A pouring method for concrete segmented pouring and its auxiliary steel bar structure

Through the combined structure of embedded parts and adapter parts, combined with pouring plain cement slurry and vibrating roughening treatment, the problem of insufficient connection strength in segmented pouring is solved, stability and pumping efficiency are improved, and costs are reduced.

CN118241748BActive Publication Date: 2024-10-15AVIC CONSTR GRP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410421914.9
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-04-09
Publication Date
2024-10-15
Estimated Expiration
2044-04-09

AI Technical Summary

Technical Problem

In the existing segmented concrete pouring method, the connection strength between segments is insufficient, resulting in insufficient construction stability and increasing the impact on pouring costs and construction efficiency of the steel structure.

Method used

Using a combined structure of embedded parts and adapter parts, by pouring plain cement slurry and diluted concrete on the connection surface, combined with vibration and roughening treatment, a triangular pyramid structure is formed to enhance the connection stability, and through threaded connection and rotation Blocks can be used to adjust the spacing between embedded parts to adapt to staged pouring in different scenarios.

Benefits of technology

The connection strength and stability between segments are improved, the service life of the delivery pipe is extended, the cost is reduced, and the tight connection is achieved through the supporting frame, which improves the pumping efficiency of concrete.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118241748B_ABST
    Figure CN118241748B_ABST
Patent Text Reader

Abstract

The invention discloses a casting method for segmented concrete casting and an auxiliary steel bar structure thereof, and relates to the technical field of segmented concrete casting; in order to improve the stability and firmness after casting between segments; the casting method for segmented concrete casting specifically comprises the following steps: pre-embedded parts are embedded in the first cast segment, and the embedded parts and the segments are fixedly connected; when casting the next segment of concrete, in addition to the steel bar structure of the concrete itself, adapters are connected to the embedded parts, so that the overall anchoring structure forms a shape of two triangular pyramids. The invention casts plain cement slurry at the connecting surface between the segments, so that the diluted part of the rear segment concrete is immersed in the front segment concrete during the vibration process, and the front segment concrete is roughened, so that the bite force between the two segments is increased, and the stability after the connection between the two segments is guaranteed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of segmented concrete pouring, and in particular to a segmented concrete pouring method and an auxiliary steel bar structure thereof. Background Art

[0002] In the prior art, concrete pouring refers to the process of pouring concrete into a mold until it is plasticized. When a large volume of concrete needs to be poured, in order to effectively ensure the integrity of the concrete pouring and avoid the problem of insufficient stability of the concrete caused by cold joints during the construction process, it is necessary to pour the concrete in sections. When the current concrete is poured in sections, the connectivity between the sections is not enough, and the steel pipe structure is not conducive to the pouring of concrete during use. At the same time, it cannot play a reinforcing role in the structure, which increases the pouring cost and affects the efficiency of the steel structure construction during the concrete pouring process.

[0003] After searching, the Chinese patent application number 201811178155.9 discloses a concrete steel bar composite structure, including two raft bodies, the bottom ends of the two raft bodies are commonly connected to a support plate, the raft bodies are connected by a connecting rod, a concrete cover layer is arranged above the connecting rod, anti-cracking reinforcement ribs are arranged below the support plate, the left and right ends of the anti-cracking reinforcement ribs are connected to waterstop plates, and transverse cables are arranged below the anti-cracking reinforcement ribs.

[0004] The above-mentioned patent has the following deficiencies in the reinforced concrete composite structure and pouring method: during the pouring process, only the reinforced steel hoop and buckle structure are used, so that the connection strength between the front and rear poured concrete is insufficient, and the stability of the front and rear sections of concrete after construction cannot be guaranteed. Summary of the invention

[0005] The purpose of the present invention is to solve the shortcomings of the prior art and to propose a pouring method for concrete pouring in sections and an auxiliary steel bar structure thereof.

[0006] In order to achieve the above object, the present invention adopts the following technical solutions:

[0007] A method for pouring concrete in sections, comprising the following steps:

[0008] S1: pre-embed embedded parts on the first cast segment, and fix the embedded parts and the segment;

[0009] S2: When pouring the next section of concrete, in addition to the steel bar structure of the concrete itself, an adapter is connected to the embedded part so that the overall anchoring structure forms a shape of two triangular pyramids, the embedded part includes a connecting seat and a reinforcing column one, multiple groups of reinforcing columns one are fixed to the bottom of the connecting seat by welding, and a base is welded to the end of the reinforcing column one away from the connecting seat, and a reinforcing column two is welded between two adjacent bases, and a reinforcing column three is welded to the outer wall of the reinforcing column two, and the ends of the multiple reinforcing columns three away from the reinforcing column two are welded with the same middle plate, and reinforcing steel bars are welded to one side of the base, and a support plate is welded to one end of the reinforcing steel bars;

[0010] The adapter comprises an adapter plate, a connecting rod and a mounting plate, the two ends of the connecting rod are respectively welded to the outer wall of one side of the adapter plate and the outer wall of one side of the mounting plate, the surface of the adapter plate is threadedly connected with a threaded rod, and the threaded rod and the base are fixedly connected by welding, and the two mounting plates are rotatably connected by a rotating block;

[0011] S3: Before pouring the next section of concrete, fully water and soak the joints of the previous section of concrete;

[0012] S4: Pour plain cement slurry on the connection surface, and the more diluted part of the concrete poured later will be immersed in the concrete poured earlier to make a tight and fixed connection between the two sections.

[0013] Preferably: in the step S1, when pouring one of the segments, the segment template is wetted with water, and the cleaning opening of the segment template is processed to clean up the debris and accumulated water; when the segment needs to be poured vertically again, a string tube or a conduit is used for pouring, and the height range of the vertical pouring is H>3m; when the segment is vibrated by an inserted vibrator during the pouring process, the layer thickness of the vibrator is 220mm.

[0014] Preferably: during the segmented pouring process, when pouring concrete with a layer thickness greater than 400 mm, when vibrating each segment with a vibrating rod, the oscillator oscillates with the characteristics of fast insertion and slow withdrawal, point-by-point movement, and sequential movement.

[0015] Preferably: when pouring the next section, oscillators are arranged in both sections, the insertion depths of the two oscillators are controlled to be located in the two section layers respectively, the pouring belts at both ends are compacted respectively, and when pouring the post-pouring belt, a layer of mortar is applied on the surface of the construction joint.

[0016] Preferably: after the concrete is poured, the concrete layer is scraped flat according to the elevation using a scraper, and after being scraped flat, the concrete layer is repeatedly rolled using a roller, and after standing for 10 hours, the concrete is covered with plastic sheeting and watered for curing.

[0017] Preferably, in the step S4, the first segment is poured with concrete, and its compressive strength needs to meet 1.3 MPa after testing.

[0018] Preferably, the construction joint is processed, and the processing includes the following items:

[0019] A1: When embedded parts are installed on the surface of the previous section and the next section, and they are exposed to the cold environment for a long time, the construction joints and their external embedded parts should be insulated. The specific insulation measures include plastic sheeting and laminating.

[0020] A2: When the construction joints need to be heated in cold environments, the temperature difference between the newly poured concrete and the hardened concrete should be set within 10-15°C.

[0021] A3: Before pouring the next section, the mortar applied on the surface of the construction joint on the previous section should be processed and roughened;

[0022] A4: After the roughening is completed, rinse the roughened surface with clean water to dispose of the mortar present during the roughening process;

[0023] A5: After treatment, re-apply cement mortar on the surface of the construction joint. The thickness of the cement mortar should be between 10-15mm, and the ratio of sand to glue should be 1:2.5.

[0024] An auxiliary steel bar structure for segmented concrete pouring includes a steel bar body, adapters and embedded parts. The steel bar body includes connecting steel bar 1 and connecting steel bar 2. The connecting steel bar 1 is fixed to the outer wall of the reinforcing steel bar by steel wire bundling, and the connecting steel bar 2 is fixed to the outer wall of the connecting steel bar 1 by iron wire bundling.

[0025] The beneficial effects of the present invention are:

[0026] 1. By pouring plain cement slurry at the connection surface between the segments, the diluted part of the rear segment concrete is immersed in the front segment concrete during the vibration process, and the front segment concrete is roughened to increase the bite force between the two segments and ensure the stability after the connection between the two segments.

[0027] 2. In the process of segmented pouring, use a vibrating rod to vibrate each segment in a step-by-step manner; this pouring method can effectively extend the disassembly and cleaning cycle of the delivery pipe, improve the concrete pumping efficiency, and reduce the cost caused by the need for frequent flushing of the delivery pipe.

[0028] 3. By embedding the embedded parts in the cast sections, and the number of reinforcing columns one fixed at the bottom of the connecting seat is three groups, the three groups of reinforcing columns one form a triangular pyramid structure, and the triangular pyramid structure has stability. When the embedded part and the cast sections are fixedly connected, the stability of the embedded part relative to the cast sections is ensured, thereby reducing the use of the steel bar body.

[0029] 4. The two embedded parts can be connected by threading the adapter plate and the threaded rod. The screw-in length of the threaded rod relative to the adapter plate can be adjusted within a certain range by rotating the two mounting plates relative to each other, thereby adjusting the distance between the two embedded parts. For segmented casting in different scenarios, only the adapter needs to be adjusted to cope with different segmented casting environments, without the need to re-process and produce the adapter.

[0030] 5. By providing connecting steel bars 1 and 2 as a supporting skeleton, when concrete needs to be poured in sections, the supporting skeleton and the concrete can be tightly connected after solidification, thereby improving the connection strength between the sections. BRIEF DESCRIPTION OF THE DRAWINGS

[0031] Figure 1 A schematic diagram of a flow chart of a method for pouring concrete in sections proposed by the present invention;

[0032] Figure 2 This is a schematic diagram of the overall structure of an auxiliary steel bar structure for segmented concrete pouring proposed by the present invention;

[0033] Figure 3 A schematic diagram of the embedded parts connection structure of the auxiliary steel bar structure for segmented concrete pouring proposed by the present invention;

[0034] Figure 4 This is a schematic diagram of the structure of an adapter for an auxiliary steel bar structure for segmented concrete pouring proposed by the present invention.

[0035] In the figure: 1-support plate, 2-reinforcement steel bar, 3-connecting steel bar 1, 4-connecting steel bar 2, 5-connecting seat, 6-reinforcement column 1, 7-reinforcement column 2, 8-adapter plate, 9-middle plate, 10-reinforcement column 3, 11-base, 12-threaded rod, 13-connecting rod, 14-mounting plate, 15-rotating block. DETAILED DESCRIPTION

[0036] The technical solution of the present invention is further described in detail below in conjunction with specific implementation methods.

[0037] Embodiments of the present invention are described in detail below, examples of which are shown in the accompanying drawings, wherein the same or similar reference numerals throughout represent the same or similar elements or elements having the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are only used to explain the present invention, and cannot be understood as limiting the present invention.

[0038] Embodiment 1:

[0039] A method of pouring concrete in sections, such as Figure 1 As shown, the following steps are included:

[0040] S1: pre-embed embedded parts on the first cast segment, and fix the anchors and segments together;

[0041] S2: When pouring the next section of concrete, in addition to the steel bar structure of the concrete itself, adapters are connected to the embedded parts so that the overall anchoring structure forms the shape of two triangular pyramids;

[0042] S3: Before pouring the next section of concrete, fully water and soak the joints of the previous section of concrete;

[0043] S4: Pour plain cement slurry on the connection surface, and the more diluted part of the concrete poured later will be immersed in the concrete poured earlier to make a tight and fixed connection between the two sections.

[0044] In the step S1, when pouring one of the segments, the segment template is wetted with water, and the cleaning opening of the segment template is processed to clean up the debris and accumulated water;

[0045] When the sections need to be poured vertically, they are poured by string tubes and conduits, and the height interval of vertical pouring is H>3m;

[0046] During the pouring process, when the inserted vibrator is used for oscillation, the layer thickness of the vibrator is 220mm;

[0047] In the process of using the oscillator, the oscillator is vibrated by fast insertion and slow removal, point-by-point movement, and sequential movement. When the lower segment is vibrated, the length of the oscillator inserted into the lower segment is 60mm;

[0048] During the pouring of the sections, observe the conditions of the embedded parts and reserved holes, such as deformation and concrete blockage, to ensure the safety of the concrete before the initial setting stage of pouring;

[0049] During the pouring process of the segmented pouring in step S1, the pouring time is preferably at night and in weather with low air humidity to reduce the hydrothermalization inside the bottom slab concrete. When pouring concrete with a layer thickness greater than 400 mm, during the segmented pouring process, each segment is vibrated with a vibrating rod in a step-by-step manner;

[0050] This pouring method can effectively extend the disassembly and cleaning cycle of the delivery pipe, thereby improving the concrete pumping efficiency and reducing the cost caused by the need to frequently flush the delivery pipe.

[0051] Specifically, the interval between two sections of concrete during pouring is less than 1h. When pouring the next section, oscillators are arranged in both sections, and the insertion depths of the two oscillators are controlled to be located in the two section layers respectively, and the pouring belts at both ends are compacted respectively;

[0052] When pouring the post-casting strip, apply a layer of mortar on the surface of the construction joint. When vibrating the construction joint, avoid direct contact between the vibrator and the construction joint during the vibration process. The vibrator should be pushed to vibrate the construction joint.

[0053] After the concrete is poured, use a scraper to level the concrete layer according to the elevation, and then use a roller to repeatedly roll the concrete layer. After standing for 10 hours, cover it with plastic sheeting and water it for maintenance.

[0054] The step S3 is for the treatment of the previous stage of concrete. During the treatment process, loose stones on the outer surface of the concrete after final setting are cleaned by roughening.

[0055] By soaking the joint and adding a certain amount of plain cement slurry, and roughening the surface of the previous section of concrete, the bite force between the two sections is increased to ensure the stability of the connection between the two sections.

[0056] In the step S4, the first segment is poured with concrete, and its compressive strength needs to meet 1.3 MPa after testing.

[0057] Embodiment 2:

[0058] A method for pouring concrete in sections, wherein the construction joint is being treated, and the treatment process includes the following items:

[0059] A1: When embedded parts are installed on the surface of the previous section and the next section, and they are exposed to the cold environment for a long time, the construction joints and their external embedded parts should be insulated. The specific insulation measures include plastic sheeting and laminating.

[0060] A2: When the construction joints need to be heated in cold environments, the temperature difference between the newly poured concrete and the hardened concrete should be set within 10-15°C.

[0061] A3: Before pouring the next section, the mortar applied on the surface of the construction joint on the previous section should be processed and roughened;

[0062] A4: After the roughening is completed, rinse the roughened surface with clean water to dispose of the mortar present during the roughening process;

[0063] A5: After treatment, re-apply cement mortar on the surface of the construction joint. The thickness of the cement mortar should be between 10-15mm, and the ratio of sand to glue should be 1:2.5.

[0064] Embodiment 3:

[0065] An auxiliary reinforcement structure for segmented concrete pouring, such as Figure 2-4 As shown, it includes embedded parts fixed by adapters and a steel bar body, the embedded parts include a connecting seat 5 and a reinforcing column 1 6, multiple groups of reinforcing columns 1 6 are fixed to the bottom of the connecting seat 5 by welding, and a base 11 is welded to one end of the reinforcing column 1 6 away from the connecting seat 5, and a reinforcing column 2 7 is welded between two adjacent bases 11, and a reinforcing column 3 10 is welded to the outer wall of the reinforcing column 2 7, and the ends of the multiple reinforcing columns 3 10 away from the reinforcing column 2 7 are welded with the same middle plate 9, and a reinforcing steel bar 2 is welded to one side of the base 11, and a supporting plate 1 is welded to one end of the reinforcing steel bar 2;

[0066] When the concrete is poured in sections, after one of the sections is poured, the embedded parts are embedded in the poured section. In this embodiment, the embedded parts are reinforcing steel bars 2, connecting seats 5 and reinforcing columns 6. Preferably, the number of reinforcing columns 6 fixed at the bottom of the connecting seat 5 is three groups, and the three groups of reinforcing columns 6 form a triangular pyramid structure. The triangular pyramid structure has stability. Therefore, when the embedded part and the poured section are fixedly connected, the stability of the embedded part relative to the poured section is ensured.

[0067] The adapter comprises an adapter plate 8, a connecting rod 13 and a mounting plate 14, the two ends of the connecting rod 13 are respectively welded to the outer wall of one side of the adapter plate 8 and the outer wall of one side of the mounting plate 14, the surface of the adapter plate 8 is threadedly connected with a threaded rod 12, and the threaded rod 12 and the base 11 are fixedly connected by welding, and the two mounting plates 14 are rotatably connected by a rotating block 15;

[0068] When it is necessary to connect two embedded parts, the two embedded parts can be connected by threading the adapter plate 8 and the threaded rod 12. When it is necessary to adjust the spacing distance between the two embedded parts, the screw-in length of the threaded rod 12 relative to the adapter plate 8 can be adjusted within a certain range by relatively rotating the two mounting plates 14, thereby achieving the distance adjustment between the two embedded parts.

[0069] The steel bar body includes a connecting steel bar 1 3 and a connecting steel bar 2 4, wherein the connecting steel bar 1 3 is fixed to the outer wall of the reinforcing steel bar 2 by steel wire bundling, and the connecting steel bar 2 4 is fixed to the outer wall of the connecting steel bar 1 3 by iron wire bundling;

[0070] By providing the connecting steel bars 1 3 and the connecting steel bars 2 4, a supporting skeleton can be used. When concrete needs to be poured in sections, the supporting skeleton and the concrete can be tightly connected after solidification, thereby improving the strength between the sections.

[0071] In this embodiment, when the segmented casting is carried out, the embedded parts are embedded in the segmented casting, and the three groups of reinforcing columns 6 constitute a triangular pyramid structure. The triangular pyramid structure has stability. Therefore, when the embedded part and the segmented casting are fixedly connected, the stability of the embedded part relative to the segmented casting is ensured. When two embedded parts are connected, the two embedded parts are connected by threading the adapter plate 8 and the threaded rod 12. When it is necessary to adjust the spacing distance between the two embedded parts, the two mounting plates 14 are rotated relative to each other, so that the screw-in length of the threaded rod 12 relative to the adapter plate 8 is adjusted within a certain range.

[0072] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes according to the technical scheme and inventive concept of the present invention within the technical scope disclosed by the present invention, which should be covered by the protection scope of the present invention.

Claims

1. A method for pouring concrete in sections, characterized in that: The following steps are involved: S1: pre-embed embedded parts on the first cast segment, and fix the embedded parts and the segment; S2: When pouring the next section of concrete, in addition to the steel bar structure of the concrete itself, an adapter is connected to the embedded part so that the overall anchoring structure forms a shape of two triangular pyramids, the embedded part includes a connecting seat (5) and a reinforcing column one (6), a plurality of groups of reinforcing columns one (6) are fixed to the bottom of the connecting seat (5) by welding, and a base (11) is welded to the end of the reinforcing column one (6) away from the connecting seat (5), and a reinforcing column two (7) is welded between two adjacent bases (11), and a reinforcing column three (10) is welded to the outer wall of the reinforcing column two (7), and a plurality of reinforcing columns three (10) are welded to the same middle plate (9) at the ends away from the reinforcing column two (7), and a reinforcing steel bar (2) is welded to one side of the base (11), and a support plate (1) is welded to one end of the reinforcing steel bar (2); The adapter comprises an adapter plate (8), a connecting rod (13) and a mounting plate (14); two ends of the connecting rod (13) are respectively welded to an outer wall of one side of the adapter plate (8) and an outer wall of one side of the mounting plate (14); a threaded rod (12) is threadedly connected to the surface of the adapter plate (8); the threaded rod (12) and the base (11) are fixedly connected by welding; and the two mounting plates (14) are rotatably connected by a rotating block (15); S3: Before pouring the next section of concrete, fully water and soak the joints of the previous section of concrete; S4: Pour plain cement slurry on the connection surface, and the more diluted part of the concrete poured later will be immersed in the concrete poured earlier to make a tight and fixed connection between the two sections.

2. A method for pouring concrete in sections according to claim 1, characterized in that: In the step S1, when pouring one of the segments, the segment template is wetted with water, and the cleaning opening of the segment template is processed to clean up the debris and accumulated water; when the segment needs to be poured vertically again, a string tube or a conduit is used for pouring, and the height range of the vertical pouring is H>3m; when the segment is vibrated by an inserted oscillator during the pouring process, the layer thickness of the vibrator is 220mm.

3. A method for pouring concrete in sections according to claim 2, characterized in that: During the segmented pouring process, when pouring concrete with a layer thickness greater than 400mm, when using a vibrating rod to vibrate each segment, the oscillator vibrates with the characteristics of fast insertion and slow withdrawal, point-by-point movement, and sequential movement.

4. A method for pouring concrete in sections according to claim 3, characterized in that: When pouring the next section, oscillators are arranged in the two sections, and the insertion depth of the two oscillators is controlled to be located in the two section layers respectively. The pouring belts at both ends are compacted respectively. When pouring the post-pouring belt, a layer of mortar is applied on the surface of the construction joint.

5. A method for pouring concrete in sections according to claim 4, characterized in that: After the concrete is poured, use a scraper to level the concrete layer according to the elevation. After leveling, use a roller to repeatedly roll the concrete layer. After standing for 10 hours, cover with plastic sheet and water for maintenance.

6. A method for pouring concrete in sections according to claim 5, characterized in that: In the step S4, the first segment is poured with concrete, and its compressive strength needs to meet 1.3 MPa after testing.

7. A method for pouring concrete in sections according to claim 6, characterized in that: The construction joint is being treated, and the treatment process includes the following items: A1: When embedded parts are installed on the surface of the previous section and the next section, and they are exposed to the cold environment for a long time, the construction joints and their external embedded parts should be insulated. The specific insulation measures include plastic sheeting and laminating. A2: When the construction joints need to be heated in cold environments, the temperature difference between the newly poured concrete and the hardened concrete should be set within 10-15°C. A3: Before pouring the next section, the mortar applied on the surface of the construction joint on the previous section should be processed and roughened; A4: After the roughening is completed, rinse the roughened surface with clean water to dispose of the mortar present during the roughening process; A5: After treatment, re-apply cement mortar on the surface of the construction joint. The thickness of the cement mortar should be between 10-15mm, and the ratio of sand to glue should be 1:2.

5.

8. An auxiliary steel bar structure for segmented concrete pouring, comprising a steel bar body and an adapter and an embedded part according to any one of claims 1 to 7, characterized in that: The steel bar body comprises a connecting steel bar one (3) and a connecting steel bar two (4), wherein the connecting steel bar one (3) is fixed to the outer wall of the reinforcing steel bar (2) by means of steel wire bundling, and the connecting steel bar two (4) is fixed to the outer wall of the connecting steel bar one (3) by means of iron wire bundling.