Peak load regulation system of coal-fired units based on fuel side and high enthalpy working fluid energy storage and supply device

By introducing energy storage and supply devices based on fuel side and high enthalpy working fluid in coal-fired units, the problem of insufficient boiler energy supply is solved, and the response to rapid load is achieved, and the flexible peak shaving capacity and steam production of the unit are improved. Rate.

CN118482381BActive Publication Date: 2024-11-12SHANGHAI JIAOTONG UNIV
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410940995.3
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-07-15
Publication Date
2024-11-12
Estimated Expiration
2044-07-15

Smart Images

  • Figure CN118482381B_ABST
    Figure CN118482381B_ABST
Patent Text Reader

Abstract

The present invention provides a coal-fired unit peak-shaving system based on a fuel side and a high-enthalpy working fluid energy storage and supply device, comprising: a thermal mechanism of a coal-fired unit, the thermal mechanism of the coal-fired unit comprising a high-pressure cylinder, a medium-pressure cylinder, a low-pressure cylinder and a generator connected in sequence; a high-enthalpy working fluid energy storage and supply mechanism with a storage chamber, the high-enthalpy working fluid energy storage and supply mechanism comprising a heat storage tank and an energy storage pipeline and an energy release pipeline connected to the heat storage tank; a coal powder storage bin mechanism with a storage function, the coal powder storage bin mechanism comprising a coal powder storage bin, an openable and closable small powder bin energy storage pipeline connected to a coal mill and a fine powder separator, and a plurality of openable and closable small powder bin energy release pipelines connected to the coal powder storage bin; the beneficial effects of the present invention are as follows: the present invention couples a coal-fired unit with a fuel side and a high-enthalpy working fluid energy storage and supply device, and the flexible peak-shaving function of the coal-fired unit can be realized through the energy storage and release of the coal powder stored in the coal powder storage bin and the high-quality working fluid in the heat storage tank.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of coal-fired unit peak regulation, and in particular to a coal-fired unit peak regulation system based on a fuel side and a high enthalpy working fluid energy storage and supply device. Background Art

[0002] In order to further improve the coal-fired units' ability to absorb large proportions of intermittent wind, light and other renewable energy sources and ensure the safe and stable operation of the power grid, the load change rate of existing or newly built coal-fired units (whether ultra-supercritical or subcritical) will continue to be improved to cope with the demand for increased rapid load change capacity of coal-fired units caused by large-scale wind / light loss in the future new power system with a high proportion of renewable energy. However, compared with equipment such as turbines and generators, the thermal system of coal-fired units, especially the boiler part, has a longer load response time, usually more than 10 minutes. This is because the boiler involves multiple complex processes such as coal powder preparation, coal powder transportation, coal powder combustion and working fluid heat absorption, resulting in large thermal inertia and delay. Therefore, under the condition of rapid load change, the energy supply of the coal-fired unit boiler often cannot meet the demand in time, which becomes the fundamental reason for limiting the rapid increase in its load change rate. Summary of the invention

[0003] In view of the shortcomings of the prior art described above, the purpose of the present invention is to provide a coal-fired unit peak-shaving system based on the fuel side and a high-enthalpy working fluid energy storage and supply device, which is used to solve the problem of insufficient energy supply of the coal-fired unit boiler under rapidly changing load in the prior art.

[0004] To achieve the above objectives and other related objectives, the present invention provides the following technical solutions:

[0005] The peak load regulation system of coal-fired units based on fuel side and high enthalpy working fluid storage and supply device includes:

[0006] A thermal mechanism of a coal-fired unit, the thermal mechanism of the coal-fired unit comprising a high-pressure cylinder, a medium-pressure cylinder, a low-pressure cylinder and a generator connected in sequence, and also comprising a high-pressure heater connected to the high-pressure cylinder and the medium-pressure cylinder, a deaerator connected to the medium-pressure cylinder, and a low-pressure heater and a condenser connected to the low-pressure cylinder;

[0007] The steam extraction outlets of the high-pressure cylinder and the medium-pressure cylinder are connected to the hot end inlet of the high-pressure heater, and the steam extraction outlet of the medium-pressure cylinder is also connected to the inlet of the deaerator, the outlet of the deaerator is also connected to the high-pressure heater through a feedwater pump, the cold end outlet of the high-pressure heater is connected to the inlet of a boiler economizer, the steam extraction outlet of the low-pressure cylinder is connected to the hot end inlet of the low-pressure heater, the outlet of the condenser is connected to the cold end inlet of the low-pressure heater through a condensate pump, and the low-pressure heater is also connected to the inlet of the deaerator;

[0008] A high-enthalpy working fluid energy storage and supply mechanism with a storage cavity, the high-enthalpy working fluid energy storage and supply mechanism comprising a heat storage tank and an energy storage pipeline and an energy release pipeline connected to the heat storage tank, the heat storage tank is provided with a heat exchanger and a steam-water separator, and the energy storage pipeline comprises an openable and closable boiler water energy storage pipeline connected to the heat storage tank and an openable and closable steam energy storage pipeline connected to the heat exchanger, and the energy release pipeline comprises an openable and closable boiler water energy release pipeline connected to the heat storage tank and an openable and closable steam energy release pipeline connected to the steam-water separator;

[0009] A pulverized coal storage bin mechanism with a storage function, the pulverized coal storage bin mechanism comprising a coal feeder, a coal mill connected to the coal feeder, a fine powder separator, a pulverized coal storage bin connected to the fine powder separator, an openable and closable small powder bin energy storage pipeline connected to the coal mill and the fine powder separator, and a plurality of openable and closable small powder bin energy release pipelines connected to the pulverized coal storage bin.

[0010] In one embodiment of the present invention, a valve 1 for controlling the opening and closing of the boiler water energy storage pipeline is provided on the boiler water energy storage pipeline, and when the valve 1 is opened, the chemical water in the boiler feed water system can be passed into the heat storage tank; the steam energy storage pipeline is provided with a temperature and pressure measuring point 1, a valve 2 for controlling the opening and closing of the steam energy storage pipeline, a check valve 1 and a flow meter 1 in sequence, the steam energy storage pipeline is also connected to the steam extraction outlet of the high-pressure cylinder or the outlet of the reheater, and when the valve 2 is opened, the high-temperature and high-pressure steam in the thermal mechanism of the coal-fired unit can be passed into the heat exchanger in the heat storage tank.

[0011] In one embodiment of the present invention, the boiler water energy release pipeline is provided with valve three, flow meter two, check valve two and temperature and pressure measuring point two for controlling the opening and closing of the boiler water energy release pipeline in sequence, and the boiler water energy release pipeline is also connected to the inlet of the boiler economizer, and the high-temperature water in the heat storage tank can be passed into the boiler economizer when the valve three is opened; the steam energy release pipeline is provided with valve four, pressure reducing valve, flow meter three, check valve three and temperature and pressure measuring point three for controlling the opening and closing of the steam energy release pipeline in sequence, and the steam energy release pipeline is also connected to the inlet of the boiler superheater, and the high-temperature and high-pressure steam in the heat exchanger in the heat storage tank can be passed into the boiler superheater when the valve four is opened.

[0012] In one embodiment of the present invention, the high-enthalpy working fluid energy storage and supply mechanism also includes an auxiliary steam pipeline connected to the heat exchanger, and a valve five and a temperature and pressure measuring point four for controlling the opening and closing of the auxiliary steam pipeline are sequentially provided on the auxiliary steam pipeline, and the auxiliary steam pipeline is also connected to the inlet of the auxiliary steam manifold or the hot side inlet of the high-pressure heater; the high-enthalpy working fluid energy storage and supply mechanism also includes a pressure regulating pipeline and a drain pipeline connected to the heat storage tank, and a pressure regulating valve for controlling the opening and closing of the pressure regulating pipeline is provided on the pressure regulating pipeline, and a drain valve for controlling the opening and closing of the drain pipeline is provided on the drain pipeline.

[0013] In one embodiment of the present invention, a valve six and a first explosion-proof door for controlling the opening and closing of the small powder bin energy storage pipeline are provided in sequence on the small powder bin energy storage pipeline, and the coal powder in the coal mill can be passed into the fine powder separator when the valve six is ​​opened; a valve seven for controlling the opening and closing of the small powder bin energy release pipeline is provided on the small powder bin energy release pipeline, and the small powder bin energy release pipeline is also connected to the input pipeline of the boiler burner, and the coal powder in the coal powder storage bin can be passed into the boiler burner when the valve seven is opened.

[0014] In one embodiment of the present invention, the fine powder separator is also connected to the input pipeline of the boiler burner through the powder exhaust fan, and the coal powder storage bin is also provided with a temperature and pressure measuring point five, a manhole, a second explosion-proof door, a high material level alarm, a low material level alarm, a discharge hole and a material level measuring point. The coal powder storage bin is also connected with an emptying pipeline and a moisture absorption pipeline. The emptying pipeline is provided with an emptying valve for controlling the opening and closing of the emptying pipeline, and the moisture absorption pipeline is provided with a moisture absorption valve for controlling the opening and closing of the moisture absorption pipeline.

[0015] In one embodiment of the present invention, the pulverized coal storage bin is connected with a protective pipeline 1 and a protective pipeline 2 which are connected to each other. The protective pipeline 1 is provided with a valve 8 and a check valve 4 for controlling the opening and closing of the protective pipeline 1 in sequence. The protective pipeline 2 is provided with a valve 9 and a check valve 5 for controlling the opening and closing of the protective pipeline 2 in sequence. Nitrogen can be introduced into the upper and lower parts of the pulverized coal storage bin when the valve 8 and the valve 9 are opened.

[0016] As described above, the peak-shaving system of a coal-fired unit based on a fuel side and a high-enthalpy working fluid energy storage and supply device of the present invention has the following beneficial effects: the present invention couples a coal-fired unit with an energy storage and supply device containing a fuel side and a high-enthalpy working fluid, and through the energy storage and release of the pulverized coal stored in the pulverized coal storage bin and the high-quality working fluid in the heat storage tank, the flexible peak-shaving function of the coal-fired unit can be realized. When the high-enthalpy working fluid energy storage and supply device needs to store energy, first, part of the working fluid in the water supply system of the coal-fired unit is sent into the heat storage tank through the boiler water energy storage pipeline, and then part of the high-pressure and high-temperature steam is extracted through the steam energy storage pipeline to enter the heat storage tank for heating, so that the working fluid is heated and pressurized to the design value, so that the device is in an available state; when the coal-fired unit needs to climb quickly, When the engine is climbing, the steam extraction of some high-pressure cylinders is reduced or cut off. The reduction in steam extraction leads to a rapid increase in the power generation of the unit. At the same time, the high-enthalpy working fluid in the heat storage tank is mixed with the boiler feed water at the inlet of the boiler economizer. The reduction in steam extraction and the energy supply of the high-enthalpy working fluid energy storage and supply device cooperate with each other to ensure that the boiler feed water temperature maintains the original feed water stable. The saturated steam generated during the energy release of the high-enthalpy working fluid energy storage and supply device enters the boiler superheater, which can further increase the steam production rate of the coal-fired unit boiler. In addition, the pulverized coal pre-stored in the pulverized coal storage bin is used to replenish energy into the boiler furnace in time, which can further improve the boiler's variable load response rate. Therefore, through the coordination of the three, the unit's rapid climbing ability can be improved. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] Figure 1 Shown is a schematic diagram of the overall structure of a thermal mechanism of a coal-fired unit and a high-enthalpy working fluid energy storage and supply mechanism in a coal-fired unit peak-shaving system based on a fuel side and a high-enthalpy working fluid energy storage and supply device disclosed in an embodiment of the present invention;

[0018] Figure 2 Shown is an overall structural schematic diagram of a pulverized coal storage mechanism in a peak-shaving system of a coal-fired unit based on a fuel side and a high-enthalpy working fluid energy storage and supply device disclosed in an embodiment of the present invention.

[0019] Component number description

[0020] 1. Steam energy storage pipeline; 2. Temperature and pressure measuring point 1; 3. Valve 2; 4. Check valve 1; 5. Flow meter 1; 6. Pressure regulating pipeline; 7. Pressure regulating valve; 8. Steam-water separator; 9. Temperature and pressure measuring point 6; 10. Pressure and temperature alarm; 11. Valve 4; 12. Steam energy release pipeline; 13. Pressure reducing valve; 14. Flow meter 3; 15. Check valve 3; 16. Temperature and pressure measuring point 3; 17. Boiler superheater; 18. Valve 1; 19. Boiler water energy storage pipeline; 20. Heat exchanger; 21. Liquid level meter; 22. Liquid level alarm; 23 , drain pipe; 24, drain valve; 25, heat storage tank; 26, valve five; 27, auxiliary steam pipe; 28, temperature and pressure measuring point four; 29, auxiliary steam manifold; 30, valve three; 31, boiler water energy release pipe; 32, flow meter two; 33, check valve two; 34, temperature and pressure measuring point two; 35, boiler economizer; 36, high pressure heater; 37, feed water pump; 38, deaerator; 39, low pressure heater; 40, condensate pump; 41, condenser; 42, generator; 43, low pressure cylinder; 44, medium pressure cylinder; 45, reheater; 46 , high-pressure cylinder; 47, extraction outlet 1 of high-pressure cylinder; 48, extraction outlet 2 of high-pressure cylinder; 49, extraction outlet 1 of medium-pressure cylinder; 50, extraction outlet 2 of medium-pressure cylinder; 51, extraction outlet 1 of low-pressure cylinder; 52, extraction outlet 2 of low-pressure cylinder; 53, extraction outlet 3 of low-pressure cylinder; 54, extraction outlet 4 of low-pressure cylinder; 55, coal feeder; 56, coal mill; 57, coal powder storage bin; 58, small powder bin energy storage pipeline; 59, valve 6; 60, first explosion-proof door; 61, fine powder separator; 62, pressure balance pipe; 63, powder exhaust fan; 64. Material level measuring point; 65. Drain pipeline; 66. Drain valve; 67. Moisture absorption pipeline; 68. Moisture absorption valve; 69. Temperature and pressure measuring point five; 70. Manhole; 71. Second explosion-proof door; 72. Discharge hole; 73. Small powder silo energy release pipeline; 74. Valve seven; 75. Protection pipeline one; 76. Valve eight; 77. Check valve four; 78. Protection pipeline two; 79. Valve nine; 80. Check valve five; 81. Low material level alarm; 82. High material level alarm; 83. Connecting pipeline one; 84. Connecting pipeline two; 85. Connecting pipeline three. DETAILED DESCRIPTION

[0021] The following describes the embodiments of the present invention through specific examples, and those skilled in the art can easily understand other advantages and effects of the present invention from the contents disclosed in this specification. It should be noted that the following embodiments and features in the embodiments can be combined with each other without conflict.

[0022] See also Figure 1 and Figure 2The present invention provides a coal-fired unit peak-shaving system based on the fuel side and a high-enthalpy working fluid energy storage and supply device, including: a thermal mechanism of the coal-fired unit, the thermal mechanism of the coal-fired unit includes a high-pressure cylinder 46, a medium-pressure cylinder 44, a low-pressure cylinder 43 and a generator 42 connected in sequence, and also includes a high-pressure heater 36 connected to the high-pressure cylinder 46 and the medium-pressure cylinder 44, a deaerator 38 connected to the medium-pressure cylinder 44, and a low-pressure heater 39 and a condenser 41 connected to the low-pressure cylinder 43, and the high-pressure cylinder 46 and the medium-pressure cylinder 44 are also connected to the reheater 45, and the high-pressure cylinder 46 is also connected to the boiler superheater 17.

[0023] exist Figure 1 On the right side, the steam extraction outlet 1 47 of the high-pressure cylinder, the steam extraction outlet 2 48 of the high-pressure cylinder and the steam extraction outlet 1 49 of the intermediate-pressure cylinder are all connected to the hot end inlet (located on the top side of the high-pressure heater 36) of the high-pressure heater 36, the cold end outlet (located on the left side of the high-pressure heater 36) of the high-pressure heater 36 is connected to the inlet of the boiler economizer 35, and the steam extraction outlet 2 50 of the intermediate-pressure cylinder is connected to the inlet of the deaerator 38, and the outlet of the deaerator 38 is also connected to the high-pressure heater 36 through the feed water pump 37, and the steam extraction outlet 1 51 of the low-pressure cylinder to the steam extraction outlet 4 54 of the low-pressure cylinder are all connected to the hot end inlet (located on the top side of the low-pressure heater 39), the outlet of the condenser 41 is connected to the cold end inlet (located on the right side of the low-pressure heater 39) of the low-pressure heater 39 through the condensate pump 40, and the low-pressure heater 39 is also connected to the inlet of the deaerator 38.

[0024] exist Figure 1 In the dotted frame on the left, there is a high-enthalpy working fluid energy storage and supply mechanism with a storage cavity. The high-enthalpy working fluid energy storage and supply mechanism includes a heat storage tank 25 and an energy storage pipeline and an energy release pipeline connected to the heat storage tank 25. A heat exchanger 20 and a steam-water separator 8 are arranged in the heat storage tank 25, wherein the heat exchanger 20 is a water-steam heat exchanger (indirect or direct), and the steam-water separator 8 is used to separate water and steam in the high-quality working fluid stored in the heat storage tank 25, and the energy storage pipeline includes an openable and closable boiler water energy storage pipeline 19 connected to the heat storage tank 25 and an openable and closable steam energy storage pipeline 1 connected to the heat exchanger 20, and the energy release pipeline includes an openable and closable boiler water energy release pipeline 31 connected to the heat storage tank 25 and an openable and closable steam energy release pipeline 12 connected to the steam-water separator 8.

[0025] The boiler water energy storage pipeline 19 is provided with a valve 18 for controlling the opening and closing of the boiler water energy storage pipeline 19, and the chemical water in the boiler feed water system can be passed into the heat storage tank 25 when the valve 18 is opened, wherein the boiler water energy storage pipeline 19 is connected with the coal-fired boiler feed water system, that is, the coal-fired boiler feed water system is connected with the heat storage tank 25 through the boiler water energy storage pipeline 19; the steam energy storage pipeline 1 is provided with a temperature and pressure measuring point 2, a valve 3 for controlling the opening and closing of the steam energy storage pipeline 1, a check valve 4 and a flow meter 5 in sequence, and the steam energy storage pipeline 1 is also connected to the steam extraction outlet 47 of the high-pressure cylinder through a connecting pipeline 83 or to the outlet of the reheater 45 through a connecting pipeline 84, that is, The extraction steam outlet 47 of the high-pressure cylinder or the outlet of the reheater 45 is connected to the steam side inlet of the heat exchanger 20 through the steam storage pipeline 1, and when the valve 23 is opened, the high-temperature and high-pressure steam in the thermal mechanism of the coal-fired unit can be passed into the heat exchanger 20 in the heat storage tank 25 through the steam storage pipeline 1 connected to the extraction steam outlet 47 of the high-pressure cylinder. Therefore, the working medium of the water supply system exchanges heat with the extraction steam of the high-pressure cylinder 46 through the heat exchanger 20, and the boiler water becomes a saturated working medium after direct or indirect heat exchange in the heat exchanger 20. After heat exchange, the extraction steam of the high-pressure cylinder 46 flows out from the auxiliary steam pipeline 27 below and is connected to the auxiliary steam header 29 (or through the connecting pipeline 3 85 and the hot end inlet of the high-pressure heater 36).

[0026] The boiler water energy release pipeline 31 is provided with valve 30, flow meter 32, check valve 33 and temperature and pressure measuring point 34 for controlling the opening and closing of the boiler water energy release pipeline 31 in sequence. The boiler water energy release pipeline 31 is also connected to the inlet of the boiler economizer 35, and can pass the high-temperature water in the heat storage tank 25 into the boiler economizer 35 when the valve 30 is opened. Among them, the flow meter 32, check valve 33 and temperature and pressure measuring point 34 are set to adjust the pressure and flow of the working medium entering the inlet of the boiler economizer 35; the steam energy release pipeline 12 is provided with valve 4 11, pressure reducing valve 13, Flowmeter three 14, check valve three 15 and temperature and pressure measuring point three 16, the steam energy release pipeline 12 is also connected to the inlet of the boiler superheater 17, wherein the pressure reducing valve 13, flowmeter three 14, check valve three 15 and temperature and pressure measuring point three 16 are arranged to adjust the steam pressure and flow entering the boiler superheater 17, and can pass the high-temperature and high-pressure steam in the heat exchanger 20 in the heat storage tank 25 into the boiler superheater 17 when the valve four 11 is opened, that is, the steam energy release pipeline 12 (high-pressure saturated steam) is connected to the inlet of the boiler superheater 17 (subcritical boiler) and the outlet of the steam-water separator 8 (super (ultra) critical boiler).

[0027] The high-enthalpy working medium energy storage and supply mechanism also includes an auxiliary steam pipeline 27 connected to the heat exchanger 20, and a valve 5 26 and a temperature and pressure measuring point 4 28 for controlling the opening and closing of the auxiliary steam pipeline 27 are sequentially arranged on the auxiliary steam pipeline 27. The auxiliary steam pipeline 27 is also connected to the inlet of the auxiliary steam header 29 or the hot side inlet of the high-pressure heater 36, that is, the steam side outlet of the heat exchanger 20 is connected to the hot side inlet of the auxiliary steam header 29 or the high-pressure heater 36 through the auxiliary steam pipeline 27; the high-enthalpy working medium energy storage and supply mechanism also includes a pressure regulating pipeline 6 and a drain pipeline 23 connected to the heat storage tank 25, and a pressure regulating valve 7 for controlling the opening and closing of the pressure regulating pipeline 6 is arranged on the pressure regulating pipeline 6, and a temperature and pressure measuring point 28 is arranged on the drain pipeline 23. A drain valve 24 is used to control the opening and closing of the drain pipe 23, and the heat storage tank 25 is also provided with a pressure and temperature alarm 10, a liquid level gauge 21 and a liquid level alarm 22. Furthermore, a valve 18 and a valve 2 3 are provided in the energy storage pipeline, and the valve 18 and the valve 2 3 are in an open state during the heat storage stage, so that the working fluid and high-temperature and high-pressure steam of the water supply system are connected to the heat storage tank 25 through the energy storage pipeline and insulation is achieved; the energy release pipeline is provided with a valve 30 and a valve 4 11, and the valve 30 and the valve 4 11 are in an open state during the period when rapid load increase and peak regulation are required, and the energy release pipeline of the heat storage tank 25 is connected to the input pipeline of the boiler economizer 35 and the boiler superheater 17.

[0028] exist Figure 2 The pulverized coal storage bin mechanism with storage function includes a coal feeder 55, a coal mill 56 connected to the coal feeder 55, a fine powder separator 61, a pulverized coal storage bin 57 connected to the fine powder separator 61, a small pulverized coal storage bin energy storage pipeline 58 connected to the coal mill 56 and the fine powder separator 61, and a plurality of small pulverized coal storage bin energy release pipelines 73 connected to the pulverized coal storage bin 57. The pulverized coal storage bin 57 is made of Q345 material with good strength and has a special structure. The special design has an inclination angle of 71° (greater than 70° recommended by relevant specifications); a valve 6 59 and a first explosion-proof door 60 for controlling the opening and closing of the small powder bin energy storage pipeline 58 are provided in sequence on the small powder bin energy storage pipeline 58, and the coal powder in the pulverizer 56 can be passed into the fine powder separator 61 when the valve 6 59 is opened. After a period of accumulation, the coal powder storage bin 57 can be filled with coal powder (the filling of powder is stopped after reaching the high material level), which is used as supplementary fuel when the boiler is rapidly loaded.

[0029] The small powder bin energy release pipeline 73 is provided with a valve 74 for controlling the opening and closing of the small powder bin energy release pipeline 73. In the present embodiment, there are four small powder bin energy release pipelines 73, each of which is provided with a valve 74. The small powder bin energy release pipeline 73 is also connected to the input pipeline of the boiler burner, and can pass the coal powder in the coal powder storage bin 57 into the boiler burner when the valve 74 is opened; the fine powder separator 61 is also connected to the input pipeline of the boiler burner through the powder exhaust fan 63, and the boiler burner is not in Figure 2 It is marked that the coal powder storage bin 57 is also provided with a temperature and pressure measuring point 5 69, a manhole 70, a second explosion-proof door 71, a high material level alarm 82, a low material level alarm 81, a discharge hole 72 and a material level measuring point 64, wherein the temperature and pressure measuring point 5 69 is used to monitor the temperature, pressure and other relevant data of the powder bin in real time and participate in the control to ensure that the coal powder storage bin 57 can operate safely and reliably. When the coal powder is higher than the high material level alarm 82, an alarm is started and the coal supply is stopped. When it is lower than the low material level alarm 81, an alarm is also sounded. In this embodiment, the number of material level measuring points 64 is also four. The coal powder storage bin 57 is also connected with an emptying pipeline 65 and a moisture absorption pipeline 67. The emptying pipeline 65 is provided with an emptying valve 66 for controlling the opening and closing of the emptying pipeline 65, and the moisture absorption pipeline 67 is provided with a moisture absorption valve 68 for controlling the opening and closing of the moisture absorption pipeline 67. The emptying pipeline 65 is used for emergency emptying, and the moisture absorption pipeline 67 is used to ensure the dryness of the coal powder.

[0030] The pulverized coal storage bin 57 is connected with a protective pipeline 1 75 and a protective pipeline 2 78 which are connected to each other. The protective pipeline 1 75 is provided with a valve 8 76 and a check valve 4 77 for controlling the opening and closing of the protective pipeline 1 75 in sequence. The protective pipeline 2 78 is provided with a valve 9 79 and a check valve 5 80 for controlling the opening and closing of the protective pipeline 2 78 in sequence. When the valve 8 76 and the valve 9 79 are opened, nitrogen can be introduced into the upper and lower parts of the pulverized coal storage bin 57. After the pulverized coal enters the pulverized coal storage bin 57, the protective pipeline 1 75 and the protective pipeline 2 78 of nitrogen are evenly distributed in the circumferential direction at the upper and lower parts of the pulverized coal bin, and the pressure is set. The balance pipe 62 balances the pressure at the upper and lower parts of the powder bin to prevent the coal powder from agglomerating and bridging. Furthermore, when the small powder bin energy storage pipeline 58 is being charged, the mixed coal powder enters the fine powder separator 61 from the coal mill 56 through the valve six 59. After being separated by the fine powder separator 61, the coal powder that cannot be separated is directly sent to the boiler burner through the powder exhaust fan 63. When the small powder bin energy release pipeline 73 is undergoing rapid load change, the coal powder is divided into four paths from the coal powder storage bin 57 and the feeders respectively enter the corresponding four-layer burners, and the powder is evenly delivered to the four corner burners.

[0031] Specifically, firstly, a certain amount of required working fluid is injected into the heat storage tank 25 through the boiler water supply system, and high-temperature steam (temperature ≥ 380°C) in the thermal mechanism of the coal-fired unit is selected as the heat source for energy storage heating of the heat storage tank 25. When the heat storage tank 25 needs to store heat, the high-temperature steam enters the heat exchanger 20 in the heat storage tank 25 through the steam energy storage pipeline 1 to increase the temperature and pressure of the working fluid in the heat storage tank 25. When the temperature and pressure of the working fluid are increased to a given temperature and pressure (at this time, the working fluid stored in the heat storage tank 25 is high enthalpy water and steam), energy storage is stopped. In addition, when the temperature / pressure of the working fluid in the heat storage tank 25 is lower than 5% of the design value, high-temperature steam is continuously introduced to ensure that the temperature and pressure of the working fluid in the heat storage tank 25 are always in an available state. At the same time, the existing coal mill 56 of the coal-fired unit is used as the coal powder source of the coal powder storage bin 57, and a certain amount of coal powder is regularly injected into the coal powder storage bin 57.

[0032] When the coal-fired unit needs to climb quickly, the high-enthalpy working fluid in the heat storage tank 25 is first replenished into the boiler water system in time through the energy release pipeline. Since the energy of the replenished high-enthalpy working fluid is greater than the energy of the working fluid entering the boiler circulating water system at this time, and this part of the energy can directly increase the working fluid temperature, there is no heat release from fuel combustion and heat absorption of the working fluid. Therefore, the boiler steam production rate and response rate can be quickly improved. At the same time, in order to compensate for the fact that the output of the original boiler pulverizing system cannot keep up with the boiler load change rate due to the grinding process during the climbing process of the unit, the pulverized coal pre-stored in the pulverized coal storage bin 57 is promptly and quickly delivered to the furnace to organize combustion. , improve the boiler steam production rate; in addition, due to the addition of high enthalpy working fluid, part of the steam extraction of the turbine high-pressure heater 36 can be cut off or reduced, thereby quickly improving the turbine working capacity to a certain extent, but the reduction of steam extraction will cause the feed water temperature to drop. For this reason, the high enthalpy working fluid can enter the inlet of the boiler economizer 35 and mix with the original feed water to make up for the heat of the boiler feed water reduction caused by the reduction of steam extraction, ensuring that the boiler feed water temperature maintains the original feed water temperature unchanged, and through the coordination of the high enthalpy working fluid energy storage and supply mechanism, the pulverized coal storage mechanism, and the steam turbine extraction room, the unit's variable load response rate is improved, thereby improving the unit's rapid and variable load flexible peak regulation capability.

[0033] The present invention couples a coal-fired unit with a fuel-side, high-enthalpy working fluid energy storage and supply device. Through the energy storage and release of the pulverized coal stored in the pulverized coal storage bin 57 and the high-quality working fluid in the heat storage tank 25, the flexible peak-shaving function of the coal-fired unit can be realized. When the high-enthalpy working fluid energy storage and supply device needs to store energy, first, part of the working fluid in the water supply system of the coal-fired unit is sent to the heat storage tank 25 through the boiler water energy storage pipeline 19, and then part of the high-pressure and high-temperature steam is extracted through the steam energy storage pipeline 1 to enter the heat storage tank 25 for heating, so that the working fluid is heated and pressurized to the designed value, so that the device is in an available state; when the coal-fired unit needs to climb quickly, the steam extraction of part of the high-pressure cylinder 46 is reduced or cut off, and the steam extraction is stopped. The reduction in the amount of steam causes the unit's power generation to increase rapidly. At the same time, the high-enthalpy working fluid in the heat storage tank 25 is mixed with the boiler feed water at the inlet of the boiler economizer 35. The reduced amount of steam extraction cooperates with the energy supply of the high-enthalpy working fluid storage and supply device to ensure that the boiler feed water temperature maintains the original stable feed water. The saturated steam generated during the energy release of the high-enthalpy working fluid storage and supply device enters the boiler superheater 17, thereby further improving the steam production rate of the coal-fired unit boiler. In addition, the pulverized coal pre-stored in the pulverized coal storage bin 57 can be used to replenish energy in the boiler furnace in time, thereby further improving the boiler's variable load response rate. Therefore, through the coordination of the three, the unit's rapid climbing ability can be improved.

[0034] The above embodiments are merely illustrative of the principles and effects of the present invention, and are not intended to limit the present invention. All equivalent modifications or changes made by those skilled in the art without departing from the spirit and technical ideas disclosed by the present invention shall still be covered by the claims of the present invention.

Claims

1. A coal-fired unit peak load regulation system based on the fuel side and high enthalpy working fluid energy storage and supply device, characterized in that: include: A thermal mechanism of a coal-fired unit, the thermal mechanism of the coal-fired unit comprising a high-pressure cylinder (46), a medium-pressure cylinder (44), a low-pressure cylinder (43) and a generator (42) connected in sequence, and also comprising a high-pressure heater (36) connected to the high-pressure cylinder (46) and the medium-pressure cylinder (44), a deaerator (38) connected to the medium-pressure cylinder (44), and a low-pressure heater (39) and a condenser (41) connected to the low-pressure cylinder (43); The steam extraction outlets of the high-pressure cylinder (46) and the intermediate-pressure cylinder (44) are connected to the hot end inlet of the high-pressure heater (36), and the steam extraction outlet of the intermediate-pressure cylinder (44) is also connected to the inlet of the deaerator (38). The outlet of the deaerator (38) is also connected to the high-pressure heater (36) through a feedwater pump (37). The cold end outlet of the high-pressure heater (36) is connected to the inlet of a boiler economizer (35). The steam extraction outlet of the low-pressure cylinder (43) is connected to the hot end inlet of the low-pressure heater (39). The outlet of the condenser (41) is connected to the cold end inlet of the low-pressure heater (39) through a condensate pump (40). The low-pressure heater (39) is also connected to the inlet of the deaerator (38). A high-enthalpy working fluid energy storage and supply mechanism having a storage cavity, the high-enthalpy working fluid energy storage and supply mechanism comprising a heat storage tank (25) and an energy storage pipeline and an energy release pipeline connected to the heat storage tank (25); a heat exchanger (20) and a steam-water separator (8) are provided in the heat storage tank (25); the energy storage pipeline comprises an openable and closable boiler water energy storage pipeline (19) connected to the heat storage tank (25) and an openable and closable steam energy storage pipeline (1) connected to the heat exchanger (20); the energy release pipeline comprises an openable and closable boiler water energy release pipeline (31) connected to the heat storage tank (25) and an openable and closable steam energy release pipeline (12) connected to the steam-water separator (8); A pulverized coal storage bin mechanism with a storage function, the pulverized coal storage bin mechanism comprising a coal feeder (55), a coal mill (56) connected to the coal feeder (55), a fine powder separator (61), a pulverized coal storage bin (57) connected to the fine powder separator (61), an openable and closable small powder bin energy storage pipeline (58) connected to the coal mill (56) and the fine powder separator (61), and a plurality of openable and closable small powder bin energy release pipelines (73) connected to the pulverized coal storage bin (57).

2. The peak load regulation system of coal-fired units based on the fuel side and high enthalpy working fluid energy storage and supply device according to claim 1 is characterized in that: The boiler water energy storage pipeline (19) is provided with a valve (18) for controlling the opening and closing of the boiler water energy storage pipeline (19), and when the valve (18) is opened, the chemical water in the boiler feed water system can be passed into the heat storage tank (25); the steam energy storage pipeline (1) is provided with a temperature and pressure measuring point (2), a valve (3) for controlling the opening and closing of the steam energy storage pipeline (1), a check valve (4) and a flow meter (5) in sequence; the steam energy storage pipeline (1) is also connected to the steam extraction outlet of the high-pressure cylinder (46) or the outlet of the reheater (45), and when the valve (3) is opened, the high-temperature and high-pressure steam in the thermal mechanism of the coal-fired unit can be passed into the heat exchanger (20) in the heat storage tank (25).

3. The peak load regulation system of coal-fired units based on the fuel side and high enthalpy working fluid energy storage and supply device according to claim 2 is characterized in that: The boiler water energy release pipeline (31) is provided with a valve three (30) for controlling the opening and closing of the boiler water energy release pipeline (31), a flow meter two (32), a check valve two (33) and a temperature and pressure measuring point two (34) in sequence. The boiler water energy release pipeline (31) is also connected to the inlet of the boiler economizer (35) and can pass the high-temperature water in the heat storage tank (25) into the boiler economizer (35) when the valve three (30) is opened. The steam energy release pipeline ( A valve four (11), a pressure reducing valve (13), a flow meter three (14), a check valve three (15) and a temperature and pressure measuring point three (16) for controlling the opening and closing of the steam energy release pipeline (12) are sequentially arranged on the steam energy release pipeline (12). The steam energy release pipeline (12) is also connected to the inlet of the boiler superheater (17) and can pass the high-temperature and high-pressure steam in the heat exchanger (20) in the heat storage tank (25) into the boiler superheater (17) when the valve four (11) is opened.

4. The peak load regulation system of coal-fired units based on the fuel side and high enthalpy working fluid energy storage and supply device according to claim 3 is characterized in that: The high-enthalpy working medium energy storage and supply mechanism also includes an auxiliary steam pipeline (27) connected to the heat exchanger (20), and the auxiliary steam pipeline (27) is provided with a valve five (26) and a temperature and pressure measuring point four (28) for controlling the opening and closing of the auxiliary steam pipeline (27) in sequence. The auxiliary steam pipeline (27) is also connected to the inlet of the auxiliary steam header (29) or the hot side inlet of the high-pressure heater (36); the high-enthalpy working medium energy storage and supply mechanism also includes a pressure regulating pipeline (6) and a drain pipeline (23) connected to the heat storage tank (25), and the pressure regulating pipeline (6) is provided with a pressure regulating valve (7) for controlling the opening and closing of the pressure regulating pipeline (6), and the drain pipeline (23) is provided with a drain valve (24) for controlling the opening and closing of the drain pipeline (23).

5. The peak load regulation system of coal-fired units based on the fuel side and high enthalpy working fluid energy storage and supply device according to claim 1 is characterized in that: The small powder bin energy storage pipeline (58) is provided with a valve six (59) and a first explosion-proof door (60) for controlling the opening and closing of the small powder bin energy storage pipeline (58), and when the valve six (59) is opened, the coal powder in the coal mill (56) can be passed into the fine powder separator (61); the small powder bin energy release pipeline (73) is provided with a valve seven (74) for controlling the opening and closing of the small powder bin energy release pipeline (73); the small powder bin energy release pipeline (73) is also connected to the input pipeline of the boiler burner, and when the valve seven (74) is opened, the coal powder in the coal powder storage bin (57) can be passed into the boiler burner.

6. The peak load regulation system of coal-fired units based on the fuel side and high enthalpy working fluid energy storage and supply device according to claim 5 is characterized in that: The fine powder separator (61) is also connected to the input pipeline of the boiler burner through the powder exhaust fan (63). The coal powder storage bin (57) is also provided with a temperature and pressure measuring point five (69), a manhole (70), a second explosion-proof door (71), a high material level alarm (82), a low material level alarm (81), a discharge hole (72) and a material level measuring point (64). The coal powder storage bin (57) is also connected with an emptying pipeline (65) and a moisture absorption pipeline (67). The emptying pipeline (65) is provided with an emptying valve (66) for controlling the opening and closing of the emptying pipeline (65). The moisture absorption pipeline (67) is provided with a moisture absorption valve (68) for controlling the opening and closing of the moisture absorption pipeline (67).

7. The peak load regulation system of coal-fired units based on the fuel side and high enthalpy working fluid energy storage and supply device according to claim 6 is characterized in that: The pulverized coal storage bin (57) is connected to a protective pipeline 1 (75) and a protective pipeline 2 (78) which are connected to each other. The protective pipeline 1 (75) is provided with a valve 8 (76) and a check valve 4 (77) for controlling the opening and closing of the protective pipeline 1 (75) in sequence. The protective pipeline 2 (78) is provided with a valve 9 (79) and a check valve 5 (80) for controlling the opening and closing of the protective pipeline 2 (78) in sequence. When the valve 8 (76) and the valve 9 (79) are opened, nitrogen can be introduced into the upper and lower parts of the pulverized coal storage bin (57).