_ABST
    Figure CN118208188B_ABST
Patent Text Reader

Abstract

The invention relates to a new method for deep coalbed methane process intervention timing for the whole life cycle; the method solves the problems of single deep coalbed methane drainage process, poor process adaptability and inability of the process to match the coalbed methane mining in the whole life cycle; the technical scheme is: by calculating the cavitation limit flow ratio Mc and the dimensionless volume flow ratio M, if M>Mc, cavitation occurs and the jet pump process is not applicable, and at the same time, a tubing lowering timing chart is obtained according to a formula design, actual data is substituted to query whether the moment is the best tubing lowering timing, and the two process lowering timings are coupled to obtain a new method for deep coalbed methane process intervention timing for the whole life cycle, which first uses a jet pump, then a jet pump, then casing production and finally tubing production; the invention takes into account a variety of processes for deep coalbed methane drainage, couples the applicable timing of each process, makes the scheme more reasonable, and the chart is convenient to consult, which is conducive to practical application.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to coalbed methane mining and process optimization, and belongs to the field of coalbed methane mining and drainage. Background Art

[0002] Most of the medium and shallow coal seams are vertical wells, and mechanical pumping is generally efficient and practical. However, deep coalbed methane and medium and shallow coalbed methane are quite different in geological conditions, production characteristics, etc. For example, the characteristics of deep coalbed methane such as deep burial depth, high mineralization, and high gas volume will cause the pumping unit lifting system that is maturely used in medium and shallow coalbed methane wells to have poor adaptability in deep coalbed methane wells, and there are problems such as corrosion, eccentric wear, crystallization and gas lock, which leads to frequent suspension of production and well repairs, resulting in discontinuity in the production cycle, damage to the reservoir, and affecting the release of gas well production capacity. Therefore, efficient drainage has become one of the key technical bottlenecks restricting the efficient development of deep coalbed methane. It is urgent to study drainage technology suitable for the production characteristics of deep coalbed methane.

[0003] The current alternative processes include jet pumps and optimized tubing production. The working principle of the jet pump is to convert the pressure energy into kinetic energy through a diffuser, and finally transport the fluid at a higher pressure. The working principle of the optimized tubing is to adjust the size of the self-spraying tubing to reduce the slip loss of the airflow, so as to make full use of the gas well's own energy for self-powered gas lift drainage and gas production. Summary of the invention

[0004] Purpose of the invention: In order to solve the problems of the current single deep coalbed methane extraction process, poor process adaptability and the process cannot match the full life cycle of coalbed methane extraction, it is necessary to design a new method for the timing of deep coalbed methane process intervention for the entire life cycle.

[0005] To achieve the above object, the present invention provides a new method for deep coalbed methane process intervention timing for the entire life cycle, and the technology includes the following steps:

[0006] S100: The applicable time of this process is determined by whether cavitation occurs in the jet pump. When the jet pump is working, there is always a cavitation limit flow ratio Mc. When the dimensionless volume flow ratio M is greater than Mc, cavitation occurs. The formula for Mc is: The initial formula for M is Introducing the gas-liquid ratio into M yields Where R is the dimensionless area ratio (jet pump nozzle area to upper duct area), K j is the nozzle friction coefficient, p 1 is the power fluid inlet pump pressure (unit, MPa), p 3 is the suction pressure (unit, MPa), P v is the saturated vapor pressure of the produced fluid (unit: MPa), q 1 ,q 3are the volume flow rates of power fluid and formation fluid respectively (unit, cubic meter / day), I c is the empirical cavitation constant, which is usually taken as a conservative value of 1.35, GLR is the gas-liquid ratio (unit, cubic / cubic), f w is the original pore water saturation.

[0007] S200: The water production of coalbed methane wells is large, and the casing's liquid-carrying capacity is insufficient, resulting in liquid-carrying production in the wellbore, and large wellbore energy loss. When the reservoir energy is sufficient, the gas well can produce with liquid, but the reservoir energy of the coalbed methane well decreases rapidly. After the bottom hole pressure drops, the wellhead pressure is too small during liquid-carrying production and cannot meet the gathering and transportation pressure. At this time, it is necessary to run the oil pipe to improve the liquid accumulation in the wellbore, so that the original liquid-carrying production is transformed into liquid-carrying production, reducing the wellbore energy loss. During casing production: the bottom hole flow pressure is equal to the wellhead casing pressure + wellbore energy loss: p wf1 =p c +Δp 1 ; After the oil pipe is lowered: the wellhead oil pressure is equal to the bottom hole flow pressure - wellbore energy loss: p t =p wf2 -Δp 2 Assuming that the gas and water production before and after the oil pipe is lowered are the same, the formation pressure is the same, that is, the bottom hole flow pressure is the same, the above equations are combined to obtain the wellhead pressure after the oil pipe is lowered: p t =p c +(Δp 1 -Δp 2 ), and judge whether the timing of running the process is reasonable by the change of wellhead pressure after running the oil pipe.

[0008] S300: Deep coalbed methane must go through a pure liquid production period in the early stage, that is, at this time, a jet pump is put into operation to increase the drainage rate. When the gas output reaches a certain value, cavitation occurs in the jet pump. At this time, the process is no longer suitable, and casing production is carried out. When the wellhead pressure is greater than zero after the oil pipe is put into operation, the oil pipe is put into operation to carry out full life cycle production. BRIEF DESCRIPTION OF THE DRAWINGS

[0009] In the attached picture:

[0010] Figure 1 Method technology roadmap;

[0011] Figure 2 Jet pump process adaptability chart;

[0012] Figure 3 Oil pipe lowering timing chart;

[0013] Figure 4 Schematic diagram of process intervention in gas well production; DETAILED DESCRIPTION

[0014] According to the following Figure 1The technical route and preferred embodiments of the present invention are described in detail, and the method comprises the following steps:

[0015] Step 1: According to the actual pump selection, give the dimensionless area ratio, here R = 0.64, K j =0.5, the actual injection pressure and injection liquid volume are given on site, the gas-liquid ratio is the actual production parameter, which changes with production time, p 3 Calculated by the Hagedon-Brown model, f w is the original formation parameter, and the relevant data are substituted to obtain Figure 2 .

[0016] Step 2: Calculate the pressure loss △p before and after the oil pipe is lowered using the Hagedon-Brown model 1 and △p 2 At this time, the wellhead pressure when the tubing is lowered can be calculated based on the wellhead pressure during casing production. At this time, the casing wellhead pressure is subtracted from the tubing wellhead pressure. If it is greater than zero, it means that the timing of lowering is reasonable. Assume that the diameter of the lowered tubing is 2 inches 3, and the gas production of 1 to 100,000 cubic meters / day and the water production of 0 to 120 cubic meters / day are substituted into the formula. The calculation results are as follows: Figure 3 .

[0017] Step 3: Taking the actual production well as an example, the actual production well jet pump process adaptation timing is obtained through the second step. Figure 2 It is known that when the injection volume is 200 cubic meters / day of power liquid, the applicable time is 28 days, when the injection volume is 400 cubic meters / day of power liquid, the applicable time is 33 days, and when the injection volume is 600 cubic meters / day of power liquid, the applicable time is 36 days. The well was put into the oil pipe when the gas production was 44,000 cubic meters / day and the water production was 110 cubic meters. The wellhead dropped by 1Mpa, indicating that the timing of the oil pipe was not appropriate. According to the current production, the timing of the oil pipe should be when the water production dropped to about 90 cubic meters. The timing of the intervention of the gas well production process is shown in Figure 1. Figure 4 .

[0018] Compared with the prior art, the present invention has the following beneficial effects: (1) it can be used to determine the timing of technological intervention in most deep coalbed methane wells; (2) it takes into account multiple factors to make the plan more reasonable; (3) the diagrams are easy to consult, which is conducive to practical application.

[0019] Finally, it should be noted that the above embodiments are only used to illustrate rather than limit the technical solutions of the present invention. Although the present invention has been described in detail with reference to the above embodiments, those skilled in the art should understand that the present invention can still be modified or replaced by equivalents. Any modification or partial replacement that does not depart from the spirit and scope of the present invention should be included in the scope of the claims of the present invention.

Claims

1. A new method for deep coalbed methane process intervention timing for the entire life cycle, characterized in that: The method comprises the following steps: S100: The applicable time of this process is determined by whether cavitation occurs in the jet pump. When the jet pump is working, there is always a cavitation limit flow ratio Mc. When the dimensionless volume flow ratio M is greater than Mc, cavitation occurs. The formula for Mc is: , the initial formula of M is , introducing the gas-liquid ratio into M to obtain , where R is the dimensionless area ratio, and its unit is dimensionless. K j is the nozzle friction coefficient, its unit is dimensionless, p 1 is the power fluid inlet pump pressure, and its unit is limited to MPa. p 3 is the suction pressure, the unit is limited to MPa, P v is the saturated vapor pressure of the produced fluid, and its unit is limited to MPa. q 1. q 3 are the volume flow rates of power fluid and formation fluid respectively, and their units are limited to cubic meters per day. I c is the empirical cavitation constant, which is a conservative value of 1.

35. Its unit is dimensionless. GLR is the gas-liquid ratio, and its unit is limited to cubic meter / cubic meter. f w is the original pore water saturation, and its unit is dimensionless; S200: The water production of coalbed methane wells is large, and the casing's liquid-carrying capacity is insufficient, resulting in production with liquid in the wellbore and large wellbore energy loss. When the reservoir energy is sufficient, the gas well can produce with liquid, but the reservoir energy of the coalbed methane well decreases rapidly. After the bottom hole pressure drops, the wellhead pressure is too small during liquid production and cannot meet the gathering and transportation pressure. At this time, it is necessary to run the oil pipe to improve the liquid accumulation in the wellbore, so that the original liquid production is converted into liquid-carrying production and the wellbore energy loss is reduced. During casing production: the bottom hole flow pressure is equal to the wellhead casing pressure + wellbore energy loss: , where P wf1 It is the bottom hole flow pressure during casing production, and its unit is limited to MPa. P c It is the casing pressure at the wellhead during casing production, and its unit is limited to MPa. P 1 is the wellbore energy loss during casing production, and its unit is limited to MPa; after the tubing is lowered: the wellhead oil pressure is equal to the bottom hole flow pressure - wellbore energy loss: , P wf2 It is the bottom hole flow pressure after the oil pipe is lowered, and its unit is limited to MPa. P t is the oil pressure at the wellhead after the oil pipe is lowered, and its unit is limited to MPa, Δ P 2 is the energy loss of the wellbore after the tubing is lowered, and its unit is limited to MPa. Assuming that the gas and water production before and after the tubing is lowered are the same, the formation pressure is the same, that is, the bottom hole flow pressure is the same, the above equations are combined to obtain the wellhead pressure after the tubing is lowered: , judging whether the timing of running the process is reasonable by the change of wellhead pressure after running the oil pipe; S300: Deep coalbed methane must go through a pure liquid production period in the early stage, that is, at this time, a jet pump is put into operation to increase the drainage rate. When the gas output reaches a certain value, cavitation occurs in the jet pump. At this time, the process is no longer suitable, and casing production is carried out. When the wellhead pressure is greater than zero after the oil pipe is put into operation, the oil pipe is put into operation to carry out full life cycle production.

2. A new method for deep coalbed methane process intervention timing for the entire life cycle according to claim 1, characterized in that: The specific steps of the full life cycle production in S300 are: Substitute the actual data to calculate the cavitation limit flow ratio and dimensionless volume flow ratio If M>Mc, cavitation occurs. At this time, the jet pump is no longer suitable and the jet pump should be removed for casing production. At the same time, the diameter of the oil pipe is set to 2 inches 3. The gas production of 100,000 to 100,000 cubic meters per day and the water production of 0 to 120 cubic meters per day are substituted into the Hagedon-Brown model to obtain Δ P 1 and Δ P 2, and then through the formula The timing chart of tubing running is obtained. At this time, the actual data is substituted into the chart to observe whether it is the right time to run the tubing. Thus, a new method for the timing of deep coalbed methane process intervention in the whole life cycle is formed, which includes jet pump production, casing production and finally tubing running production.