A wind turbine tower connection inspection robot

Through the inspection robot of the fan tower connection part automatically detects the loose nut and supplements the sealing material, the problem of insufficient sealing at the fan tower connection is solved, and the inspection efficiency and the stability and service life of the tower are improved.

CN118346540BInactive Publication Date: 2024-11-12CHINA POWER (HUNAN) ENERGY INVESTMENT CO LTD

Patent Information

Application Number
CN202410632253.4
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-05-21
Publication Date
2024-11-12
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

The sealing at the connection of the fan tower is insufficient, causing moisture and air to enter the tower, accelerating the corrosion and oxidation of metal parts, reducing the strength and stability at the connection, affecting the overall stability and safety of the fan tower, and manual patrol Inefficient inspection.

Method used

Design a fan tower connection inspection robot, including frame moving components, bolt loosening detection components and sealing coating coating components. Automatically detect nut loosening and supplement sealing materials to realize automatic detection and repair of tower connections. .

Benefits of technology

Automatic detection of tower connection fasteners and supplementary sealing materials are realized, detection efficiency is improved, stability and service life of tower connections are ensured, and manual workload is reduced.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118346540B_ABST
    Figure CN118346540B_ABST
Patent Text Reader

Abstract

The present invention discloses a wind turbine tower connection inspection robot, which relates to the technical field of power facility equipment inspection; the present invention comprises a tower body, a circular rail is fixedly provided on the inner wall of the tower body, a movable frame is provided on the circular rail, a frame moving assembly is provided on one side of the top of the movable frame, a detection fixing frame is provided on the frame moving assembly, a bolt loosening detection assembly is provided on the detection fixing frame, a nut clamping and fixing assembly is provided on the bolt loosening detection assembly, a sealing paint applying assembly is provided in the movable frame, and a guide rail moving assembly is provided at the bottom of the movable frame; the present invention arranges a frame moving assembly, a bolt loosening detection assembly and a nut clamping and fixing assembly, so that the frame moving assembly drives the bolt loosening detection assembly to move to the bolt connection, and after the nut is fixedly clamped by the nut clamping and fixing assembly, the bolt connection fastener is detected for looseness through the bolt loosening detection assembly.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of power facility equipment inspection, and in particular to a wind turbine tower connection part inspection robot. Background Art

[0002] A wind turbine tower, also known as a wind turbine tower, is a structure that supports a wind turbine. It is usually made of materials such as steel or concrete. The main function of a wind turbine tower is to support the main components of a wind turbine, such as blades and generators, so that they can rotate efficiently and capture wind energy to generate electricity. A wind turbine tower usually includes a tower, a base, and a top. The tower is the main supporting structure responsible for bearing the weight and wind load of the entire wind turbine. The base is the foundation for fixing the wind turbine tower to the ground. It is usually made of concrete to ensure the stability and safety of the wind turbine tower. The top is the part that connects the blades and the generator, so that the wind turbine can rotate efficiently and generate electricity.

[0003] Usually, inspection of a wind turbine tower requires manual entry into the tower and ascending to the connection via an elevator to check whether the connection fasteners on the inner wall of the tower are loose or falling off, and tighten or replace them in time to ensure the stability of the tower. There are too many bolt fasteners used for fastening the connections inside the tower, and manual inspection takes too long, resulting in low inspection efficiency. Secondly, the sealing of the wind turbine tower connection is very important. If the wind turbine tower connection is leaky, moisture and air will enter the wind turbine tower, accelerating the corrosion and oxidation of metal parts, reducing the strength and stability of the connection, and causing the connection to loosen or fall off, affecting the overall stability and safety of the wind turbine tower, and may even lead to collapse accidents. In response to the above problems, the inventor proposes a wind turbine tower connection inspection robot to solve the above problems. Summary of the invention

[0004] In order to solve the problem of checking whether the connecting fasteners on the inner wall of the tower are loose and whether there is air leakage at the connection of the wind turbine tower and repairing it; the purpose of the present invention is to provide a wind turbine tower connection inspection robot.

[0005] In order to solve the above technical problems, the present invention adopts the following technical solutions: a wind turbine tower connection inspection robot, comprising a tower body, a circular rail is fixedly provided on the inner wall of the tower body, a moving frame is provided on the circular rail, a frame moving assembly is provided on one side of the top of the moving frame, a detection fixing frame is provided on the frame moving assembly, a bolt loosening detection assembly is provided on the detection fixing frame, a nut clamping fixing assembly is provided on the bolt loosening detection assembly, a sealing paint applying assembly is provided in the moving frame, and a guide rail moving assembly is provided at the bottom of the moving frame.

[0006] Preferably, the frame moving assembly includes a movable fixed frame, the movable fixed frame is fixedly installed on the top of the movable frame, the movable fixed frame is rotatably provided with a rotating shaft, the end of the rotating shaft is fixedly provided with a turntable, the movable fixed frame is rotatably provided with a swing rod, and the rotating shaft is slidably connected to the swing rod, a transmission shaft is rotatably provided on the upper part of the movable fixed frame, one end of the transmission shaft is fixedly provided with a rotating rod, and the rotating rod is slidably connected to the swing rod, the other end of the transmission shaft is fixedly provided with a swing frame, a swing column is inserted through the swing frame, an L-plate is fixedly provided at the end of the swing column, a movable adjustment frame is rotatably provided at the other end of the L-plate, and the detection fixed frame is fixedly connected to the movable adjustment frame.

[0007] Preferably, the bolt loosening detection assembly includes a No. 1 slide rail and a trapezoidal block, the No. 1 slide rail is fixedly installed on the detection fixed frame, the trapezoidal block is slidably installed on the No. 1 slide rail, a No. 2 slide rail is fixedly installed on the detection fixed frame close to the trapezoidal block, a rack is slidably provided on the No. 2 slide rail, and the rack is slidably connected to the trapezoidal block, and a circular frame is rotatably provided on the detection fixed frame.

[0008] Preferably, the nut clamping and fixing assembly includes a clamping and fixing frame, which is fixedly installed on the circular frame, a tooth frame is fixedly provided on the outer wall of the clamping and fixing frame, and the tooth frame is meshingly connected with the rack, two symmetrically distributed clamping blocks are slidably provided on the clamping and fixing frame, a connecting rod is rotatably provided above the clamping block, and the clamping block is slidably connected to the connecting rod, a lifting frame is slidably provided at the other end of the connecting rod, two symmetrically distributed clamping rods are fixedly provided on the clamping block, and the clamping rods pass through the clamping and fixing frame, a No. 2 electric cylinder is fixedly provided on the top of the detection and fixing frame, and the driving end of the No. 2 electric cylinder passes through the detection and fixing frame and is rotatably connected to the lifting frame.

[0009] Preferably, the sealing paint coating assembly includes a material box and a fixed bracket, the material box and the fixed bracket are both fixedly installed in a movable frame, an empty cylinder is fixedly provided on the fixed bracket, a piston rod is slidably provided in the empty cylinder, a feed bin is penetrated on one side of the inner wall of the empty cylinder, a discharge bin is penetrated at the end of the empty cylinder, a feed pipe is penetrated on the feed bin, and the feed pipe is through-connected with the material box, and a discharge pipe is penetrated on the discharge bin.

[0010] Preferably, the guide rail moving assembly includes a driving shaft, which is rotatably mounted on a moving frame, a gear is fixedly provided at the bottom end of the driving shaft, a gear ring is fixedly provided on the inner wall of the circular rail close to the gear, and the gear is meshingly connected with the gear ring, four symmetrically distributed guide wheels are rotatably provided at the bottom of the moving frame, and the guide wheels are slidably connected to the circular rail, a No. 2 motor is fixedly provided on the moving frame close to the driving shaft, and the driving end of the No. 2 motor is fixedly connected to the driving shaft.

[0011] Preferably, a pressure sensor is fixedly provided on the inner wall of the detection and fixing frame close to the trapezoidal block, a guide rod is fixedly provided on the inner wall of the detection and fixing frame close to the pressure sensor, and the guide rod passes through the trapezoidal block, a spring is sleeved on the outer wall of the guide rod, and the two ends of the spring are respectively fixedly connected to the trapezoidal block and the pressure sensor, a No. 1 electric cylinder is fixedly provided on the side of the detection and fixing frame away from the pressure sensor, and the driving end of the No. 1 electric cylinder is fixedly connected to the trapezoidal block.

[0012] Preferably, a support plate is fixedly provided on the outer wall of the movable frame close to the tower body, a discharge port is fixedly provided on the support plate, and the discharge port is through-connected with a discharge pipe, a No. 2 rotating plate is rotatably provided in the feed bin, a No. 1 rotating plate is rotatably provided in the discharge bin, a No. 3 electric cylinder is fixedly provided in the movable frame, and the driving end of the No. 3 electric cylinder is fixedly connected to the piston rod, and a wind sensor is fixedly provided on the outer wall of the movable frame close to the discharge port.

[0013] Preferably, a guide rod is fixedly provided on the movable fixed frame, a guide frame is slidably provided on the outer wall of the guide rod, a fixing rod is fixedly provided at the bottom end of the guide frame, and the fixing rod passes through the movable adjustment frame.

[0014] Preferably, a No. 1 motor is fixedly provided in the movable frame, and a driving end of the No. 1 motor is transmission-connected to the rotating shaft via a pulley transmission group.

[0015] Compared with the prior art, the present invention has the following beneficial effects:

[0016] 1. The present invention provides a frame moving assembly, a bolt loosening detection assembly and a nut clamping and fixing assembly, so that the frame moving assembly drives the bolt loosening detection assembly to move to the bolt connection, and after the nut is fixed and clamped by the nut clamping and fixing assembly, the bolt connection fastener is detected for looseness by the bolt loosening detection assembly, and the guide rail moving assembly and the sealing coating coating assembly are provided so that the guide rail moving assembly drives the sealing coating coating assembly to evenly apply the sealing coating to the tower connection ventilation part, and the above operations achieve the effect of detecting the looseness of the nut of the tower connection fastener and filling the tower ventilation part with sealing material to repair the tower;

[0017] 2. The present invention sets a bolt loosening detection component. The bolt loosening component drives the rack to move through the trapezoidal block. The rack drives the nut clamping and fixing component to rotate to the right through the tooth frame. The spring is squeezed by the moving distance of the trapezoidal block. The spring is squeezed and the elastic force acts on the pressure sensor. The looseness of the nut is judged by the pressure of the pressure sensor. The above operation realizes automatic detection of the tower connection fasteners, reduces the workload of the detection personnel, and can perform automatic detection at any time to improve the detection efficiency.

[0018] 3. The present invention sets a sealing coating coating component. When the piston rod moves forward in the empty cylinder, the sealing coating in the empty cylinder is transported to the discharge port through the discharge bin and the discharge pipe, and the sealing coating is coated on the ventilated part of the tower connection through the discharge port. When the piston rod moves backward in the empty cylinder, the sealing coating in the material box is transported to the empty cylinder through the feed pipe and the feed bin under the action of pressure, so as to replenish the sealing coating in the empty cylinder. The above operation can achieve the effect of automatically filling the ventilated part of the tower connection with the sealing material, thereby ensuring the strength and stability of the tower connection and improving the service life. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0020] Figure 1 It is a schematic diagram of the overall structure of the present invention;

[0021] Figure 2 It is a schematic diagram of the overall structure of the mobile frame in the present invention;

[0022] Figure 3 It is a structural schematic diagram of the bolt loosening detection assembly in the present invention;

[0023] Figure 4 It is a structural schematic diagram of the nut clamping and fixing assembly in the present invention;

[0024] Figure 5 It is a structural schematic diagram of the frame moving assembly in the present invention;

[0025] Figure 6 It is a schematic diagram of the structure of the sealing coating application component in the present invention;

[0026] Figure 7 It is a schematic diagram of the structure of the hollow cylinder of the present invention in side section;

[0027] Figure 8 It is a structural schematic diagram of the guide rail moving assembly in the present invention;

[0028] Fig. 9 for Figure 2 A schematic diagram of the structure enlargement at the center A;

[0029] Fig.10 for Figure 5 A magnified schematic diagram of the structure at point B in the middle.

[0030] In the figure: 1, tower body; 2, circular rail; 3, moving frame; 4, frame moving assembly; 401, moving fixed frame; 402, rotating shaft; 403, turntable; 404, swing rod; 405, transmission shaft; 406, rotating rod; 407, swing frame; 408, swing column; 409, L plate; 410, mobile adjustment frame; 411, guide rod; 412, guide frame; 413, fixed rod; 414, No. 1 motor; 5, detection fixed frame; 6, bolt loosening detection assembly; 601, No. 1 slide rail; 602, trapezoidal block; 603, No. 2 slide rail; 604, rack; 605, circular frame; 606, gear frame; 607, pressure sensor; 608, guide rod; 609, spring; 610, No. Electric cylinder; 7. Nut clamping and fixing assembly; 701. Clamping and fixing frame; 702. Clamping block; 703. Connecting rod; 704. Lifting frame; 705. Clamping rod; 706. No. 2 electric cylinder; 8. Sealing paint application assembly; 801. Material box; 802. Fixed bracket; 803. Empty cylinder; 804. Piston rod; 805. Feed bin; 806. Discharge bin; 807. Support plate; 808. Discharge port; 809. Wind sensor; 810. Feed pipe; 811. Discharge pipe; 812. No. 3 electric cylinder; 813. No. 1 rotating plate; 814. No. 2 rotating plate; 9. Guide rail moving assembly; 901. Drive shaft; 902. Gear; 903. Gear ring; 904. Guide wheel; 905. No. 2 motor. DETAILED DESCRIPTION

[0031] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0032] Example: Figure 1-10 As shown, the present invention provides a technical solution: a wind turbine tower connection inspection robot, comprising a tower body 1, a circular rail 2 is fixedly provided on the inner wall of the tower body 1, a moving frame 3 is provided on the circular rail 2, a frame moving assembly 4 is provided on one side of the top of the moving frame 3, a detection fixing frame 5 is provided on the frame moving assembly 4, a bolt loosening detection assembly 6 is provided on the detection fixing frame 5, a nut clamping fixing assembly 7 is provided on the bolt loosening detection assembly 6, a sealing paint applying assembly 8 is provided in the moving frame 3, and a guide rail moving assembly 9 is provided at the bottom of the moving frame 3.

[0033] The frame moving component 4 includes a moving fixed frame 401, which is fixedly installed on the top of the moving frame 3. A rotating shaft 402 is rotatably provided on the moving fixed frame 401, and a turntable 403 is fixedly provided at the end of the rotating shaft 402. A swing rod 404 is rotatably provided on the moving fixed frame 401, and the rotating shaft 402 is slidably connected to the swing rod 404. A transmission shaft 405 is rotatably provided on the upper part of the moving fixed frame 401, and a rotating rod 406 is fixedly provided at one end of the transmission shaft 405, and the rotating rod 406 is slidably connected to the swing rod 404, and a swing frame 407 is fixedly provided at the other end of the transmission shaft 405. A swing column 408 is inserted through the swing frame 407, and an L plate 409 is fixedly provided at the end of the swing column 408. A moving adjustment frame 410 is rotatably provided on the other end of the L plate 409, and the detection fixed frame 5 is fixedly connected to the moving adjustment frame 410.

[0034] By adopting the above technical solution, the movable adjustment frame 410 can move up and down while moving horizontally on the movable fixed frame 401 .

[0035] The bolt loosening detection component 6 includes a No. 1 slide rail 601 and a trapezoidal block 602. The No. 1 slide rail 601 is fixedly installed on the detection fixed frame 5. The trapezoidal block 602 is slidably installed on the No. 1 slide rail 601. A No. 2 slide rail 603 is fixedly installed on the side of the detection fixed frame 5 close to the trapezoidal block 602. A rack 604 is slidably provided on the No. 2 slide rail 603, and the rack 604 is slidably connected to the trapezoidal block 602. A circular frame 605 is rotatably provided on the detection fixed frame 5.

[0036] By adopting the above technical solution, the trapezoidal block 602 pushes the rack 604 to move under the guidance of the second slide rail 603.

[0037] The nut clamping and fixing assembly 7 includes a clamping and fixing frame 701, which is fixedly installed on the circular frame 605. A tooth frame 606 is fixedly provided on the outer wall of the clamping and fixing frame 701, and the tooth frame 606 is meshed and connected with the rack 604. Two symmetrically distributed clamping blocks 702 are slidably provided on the clamping and fixing frame 701. A connecting rod 703 is rotatably provided above the clamping block 702, and the clamping block 702 is slidably connected to the connecting rod 703. A lifting frame 704 is slidably provided on the other end of the connecting rod 703. Two symmetrically distributed clamping rods 705 are fixedly provided on the clamping block 702, and the clamping rod 705 passes through the clamping and fixing frame 701. A No. 2 electric cylinder 706 is fixedly provided on the top of the detection and fixing frame 5, and the driving end of the No. 2 electric cylinder 706 passes through the detection and fixing frame 5 and is rotatably connected to the lifting frame 704.

[0038] By adopting the above technical solution, the driving end of the No. 2 electric cylinder 706 pushes the lifting frame 704 to move, and the lifting frame 704 drives the two clamping rods 705 to contact the nuts through the connecting rod 703 to clamp and fix the nuts.

[0039] The sealing coating application component 8 includes a material box 801 and a fixed bracket 802, both of which are fixedly installed in the movable frame 3, an empty cylinder 803 is fixedly provided on the fixed bracket 802, a piston rod 804 is slidably provided in the empty cylinder 803, a feed bin 805 is penetrated on one side of the inner wall of the empty cylinder 803, a discharge bin 806 is penetrated at the end of the empty cylinder 803, a feed pipe 810 is penetrated on the feed bin 805, and the feed pipe 810 is penetrated and connected with the material box 801, and a discharge pipe 811 is penetrated on the discharge bin 806.

[0040] By adopting the above technical solution, the sealing coating in the material box 801 is transported to the empty cylinder 803 and discharged from the empty cylinder 803 to the discharge pipe 811.

[0041] The guide rail moving assembly 9 includes a driving shaft 901, which is rotatably mounted on the moving frame 3. A gear 902 is fixedly disposed at the bottom end of the driving shaft 901. A gear ring 903 is fixedly disposed on the inner wall of the circular rail 2 close to the gear 902, and the gear 902 is meshingly connected with the gear ring 903. Four symmetrically distributed guide wheels 904 are rotatably disposed at the bottom of the moving frame 3, and the guide wheels 904 are slidably connected to the circular rail 2. A No. 2 motor 905 is fixedly disposed on the moving frame 3 close to the driving shaft 901, and the driving end of the No. 2 motor 905 is fixedly connected to the driving shaft 901.

[0042] By adopting the above technical solution, the second motor 905 drives the gear 902 to rotate on the gear ring 903 through the driving shaft 901.

[0043] A pressure sensor 607 is fixedly provided on the inner wall of the detection and fixing frame 5 close to the trapezoidal block 602, a guide rod 608 is fixedly provided on the inner wall of the detection and fixing frame 5 close to the pressure sensor 607, and the guide rod 608 passes through the trapezoidal block 602, a spring 609 is sleeved on the outer wall of the guide rod 608, and the two ends of the spring 609 are respectively fixedly connected to the trapezoidal block 602 and the pressure sensor 607, a No. 1 electric cylinder 610 is fixedly provided on the side of the detection and fixing frame 5 away from the pressure sensor 607, and the driving end of the No. 1 electric cylinder 610 is fixedly connected to the trapezoidal block 602.

[0044] By adopting the above technical solution, the trapezoidal block 602 moves to squeeze the spring 609 , and the spring 609 is compressed to exert pressure on the pressure sensor 607 .

[0045] A support plate 807 is fixedly provided on the outer wall of the movable frame 3 near the tower body 1, a discharge port 808 is fixedly provided on the support plate 807, and the discharge port 808 is through-connected with a discharge pipe 811, a No. 2 rotating plate 814 is rotatably provided in the feed bin 805, a No. 1 rotating plate 813 is rotatably provided in the discharge bin 806, a No. 3 electric cylinder 812 is fixedly provided in the movable frame 3, and the driving end of the No. 3 electric cylinder 812 is fixedly connected to the piston rod 804, and a wind sensor 809 is fixedly provided on the outer wall of the movable frame 3 near the discharge port 808.

[0046] By adopting the above technical solution, the sealing coating in the empty cylinder 803 is transported to the discharge port 808 through the discharge pipe 811 .

[0047] A guide rod 411 is fixedly disposed on the movable fixed frame 401 , a guide frame 412 is slidably disposed on the outer wall of the guide rod 411 , a fixing rod 413 is fixedly disposed at the bottom end of the guide frame 412 , and the fixing rod 413 penetrates the movable adjustment frame 410 .

[0048] By adopting the above technical solution, the fixed rod 413 drives the movable adjustment frame 410 to move under the guidance of the guide frame 412 .

[0049] A No. 1 motor 414 is fixedly disposed in the moving frame 3 , and a driving end of the No. 1 motor 414 is transmission-connected to the rotating shaft 402 via a pulley transmission group.

[0050] By adopting the above technical solution, the first motor 414 drives the rotating shaft 402 to rotate through the pulley transmission group.

[0051] Working principle: First, the No. 2 motor 905 is controlled to be turned on. The No. 2 motor 905 drives the gear 902 to rotate on the gear ring 903 through the driving shaft 901. The gear 902 rotates on the gear ring 903 to drive the moving frame 3 to move on the circular track 2 under the guidance of the guide wheel 904. The moving frame 3 moves to the corresponding wind turbine tower connection fixing bolt, and the No. 1 motor 414 is controlled to be turned on. The driving end of the No. 1 motor 414 drives the rotating shaft 402 to rotate one circle through the pulley transmission group. 402 first drives the swing rod 404 to swing from the right side to the left side and stop through the turntable 403. While the swing rod 404 swings, it drives the transmission shaft 405 to rotate half a circle counterclockwise through the rotating rod 406. The transmission shaft 405 rotates half a circle counterclockwise to drive the swing frame 407 to rotate synchronously. The swing frame 407 drives the movable adjustment frame 410 to move from the right side to the left side in an arc trajectory under the guidance of the fixed rod 413 and the guide frame 412 through the swing column 408 and the L plate 409.

[0052] When the mobile adjustment frame 410 moves, it drives the detection and fixing frame 5 to move synchronously. The movement of the detection and fixing frame 5 drives the clamping and fixing frame 701 to move to the nut fixed on the corresponding bolt, and the No. 2 electric cylinder 706 is controlled to be turned on. The driving end of the No. 2 electric cylinder 706 contracts and drives the lifting frame 704 to rise. During the rising process of the lifting frame 704, the two groups of clamping rods 705 are driven to approach each other through the connecting rod 703 and the clamping block 702 to clamp and fix the nut. After the nut is clamped and fixed, the No. 1 electric cylinder 610 is controlled to be turned on. The driving end of the No. 1 electric cylinder 610 extends through the trapezoidal block 602 to drive the rack 604 to move. 04 The clamping and fixing frame 701 is driven to rotate by the tooth frame 606. The spring 609 is squeezed during the movement of the trapezoidal block 602. The spring 609 is squeezed and exerts a reaction force on the pressure sensor 607. If the pressure sensor 607 is subjected to pressure, it means that the nut is loose, otherwise it is normal. The feedback of the pressure sensor 607 on the magnitude of the pressure can reflect the degree of looseness of the nut. After the nut detection is completed, the shaft 402 continues to rotate to complete the remaining circumference. The shaft 402 continues to rotate and drives the detection and fixing frame 5 to reset through the same steps above, and the fixing degree of the nut at the tower connection is detected in turn;

[0053] When the movable frame 3 is moving, if the wind sensor 809 senses that there is ventilation at the connection between the two towers, the No. 3 electric cylinder 812 will be turned on immediately, and the driving end of the No. 3 electric cylinder 812 will extend and push the piston rod 804 to move toward one end of the discharge bin 806 in the empty cylinder 803, and the No. 2 rotating plate 814 in the feed bin 805 is arranged to rotate toward the inside of the empty cylinder 803, and the No. 1 rotating plate 813 in the discharge bin 806 is arranged to rotate outwardly. When the piston rod 804 is moving, the No. 2 rotating plate 814 on the feed bin 805 is pressed against the inner wall of the feed bin 805 under the action of pressure, and the No. 1 rotating plate 813 on the discharge bin 806 is pressed against the inner wall of the feed bin 805 under the action of pressure. The sealing coating in the empty cylinder 803 is flipped outward from bottom to top, and is transported to the discharge port 808 through the discharge bin 806 and the discharge pipe 811, and is applied to the ventilated part of the tower body 1 through the discharge port 808, and then the sealing coating is scraped flat by a scraper. When the piston rod 804 moves backward and resets, the No. 1 rotating plate 813 in the discharge bin 806 fits tightly with the inner wall of the discharge bin 806 under the action of pressure, and the No. 2 rotating plate 814 in the feed bin 805 flips inward under the action of pressure, and the sealing coating in the material box 801 is transported to the feed bin 805 through the feed bin 805 under the action of pressure, and enters the empty cylinder 803 through the feed bin 805.

[0054] Obviously, those skilled in the art can make various changes and modifications to the present invention without departing from the spirit and scope of the present invention. Thus, if these modifications and variations of the present invention fall within the scope of the claims of the present invention and their equivalents, the present invention is also intended to include these modifications and variations.

Claims

1. A wind turbine tower connection inspection robot, comprising a tower body (1), characterized in that: A circular rail (2) is fixedly provided on the inner wall of the tower body (1), a movable frame (3) is provided on the circular rail (2), a frame moving assembly (4) is provided on one side of the top end of the movable frame (3), a detection fixing frame (5) is provided on the frame moving assembly (4), a bolt loosening detection assembly (6) is provided on the detection fixing frame (5), a nut clamping and fixing assembly (7) is provided on the bolt loosening detection assembly (6), a sealing paint applying assembly (8) is provided in the movable frame (3), and a guide rail moving assembly (9) is provided at the bottom of the movable frame (3); The frame moving assembly (4) comprises a moving fixed frame (401), wherein the moving fixed frame (401) is fixedly mounted on the top of the moving frame (3), a rotating shaft (402) is rotatably provided on the moving fixed frame (401), a rotating disk (403) is fixedly provided at the end of the rotating shaft (402), a swing rod (404) is rotatably provided on the moving fixed frame (401), and the rotating shaft (402) is slidably connected to the swing rod (404), and a transmission shaft (405) is rotatably provided on the upper part of the moving fixed frame (401), A rotating rod (406) is fixedly provided at one end of the transmission shaft (405), and the rotating rod (406) is slidably connected to the swing rod (404); a swing frame (407) is fixedly provided at the other end of the transmission shaft (405); a swing column (408) is inserted through the swing frame (407); an L plate (409) is fixedly provided at the end of the swing column (408); a movable adjustment frame (410) is rotatably provided at the other end of the L plate (409); and the detection fixed frame (5) is fixedly connected to the movable adjustment frame (410).

2. A wind turbine tower connection inspection robot according to claim 1, characterized in that: The bolt loosening detection assembly (6) comprises a first slide rail (601) and a trapezoidal block (602); the first slide rail (601) is fixedly mounted on a detection fixed frame (5); the trapezoidal block (602) is slidably mounted on the first slide rail (601); a second slide rail (603) is fixedly mounted on a side of the detection fixed frame (5) close to the trapezoidal block (602); a rack (604) is slidably mounted on the second slide rail (603); and the rack (604) is slidably connected to the trapezoidal block (602); and a circular frame (605) is rotatably mounted on the detection fixed frame (5).

3. A wind turbine tower connection inspection robot according to claim 1, characterized in that: The nut clamping and fixing assembly (7) comprises a clamping and fixing frame (701), the clamping and fixing frame (701) is fixedly mounted on the circular frame (605), a tooth frame (606) is fixedly arranged on the outer wall of the clamping and fixing frame (701), and the tooth frame (606) is meshedly connected with the rack (604), two symmetrically distributed clamping blocks (702) are slidably arranged on the clamping and fixing frame (701), a connecting rod (703) is rotatably arranged above the clamping block (702), and the clamping block (702) is (702) is slidably connected to the connecting rod (703), and the other end of the connecting rod (703) is slidably provided with a lifting frame (704), and two symmetrically distributed clamping rods (705) are fixedly provided on the clamping block (702), and the clamping rods (705) pass through the clamping fixed frame (701), and a No. 2 electric cylinder (706) is fixedly provided on the top of the detection fixed frame (5), and the driving end of the No. 2 electric cylinder (706) passes through the detection fixed frame (5) and is rotatably connected to the lifting frame (704).

4. A wind turbine tower connection inspection robot according to claim 1, characterized in that: The sealing coating application assembly (8) comprises a material box (801) and a fixed bracket (802), wherein the material box (801) and the fixed bracket (802) are both fixedly installed in a movable frame (3), an empty cylinder (803) is fixedly provided on the fixed bracket (802), a piston rod (804) is slidably provided in the empty cylinder (803), a feed bin (805) is provided through one side of the inner wall of the empty cylinder (803), a discharge bin (806) is provided through the end of the empty cylinder (803), a feed pipe (810) is provided through the feed bin (805), and the feed pipe (810) is connected to the material box (801), and a discharge pipe (811) is provided through the discharge bin (806).

5. A wind turbine tower connection inspection robot according to claim 1, characterized in that: The guide rail moving assembly (9) comprises a driving shaft (901), the driving shaft (901) being rotatably mounted on the moving frame (3), a gear (902) being fixedly provided at the bottom end of the driving shaft (901), a gear ring (903) being fixedly provided on the inner wall of the circular rail (2) close to the gear (902), and the gear (902) and the gear ring (903) being meshingly connected, four symmetrically distributed guide wheels (904) being rotatably provided at the bottom of the moving frame (3), and the guide wheels (904) being slidably connected to the circular rail (2), a No. 2 motor (905) being fixedly provided on the moving frame (3) close to the driving shaft (901), and a driving end of the No. 2 motor (905) being fixedly connected to the driving shaft (901).

6. A wind turbine tower connection inspection robot as claimed in claim 2, characterized in that: A pressure sensor (607) is fixedly provided on the inner wall of the detection fixing frame (5) close to the trapezoidal block (602), a guide rod (608) is fixedly provided on the inner wall of the detection fixing frame (5) close to the pressure sensor (607), and the guide rod (608) penetrates the trapezoidal block (602), a spring (609) is sleeved on the outer wall of the guide rod (608), and the two ends of the spring (609) are respectively fixedly connected to the trapezoidal block (602) and the pressure sensor (607), and a No. 1 electric cylinder (610) is fixedly provided on the side of the detection fixing frame (5) away from the pressure sensor (607), and the driving end of the No. 1 electric cylinder (610) is fixedly connected to the trapezoidal block (602).

7. A wind turbine tower connection inspection robot according to claim 4, characterized in that: A support plate (807) is fixedly provided on the outer wall of the movable frame (3) near the tower body (1), a discharge port (808) is fixedly provided on the support plate (807), and the discharge port (808) is connected to a discharge pipe (811). A second rotating plate (814) is rotatably provided in the feed bin (805), and a first rotating plate (813) is rotatably provided in the discharge bin (806). A third electric cylinder (812) is fixedly provided in the movable frame (3), and a driving end of the third electric cylinder (812) is fixedly connected to the piston rod (804). A wind sensor (809) is fixedly provided on the outer wall of the movable frame (3) near the discharge port (808).

8. A wind turbine tower connection inspection robot as claimed in claim 3, characterized in that: A guide rod (411) is fixedly provided on the movable fixed frame (401), a guide frame (412) is slidably provided on the outer wall of the guide rod (411), a fixing rod (413) is fixedly provided at the bottom end of the guide frame (412), and the fixing rod (413) passes through the movable adjustment frame (410).

9. A wind turbine tower connection inspection robot according to claim 1, characterized in that: A No. 1 motor (414) is fixedly disposed in the movable frame (3), and a driving end of the No. 1 motor (414) is transmission-connected to the rotating shaft (402) via a pulley transmission group.

Citation Information

Patent Citations

  • Angle steel tower bolt fastening robot

    CN112873217A

  • Wind power tower bolt detection robot

    CN116292141A

  • Traveling mechanism of wind power tower bolt maintenance robot

    CN117087779A

  • Maintenance robot, and wind power generator having the same

    KR1020130025592A

  • Maintenance robot for wind power generator

    KR1020130026039A

Cited By

  • Tightness degree monitoring device for connecting position of tower drum of wind driven generator

    CN122565658A