Ductile iron pipe and construction method thereof
By connecting standard pipe sections and ejection equipment in series, combined with the use of cylindrical air cushions, the problems of different burial depths and curvatures in urban water transmission line construction are solved, and efficient ductile iron pipe construction is achieved, which meets the requirements of long construction distances and The venue has strict requirements.
Patent Information
- Application Number
- CN202410511163.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-26
- Publication Date
- 2024-10-01
- Estimated Expiration
- 2044-04-26
AI Technical Summary
During the construction of water transmission lines in cities, we often face problems such as pipeline burial depths, long construction distances, curved construction lines, and strict site requirements. Existing ductile iron pipes and construction methods cannot meet these needs.
Multiple standard pipe sections connected in series from end to end are used, including straight pipe sections, sleeve sections and expanded diameter sections. They are equipped with rubber adjustment layers and push ends. The pipes are bent and advanced through push equipment and cylindrical air cushions, reducing the need for Construction land occupation and use of machinery and equipment.
It achieves efficient construction in projects with shallow burial depth, long construction distance and a certain arc route, reduces construction site requirements, improves sealing and thrust efficiency, and is suitable for projects with strict site requirements.
Smart Images

Figure CN118499566B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of underground pipeline construction, and more specifically, to a ductile iron pipe and a construction method thereof. Background Art
[0002] With the continuous advancement of urbanization, the scale of cities is getting higher and higher. In urban water supply projects and gas transmission projects, pipeline laying is required. At present, the usual process is to use T-type ductile iron pipes for laying. T-type ductile iron pipes use sliding flexible interfaces, which have the characteristics of simple structure, easy installation, and good sealing. During on-site operations, pipe trenches are usually opened on the ground first, and then each section of T-type ductile iron pipe is positioned and placed through equipment such as cranes. When connecting, the interface is connected manually. At present, with the continuous increase and update of urban water supply demand, DN400~DN2600 large-diameter ductile iron pipes are constantly used in various water supply projects. Due to the weight of large-diameter ductile iron pipes and the need to cooperate with larger lifting equipment during construction, the requirements for construction sites and personnel organization are more stringent.
[0003] In the latest engineering applications, the jacking method is often used in underground pipeline construction. By using the jacking equipment at the end of the pipeline, all the pipe sections in front are pushed forward. CN111750174A discloses a socket-type ductile iron jacking pipe and a casting method. However, the scenario in which it is used is the non-excavation pipeline construction with a deeper burial depth. It needs to be equipped with a jacking shield before it can be used. It does not meet the application of water pipeline engineering with a shallow burial depth. In the construction process of conventional water supply lines in cities, it is often faced with the requirements that the pipeline must be excavated due to the shallow burial depth, the construction distance is long, the construction line has a certain curvature, and the red line requirements of the construction area are strict. Conventional construction methods require various types of machinery to occupy the road due to the need to accompany the advancement of the pipeline. The conventional jacking method and the ductile iron pipe used do not meet the construction requirements in this scenario. Therefore, it is necessary to propose a ductile iron pipe and its construction method that can meet the above requirements. Summary of the invention
[0004] An object of the present invention is to provide a ductile iron pipe and a construction method thereof, which can meet the needs of pipeline construction scenarios where the construction distance is long and ground grooving is required and the pipeline has a certain curvature.
[0005] In order to achieve these purposes and other advantages according to the present invention, according to one aspect of the present invention, the present invention provides a ductile iron pipe and a construction method thereof, the ductile iron pipe comprising:
[0006] A plurality of standard pipe sections connected end to end in series, the standard pipe section comprising a straight pipe section, one end of the straight pipe section extending along the axis with a supporting section, the supporting section comprising a sleeve section and an expanded diameter section, the inner diameter of the sleeve section being greater than the outer diameter of the straight pipe section, the sleeve section and the straight pipe section being connected via the expanded diameter section, the inner wall of the expanded diameter section being attached with a first rubber adjustment layer, the other end of the straight pipe section extending along the axis with an insertion section, the insertion section being matched and sleeved in the supporting section of a previous standard pipe section, the insertion section comprising a push end head and a sleeve section, the outer wall periphery of the end of the sleeve section being provided with a push end head, the cross section of the push end head being a right-angle wedge-shaped with one side inclined, the inclined surface of the push end head contacting the first rubber adjustment layer, the length of the push end head extending from the outer wall of the sleeve section being less than the minimum spacing between the sleeve section and the straight pipe section, a plurality of grouting holes being provided around the sleeve section, and an annular grouting area being reserved between the outer wall of the sleeve section and the corresponding inner wall of the sleeve section.
[0007] Preferably, a second rubber adjustment layer is fixed to the inclined surface of the pushing end, a first rubber sealing layer is arranged around the inner wall of the sleeve section between the grouting hole and the end of the sleeve section, and a second rubber sealing layer is arranged around the sleeve section at a position corresponding to the first rubber sealing layer, and the corresponding first rubber sealing layer and second rubber sealing layer are tightly fitted.
[0008] Preferably, a plurality of U-shaped bayonet pins are provided at intervals around the inner wall of the sleeve section between the first rubber sealing layer and the expanded diameter section, and an acute angle is formed between the two arms of the U-shaped bayonet pin when no force is applied, the U-shaped bayonet pin is elastic, one arm of the U-shaped bayonet pin is fixedly connected to the inner wall of the sleeve section, and the end of the other arm faces the pushing end and touches the outer wall of the sleeve section, and the total height of the two arms of the U-shaped bayonet pin when the force is applied to be parallel is less than the distance between the inner wall of the sleeve section and the pushing end.
[0009] Preferably, the first rubber adjustment layer, the second rubber adjustment layer, the first rubber sealing layer and the second rubber sealing layer are all rubber sealing strips with compressible thickness, the exposed edges of the cross-sections are serrated, and the rubber sealing strips contain multiple rows of compression holes.
[0010] Preferably, when the first rubber adjustment layer is in contact with the second rubber adjustment layer but neither is compressed, the free arm end of the U-shaped bayonet contacts the right-angled surface of the push end.
[0011] Preferably, the construction method of the ductile iron pipe comprises the following steps:
[0012] S1. Pipe trenches are opened on the ground along the planned pipeline construction route. Pushing equipment and pushing tooling are installed at the ends of the pipe trenches. Guide brackets are set at the curved parts of the pipe trenches.
[0013] S2. Cylindrical air cushions are placed at intervals along the bottom wall of the pipe groove, and the first section of the standard pipe section is hoisted on several cylindrical air cushions. The axis of the first section of the standard pipe section is parallel to the axis of the pipe groove in which it is located, and the distance between the first section of the standard pipe section and the jacking equipment is just enough to accommodate the second section of the standard pipe section;
[0014] S3, put the second section standard pipe section between the first section standard pipe section and the jacking tooling, ensure that the first section standard pipe section, the second section standard pipe section and the jacking tooling are coaxial, use the jacking equipment to push forward until the second section standard pipe section reaches the position of the first section standard pipe section before jacking, repeat S3 until the whole section of the pipeline is completed;
[0015] S4. Remove the guide bracket and deflate all cylindrical air cushions until the entire pipeline section is on the ground. For every junction between two standard pipe sections, grouting is performed from the grouting hole to seal it.
[0016] Preferably, the cylindrical air cushion comprises an airbag body and an air valve, and the airbag body is a closed cavity.
[0017] The present invention has at least the following beneficial effects:
[0018] First, the present invention is applicable to engineering projects with shallow burial depth, long construction distance and construction route with a certain curvature. A certain angle can be formed between each two front-to-back connected standard pipe sections of the present invention to adapt to the route;
[0019] Second, the present invention uses a jacking method to transport the entire section of the pipeline forward, avoiding the need for hoisting equipment and transport vehicles to accompany the project in conventional construction methods, greatly reducing the site occupied by the construction, and is suitable for engineering projects with strict site requirements;
[0020] Third, the present invention uses a cylindrical air cushion as a cushion under the pipeline during forward pushing. The cylindrical air cushion is reusable and easy to operate, avoiding the need for wheeled or tracked supporting equipment in conventional methods. Moreover, since the cylindrical air cushion can roll along with the pipeline on it during pushing, the thrust required for pushing is relatively low. The present invention also has relatively low requirements for pushing equipment. The cylindrical air cushion can also effectively protect the surface of the ductile iron pipe from wear.
[0021] Fourthly, in the present invention, the two standard pipe sections intersecting each other are provided with multiple rubber sealing layers, so that the intersection of the two standard pipe sections can be grouting-injected after forming a certain angle, and the risk of leakage is lower;
[0022] Other advantages, objectives and features of the present invention will be embodied in part through the following description, and in part will be understood by those skilled in the art through study and practice of the present invention. BRIEF DESCRIPTION OF THE DRAWINGS
[0023] Figure 1A schematic diagram of the front and rear ends of a standard pipe segment in a technical solution of the present invention;
[0024] Figure 2 A schematic diagram of a ductile iron pipe construction site in another technical solution of the present invention;
[0025] Figure 3 A schematic diagram of a construction site for a curved arc section of a ductile iron pipe in another technical solution of the present invention;
[0026] Figure 4 It is a schematic diagram of the construction position of the first section of a ductile iron pipe in another technical solution of the present invention;
[0027] Figure 5 It is a cross-sectional schematic diagram of the connection position of two standard pipe sections after completion in another technical solution of the present invention;
[0028] Figure 6 It is a cross-sectional schematic diagram of the handover process of two standard pipe joints at the handover position in another technical solution of the present invention;
[0029] Figure 7 It is a cross-sectional schematic diagram of another technical solution of the present invention when two standard pipe sections are connected at an angle;
[0030] Figure 8 It is a cross-sectional schematic diagram of a first rubber adjustment layer, a second rubber adjustment layer, a first rubber sealing layer, and a second rubber sealing layer in another technical solution of the present invention;
[0031] Fig. 9 It is a schematic diagram of a cylindrical air cushion in another technical solution of the present invention. DETAILED DESCRIPTION
[0032] The present invention is further described in detail below in conjunction with the accompanying drawings and specific embodiments so that those skilled in the art can implement the invention with reference to the description.
[0033] It should be understood that the terms such as “having”, “including” and “comprising” used herein do not exclude the existence or addition of one or more other elements or combinations thereof.
[0034] It should be noted that the experimental methods described in the following embodiments are conventional methods unless otherwise specified, and the components and materials can be obtained from commercial sources unless otherwise specified; in the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "set" should be understood in a broad sense, for example, they can be fixedly connected, set, or detachably connected, set, or connected and set in one piece. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood in specific circumstances. The orientation or position relationship indicated by the terms "lateral", "longitudinal", "upper", "lower", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", etc. is based on the orientation or position relationship shown in the accompanying drawings, which is only for the convenience of describing the present invention and simplifying the description, and does not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation of the present invention.
[0035] like Figures 1 to 9As shown, the present invention provides a ductile iron pipe, comprising a plurality of standard pipe sections 1 connected in series end to end, wherein the standard pipe section 1 comprises a straight pipe section 10, wherein one end of the straight pipe section 10 is provided with a support section 11 extending along the axis, wherein the support section 11 comprises a sleeve section 111 and an expanded diameter section 112, wherein the inner diameter of the sleeve section 111 is greater than the outer diameter of the straight pipe section 10, wherein the sleeve section 111 is connected to the straight pipe section 10 via the expanded diameter section 112, wherein the inner wall of the expanded diameter section 112 is attached with a first rubber adjustment layer 113, wherein the other end of the straight pipe section 10 is provided with an insertion section 12 extending along the axis, wherein the insertion section 12 is matched and sleeved on the previous one In the supporting section 11 of the standard pipe section 1, the insertion section 12 includes a top push end 121 and a sleeve section 122. The outer wall of the end of the sleeve section 122 is provided with a top push end 121. The cross section of the top push end 121 is a right-angle wedge-shaped with one side inclined. The inclined surface of the top push end 121 touches the first rubber adjustment layer 113. The length of the top push end 121 extending from the outer wall of the sleeve section 122 is less than the minimum spacing between the sleeve section 111 and the straight pipe section 10. A plurality of grouting holes 13 are opened around the sleeve section 111. An annular space is reserved between the outer wall of the sleeve section 122 and the corresponding inner wall of the sleeve section 111. Grouting area 130, in this technical solution, the end of the supporting section 11 of each section of the standard pipe section 1 is subjected to axial thrust, so that the top push end 121 of the standard pipe section 1 pushes all the standard pipe sections 1 in front to move forward, and at the intersection of the two sections of the standard pipe section 1, due to the gap between the matching sleeve section 111 and the sleeve section 122, a certain inclination angle can be formed between the two sections of the standard pipe section 1, the first rubber adjustment layer 113 is a whole piece of rubber layer that can be compressed along the thickness direction, and the inner wall of the expansion section 112 is matched with a groove to accommodate the first rubber adjustment layer 113, and a part of the first rubber adjustment layer 113 The sub-card is embedded in the matching groove of the expanded diameter section 112, and a part of it extends out of the inner wall surface of the expanded diameter section 112. When under extreme compression, the first rubber adjustment layer 113 can be completely compressed into the groove of the expanded diameter section 112. When the standard pipe section 1 of the latter section forms a certain angle with the previous section of the standard pipe section 1, the pushing end 121 at the intersection position can continue to apply thrust to the first rubber adjustment layer 113 that has been matched and compressed. The space between the sleeve section 122 and the sleeve section 111 can be provided with an anti-slip device to prevent the insertion section 12 of the standard pipe section 1 from slipping out of the supporting section 11 of the previous standard pipe section 1 during the pushing process.
[0036] In the present technical solution, after the construction of all the standard pipe sections is completed, the gaps between all the sleeve sections 111 and the sleeve sections 122 or the straight pipe sections 10 are sealed using flexible materials such as rubber rings or hard templates. After confirming that the sealing is in place and no gaps will appear, grouting is completed through the grouting holes 13 to form an annular grouting area 130 at the intersection of any two connected standard pipe sections 1. The grouting material can use inorganic waterproof grouting materials, organic waterproof grouting materials, polymer cement-based grouting materials, asphalt waterproof grouting materials, etc. The supporting section 11 of the standard pipe section 1 in the present technical solution is subjected to thrust to push all the standard pipe sections 1 in front forward. A certain angle can be formed between any two connected standard pipe sections 1 to meet the construction needs. After all the pipe sections arrive at the position, the sealing of each intersection is completed by grouting. The present invention is quick to construct and occupies a small area.
[0037] Preferably, a second rubber adjustment layer 123 is fixed to the inclined surface of the push end 121, a first rubber sealing layer 114 is arranged around the inner wall of the sleeve section 111 between the grouting hole 13 and the end of the sleeve section 111, and a second rubber sealing layer 124 is arranged around the sleeve section 122 at a position corresponding to the first rubber sealing layer 114, and the corresponding first rubber sealing layer 114 and second rubber sealing layer 124 fit tightly. In the present technical solution, the second rubber sealing layer 124 is a rubber pad that can be compressed along the thickness direction, and the top push head 121 is provided with a groove for the second rubber adjustment layer 123, and the second rubber adjustment layer 123 can be compressed into the matching groove on the top push head 121 when under extreme compression, and the push end 121 applies a force to the first rubber adjustment layer 113 through the second rubber adjustment layer 123, thereby pushing the previous section of the standard pipe section 1, and the first rubber adjustment layer 113 and the second rubber adjustment layer 12 3 cooperatively deforms to adapt to the angle change between two adjacent standard pipe sections 1, the first rubber sealing layer 114 and the second rubber sealing layer 124 are rubber pads that can be compressed along the thickness direction, the sleeve section 111 is provided with a groove for the first rubber sealing layer 114, and the first rubber sealing layer 114 can be compressed into the groove on the sleeve section 111 when under extreme compression, and the total thickness of the first rubber sealing layer 114 and the second rubber sealing layer 124 after being compressed is equal to the distance between the sleeve section 111 and the sleeve section 122 at the intersection of two straight connected standard pipe sections 1, when the two standard pipe sections 1 form a certain angle, the first rubber sealing layer 114 and the second rubber sealing layer 124 always have a contact portion with each other and remain fully or partially compressed, and when all standard pipe sections 1 are pushed to the designed position, it is no longer necessary to seal the gap between the sleeve section 111 and the sleeve section 122 or the straight pipe section 10, and grouting can be directly performed through the grouting hole 13.
[0038] In another technical solution, a plurality of U-shaped bayonet pins 14 are provided at intervals around the inner wall of the sleeve section 111 between the first rubber sealing layer 114 and the expanded diameter section 112. The two arms of the U-shaped bayonet pin 14 form an acute angle when no force is applied. The U-shaped bayonet pin 14 is elastic. One arm of the U-shaped bayonet pin 14 is fixedly connected to the inner wall of the sleeve section 111, and the end of the other arm faces the pushing end 121 and touches the outer wall of the sleeve section 122. When the two arms of the U-shaped bayonet pin 14 are parallel under force, the total height is less than the distance between the inner wall of the sleeve section 111 and the pushing end 121. In the technical solution, if there is no anti-slip measure for two connected standard pipe sections 1 and a certain degree of angle exists, they may slip out during the construction process, and re-docking is difficult. The two arms of the U-shaped bayonet pin 14 form an acute angle when no force is applied. When the arm is under pressure, it is squeezed in the direction close to one arm, and the two arms can be parallel or overlapped, and after the pressure is released, the two arms can elastically return to the shape before the force is applied. The U-shaped bayonet 14 is arranged on the inner circumference of the sleeve section 111 of the previous standard pipe section 1, and one arm is fixed to the inside of the sleeve section 111. When the insertion section 12 of the subsequent standard pipe section 1 extends into the supporting section 11 of the previous standard pipe section 1, the pushing end 121 applies pressure to the free arm of the U-shaped bayonet 14 during its advancement to make it retract. After the pushing end 121 advances to a certain distance, since the rear part of the pushing end 121 is a straight surface, the U-shaped bayonet 14 loses pressure and returns to its original shape. At this time, the pushing end 121 can continue to move forward but cannot retreat. Unless all the U-shaped bayonet pins 14 are destroyed, the two connected standard pipe sections 1 will not fall out.
[0039] In another technical solution, the first rubber adjustment layer 113, the second rubber adjustment layer 123, the first rubber sealing layer 114, and the second rubber sealing layer 124 are all rubber sealing strips with compressible thickness, and the exposed edges of the cross-sections are serrated. The rubber sealing strips contain multiple rows of compression holes, and the compression holes can be circular or in other shapes. The inclined surface of the push end 121 and the inner wall of the expanded diameter section 112 are matched with grooves to fix the second rubber adjustment layer 123 and the first rubber adjustment layer 113 respectively.
[0040] In another technical solution, when the first rubber adjustment layer 113 and the second rubber adjustment layer 123 are in contact but not compressed, the free arm end of the U-shaped bayonet 14 touches the right-angle surface of the pushing end 121. After the standard pipe segment 1 connected at both ends undergoes the pushing operation and all the U-shaped bayonet 14 are compressed and restored to their original shape, when the standard pipe segment 1 adjusts its angle, the first rubber adjustment layer 113 and the second rubber adjustment layer 123 always maintain contact, thereby preventing the slurry from leaking into the interior of the standard pipe segment 1 during subsequent grouting.
[0041] In the above technical solution, if Figure 6As shown in a, when the insertion section 12 enters the matching supporting section 11, the pushing end 121 first compresses the first rubber sealing layer 114 during the forward movement, and then pushes the U-shaped bayonet 14 to a state where the two arms are parallel;
[0042] like Figure 6 As shown in FIG. 2 b, when the insertion section 12 can apply thrust to the support section 11, when the second rubber adjustment layer 123 on the push end 121 contacts the first rubber adjustment layer 113, the right-angled surface of the push end 121 just exceeds the free arm of the U-shaped bayonet 14, the U-shaped bayonet 14 restores its shape and the free arm falls and abuts against the right-angled surface of the push section head 121, at which time the first rubber sealing layer 114 and the second rubber sealing layer 124 have a contact surface, and the insertion section 12 cannot escape from the support section 11 during normal operation;
[0043] As shown in 6C, when the pushing section head 121 is subjected to a large pressure and contacts the inner wall of the reducing section 112, the first rubber adjustment layer 113 and the second rubber adjustment layer 123 are respectively compressed into the matching grooves, and the end of the free arm of the U-shaped bayonet 14 contacts the outer wall of the sleeve section 122 and is separated from the right-angle surface of the pushing end head 121 by one end. At this time, there is a contact surface between the first rubber sealing layer 114 and the second rubber sealing layer 124.
[0044] In another technical solution, the construction method of the ductile iron pipe comprises the following steps:
[0045] S1. A pipe trench 4 is opened on the ground along the planned construction route of the pipeline, and a jacking device 3 and a jacking tool 30 are installed at the end of the pipe trench 4. A guide bracket 5 is supported at the curved part of the pipe trench 4. Specifically, after the pipe trench 4 is mechanically excavated to 200 mm above the elevation, the bottom 200 mm above the elevation is manually cleared to ensure the elevation and make the bottom of the pipe trench 4 basically flat. The jacking device 3 includes a hydraulic push rod and a fixed bracket. The jacking tool 30 is processed based on the diameter of the ductile iron pipe and the length of the pipe segment in this construction operation. If the route of this construction is a non-straight section, it is necessary to determine whether the standard pipe segment 1 meets the requirements after angle adjustment. A guide bracket 5 is manually installed at the part where the pipeline angle adjustment is required. The guide bracket includes a frame with good stability composed of steel pipes and fasteners. Guide steel plates 50 are installed on both sides of the predetermined standard pipe segment 1 advancement route, so that the standard pipe segment 1 is restricted by the guide steel plates 50 on both sides when it is pushed forward and is pushed along the preset route.
[0046] S2. Cylindrical air cushions 2 are placed at intervals along the bottom wall of the pipe groove 4, and the first section of the standard pipe segment 1 is hoisted on several cylindrical air cushions 2. The axis of the first section of the standard pipe segment 1 is parallel to the axis of the pipe groove 4 in which it is located, and the distance between the first section of the standard pipe segment 1 and the jacking device 3 is just enough to accommodate the second section of the standard pipe segment 1; specifically, the cylindrical air cushion 2 can roll with the forward push of the standard pipe segment 1 under pressure, and the height of each section of the standard pipe segment 1 is basically consistent and horizontal when supported by several cylindrical air cushions 2 parallel to each other. In this technical solution, the cylindrical air cushion 2 is deformed under pressure, and the size and inflation volume of the cylindrical air cushion 2 need to be unified. When the standard pipe segment 1 is supported by the cylindrical air cushion 2, the supporting section 11 of each section of the standard pipe segment 1 is lower than the bottom surface of the pipe groove 4. When the cylindrical air cushion 2 below the current section of the standard pipe segment 1 is deflated, the longitudinal angle between the front and rear sections of the standard pipe segment 1 is within the allowable angle variation range.
[0047] S3, put the secondary standard pipe section 1 between the primary standard pipe section 1 and the jacking tooling 30, ensure that the primary standard pipe section 1, the secondary standard pipe section 1 and the jacking tooling 30 are coaxial, use the jacking device 3 to push forward until the secondary standard pipe section 1 reaches the position of the primary standard pipe section 1 before jacking, repeat S3 until the entire section of the pipeline is completed. Specifically, during the jacking operation, the staff needs to ensure that there are multiple cylindrical air cushions in place in front of the frontmost pipe section.
[0048] S4. Remove the guide bracket 5 and deflate all the cylindrical air cushions 2 until the entire section of the pipeline is on the ground. For every intersection of two standard pipe sections 1, grouting is performed from the grouting hole 13 to seal it. Specifically, when the pushing-up work of the entire pipeline section is completed, the straight pipe sections 11 of all standard pipe sections 1 are supported by the cylindrical air cushions 2. After the cylindrical air cushions 2 are deflated, the standard pipe sections 1 stand on the bottom surface of the pipe groove 4 by the outer wall of the sleeve section 111. During the deflation process, the deflated cylindrical air cushions 2 of two adjacent standard pipe sections 1 can be drawn out from the gap between the straight pipe section 11 and the bottom surface of the pipe groove 4. When performing the grouting operation, the sealing of the connection of the standard pipe section 1 needs to be monitored. If the sealing fails, it needs to be sealed in time.
[0049] In another technical solution, the cylindrical air cushion includes an airbag body 20 and a valve 21. The airbag body 20 is a closed cavity. The wall of the airbag body 20 is composed of an airtight layer wrapped with a plurality of anti-puncture layers and wear-resistant layers. When the valve 21 is opened, the gas in the airbag body 20 is connected to the outside and can complete the inflation and deflation operations. When the valve 21 is closed, the internal gas of the airbag body 20 cannot be discharged during the compression and deformation.
[0050] Although the embodiments of the present invention have been disclosed as above, they are not limited to the applications listed in the specification and the implementation modes, and they can be fully applied to various fields suitable for the present invention. For those familiar with the art, additional modifications can be easily implemented. Therefore, without departing from the general concept defined by the claims and the scope of equivalents, the present invention is not limited to the specific details and the illustrations shown and described herein.
Claims
1. A ductile iron pipe, characterized in that: include: A plurality of standard pipe sections connected in series end to end, the standard pipe section comprising a straight pipe section, one end of the straight pipe section extending along the axis with a supporting section, the supporting section comprising a sleeve section and an expanded diameter section, the inner diameter of the sleeve section being larger than the outer diameter of the straight pipe section, the sleeve section and the straight pipe section being connected via the expanded diameter section, the inner wall of the expanded diameter section being attached with a first rubber adjustment layer, the other end of the straight pipe section extending along the axis with an insertion section, the insertion section being matched and sleeved in the supporting section of a previous standard pipe section, the insertion section comprising a push end head and a sleeve section, the outer wall of the end of the sleeve section being provided with a push end head, the cross section of the push end head being a right-angle wedge-shaped with one side inclined, the inclined surface of the push end head contacting the first rubber adjustment layer, the length of the push end head extending from the outer wall of the sleeve section being less than the minimum spacing between the sleeve section and the straight pipe section, a plurality of grouting holes being provided around the sleeve section, and an annular grouting area being reserved between the outer wall of the sleeve section and the corresponding inner wall of the sleeve section; A second rubber adjustment layer is fixed to the inclined surface of the push end head, a first rubber sealing layer is arranged around the inner wall of the sleeve section between the grouting hole and the end of the sleeve section, and a second rubber sealing layer is arranged around the sleeve section at a position corresponding to the first rubber sealing layer, and the corresponding first rubber sealing layer and the second rubber sealing layer are tightly fitted; The inner wall of the sleeve section is located between the first rubber sealing layer and the expanded diameter section and is provided with a plurality of U-shaped bayonet pins at intervals. When no force is applied, the two arms of the U-shaped bayonet pin form an acute angle. The U-shaped bayonet pin is elastic. One arm of the U-shaped bayonet pin is fixedly connected to the inner wall of the sleeve section, and the end of the other arm faces the push end and contacts the outer wall of the sleeve section. When the two arms of the U-shaped bayonet pin are parallel under force, the total height is less than the distance between the inner wall of the sleeve section and the push end. The first rubber adjustment layer, the second rubber adjustment layer, the first rubber sealing layer, and the second rubber sealing layer are all rubber sealing strips with compressible thickness, the exposed edges of the cross-sections are serrated, and the rubber sealing strips contain multiple rows of compression holes; When the first rubber adjustment layer is in contact with the second rubber adjustment layer but neither is compressed, the free arm end of the U-shaped bayonet contacts the right-angle surface of the push end.
2. The construction method of ductile iron pipe according to claim 1, characterized in that: The following steps are involved: S1. Pipe trenches are opened on the ground along the planned pipeline construction route. Pushing equipment and pushing tooling are installed at the ends of the pipe trenches. Guide brackets are set at the curved parts of the pipe trenches. S2. Cylindrical air cushions are placed at intervals along the bottom wall of the pipe groove, and the first section of the standard pipe section is hoisted on several cylindrical air cushions. The axis of the first section of the standard pipe section is parallel to the axis of the pipe groove in which it is located, and the distance between the first section of the standard pipe section and the jacking equipment is just enough to accommodate the second section of the standard pipe section; S3, put the second section standard pipe section between the first section standard pipe section and the jacking tooling, ensure that the first section standard pipe section, the second section standard pipe section and the jacking tooling are coaxial, use the jacking equipment to push forward until the second section standard pipe section reaches the position of the first section standard pipe section before jacking, repeat S3 until the whole section of the pipeline is completed; S4. Remove the guide bracket and deflate all cylindrical air cushions until the entire pipeline section is on the ground. For every junction between two standard pipe sections, grouting is performed from the grouting hole to seal it.
3. The construction method of ductile iron pipe according to claim 2, wherein the cylindrical air cushion comprises an airbag body and an air valve, and the airbag body is a closed cavity.