A beam-slab integrated prefabricated waffle plate structure and construction method thereof

Through the combination of beam-board integrated prefabricated waffle plate structure and prefabricated waffle beam plate units, the problem of difficult and high-cost construction of high-tech electronic factory floor slabs is solved, rapid construction and construction cost reduction are achieved, and anti-microvibration performance is ensured. and transportation cheapness.

CN118481286BActive Publication Date: 2024-10-22FUJIAN CONSTRUCTION ENGINEERING PREFABRICATED BUILDING RESEARCH INSTITUTE CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410934456.9
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-07-12
Publication Date
2024-10-22
Estimated Expiration
2044-07-12

AI Technical Summary

Technical Problem

The construction of existing high-tech electronic factory floor slabs is difficult and takes a long time, and the cast-in-place process requires the erection of a large-scale support system, resulting in slow construction and high cost, making it difficult to meet the demand for rapid production. Moreover, the floor slabs are large in size, heavy in weight, and require transportation and installation costs. high.

Method used

The beam-plate integrated prefabricated waffle plate structure is adopted. Prefabricated frame beams and prefabricated waffle beam plate units are used to achieve the construction site without support and formwork. The combination of prefabricated waffle beam plate units and post-poured concrete simplifies the construction process, and through The inverted T-shaped supporting member and closed hoop structure improve installation convenience and load-bearing capacity.

Benefits of technology

It significantly speeds up the construction progress, reduces the construction cost, improves the construction speed and installation convenience, ensures anti-microvibration performance and cheap transportation, and meets the needs of rapid production of high-tech factories.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118481286B_ABST
    Figure CN118481286B_ABST
Patent Text Reader

Abstract

The present invention is a prefabricated waffle plate structure with integrated beam and slab and a construction method thereof, the structure comprising columns, prefabricated frame beams and prefabricated waffle beam and slab units; the columns are distributed in an array, and beam and slab supporting parts and beam supporting parts are provided at the upper ends of the columns; the two ends of the prefabricated frame beam are respectively mounted on the beam supporting parts, and the front and rear side walls of the prefabricated frame beam are provided with main supporting parts; the prefabricated waffle beam and slab units are mounted between the prefabricated frame beams. The construction method includes, in sequence, completing the array construction of the columns; installing the beam and slab supporting parts and beam supporting parts on the columns; mounting the prefabricated frame beam on two columns; mounting the prefabricated waffle beam and slab units between the prefabricated frame beams; completing the hoisting of the main beam top steel bar skeleton and the rib beam top steel bar skeleton; completing the hoisting of the transverse plate surface steel bars and the longitudinal plate surface steel bars; and pouring concrete at the nodes. The present invention realizes the support-free and formwork-free construction of the prefabricated waffle plate with integrated beam and slab on the premise of meeting the anti-micro-vibration requirements, speeding up the construction progress and saving costs.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of prefabricated assembled building structures, in particular to a beam-slab integrated prefabricated waffle slab structure and a construction method thereof. Background Art

[0002] In current high-tech electronic factories, such as chip processing factories or panel factories, the floor slabs need to meet the requirements of anti-micro-vibration, that is, the floor slabs cannot vibrate slightly during the production process to avoid affecting product production and ensure the yield rate of products. In order to meet the anti-micro-vibration effect, the thickness of the factory floor slabs is much higher than that of ordinary buildings. In addition, since most high-tech electronic factories are high-cleanliness factories, it is necessary to open several through holes on the floor slabs to control the air flow in the factory and ensure the requirements for air cleanliness.

[0003] At present, the floor slabs of high-tech electronic factories are mainly cast-in-place, and the cast-in-place process needs to meet the following requirements for the floor slabs: 1. The flatness of the slab surface is high, and the error within two meters does not exceed two millimeters; 2. The surface needs to be leveled; 3. During the construction process, in addition to the layout of the external formwork, the layout of the circular hole membrane is also required, and then the steel bars are tied for overall casting.

[0004] The above requirements have the following problems:

[0005] 1. Due to the high construction requirements, for example, the flatness of the lower surface of the floor slab requires the use of a black plastic template, and the upper surface of the floor slab needs to be leveled, so the on-site construction is difficult, the construction period is long, and the quality of the construction personnel is required to be high.

[0006] 2. The floor slab of a high-tech electronic factory building is large in area and high in height. The cast-in-place process requires a large-scale support system, which is slow to construct and expensive.

[0007] 3. The cast-in-place process requires the concrete to harden before the formwork and support can be removed, and then the equipment can be installed. The construction period is long, which seriously affects the project delivery time and makes it difficult to meet the requirements for high-tech production lines to be put into production as soon as possible.

[0008] CN109469326A discloses a construction method for special-shaped lattice panels, and the lattice panels disclosed therein are used as floor panels of wafer factories; CN 109695345A discloses a structural construction method for buildings, and the precast floors disclosed therein are used as floor panels of factories. However, both the lattice panels and the precast floors have a planar size close to the column grid size. According to the current technology, the column grid size is usually 6m*6m, so they are basically not suitable for road transportation. In addition, the floor panels disclosed in the above patents are large in size and have few post-cast layers, so they are heavy overall, and the corresponding transportation and installation costs are high. Summary of the invention

[0009] The purpose of the present invention is to provide a beam-slab integrated prefabricated waffle slab structure, which, under the premise of meeting the anti-micro-vibration requirements, can achieve the construction site without support and formwork through prefabrication and assembly, significantly speeding up the construction progress and reducing the construction cost.

[0010] A beam-slab integrated prefabricated waffle slab structure, comprising columns, prefabricated frame beams and prefabricated waffle beam-slab units;

[0011] The columns are distributed in an array, and beam and slab supporting members and beam supporting members are provided at the upper ends of the columns;

[0012] The cross section of the prefabricated frame beam is rectangular as a whole, and its two ends are respectively mounted on the beam supporting members of the adjacent columns on the left and right sides, and the front and rear side walls of the prefabricated frame beam are provided with main supporting members;

[0013] The prefabricated waffle beam-slab unit comprises a reinforced concrete floor slab, and the left and right sides of the reinforced concrete floor slab are respectively provided with rib beams extending upward and front and back first, and the reinforced concrete floor slab is provided with through holes arranged in an array; the front and rear sides and the left and right sides of any through hole are provided with annular steel bars extending out of the reinforced concrete floor slab, and the annular steel bars between any two adjacent through holes are the same; a cylindrical inner mold is provided above any through hole; the inner side wall surfaces of the front and rear ends of the rib beam are also provided with embedded steel plates; the rib beams of the prefabricated waffle beam-slab unit frame are mounted on the beam-slab supporting parts or the main supporting parts of two mutually parallel prefabricated frame beams;

[0014] The rib beam is provided with stirrups B extending from the upper surface of the rib beam and arranged in sequence in the front-to-back direction; two adjacent rib beams in the two prefabricated waffle beam-slab units are provided with a rear-placed rib beam top steel bar skeleton;

[0015] The top surface of the prefabricated frame beam is provided with a groove extending along the length direction thereof; an open hoop extending out of the groove is provided inside the prefabricated frame beam, and the prefabricated frame beam is also provided with connecting steel bars extending out of the front and rear sides of the prefabricated frame beam, and the connecting steel bars are provided in multiple rows and the multiple rows of connecting steel bars are arranged in sequence in the left and right directions; the prefabricated frame beam is also provided with longitudinal steel bars A inside, and the longitudinal steel bars A extend into the beam-column node;

[0016] The prefabricated frame beam is also provided with a rear main beam top steel bar skeleton, which is arranged through the entire length to cover all prefabricated frame beams in the same extension direction, and the main beam top steel bar skeleton and the open hoop cooperate to form a closed hoop structure;

[0017] An L-shaped connector is provided between the embedded steel plate and the main supporting member, and the L-shaped connector is welded to the two. In the cylindrical inner mold arranged in an array, transverse plate surface reinforcements and longitudinal plate surface reinforcements are respectively provided between the transverse gaps and between the longitudinal gaps. Among them, the transverse plate surface reinforcements are arranged through the length to cover all prefabricated waffle beam and plate units in the left and right extension directions.

[0018] Pour concrete on site at the beam-column joints of columns and prefabricated frame beams, the top steel bar skeleton of rib beams, the top steel bar skeleton of main beams, the transverse slab steel bars and the longitudinal slab steel bars. The cast-in-place concrete must cover the top steel bar skeleton of rib beams, the top steel bar skeleton of main beams, the transverse slab steel bars and the longitudinal slab steel bars.

[0019] 10. A method for installing a beam-slab integrated prefabricated waffle plate structure, comprising the following steps:

[0020] S1. Complete the array construction of columns;

[0021] S2. According to the height of the prefabricated frame beam and the prefabricated waffle beam-slab unit, the beam-slab support members and the beam support members are installed on the columns;

[0022] S3. The prefabricated frame beam is placed on two columns, and the ends of the prefabricated frame beam are supported on the beam support member;

[0023] S4. The prefabricated waffle beam-slab unit is placed between the prefabricated frame beams, and the rib beams on one side of the prefabricated waffle beam-slab unit are supported on the beam-slab support member or the main support member, and the rib beams on the other side are supported on the main support member;

[0024] S5. Complete the welding of the L-shaped connector, the embedded steel plate and the main supporting member; first hoist the main beam top steel frame into the groove of the prefabricated frame beam, wherein the main beam top steel frame covers all prefabricated frame beams in the same extension direction; then hoist the rib beam top steel frame to the two adjacent rib beams in the two prefabricated waffle beam-slab units;

[0025] S6. hoist the transverse slab reinforcement and the longitudinal slab reinforcement into the prefabricated waffle beam and slab unit in sequence;

[0026] S7. Pour concrete on site at the beam-column joints of columns and precast frame beams, the top steel bar skeleton of rib beams, the top steel bar skeleton of main beams, the transverse slab steel bars and the longitudinal slab steel bars. The cast-in-place concrete must cover the top steel bar skeleton of rib beams, the top steel bar skeleton of main beams, the transverse slab steel bars and the longitudinal slab steel bars.

[0027] Compared with the previous technology, the beneficial effects of the present invention are:

[0028] 1. The present invention replaces the composite slab area of ​​the existing beam-slab integrated unit with a prefabricated waffle beam-slab unit. Compared with the traditional construction method, the present invention can achieve support-free and formwork-free construction on the construction site, significantly improving the installation speed. In addition, the prefabricated waffle beam-slab unit is prefabricated in a standardized factory, which significantly reduces the difficulty of later plate surface leveling and maximizes the construction speed.

[0029] 2. The combination of prefabricated waffle beam and slab units and post-poured concrete is convenient and has good integrity, which can ensure the anti-micro-vibration and waterproof performance of the prefabricated floor.

[0030] 3. Prefabricated waffle beam and slab units are lighter in weight than fully prefabricated waffle slabs, can meet the size restrictions for road transportation, are cheap in transportation costs and are easy to install.

[0031] 4. The main supporting part adopts an inverted T-shaped structural design to ensure that the prefabricated frame beam is flush with the bottom of the main supporting part, which does not affect the installation of subsequent production equipment; at the same time, it has a large bearing capacity and is easy to install.

[0032] 5. The top steel bar skeleton of the rib beam, the top steel bar skeleton of the main beam, the transverse plate steel bars, and the longitudinal plate steel bars are connected with the corresponding structures, which is convenient for installation and ensures the reliability of the connection between each component. BRIEF DESCRIPTION OF THE DRAWINGS

[0033] Figure 1 It is a schematic diagram of the overall structure of a beam-slab integrated prefabricated waffle slab structure;

[0034] Figure 2 It is a structural diagram of the column;

[0035] Figure 3 It is a structural schematic diagram of the prefabricated frame beam;

[0036] Figure 4 A schematic diagram of the structure of the main supporting member;

[0037] Figure 5 An exploded view of the main supporting part;

[0038] Figure 6 It is the structural schematic diagram of the prefabricated waffle beam-slab unit;

[0039] Figure 7 for Figure 6 Exploded diagram of

[0040] Figure 8 This is a schematic diagram of the structure of the transverse reinforcement at the bottom of the slab;

[0041] Fig. 9 It is a schematic diagram of the structure of the longitudinal reinforcement at the bottom of the slab;

[0042] Fig.10 This is a schematic diagram of the structure of the main beam top steel bar skeleton;

[0043] Fig.11 It is a structural diagram of the steel bar skeleton at the top of the rib beam;

[0044] Fig.12 It is a schematic diagram of the structure of the longitudinal plate reinforcement;

[0045] Fig.13 It is a schematic diagram of the structure of the transverse plate reinforcement;

[0046] Fig.14It is a structural schematic diagram of the connection between the embedded steel plate and the main supporting member;

[0047] Fig.15 This is the construction step diagram for steps 1 and 2;

[0048] Fig.16 This is the construction step diagram for step 3;

[0049] Fig.17 This is the construction step diagram for step 4;

[0050] Fig.18 This is the construction step diagram for step 5;

[0051] Fig.19 This is the construction step diagram for step 6;

[0052] Description of symbols

[0053] 1-column, 11-beam support, 12-beam support;

[0054] 2-prefabricated frame beam, 21-groove, 22-open hoop, 23-connecting steel bar, 24-longitudinal steel bar A, 25-shear keyway A;

[0055] 3- prefabricated waffle beam-slab unit, 31- reinforced concrete floor slab, 32- rib beam, 321- stirrup B, 322- longitudinal reinforcement B, 323- shear keyway B, 33- through hole, 34- annular reinforcement, 35- cylindrical inner mold, 36- embedded steel plate, 37- transverse reinforcement at the bottom of the slab, 371- lower transverse reinforcement, 372- lower transverse stirrup, 38- longitudinal reinforcement at the bottom of the slab, 381- lower longitudinal reinforcement, 382- lower longitudinal stirrup, 39- rib beam reinforcement;

[0056] 4-main supporting member, 41-anchor plate, 42-shear steel plate, 43-connecting bottom plate, 44-vertical steel plate;

[0057] 5-rib beam top reinforcement skeleton, 51-through-length reinforcement A, 52-closed stirrups;

[0058] 6- main beam top steel bar skeleton, 61- full length steel bar B, 62- tension bar;

[0059] 7- transverse plate reinforcement, 71- upper transverse reinforcement, 72- upper transverse stirrups;

[0060] 8-longitudinal plate reinforcement, 81-upper longitudinal reinforcement, 82-upper longitudinal stirrups;

[0061] 9- L-shaped connector. DETAILED DESCRIPTION

[0062] The present invention is described in detail below in conjunction with specific embodiments and accompanying drawings:

[0063] like Figure 1-19 As shown: a beam-slab integrated prefabricated waffle slab structure, comprising a column 1, a prefabricated frame beam 2 and a prefabricated waffle beam-slab unit 3;

[0064] The columns 1 are distributed in an array, and the upper ends of the columns 1 are provided with beam and slab supporting members 11 and beam supporting members 12;

[0065] The cross section of the prefabricated frame beam 2 is rectangular as a whole, and its two ends are respectively mounted on the beam supporting members 12 of the adjacent columns 1 on the left and right sides, and the front and rear side walls of the prefabricated frame beam 2 are provided with main supporting members 4;

[0066] The prefabricated waffle beam-slab unit 3 comprises a reinforced concrete floor 31, and the left and right sides of the reinforced concrete floor 31 are respectively provided with rib beams 32 extending upward and front and back first, and the reinforced concrete floor 31 is provided with through holes 33 arranged in an array; the front and rear sides and the left and right sides of any through hole 33 are provided with annular steel bars 34 extending out of the reinforced concrete floor 31, and the annular steel bars 34 between any two adjacent through holes 33 are the same; a cylindrical inner mold 35 is provided above any through hole 33; the inner side wall surfaces of the front and rear ends of the rib beam 32 are also provided with embedded steel plates 36; the rib beam 32 of the prefabricated waffle beam-slab unit 3 is mounted on the beam and slab support member 11 or the main support members 4 of the two mutually parallel prefabricated frame beams 2;

[0067] The rib beam 32 is provided with stirrups B321 extending from the upper surface of the rib beam 32 and arranged in sequence in the front-to-back direction; two adjacent rib beams 32 in the two prefabricated waffle beam-slab units 3 are provided with a rear rib beam top steel bar skeleton 5;

[0068] The top surface of the prefabricated frame beam 2 is provided with a groove 21 extending along its length direction; an open hoop 22 extending from the groove 21 is provided inside the prefabricated frame beam 2, and the prefabricated frame beam 2 is also provided with connecting steel bars 23 extending from the front and rear sides of the prefabricated frame beam 2, and the connecting steel bars 23 are provided with multiple rows and the multiple rows of connecting steel bars 23 are arranged in sequence in the left and right directions; the prefabricated frame beam 2 is also provided with longitudinal steel bars A24, and the longitudinal steel bars A24 extend into the beam-column node;

[0069] The prefabricated frame beam 2 is also provided with a rear main beam top steel bar skeleton 6, which is arranged through the entire length to cover all prefabricated frame beams 2 in the same extension direction, and the main beam top steel bar skeleton 6 and the open hoop 22 cooperate to form a closed hoop structure;

[0070] An L-shaped connector 9 is provided between the embedded steel plate 36 and the main supporting member 4, and the L-shaped connector 9 is welded to the two. In the cylindrical inner mold 35 arranged in an array, transverse plate surface reinforcements 7 and longitudinal plate surface reinforcements 8 are respectively provided between the transverse gaps and the longitudinal gaps thereof; wherein the transverse plate surface reinforcements 7 are arranged through the length to cover all the prefabricated waffle beam and plate units 3 in the left and right extension directions;

[0071] Concrete is poured on site at the beam-column joints of the column 1 and the prefabricated frame beam 2, at the rib beam top steel bar skeleton 5, at the main beam top steel bar skeleton 6, at the transverse slab surface steel bars 7 and at the longitudinal slab surface steel bars 8. The cast-in-place concrete must cover the rib beam top steel bar skeleton 5, the main beam top steel bar skeleton 6, the transverse slab surface steel bars 7 and the longitudinal slab surface steel bars 8.

[0072] The columns 1 and prefabricated frame beams 2 here are not much different from the traditional beam-slab integrated unit structure. The main difference lies in the structure of the prefabricated waffle beam-slab unit and the design of related configurations.

[0073] The prefabricated waffle beam and slab unit 3 retains a breathable channel, wherein the cylindrical inner mold 35 is directly cast on the prefabricated waffle beam and slab unit 3; the concave area in the middle of the prefabricated waffle beam and slab unit 3 is matched with transverse slab surface steel bars and longitudinal slab surface steel bars, and finally cast-in-place concrete construction is carried out, thereby ensuring the thickness of the formed floor slab and the anti-micro-vibration effect, while ensuring that the prefabricated components are not too heavy.

[0074] The steel bars inside the prefabricated waffle beam slab unit 3 are divided into slab bottom transverse steel bars 37, slab bottom longitudinal steel bars 38 and rib beam steel bars 39;

[0075] A plurality of transversely parallel and spaced bottom slab transverse steel bars 37 and a plurality of longitudinally parallel and spaced bottom slab longitudinal steel bars 38 are alternately arranged and poured with concrete and reserved through holes 33 to form a reinforced concrete floor slab 31, and rib beam steel bars 39 are poured with concrete to form rib beams 32;

[0076] The bottom transverse reinforcement 37 of the slab includes a lower transverse reinforcement 371 and a lower transverse stirrup 372. A plurality of lower transverse reinforcements 371 extend left and right and are bent at both ends to form an anchoring structure extending into the rib beam 32. A plurality of lower transverse stirrups 372 are arranged in sequence left and right, and the lower transverse reinforcement 371 is connected to the bottom of the lower transverse stirrup 372. The portion of the lower transverse stirrup 372 extending out of the reinforced concrete floor slab 31 forms the annular reinforcement 34.

[0077] The bottom longitudinal reinforcement 38 of the slab includes a lower longitudinal reinforcement 381 and a lower longitudinal stirrup 382. A plurality of lower longitudinal reinforcements 381 extend in the left-right direction, and a plurality of lower longitudinal stirrups 382 are arranged in sequence in the front-back direction, and the lower longitudinal reinforcement 381 is connected to the bottom of the lower longitudinal stirrup 382. The portion of the lower longitudinal stirrup 382 extending out of the reinforced concrete floor slab 31 forms the annular reinforcement 34.

[0078] The rib beam reinforcement 39 includes longitudinal reinforcement B322 and rib beam stirrups. The top of the rib beam stirrups extends out of the upper surface of the rib beam 32 to form the stirrups B321. The rib beam 32 that cooperates with the beam and slab supporting member 11 is also provided with longitudinal reinforcement B322 inside, and the longitudinal reinforcement B322 extends into the beam-column node.

[0079] The front and rear end surfaces of the rib beam 32 that cooperates with the beam and slab supporting member 11 are also provided with shear-resistant key grooves B323.

[0080] The left and right end surfaces of the prefabricated frame beam 2 are also provided with shear key grooves A25. Here, the shear key grooves B323 and the shear key grooves A25 are mainly used to ensure the strength of the pouring node connection.

[0081] The beam-slab supporting member 11 and the beam supporting member 12 are both steel brackets, and the two steel brackets are locked on the side walls of the column 1 respectively.

[0082] like Figure 4 , 5 As shown: the main supporting member 4 includes an anchor plate 41, a shear steel plate 42, a connecting bottom plate 43 and a vertical steel plate 44; the shear steel plate 42 is arranged on the inner side of the anchor plate 41, and the two anchor plates 41 are arranged on the front and rear sides of the prefabricated frame beam 2; the bottoms of the two anchor plates 41 are connected by a connecting bottom plate 43; the main supporting member 4 and the prefabricated frame beam 2 are cast in one piece;

[0083] The front and rear edges of the connecting base plate 43 extend out of the front and rear sides of the prefabricated frame beam 2; the vertical steel plate 44 is connected to the middle of the connecting base plate 43 and is connected to the outer side of the anchor plate 41 to form an inverted T-shaped supporting structure, so that the two sides of the vertical steel plate 44 respectively support the rib beams 32 of the corresponding reinforced concrete floor slab 31.

[0084] Since the shear resistance of the inverted T-shaped supporting structure is smaller than that of the trough-shaped supporting structure of the existing beam-slab integrated floor, it is considered to provide an L-shaped connecting member 9 between the embedded steel plate 36 and the main supporting member 4 and weld it to improve the shear resistance.

[0085] like Fig.11 As shown: the rib beam top steel bar skeleton 5 includes a full-length steel bar A51 and a closed stirrup 52; a plurality of full-length steel bars A51 are arranged in parallel, and a plurality of closed stirrups 52 are arranged between the full-length steel bars A51, and the closed stirrups 52 are arranged in sequence in the extension direction of the full-length steel bars A51. Here, the closed stirrups 52 and stirrups B321 of the rib beam top steel bar skeleton 5 are staggered.

[0086] like Fig.10 As shown: the main beam top steel bar skeleton 6 includes a full-length steel bar B61 and a tie bar 62; a plurality of full-length steel bars B61 are arranged in an array, and a tie bar 62 is arranged outside the full-length steel bar B61; the tie bar 62 is arranged in sequence in the extension direction of the full-length steel bar B61. Here, the tie bar 62 of the main beam top steel bar skeleton 6 cooperates with the open hoop 22 to form a closed hoop structure.

[0087] like Fig.13As shown: the transverse plate surface reinforcement 7 includes an upper transverse reinforcement 71 and an upper transverse stirrup 72, a plurality of upper transverse reinforcements 71 extend left and right, a plurality of upper transverse stirrups 72 are arranged in sequence left and right, and the upper transverse reinforcement 71 is connected to the top of the upper transverse stirrup 72; the upper transverse stirrup 72 and the lower transverse stirrup 372 are staggered.

[0088] like Fig.12 As shown, the longitudinal plate surface reinforcement 8 includes an upper longitudinal reinforcement 81 and an upper longitudinal stirrup 82, a plurality of upper longitudinal reinforcements 81 extend in the left-right direction, a plurality of upper longitudinal stirrups 82 are arranged in sequence in the front-back direction, and the upper longitudinal reinforcement 81 is connected to the top of the upper longitudinal stirrup 82. The upper longitudinal stirrup 82 and the upper longitudinal stirrup 382 are staggered.

[0089] like Figure 1 , 15 -19: A construction method of a beam-slab integrated prefabricated waffle slab structure, comprising the following steps:

[0090] S1. Complete the array construction of column 1;

[0091] S2 according to the height of the prefabricated frame beam 2 and the prefabricated waffle beam unit 3, the beam support member 11 and the beam support member 12 are installed on the column 1;

[0092] S3. The prefabricated frame beam 2 is placed on two columns 1, and the ends of the prefabricated frame beam 2 are supported on the beam support member 12;

[0093] S4. The prefabricated waffle beam unit 3 is mounted between the prefabricated frame beams 2, the prefabricated waffle beam unit 3 is supported on one side of the rib beam 32 on the beam support member 11 or the main support member 4, and the other side of the rib beam 32 is supported on the main support member 4;

[0094] S5. Complete the welding of the L-shaped connector 9 with the embedded steel plate 36 and the main support member 4; first hoist the main beam top steel frame 6 into the groove 21 of the prefabricated frame beam 2, wherein the main beam top steel frame 6 covers all prefabricated frame beams 2 in the same extension direction; then hoist the rib beam top steel frame 5 to the two adjacent rib beams 32 in the two prefabricated waffle beam-slab units 3;

[0095] S6. The transverse plate steel bars 7 and the longitudinal plate steel bars 8 are successively hoisted into the prefabricated waffle beam and slab unit 3;

[0096] S7. Pour concrete on site at the beam-column joints of the column 1 and the precast frame beam 2, at the rib beam top steel bar skeleton 5, at the main beam top steel bar skeleton 6, at the transverse slab surface steel bars 7 and at the longitudinal slab surface steel bars 8. The cast-in-place concrete must cover the rib beam top steel bar skeleton 5, the main beam top steel bar skeleton 6, the transverse slab surface steel bars 7 and the longitudinal slab surface steel bars 8.

[0097] Finally, it should be noted that the above is only a preferred embodiment of the present invention and is not intended to limit the present invention. Although the present invention has been described in detail with reference to the aforementioned embodiments, it is still possible for those skilled in the art to modify the technical solutions described in the aforementioned embodiments or to make equivalent substitutions for some of the technical features therein. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. A beam-slab integrated prefabricated waffle slab structure, characterized in that: It comprises a column (1), a prefabricated frame beam (2) and a prefabricated waffle beam-slab unit (3); The columns (1) are distributed in an array, and the upper ends of the columns (1) are provided with beam and slab support members (11) and beam support members (12); The cross-section of the prefabricated frame beam (2) is generally rectangular, and its two ends are respectively mounted on beam support members (12) of adjacent columns (1) on the left and right sides, and main support members (4) are provided on the front and rear side walls of the prefabricated frame beam (2); The prefabricated waffle beam-slab unit (3) comprises a reinforced concrete floor slab (31), wherein the left and right sides of the reinforced concrete floor slab (31) are respectively provided with rib beams (32) extending upward and forward and backward, and the reinforced concrete floor slab (31) is provided with through holes (33) arranged in an array; the front and rear sides and the left and right sides of any through hole (33) are provided with annular steel bars (34) extending out of the reinforced concrete floor slab (31), and the annular steel bars (34) between any two adjacent through holes (33) are the same; a cylindrical inner mold (35) is provided above any through hole (33); the inner side wall surfaces of the front and rear ends of the rib beam (32) are also provided with embedded steel plates (36); the rib beam (32) of the prefabricated waffle beam-slab unit (3) is mounted on a beam-slab support member (11) or a main support member (4) of two mutually parallel prefabricated frame beams (2); The rib beam (32) is provided with stirrups B (321) extending from the upper surface of the rib beam (32) and arranged in sequence in the front-to-back direction; two adjacent rib beams (32) in the two prefabricated waffle beam-slab units (3) are provided with a rear-placed rib beam top steel bar skeleton (5); The top surface of the prefabricated frame beam (2) is provided with a groove (21) extending along the length direction thereof; an open hoop (22) extending out of the groove (21) is provided inside the prefabricated frame beam (2); the prefabricated frame beam (2) is further provided with connecting steel bars (23) extending out of the front and rear sides of the prefabricated frame beam (2); the connecting steel bars (23) are provided in a plurality of rows and the plurality of rows of connecting steel bars (23) are arranged in sequence in the left-right direction; the prefabricated frame beam (2) is further provided with longitudinal steel bars A (24) inside, and the longitudinal steel bars A (24) extend into the beam-column node; The prefabricated frame beam (2) is also provided with a rear-mounted main beam top steel bar skeleton (6), the main beam top steel bar skeleton (6) is arranged throughout the length to cover all prefabricated frame beams (2) in the same extension direction, and the main beam top steel bar skeleton (6) and the open hoop (22) cooperate to form a closed hoop structure; An L-shaped connecting piece (9) is provided between the embedded steel plate (36) and the main supporting piece (4), and the L-shaped connecting piece (9) is welded to both of them; in the cylindrical inner mold (35) arranged in an array, transverse plate surface steel bars (7) and longitudinal plate surface steel bars (8) are provided between the transverse gaps and between the longitudinal gaps, respectively; Casting concrete on site at the beam-column joints of the columns (1) and the prefabricated frame beams (2), at the rib beam top steel frame (5), at the main beam top steel frame (6), at the transverse slab surface steel frames (7), and at the longitudinal slab surface steel frames (8), wherein the cast-in-place concrete needs to cover the rib beam top steel frame (5), the main beam top steel frame (6), the transverse slab surface steel frames (7), and the longitudinal slab surface steel frames (8); The main supporting member (4) comprises an anchor plate (41), a shear steel plate (42), a connecting bottom plate (43) and a vertical steel plate (44); the shear steel plate (42) is fixed to the inner side of the anchor plate (41); the two anchor plates (41) are respectively arranged on the front and rear sides of the prefabricated frame beam (2); the bottoms of the two anchor plates (41) are connected by a connecting bottom plate (43); the main supporting member (4) and the prefabricated frame beam (2) are integrally cast; The front and rear edges of the connecting bottom plate (43) extend out of the front and rear side surfaces of the prefabricated frame beam (2); the vertical steel plate (44) is connected to the middle of the connecting bottom plate (43) and to the outer side surface of the anchor plate (41), forming an inverted T-shaped supporting structure, so that the two sides of the vertical steel plate (44) respectively support the rib beams (32) of the corresponding reinforced concrete floor slab (31).

2. The beam-slab integrated prefabricated waffle slab structure according to claim 1, characterized in that: The steel bars inside the prefabricated waffle beam-slab unit (3) are divided into slab bottom transverse steel bars (37), slab bottom longitudinal steel bars (38) and rib beam steel bars (39); A plurality of transversely parallel and spaced-apart bottom transverse steel bars (37) and a plurality of longitudinally parallel and spaced-apart bottom longitudinal steel bars (38) are alternately arranged and poured with concrete and reserved through holes (33) to form a reinforced concrete floor slab (31), and rib beam steel bars (39) are poured with concrete to form rib beams (32); The slab bottom transverse reinforcement (37) comprises a lower transverse reinforcement (371) and a lower transverse stirrup (372), wherein a plurality of lower transverse reinforcements (371) extend in a left-right direction and are bent at both ends to form an anchoring structure extending into the rib beam (32), a plurality of lower transverse stirrups (372) are arranged in sequence in a left-right direction, and the lower transverse reinforcement (371) is connected to the bottom of the lower transverse stirrup (372); The slab bottom longitudinal reinforcement (38) comprises lower longitudinal reinforcement (381) and lower longitudinal stirrups (382), wherein a plurality of lower longitudinal reinforcements (381) extend in a left-right direction, a plurality of lower longitudinal stirrups (382) are arranged in sequence in a front-back direction, and the lower longitudinal reinforcement (381) is connected to the bottom of the lower longitudinal stirrups (382); The rib beam reinforcement (39) comprises longitudinal reinforcement B (322) and rib beam stirrups, the top of the rib beam stirrups extending out of the upper surface of the rib beam (32) to form the stirrups B (321); the rib beam (32) matched with the beam and slab support member (11) is also provided with longitudinal reinforcement B (322) inside, and the longitudinal reinforcement B (322) extends into the beam-column node.

3. The beam-slab integrated prefabricated waffle slab structure according to claim 2, characterized in that: The front and rear end surfaces of the rib beam (32) that cooperates with the beam and slab supporting member (11) are also provided with shear-resistant key grooves B (323).

4. The beam-slab integrated prefabricated waffle slab structure according to claim 1, characterized in that: The left and right end surfaces of the prefabricated frame beam (2) are also provided with shear-resistant key grooves A (25).

5. The beam-slab integrated prefabricated waffle slab structure according to claim 1, characterized in that: The beam-slab supporting member (11) and the beam supporting member (12) are both steel brackets, and the two steel brackets are respectively locked on the side walls of the column (1).

6. The beam-slab integrated prefabricated waffle slab structure according to claim 1, characterized in that: The rib beam top steel bar skeleton (5) comprises a full-length steel bar A (51) and closed stirrups (52); a plurality of full-length steel bars A (51) are arranged in parallel, a plurality of closed stirrups (52) are provided between the full-length steel bars A (51), and the closed stirrups (52) are arranged in sequence in the extension direction of the full-length steel bars A (51).

7. The beam-slab integrated prefabricated waffle slab structure according to claim 1, characterized in that: The main beam top reinforcement skeleton (6) comprises a full-length reinforcement B (61) and tension bars (62); a plurality of full-length reinforcements B (61) are arranged in an array, and tension bars (62) are arranged outside the full-length reinforcements B (61); and the tension bars (62) are arranged in sequence in the extension direction of the full-length reinforcements B (61).

8. The beam-slab integrated prefabricated waffle slab structure according to claim 1, characterized in that: The transverse plate surface reinforcement (7) comprises an upper transverse reinforcement (71) and an upper transverse stirrup (72), wherein a plurality of upper transverse reinforcements (71) extend in the left-right direction, a plurality of upper transverse stirrups (72) are arranged in sequence in the left-right direction, and the upper transverse reinforcement (71) is connected to the top of the upper transverse stirrup (72); The longitudinal plate surface reinforcement (8) comprises an upper longitudinal reinforcement (81) and an upper longitudinal stirrup (82), wherein a plurality of upper longitudinal reinforcements (81) extend in a left-right direction, a plurality of upper longitudinal stirrups (82) are arranged in sequence in a front-back direction, and the upper longitudinal reinforcement (81) is connected to the top of the upper longitudinal stirrup (82).

9. A construction method for a beam-slab integrated prefabricated waffle slab structure according to any one of claims 1 to 8, characterized in that: The steps include: S1. Complete the array construction of the columns (1); S2. According to the height of the prefabricated frame beam (2) and the prefabricated waffle beam-slab unit (3), the beam-slab support member (11) and the beam support member (12) are installed on the column (1); S3. The prefabricated frame beam (2) is placed on two columns (1), and the end of the prefabricated frame beam (2) is supported on the beam support member (12); S4. The prefabricated waffle beam-slab unit (3) is placed between the prefabricated frame beams (2), and the rib beam (32) on one side of the prefabricated waffle beam-slab unit (3) is supported on the beam-slab support member (11) or the main support member (4), and the rib beam (32) on the other side is supported on the main support member (4); S5. Complete the welding of the L-shaped connector (9) with the embedded steel plate (36) and the main support member (4); first hoist the main beam top steel frame (6) into the groove (21) of the prefabricated frame beam (2), wherein the main beam top steel frame (6) covers all prefabricated frame beams (2) in the same extension direction; then hoist the rib beam top steel frame (5) to two adjacent rib beams (32) in the two prefabricated waffle beam-slab units (3); S6. The transverse slab reinforcement (7) and the longitudinal slab reinforcement (8) are successively hoisted into the prefabricated waffle beam-slab unit (3); S7. Concrete is poured on site at the beam-column joints of the columns (1) and the precast frame beams (2), at the rib beam top reinforcement skeleton (5), at the main beam top reinforcement skeleton (6), at the transverse slab surface reinforcement (7), and at the longitudinal slab surface reinforcement (8). The cast-in-place concrete must cover the rib beam top reinforcement skeleton (5), the main beam top reinforcement skeleton (6), the transverse slab surface reinforcement (7), and the longitudinal slab surface reinforcement (8).